1/100
Instream Storage Structure, Gudvella
Cast of concrete 8th lift RCC M25A20 grade at right side D/s flank wall including return wall from RL 157.84m to 159.34m is under progress in the presence of Dept JE, site engineer of PMC and agency forman. The slump test value is 73 mm on 06.02.2026
2/100
Instream Storage Structure, Gudvella
Cast of concrete 8th lift RCC M25A20 grade at right side D/s flank wall including return wall from RL 157.84m to 159.34m is under progress in the presence of Dept JE, site engineer of PMC and agency forman. The slump test value is 73 mm on 06.02.2026
3/100
Instream Storage Structure, Gudvella
Roller track and guide installation work at barrage bay no 9 is under progress on 06.02.2026
4/100
Instream Storage Structure, Gudvella
Column assembly work under progress as per approval drawing on 06.02.2026
5/100
Barrage across river Turi & Guntat
Checking of reinforcement of Deck slab no.4 of Turi barrage
6/100
Instream Storage Structure, Gudvella
• 1. Reinforcement work work at right side D/s wing wall for 6th lift RCC is under progress.
2. Shuttering work at right side d/s flared out wall is under progress.
3. Shuttering work at right side D/s flank wall for 8th lift RCC is under progress on 06.02.2026
7/100
Barrage across river Turi & Guntat
2nd stage embedded part installation in progress at Turi site.
8/100
Instream Storage Structure, Gudvella
Shuttering work at u/s flared out wall (A2) is under progress on 06.02.2026
9/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.6&7 for 7th lift of bay no.7 is in progress in presence of PM,EPC agency,Site Engineers of PMC & Site Engineer of EPC agency. The slump test value is 84mm on 06.02.2026
10/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.6&7 for 7th lift of bay no.7 is in progress in presence of PM,EPC agency,Site Engineers of PMC & Site Engineer of EPC agency. The slump test value is 84mm on 06.02.2026
11/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for right & left kerb at Deck slab of span-7,block-1 upto RL-247.30m is in progress through concrete pump in presence of PM EPC agency, site engineer of PMC & PM of EPC agency. The slump test value is 85mm on 06.02.2026
12/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for right & left kerb at Deck slab of span-7,block-1 upto RL-247.30m is in progress through concrete pump in presence of PM EPC agency, site engineer of PMC & PM of EPC agency. The slump test value is 85mm on 06.02.2026
13/100
Instream Storage Structure, Nandagaon
• 2. Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay No.7 of Pier No. 6&7 for 7th lift has been checked and found correct by HM Expert of PMC during his site visit on dt.02.02.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through air water jetting and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 06.02.2026
14/100
Instream Storage Structure, Nandagaon
• 1. The area for left & right kerb of RCC Deck slab has been checked before placement in presence of PM,EPC Agency,Site Engineer of PMC & Site Engineer of EPC agency as follows:
(i) Binding of 8mm dia 2-legged stirrups for right & left kerb of Span- 7 and fixing of rail posts bars are completed.
(ii) Rigid and smooth shuttering with 40mm clear cover are completed.
(iii) Fixing & placing of joint materials at expansion gap of kerb is done.
(iv) Area is cleaned using air water jet and passed by SE, KID, Bhawanipatna and ready to place concrete with RCC M35A20 grade upto RL-247.30m on 06.02.2026
15/100
Instream Storage Structure, Nandagaon
Trestle fit up, assembly and welding is under progress on 06.02.2026
16/100
Instream Storage Structure, Nandagaon
Trestle fit up, assembly and welding is under progress on 06.02.2026
17/100
Instream Storage Structure, Nandagaon
1st nos of under sluice gate both barrage bay gate and stoplog gate side sil beam, roller track and centre guide erection work under progress on 06.02.2026
18/100
Instream Storage Structure, Nandagaon
Shuttering at D/S right flared out wall, Block-2 is in progress on 06.02.2026
19/100
Instream Storage Structure, Nandagaon
Shuttering for CC blocks at U/S right flared out wall is in progress on 06.02.2026
20/100
Instream Storage Structure, Nandagaon
Reinforcement binding, Shuttering & curing at right abutment Block-2.is under progress on 06.02.2026
21/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete at pier no.6 & 7, bay-7, Block-1 is in progress on 06.02.2026
22/100
Instream Storage Structure, Dhanei
U/S and D/S Flared-out wall casting Chipping of concrete in Gate grooves in progress in presence of Site engineer PMC.
23/100
Instream Storage Structure, Dhanei
U/S and D/S Flared-out wall casting Chipping of concrete in Gate grooves in progress in presence of Site engineer PMC.
24/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
R.H.S under sluice shuttering work is going on at choudhary gada iss project.
25/100
Integrated Barrage across river Kochila and across river Baitarini
Downstream divide wall reinforcement fixing work in progress at baitarani iss project.
26/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
SDE visited LAO office at Collectorate, Keonjhar and pursue the DCAC proposal submitted for acquisition of private land.
27/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Visited by QC&QA Expert, PMU in presence of Dy. TL, QAE, PSE & IEE of PSS team, A.E.E & A.E, RDD along with representative of EPC agency regarding inspection of Coarse aggregate (10mm & 20mm) and Fine aggregate and other ongoing activities at Site.
28/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of Divide wall, 6th lift is under Progress.
29/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of Double pier, 1st lift is under Progress.
30/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Visited by QC&QA Expert, PMU in presence of Dy. TL, QAE, PSE & IEE of PSS team, A.E.E & A.E, RDD along with representative of EPC agency regarding checking for Shuttering & binding of reinforcement at RHS Raft and other ongoing activities at Site.
31/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS Counterfort & Abutment, 7th lift is under Progress.
32/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of Binding of reinforcement for RHS Barrage bay Raft is under Progress.
33/100
Instream Storage Structure, Jharbeda
Drilling & Excavation of D/S RHS Under sluice Overburden Rock Breaking work is under progress.
34/100
Instream Storage Structure, Jharbeda
Curing of Pier No-8 Footing, 1st lift is under Progress.
35/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-5 is under Progress.
36/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-7 is under Progress.
37/100
Instream Storage Structure, Jharbeda
Cleaning of D/S Gravity floor Pier No-7 to Pier No-8 is in Progress.
38/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 80 mm) of U/S Cross Girder (Bay No-27) at Block No-5 done in presence of Client & PSS Team.
39/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of U/S Cross Girder (Bay No-27) at Block No-5 is under progress in presence of Client & PSS Team.
40/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-8, 13th lift at Block No-2 done in presence of Client & PSS Team.
41/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-8, 13th lift at Block No-2 is under progress in presence of Client & PSS Team.
42/100
Instream Storage Structure, Hamirpur
Cleaning of reinforcement for Pier No-21 is under progress by Sand blasting method.
43/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Deck slab is under progress.
44/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-14, 11th lift is under progress.
45/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-7, 8th lift is under progress.
46/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-8, 13th lift is under progress.
47/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-11, 13th lift is under progress.
48/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-12, 13th lift is under progress.
49/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-13, 8th lift is under progress.
50/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-22, 14th is under progress.
51/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-30, 8th lift is under progress.
52/100
Instream Storage Structure, Khalpal
Slump testing M35A20 (Value 80 mm) of Girder No-39 done in presence of Client & PSS Team.
53/100
Instream Storage Structure, Khalpal
Concreting M35A20 of Girder No-39 is under progress in presence of Client & PSS Team.
54/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site.
55/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE and dept. officials, IEE Expert along with Site engineer PMC. Inspected the overall progress of site, Pile load test, Left side fish pass area casting and U/S Left side flank diaphragm wall panel no-96 concreting.
56/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE and dept. officials, IEE Expert along with Site engineer PMC. Inspected the overall progress of site, Pile load test, Left side fish pass area casting and U/S Left side flank diaphragm wall panel no-96 concreting.
57/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE and dept. officials, IEE Expert along with Site engineer PMC. Inspected the overall progress of site, Pile load test, Left side fish pass area casting and U/S Left side flank diaphragm wall panel no-96 concreting.
58/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE and dept. officials, IEE Expert along with Site engineer PMC. Inspected the overall progress of site, Pile load test, Left side fish pass area casting and U/S Left side flank diaphragm wall panel no-96 concreting.
59/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE and dept. officials, IEE Expert along with Site engineer PMC. Inspected the overall progress of site, Pile load test, Left side fish pass area casting and U/S Left side flank diaphragm wall panel no-96 concreting.
60/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE and dept. officials, IEE Expert along with Site engineer PMC. Inspected the overall progress of site, Pile load test, Left side fish pass area casting and U/S Left side flank diaphragm wall panel no-96 concreting.
61/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site.
62/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE and dept. officials, IEE Expert along with Site engineer PMC. Inspected the overall progress of site, Pile load test, Left side fish pass area casting and U/S Left side flank diaphragm wall panel no-96 concreting. • Cube cast at site. Slump cone test conducted at site. Curing continuing at site.
63/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE and dept. officials, IEE Expert along with Site engineer PMC. Inspected the overall progress of site, Pile load test, Left side fish pass area casting and U/S Left side flank diaphragm wall panel no-96 concreting. • Cube cast at site. Slump cone test conducted at site. Curing continuing at site.
64/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE and dept. officials, IEE Expert along with Site engineer PMC. Inspected the overall progress of site, Pile load test, Left side fish pass area casting and U/S Left side flank diaphragm wall panel no-96 concreting. • Cube cast at site. Slump cone test conducted at site. Curing continuing at site.
65/100
Barrage across river Turi & Guntat
Compressive strength test of concrete cubes of grade M25 A20 conducted at Field Laboratory of Turi Barrage Site.
66/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site.
67/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE and dept. officials, IEE Expert along with Site engineer PMC. Inspected the overall progress of site and Pile load test and pile concreting.
68/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE and dept. officials, IEE Expert along with Site engineer PMC. Inspected the overall progress of site and Pile load test and pile concreting.
69/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE and dept. officials, IEE Expert along with Site engineer PMC. Inspected the overall progress of site and Pile load test and pile concreting.
70/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE and dept. officials, IEE Expert along with Site engineer PMC. Inspected the overall progress of site and Pile load test and pile concreting.
71/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE and dept. officials, IEE Expert along with Site engineer PMC. Inspected the overall progress of site and Pile load test and pile concreting.
72/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE and dept. officials, IEE Expert along with Site engineer PMC. Inspected the overall progress of site and Pile load test and pile concreting.
73/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE and dept. officials, IEE Expert along with Site engineer PMC. Inspected the overall progress of site and Pile load test and pile concreting.
74/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE and dept. officials, IEE Expert along with Site engineer PMC. Inspected the overall progress of site and Pile load test and pile concreting.
75/100
Instream Storage Structure, KansariGanda
Visit of Pri. Sec. to Govt., DoWR, CE, ACE, SE, ACE(QA&QC), SE(QA&QC) with Department officials, IEE and QA&QC expert from PMU, DyTL, IEE and QA&QC expert along with Site Engineers to ISS Kansariganda. GM and his team of the agency were attended during visit. The Secretary has keenly observed the presentation submitted by the department. She has stressed upon to give priority to in LA initiation, pending designs and finally to squeeze the work programme, so that benefits can be provided to the public at the earliest.
76/100
Instream Storage Structure, KansariGanda
Visit of Pri. Sec. to Govt., DoWR, CE, ACE, SE, ACE(QA&QC), SE(QA&QC) with Department officials, IEE and QA&QC expert from PMU, DyTL, IEE and QA&QC expert along with Site Engineers to ISS Kansariganda. GM and his team of the agency were attended during visit. The Secretary has keenly observed the presentation submitted by the department. She has stressed upon to give priority to in LA initiation, pending designs and finally to squeeze the work programme, so that benefits can be provided to the public at the earliest.
77/100
Instream Storage Structure, KansariGanda
Visit of Pri. Sec. to Govt., DoWR, CE, ACE, SE, ACE(QA&QC), SE(QA&QC) with Department officials, IEE and QA&QC expert from PMU, DyTL, IEE and QA&QC expert along with Site Engineers to ISS Kansariganda. GM and his team of the agency were attended during visit. The Secretary has keenly observed the presentation submitted by the department. She has stressed upon to give priority to in LA initiation, pending designs and finally to squeeze the work programme, so that benefits can be provided to the public at the earliest.
78/100
Instream Storage Structure, KansariGanda
Visit of Pri. Sec. to Govt., DoWR, CE, ACE, SE, ACE(QA&QC), SE(QA&QC) with Department officials, IEE and QA&QC expert from PMU, DyTL, IEE and QA&QC expert along with Site Engineers to ISS Kansariganda. GM and his team of the agency were attended during visit. The Secretary has keenly observed the presentation submitted by the department. She has stressed upon to give priority to in LA initiation, pending designs and finally to squeeze the work programme, so that benefits can be provided to the public at the earliest.
79/100
Instream Storage Structure, KansariGanda
Visit of Pri. Sec. to Govt., DoWR, CE, ACE, SE, ACE(QA&QC), SE(QA&QC) with Department officials, IEE and QA&QC expert from PMU, DyTL, IEE and QA&QC expert along with Site Engineers to ISS Kansariganda. GM and his team of the agency were attended during visit. The Secretary has keenly observed the presentation submitted by the department. She has stressed upon to give priority to in LA initiation, pending designs and finally to squeeze the work programme, so that benefits can be provided to the public at the earliest.
80/100
Instream Storage Structure, Khirasasan
RHS U/S FLANK WALL PROFILE 2 ND LIFE SHUTTERING WORK UNDER PROGRESS
81/100
Instream Storage Structure, Khirasasan
RHS D/S C F WING WALL FINAL LIFT SHUTTERING WORK UNDER PROGRESS
82/100
Instream Storage Structure, Khirasasan
RHS D/S FLANK WALL 9TH LIFT SHUTTERING WORK UNDER PROGRESS
83/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
84/100
Instream Storage Structure, Khirasasan
Slump 85mm
85/100
Instream Storage Structure, Khirasasan
checked placing supporting bars and alignment of shuttering work in RHS D/S flared out 17th step RL- 221.300 to 221.900 Now the area is ready for concrete casting M20 A20. So recommended for the purpose. Approved by AEE sir SID Sambalpur in presence of JE
86/100
Instream Storage Structure, Khirasasan
LHS U/S FLARED OUT WALL 19TH STEP SHUTTERING WORK IS UNDER PROGRESS.
87/100
Instream Storage Structure, Khirasasan
RHS D/S FLARED OUT WALL 17TH STEP SHUTTERING WORK IS UNDER PROGRESS.
88/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
89/100
Instream Storage Structure, Gudvella
Cast of concrete 15th lift PCC M20A20 grade at right side D/s flard out wall from sec 1-1 to 4-4 with RL 157.00m to 157.60m in the presence of Dept JE, site engineer of PMC and agency forman . The slump test value is 72mm on 05.02.2026
90/100
Instream Storage Structure, Gudvella
Cast of concrete 15th lift PCC M20A20 grade at right side D/s flard out wall from sec 1-1 to 4-4 with RL 157.00m to 157.60m in the presence of Dept JE, site engineer of PMC and agency forman . The slump test value is 72mm on 05.02.2026
91/100
Instream Storage Structure, Gudvella
• Today DTL visited the ISS Gudvella site along with other experts. During the visit the Department JE, PMC site engineers and the agency representative were present.
1. Inspected and reviewed the overall site condition.
2. Instructed the agency personnel to expedite the work and ensure completion within the EOT period on 05.02.2026
92/100
Instream Storage Structure, Gudvella
• Today DTL visited the ISS Gudvella site along with other experts. During the visit the Department JE, PMC site engineers and the agency representative were present.
1. Inspected and reviewed the overall site condition.
2. Instructed the agency personnel to expedite the work and ensure completion within the EOT period on 05.02.2026
93/100
Instream Storage Structure, Gudvella
Trestles fitup and assembly work under progress. Measured all dimensions as per approved drawing. Inspected welding rods as per specification. Instructed to technicians to remove the slag after completion of the welding on 05.02.2026
94/100
Instream Storage Structure, Gudvella
Trestles fitup and assembly work under progress. Measured all dimensions as per approved drawing. Inspected welding rods as per specification. Instructed to technicians to remove the slag after completion of the welding on 05.02.2026
95/100
Instream Storage Structure, Gudvella
Roller track and guide erection work under progress in Barrage bay no-6 .All dimensions were measured as per approved drawing. Sill beam installation work completed on 05.02.2026
96/100
Instream Storage Structure, Gudvella
Roller track and guide erection work under progress in Barrage bay no-6 .All dimensions were measured as per approved drawing. Sill beam installation work completed on 05.02.2026
97/100
Instream Storage Structure, Gudvella
Sill beam installation work at barrage bay no 9 is under progress on 05.02.2026
98/100
Instream Storage Structure, Gudvella
Sill beam installation work at barrage bay no 9 is under progress on 05.02.2026
99/100
Instream Storage Structure, Gudvella
Roller track and guide installation work at barrage bay no 6 is under progress on 05.02.2026
100/100
Instream Storage Structure, Gudvella
Roller track and guide installation work at barrage bay no 6 is under progress on 05.02.2026
❮
❯