1/100
Instream Storage Structure, Gudvella
Cast of concrete 2nd lift RCC M25A20 grade at right side u/s flard out wall cutoff from RL 144.70m to 145.30m is under progress in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 70mm on 22.12.2025
2/100
Instream Storage Structure, Gudvella
Cast of concrete 2nd lift RCC M25A20 grade at right side u/s flard out wall cutoff from RL 144.70m to 145.30m is under progress in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 70mm on 22.12.2025
3/100
Instream Storage Structure, Gudvella
Cast of concrete 16th lift PCC M20A20 grade at left side U/s flared out wall RL 157.60m to 158.20m is under progress in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 69mm on 22.12.2025
4/100
Instream Storage Structure, Gudvella
Cast of concrete 16th lift PCC M20A20 grade at left side U/s flared out wall RL 157.60m to 158.20m is under progress in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 69mm on 22.12.2025
5/100
Instream Storage Structure, Gudvella
Cast of concrete 14th lift PCC M20A20 grade at left side D/s flard out wall from sec 1-1 to 4-4 with RL 156.40m to 157.00m is under progress in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 72mm on 22.12.2025
6/100
Instream Storage Structure, Gudvella
Cast of concrete 14th lift PCC M20A20 grade at left side D/s flard out wall from sec 1-1 to 4-4 with RL 156.40m to 157.00m is under progress in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 72mm on 22.12.2025
7/100
Instream Storage Structure, Gudvella
Reinforcement & shuttering at right side Abutment A2 for 3rd lift rcc work underprogress on 22.12.2025
8/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 1no. CC block of size 5.1x1.5x0.6m at U/S right flared out wall from sec.4-4 to sec. 5-5 for 5th lift upto RL-238.80m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 73mm on 22.12.2025
9/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 1no. CC block of size 5.1x1.5x0.6m at U/S right flared out wall from sec.4-4 to sec. 5-5 for 5th lift upto RL-238.80m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 73mm on 22.12.2025
10/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at U/S right flared out wall from sec.1-1 to sec.2-2 for 11th lift from RL-240.00m to RL-240.60m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 73mm on 22.12.2025
11/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at U/S right flared out wall from sec.1-1 to sec.2-2 for 11th lift from RL-240.00m to RL-240.60m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 73mm on 22.12.2025
12/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.4 of bay no.5 for 2nd lift is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 81mm on 22.12.2025
13/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.4 of bay no.5 for 2nd lift is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 81mm on 22.12.2025
14/100
Instream Storage Structure, Nandagaon
Trestle fitup and welding work under progress on 22.12.2025
15/100
Instream Storage Structure, Kuakhai
Removal of sand and silt from left D/S divide wall raft area.
16/100
Instream Storage Structure, Kuakhai
Reinforcement binding and shuttering in progress at Pier no- 7A ,6 and 5.
17/100
Instream Storage Structure, Kuakhai
Casting of RCC M25A20 in pier no.8 from RL 20.28m to 22.00m is under progress.
18/100
Instream Storage Structure, Kuakhai
Binding of steel reinforcement for the girders in progress.
19/100
Instream Storage Structure, Kuakhai
Casting of CCM30A20 in left side counterfort in progress .
20/100
Instream Storage Structure, Kuakhai
Slump test done at site, slump value is 95mm.
21/100
Instream Storage Structure, Kuakhai
Casting of CC M30A20 at left counterfort (Zone-4) from RL 5.85m to 7.05m in progress.
22/100
Instream Storage Structure, Kuakhai
Mech. Expert, PSS observing the welding of 1st stage embedded plate at gate groove portion.
23/100
Instream Storage Structure, Kuakhai
SDO, Balianta along with PSS Team observing the MS rod binding of counter fort before casting.
24/100
Instream Storage Structure, Kuakhai
Reinforcement binding and side shuttering at left side under sluice (end sill).
25/100
Instream Storage Structure, Kuakhai
Cleaning of sand and silt from Left D/S divide wall raft portion in progress.
26/100
Instream Storage Structure, Kuakhai
Curing of pre-girders in progress.
27/100
Instream Storage Structure, Kuakhai
Welding of 1st stage embedded parts in pier no.6 is under progress.
28/100
Instream Storage Structure, Kuakhai
Shuttering in pier no.2B.
29/100
Instream Storage Structure, Kuakhai
Reinforcement binding in progress at Pier no-5 and 7A.
30/100
Instream Storage Structure, Kuakhai
Ongoing Shuttering work in progress at right U/S divide wall raft.
31/100
Instream Storage Structure, Kuakhai
Left-side counterfort including its stem shutter alignment is under progress.
32/100
Instream Storage Structure, Kuakhai
Slump test done at site, slump value is 95mm.
33/100
Instream Storage Structure, Kuakhai
Divide wall pile cap casting completed & Back filling with sand is under progress.
34/100
Instream Storage Structure, Kuakhai
Casting of RCC M25A20 at pier no.4 from RL 10.55m to 11.85m in progress.
35/100
Instream Storage Structure, Kuakhai
Girder casting in progress.
36/100
Instream Storage Structure, Kuakhai
Curing of girders in progress.
37/100
Instream Storage Structure, Kuakhai
Casting of RCC M35A20 in pre-cast girder (no.32 & 33) for the bridge is under progress.
38/100
Instream Storage Structure, Kuakhai
Pile cap casting is currently under progress at left U/S divide wall.
39/100
Instream Storage Structure, Kuakhai
Casting of RCCM25A20 in pier no.7A (4th lift) from RL 10.55m to 11.95m is completed.
40/100
Instream Storage Structure, Kuakhai
Ongoing casting at Left side upstream divide wall cutoff.
41/100
Instream Storage Structure, Kuakhai
Ongoing side shuttering at left barrage bay piers in progress.
42/100
Instream Storage Structure, Kuakhai
PSS Team observing the ongoing casting of M25A20 at pier no.7A.
43/100
Instream Storage Structure, Kuakhai
Slump test done at site, slump value is 85mm.
44/100
Instream Storage Structure, Kuakhai
Reinforcement binding in progress at right U/S divide wall raft portion.
45/100
Instream Storage Structure, Kuakhai
Reinforcement binding is progress at L/s block pier.
46/100
Instream Storage Structure, Kuakhai
Casting of RCCM25A20 in pier no.7A (4th lift) from RL 10.55m to 11.95m is under progress.
47/100
Instream Storage Structure, Kuakhai
SE, Prachi & SDO, Balianta along with PSS Team checking the reinforcement & shuttering works at pier no.7A for casting.
48/100
Instream Storage Structure, Kuakhai
Welding in progress at pier no.7A.
49/100
Instream Storage Structure, Kuakhai
Curing of piers in progress.
50/100
Instream Storage Structure, Kuakhai
Ongoing Side shuttering at left upstream divide wall cutoff.
51/100
Instream Storage Structure, Kuakhai
Ongoing reinforcement binding for Girders in progress.
52/100
Instream Storage Structure, Kuakhai
Reinforcement binding is progress at right side upstream divide wall raft portion.
53/100
Instream Storage Structure, Kuakhai
Slump test done at site, slump value is 90mm.
54/100
Instream Storage Structure, Kuakhai
Casting of RCC M25A20 in pier no.6 from RL 9.15m to 10.55m in progress.
55/100
Instream Storage Structure, Kuakhai
Ongoing Side shuttering at left side U/S divide wall cutoff.
56/100
Instream Storage Structure, Kuakhai
Reinforcement binding and side shuttering is under progress in pier no.2B, 3,4,5,6,7A at left side barrage bay pier.
57/100
Instream Storage Structure, Kuakhai
Ongoing Reinforcement binding in Pier no.7A.
58/100
Instream Storage Structure, Kuakhai
Reinforcement binding in progress at right U/S divide wall raft portion.
59/100
Instream Storage Structure, Kuakhai
Irrigation expert, PSS observing the ongoing reinforcement binding at left side counterfort.
60/100
Instream Storage Structure, Kuakhai
Side shuttering in progress at left side U/S divide wall cutoff.
61/100
Instream Storage Structure, Kuakhai
Curing of piers in progress.
62/100
Instream Storage Structure, Gochara
U/S coffer dam work is going on..
63/100
Instream Storage Structure, Gochara
View showing flow of river from D/S
64/100
Instream Storage Structure, Budharaja
De-Shuttering Work is in Progress at LHS U/S Flared Out Wall, 12th Lift.
65/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at RHS D/S Flared-Out Wall, 9th Step.
66/100
Instream Storage Structure, Budharaja
Shuttering and Reinforcement Work is in Progress at Staff Quarter Slab.
67/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S
68/100
Instream Storage Structure across river Sapei near village Kinjirma
28days cube test of P-03 05th lift .
69/100
Instream Storage Structure, Kopsinga
ISS-Kopasinga (Span No-27) Installation/Erection activity of Barrage Gate Assembly, Trestle Columns, Hoist bridge Platform and Monorail Columns have been initiated at the ISS- Kopasinga Barrage Project.
70/100
Instream Storage Structure, Kopsinga
ISS-Kopasinga (Span No-27) Installation/Erection activity of Barrage Gate Assembly, Trestle Columns, Hoist bridge Platform and Monorail Columns have been initiated at the ISS- Kopasinga Barrage Project.
71/100
Instream Storage Structure, Kopsinga
RHS Abutment Hoist steel placing
72/100
Instream Storage Structure, Kopsinga
RHS U/S Wing wall Shuttering work
73/100
Instream Storage Structure Across Bheden near village Saida
LHS U/S Flared out wall 3rd lift de-shuttering work is going on .
74/100
Instream Storage Structure Across Bheden near village Saida
Cleaning work progress in LHS under sluice sill beam portion
75/100
Instream Storage Structure Across Bheden near village Saida
Bay no-4 RHS Site Gate Groove Guide alignment work is in progress to the top level of the Pier.
76/100
Instream Storage Structure Across Bheden near village Saida
LHS U/S Flared out wall curing work is going on ..
77/100
Instream Storage Structure, Khirasasan
RHS D/S COUNTERFORT 5TH LIFT SHUTTERING WORK HAS COMPLETED AND READY FOR CONCRETE CASTING.
78/100
Instream Storage Structure, Khirasasan
RHS d/s flank wall 4th lift shuttering work is under progress.
79/100
Instream Storage Structure, Khirasasan
RHS D/s Flared out wall 7th step shuttering work is under progress.
80/100
Instream Storage Structure, Khirasasan
RHS D/s Flared out wall 7th step shuttering work is under progress.
81/100
Instream Storage Structure, Khirasasan
RHS d/s flank wall 4th lift shuttering work is under progress.
82/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S
83/100
Instream Storage Structure, Kudabega
Casting of span 14 stop log service gate groove
84/100
Instream Storage Structure, Kudabega
Slump 85mm of stoplog service gate, span 14
85/100
Instream Storage Structure, Kudabega
Slump 85mmof us flank wall
86/100
Instream Storage Structure, Kudabega
RHS us flank wall 6th lift, slump 85mm
87/100
Instream Storage Structure, Kudabega
Slump 80mm , span 09 of Hand railing post
88/100
Instream Storage Structure, Kudabega
Casting of deck strip Expansion joint pier No 11
89/100
Instream Storage Structure, Kudabega
Slump 85mm of deck strip Expansion joint, pier 11
90/100
Instream Storage Structure, Kudabega
Casting of deck strip Expansion joint of span 12
91/100
Instream Storage Structure, Kudabega
Slump 85mm of Bottom seal Beam, span 12
92/100
Instream Storage Structure, Kudabega
Span 15 deshuttering and shuttering work.
93/100
Instream Storage Structure, Kudabega
Span 17 gate groove deshuttering and shuttering work
94/100
Instream Storage Structure, Kudabega
RHS us wing wall and flank wall shuttering
95/100
UGPL, Left Lower Suktel Canal Division
250mm Dia HDPE pipe jointing work is in progress between J-94 to J-273 (LM-6) at village Bianrpali .
96/100
Instream Storage Structure Across Bheden near village Saida
P-3 to P-4 between mid portion Deck slab staging work is in progress .
97/100
Instream Storage Structure, Gudvella
Cast of concrete 13th lift PCC M20A20 grade at left side D/s flard out wall from sec 1-1 to 4-4 with RL 155.80m to 156.40m is under progress in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 73mm on 21.12.2025
98/100
Instream Storage Structure, Gudvella
Cast of concrete 13th lift PCC M20A20 grade at left side D/s flard out wall from sec 1-1 to 4-4 with RL 155.80m to 156.40m is under progress in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 73mm on 21.12.2025
99/100
Instream Storage Structure, Gudvella
Reinforcement at right side d/s flank wall raft RCC work is under progress on 20.12.2025
100/100
Instream Storage Structure, Gudvella
Roller track and guide installation barrage bay no 4 under progress on 20.12.2025
❮
❯