1/100
Barrage across river Turi & Guntat
Guntat site status.
2/100
Barrage across river Turi & Guntat
Turi site status.
3/100
Instream Storage Structure, Budharaja
The flow level is 208.700 m against the design RL: 206.700, i.e., 2.0 m flood lift.
4/100
Instream Storage Structure, Khirasasan
The flow level is 211.700 m against the design
RL: 210.900, i.e., 0.8 m flood lift.
5/100
Instream Storage Structure, Kopsinga
Cube test iss Kopsingha
6/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. Flow direction is straight. The direction of flow is seen in middle of the river. Now the flow level is 226.500mt against design crest level 225.500 i.e. flood lift 1mt.
7/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-215.900 mtr against design crest level RL- 215.000 mtr .i.e 0.9mtr flood lift .
8/100
UGPL, Right Lower Suktel Canal Division
Visited JE(DoWR) along with PMC team 300mm Dia DI ( k7) pipe laying Gap closing work is in progress At Village Chhtamakhana J-2548 to J-2551.
9/100
UGPL, Right Lower Suktel Canal Division
Instrumentation Cable laying work is in progress at free filtration unit of Pump House.
10/100
UGPL, Right Lower Suktel Canal Division
225mm thickness rubbles filling work is in progress at fire fighting system before grade slab casting in presence of PMC team at Pump House.
11/100
UGPL, Left Lower Suktel Canal Division
Pressure indicating transmitter Instrumentation Cable (1p×1sq.mm) Glanding work is in progress at left Pump House.
12/100
UGPL, Left Lower Suktel Canal Division
DPI (differential pressure switch) , pressure gauge and its isolation valve installation work is in progress in FWLS (force water lubrication system) of VT pumps at left Pump House.
13/100
UGPL, Left Lower Suktel Canal Division
Boundary wall column 2nd lift reinforcement binding work & shuttering work is in progress at left Pump House.
14/100
UGPL, Left Lower Suktel Canal Division
Approach channel front side soil excavation work is in progress at Pump House.
15/100
Instream Storage Structure, Dhanei
Visit of Irrigation Eng. Expert along with Site Engineer to the ISS Site. Inspected the Road bridge kerb parapet
reinforcement and shuttering alignment check.
16/100
Instream Storage Structure, Dhanei
Visit of Irrigation Eng. Expert along with Site Engineer to the ISS Site. Inspected the Road bridge kerb parapet
reinforcement and shuttering alignment check.
17/100
Instream Storage Structure, KansariGanda
Under sluice End seal final layer shutter is in progress. Curing continuing at site.
18/100
Instream Storage Structure, KansariGanda
Under sluice End seal final layer shutter is in progress. Curing continuing at site.
19/100
Instream Storage Structure, KansariGanda
Cube cast at site.
20/100
Instream Storage Structure, Gudvella
Trestle base plate welding work under progress on 04.07.2025
21/100
Instream Storage Structure, KansariGanda
Curing continuing at site.
22/100
Instream Storage Structure, Gudvella
1. Reinforcement at left side u/s wing wall including 2nos of counter fort wall for 6th lift RCC work is under progress.
2. Deshuttering work at left side u/s flank wall including returning wall is under progress on 04.07.2025
23/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site.
24/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert along with Site Engineer to the ISS Site. Inspected the End seal concrete casting.
25/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert along with Site Engineer to the ISS Site. Inspected the End seal concrete casting.
26/100
Instream Storage Structure, Nandagaon
Centring & Shuttering for RCC deck slab at span-2 of under sluice bay, Block-1 is in progress on 04.07.2025
27/100
Instream Storage Structure, Mahulpali
D/S view of ISS Mahulpali on 04.07.2025
28/100
Instream Storage Structure, Mahulpali
U/S view of ISS Mahulpali on 04.07.2025
29/100
Instream Storage Structure, Chhatamakhana
D/S view of the ISS Chhatamakhana on 04.07.2025
30/100
Instream Storage Structure, Chhatamakhana
U/S view of the ISS Chhatamakhana on 04.07.2025
31/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.49/mm2 for 28 days) of Pier No-30, 4th lift and M15A40(Strength is 20.33/mm2 for 28 days) of Flank wall Raft and M25A20 (Strength is 30.31/mm2 for 28 days) of Pier No-11, 3rd lift has done in presence of Client & PSS team.
32/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 80mm) of Girder No-20 done in presence of Client & PSS Team.
33/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Girder No-20 is under progress in presence of Client & PSS Team.
34/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85mm) of Abutment wall (A2), 10th lift at Block No-5 done in presence of Client & PSS Team.
35/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Abutment wall (A2), 10th lift at Block No-5 is under progress in presence of Client & PSS Team.
36/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85mm) of Girder No-19 done in presence of Client & PSS Team.
37/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Girder No-19 is under progress in presence of Client & PSS Team.
38/100
Instream Storage Structure, Hamirpur
Full depth wave plate stiffener welding work is in progress of under sluice Gate No-6.
39/100
Instream Storage Structure, Hamirpur
Hoist bridge platform welding work is in progress.
40/100
Instream Storage Structure, Hamirpur
Hoist bridge platform fixing work is in progress.
41/100
Instream Storage Structure, Hamirpur
Shuttering of Girder No-20, 21 &22 is under progress.
42/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Girder No-25 & 26 is under progress.
43/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Girder No-23 & 24 is under progress.
44/100
Instream Storage Structure, Jharbeda
Inflow of Storm water in the River at ISS Jharbeda.
45/100
Instream Storage Structure, Sirigida
Present status in river.
46/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-216.200 mtr against design crest level RL- 215.000 mtr .i.e 1.2mtr flood lift .
47/100
UGPL, Left Lower Suktel Canal Division
33kV Transmission line conductor stringing work is in progress in presence of E.M Expect of PMC & MEIL representative near Sadeipali GSS(IDCO land) used insulated conductor for 220kv line crossing.
48/100
UGPL, Left Lower Suktel Canal Division
Conductor stringing work is in progress near village Sadeipali grid.
49/100
UGPL, Left Lower Suktel Canal Division
Visiting by DoWR SDO and EM expert of PMC with team discuss with MEIL about on going work progress at left Pump House.
50/100
UGPL, Left Lower Suktel Canal Division
Instrumentation Cable laying and dressing work is in progress at Cable cellar room left pump house.
51/100
Instream Storage Structure, Kushabhadra
Left under sluice Deck slab casting work is completed.
52/100
Instream Storage Structure, Kuakhai
Casting of RCC M30A20 in R/s under sluice raft (Zone-1 & 2, final layer) in progress.
53/100
Instream Storage Structure, Kuakhai
Right side undersluice sill beam area 1st stage embedded parts and dowal bar welding work completed and the area is ready to receive concrete.
54/100
Instream Storage Structure, Kuakhai
TL, PMU inspecting the ongoing concreting work at R/S Undersluice.
55/100
Instream Storage Structure, Kuakhai
Casting of RCC M30A20 is progress at right side undersluice raft.
56/100
Instream Storage Structure, Kuakhai
PSS Team observing the ongoing raft casting work at right side under sluice portion.
57/100
Instream Storage Structure, Gudvella
Under sluice gate welding work under progress on 03.07.2025
58/100
Instream Storage Structure, Gudvella
U/S View Of ISS Gudvella on 03.07.2025
59/100
Instream Storage Structure, Gudvella
D/S View Of ISS Gudvella on 03.07.2025
60/100
Instream Storage Structure, Nandagaon
M25 A20 grade concrete casting on dated 05/06/25 & tested on dated 03/07/25(28 days) the Avg. value of strength of cube is 29.33N/ mm2 checked in presence of SE, QAD, BWIP and his SDO, & SDO of ISS Nandagaon and DTL, QC expert, sr site engineer of PMC and site engineer of agency on 03.07.2025
61/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade at RCC deck slab of Span-1 of under sluice bay-1 of block-1 is in progress through concrete pump in presence of SE,QAD, Bhawanipatna,DTL,Tel basin, Bhawanipatna,AEE,QAD,SDO,Kid, QAC Expert,Sr. Site Engineer of PMC, PM, EPC agency, Site engineers of PMC & EPC agency. Slump achieved 81mm on 03.07.2025
62/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade at RCC deck slab of Span-1 of under sluice bay-1 of block-1 is in progress through concrete pump in presence of SE,QAD, Bhawanipatna,DTL,Tel basin, Bhawanipatna,AEE,QAD,SDO,Kid, QAC Expert,Sr. Site Engineer of PMC, PM, EPC agency, Site engineers of PMC & EPC agency. Slump achieved 81mm on 03.07.2025
63/100
Instream Storage Structure, Nandagaon
• visit of ISS Nandagaon by SE, QAD, Bhawanipatna,DTL,Tel Basin, Bhawanipatna on dt. 03.07.2025 in presence of AEE, QAD, SDO, ISS Nandagaon, QAC Expert, SHEE, Sr. Site Engineer of PMC, PM of EPC Agency,Site Engineers of PMC and EPC Agency, ISS Nandagaon. Found the area in binding, placing of reinforcements works including shuttering at RCC Deck slab of span-1 of undersluice bay-1 of block-1 are completed as follows : (i)Binding of main n dist. bars at both bottom & top layers including placing of 8mm dia 2-legged stirrups for kerb and fixing of rail posts bars and providing drainage system at both side of slab using 100mm dia MS pipes are completed as per the approved drawings n design. (ii)Clear cover 40mm at bottom and both sides using cover blocks and fixing chairs at clear spans in between main girders are done.
(iii) Rigid and Smooth shuttering and kept space/gap at both end at expansion joints area by fixing of MS angles for providing fixing of joint materials at dirt wall and pier-1 is done. (iv) Area is cleaned using air water pressure and passed by SE, KID, Bhawanipatna and ready to place concrete with RCC M35A20 grade upto RL-247.00m on 03.07.2025
64/100
Instream Storage Structure, Nandagaon
Reinforcement binding, centring & Shuttering for RCC deck slab at Span -1 of under sluice bay, Block-1 is in progress on 03.07.2025
65/100
Instream Storage Structure, Mahulpali
D/S view of ISS Mahulpali on 03.07.2025
66/100
Instream Storage Structure, Mahulpali
U/S view of ISS Mahulpali on 03.07.2025
67/100
Instream Storage Structure, Chhatamakhana
D/S view of the ISS Chhatamakhana on 03.07.2025
68/100
Instream Storage Structure, Chhatamakhana
U/S view of the ISS Chhatamakhana on 03.07.2025
69/100
Instream Storage Structure, Kuakhai
Casting of RCC M25A20 at left side D/S divide wall raft from RL 5.35m to 6.30m in progress.
70/100
Instream Storage Structure, Kuakhai
PSS Team observing the ongoing right side undersluice raft casting.
71/100
Instream Storage Structure, Kuakhai
The Casting is currently ongoing in Zone 1 & 2, including the slope portion of Zone 3 of R/S under sluice raft.
72/100
Instream Storage Structure, Kuakhai
Casting of RCCM30A20 in R/s under sluice raft in progress.
73/100
Instream Storage Structure, Kuakhai
Addl.CE, CIC inspecting the ongoing activities in R/S under sluice raft portion.
74/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
No work at site at ISS Chaudhurygada due to increase in water level in river Mahanadi -04.07.2025
75/100
Instream Storage Structure, Kuakhai
Mechanical Expert, PSS verifying the 1st stage embedded parts in gate groove & stop-log groove (end sill) of right under sluice.
76/100
Integrated Barrage across river Kochila and across river Baitarini
There is no work at site due to incessant rain and flash flood in Baitarani river-04.07.2025
77/100
Instream Storage Structure, Kuakhai
IRR. Expert, PSS inspecting the strengthening of U/S main cofferdam.
78/100
Instream Storage Structure, Kuakhai
Right side under sluice barrage bay sill beam 1st stage embedded parts welding completed.
79/100
Instream Storage Structure, Kuakhai
DTL & Team inspecting the ongoing activities at R/s under sluice.
80/100
Instream Storage Structure, Kushabhadra
Casting of the final layer for the bridge slab is under progress.
81/100
Instream Storage Structure, Kushabhadra
7 days cube test for CC M25A20 and 28 days cube test for CC M25A20 conducted at field laboratory of the ISS.
82/100
Instream Storage Structure, Kushabhadra
Slump value 85mm against Mix design value for M25A20 is 98mm.
83/100
Instream Storage Structure, Kushabhadra
Left under sluice Deck slab casting work in progress.
84/100
Instream Storage Structure, Kushabhadra
Laying of CCM25A20 in Deck slab at left side under sluice in progress.
85/100
Instream Storage Structure, Kushabhadra
Left under sluice Deck slab area is ready to receive CC M25A20 grade concrete.
86/100
Instream Storage Structure, Kushabhadra
Right D/s flank wall shuttering from (RL 14.20m to 15.60m) is in progress.
87/100
Instream Storage Structure, Kushabhadra
7 days cube test for CC M25A20 and 28 days cube test for CC M25A20 conducted at field laboratory of the ISS. Av compressive strength comes as 22.10N/mm2 & 31.97N/mm2 respectively.
88/100
Instream Storage Structure, Kushabhadra
Inspection of reinforcement binding and shuttering of Deck slab in between left Abutment and pier no-1 by PSS Team, OCCL And the Agency.
89/100
Instream Storage Structure, Kushabhadra
Shuttering work is going on at Left under sluice Deck slab portion.
90/100
Instream Storage Structure, Kushabhadra
Right U/s flank wall with return Wall shuttering work in progress.
91/100
Instream Storage Structure, Kushabhadra
7 days cube test for CC M20A20 and 28 days cube test for CC M25A20 conducted at field laboratory of the ISS. Av compressive strength comes as 20.06 N/mm2 & 31.95 N/mm2 respectively.
92/100
Instream Storage Structure, Kushabhadra
Slump value 82 mm against Mix design value for M20A20 is 90mm.
93/100
Instream Storage Structure, Kushabhadra
Left D/s flared out wall balance excavation work in progress.
94/100
Instream Storage Structure, Kushabhadra
Left D/s flank wall and return wall shuttering work in progress.
95/100
Instream Storage Structure, Kushabhadra
Ongoing concrete laying in Right D/S flared out wall.
96/100
Instream Storage Structure, Sirigida
Present status in river.
97/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85mm) of Girder No-18 done in presence of Client & PSS Team.
98/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Girder No-18 is under progress in presence of Client & PSS Team.
99/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.67/mm2 for 28 days) of Pier No-10, 1st lift and (Strength is 30.17/mm2 for 28 days) of Pier No-25, 12th lift has done in presence of Client & PSS team.
100/100
Instream Storage Structure, Hamirpur
Observed of Sieve analysis of Coarse & Fine aggregate in presence of Client & PSS team along with EPC agency.
❮
❯