1/100
Instream Storage Structure, Gudvella
Erection work of stoplog gate is under progress at mechanical yard on 03.07.2026
2/100
Instream Storage Structure, Gudvella
Plastering work is under progress at building area on 03.07.2026
3/100
Instream Storage Structure, Gudvella
Welding and grinding work is under progress at site on 03.07.2026
4/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 03.07.2026
5/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 03.07.2026
6/100
Instream Storage Structure, Nandagaon
Monorail girder erection work under progress on Barrage bay gate no 1 on 03.07.2026
7/100
Instream Storage Structure, Nandagaon
• Site visit of ISS Nandagaon by CME, QAC Expert, HME and Sr. Site Engineer of PMC today on dt.03.07.2026 in presence of PM of EPC Agency,all Site Engineers of PMC and EPC Agency. Observations/Suggestions are made during visit as follows:
1. Casting of precast RCC bridge rails is in progress as per approved design n drawings.
2. Shuttering works at D/S right Flared out wall for 9th lift is completed and concrete shall be placed in 2nd half after cleaning the surfaces and finishing smooth & rigid shuttering works on submission of RFI.
3. @ PM of EPC Agency is suggested for continuous curing if precast RCC bridge rails using gunny bags. He is suggested also to continue curing at office building foundation base slab upto curing period.
4. Inspected the mechanical works by HME:
i) 4 nos. Service Gates erected kept on rest through temporary arrangements ,ie. one. at Left Under Sluice & 3nos. at barrage bay No.- 2.
(ii) Erection of the hoist bridge done at four bays , three at barrage bay and one at Under sluce bays on 03.07.2026
8/100
Instream Storage Structure, Nandagaon
M20 A20 grade concrete casting on dated 26/6/26 at D/S right flared out wall CC block & testing on dated 03/07/26 (7day) in presence of CME, QC exp. HME, Sr site engineering and site engineering of PMC and site engineering of EPC agency the ave. Valve of cube strength is 30.81N/mm2 on 03.07.2026
9/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for Railing is in progress on 03.07.2026
10/100
Instream Storage Structure, Nandagaon
Shuttering for CC block at D/S right flared out wall is in progress on 03.07.2026
11/100
Instream Storage Structure, Nandagaon
Hoist bridge and gate erection work under progress on pier 3 Barrage bay gate no 2 on 03.07.2026
12/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of U/S Flank wall, 7th lift at Block No-5 done in presence of Client & PSS Team.
13/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of U/S Flank wall, 7th lift at Block No-5 is under progress in presence of Client & PSS Team.
14/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-43 done in presence of Client & PSS Team.
15/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-43 is under progress in presence of Client & PSS Team.
16/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.33/mm2 for 07 days) of Pier No-3, 12th lift has done in presence of Client & PSS team.
17/100
Instream Storage Structure, Hamirpur
C.D.U assembly No-23 base frame fit -up work is in progress.
18/100
Instream Storage Structure, Hamirpur
Gantry girder's 1st stage embedded plate fixing work is in progress.
19/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
20/100
Instream Storage Structure, Hamirpur
Shuttering of Flared out wall at Block No-5 is under progress.
21/100
Instream Storage Structure, Hamirpur
Drive unit assembly fit-up work is in progress.
22/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-26, 15th lift at Block No-4 is under progress.
23/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-8 welding work is in progress.
24/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.1m.
25/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of LHS D/S Divide wall, 3rd lift done in presence of Client & PSS Team.
26/100
Instream Storage Structure, Khalpal
Concreting M25A20 of LHS D/S Divide wall, 3rd lift is under progress in presence of Client & PSS Team.
27/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 90 mm) of LHS Double pier No-18 (Starter) done in presence of Client & PSS Team.
28/100
Instream Storage Structure, Khalpal
Concreting M25A20 of LHS Double pier No-18 (Starter) is under progress in presence of Client & PSS Team.
29/100
Instream Storage Structure, Khalpal
Shuttering of LHS D/S Divide wall, 3rd lift is under progress.
30/100
Instream Storage Structure, Khalpal
Binding of reinforcement for Barrage Bay No-2 Gravity floor is under progress.
31/100
Instream Storage Structure, Hamirpur
Slump testing M15A40 (Value 40 mm) of U/S Flared out wall, 10th lift at Block No-5 done in presence of Client & PSS Team.
32/100
Instream Storage Structure, Hamirpur
Concreting M15A40 of U/S Flared out wall, 10th lift at Block No-5 is under progress in presence of Client & PSS Team.
33/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Gantry Girder No-42 done in presence of Client & PSS Team.
34/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-42 is under progress in presence of Client & PSS Team.
35/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.78/mm2 for 07 days) of Pier No-1, 13th lift and M15A40 (Strength is 20.69/mm2 for 28 days) of Flared out wall PCC and (Strength is 13.93/mm2 for 07 days) of Flank wall Raft PCC has done in presence of Client & PSS team.
36/100
Instream Storage Structure, Hamirpur
C.D.U frame welding work is in progress.
37/100
Instream Storage Structure, Hamirpur
Column/Trestle welding work is in progress.
38/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
39/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Flared out wall at Block No-5 is under progress.
40/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall at Block No-5 is under progress.
41/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-18, 16th lift at Block No-3 is under progress.
42/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for LHS U/S Divide wall, 4th lift is under progress
43/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering & Binding of reinforcement for RHS D/S Counerfort & Abutment wall, 4th lift is under progress.
44/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.3m.
45/100
Instream Storage Structure, Budharaja
CE & BM Mahanadi Basin inspected ISS Budharaja.ACE canal Circle Burla, SE SID Sambalpur & PMC team were present.Instructed to complete the ancillary works at the earliest.
46/100
Instream Storage Structure, Budharaja
shuttering work is in progress at LHS D/S Flared-out Wall, 15th Step. RL: 218.400 to 219.000.
47/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S of river.
48/100
Instream Storage Structure, Budharaja
Staff Quarter plastering work is in Progress.
49/100
Instream Storage Structure, Budharaja
De-shuttering work is in progress at LHS D/S Flared-out Wall, 14th Step. RL: 217.800 to 218.400.
50/100
Instream Storage Structure, Budharaja
View showing flow of river from U/S of river.
51/100
Instream Storage Structure, Budharaja
Staff Quarter plastering work is in Progress.
52/100
Instream Storage Structure, Budharaja
shuttering work is in progress at LHS D/S Flared-out Wall, 13th Step. RL: 217.200 to 217.800.
53/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S of river.
54/100
Instream Storage Structure, Gochara
CE & BM Mahanadi Basin inspected ISS Gochhra.ACE canal Circle Burla, SE SID Sambalpur & PMC team were present.Instructed to complete the ancillary works at the earliest.
55/100
Instream Storage Structure, Gochara
View showing flow of river from U/S of river.
56/100
Instream Storage Structure, Gochara
View showing flow of river from D/S of river.
57/100
Instream Storage Structure, Gochara
Staff quarter 1st floor out side brick wall work in progress...
58/100
Instream Storage Structure, Gochara
View showing flow of river from U/S of river.
59/100
Instream Storage Structure, Gochara
View showing flow of river from D/S of river.
60/100
Instream Storage Structure, Gochara
Staff quarter 1st floor out side brick wall work in progress...
61/100
Instream Storage Structure, Gochara
View showing flow of river from U/S of river.
62/100
Instream Storage Structure, Gochara
View showing flow of river from D/S of river.
63/100
Instream Storage Structure, Khalpal
Shuttering of LHS D/S Divide wall, 3rd lift is under progress.
64/100
Instream Storage Structure, Khalpal
Shuttering of LHS Pier No-18 (Starter) is under progress.
65/100
Instream Storage Structure, Khalpal
Binding of reinforcement for Barrage Bay No-2 Gravity floor is under progress.
66/100
Instream Storage Structure, Gudvella
Brick work at building area is under progress at site on 02.07.2026
67/100
Instream Storage Structure, Gudvella
Welding and grinding work is under progress at site on 02.07.2026
68/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 02.07.2026
69/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 02.07.2026
70/100
Instream Storage Structure, Nandagaon
Shuttering for CC block at D/S right flared out wall is in progress on 02.07.2026
71/100
Instream Storage Structure, Nandagaon
Barrage bay gate no 1 Hoist bridge and gate erection work under progress on 02.07.2026
72/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
73/100
Instream Storage Structure, Khalpal
Testing of Compressive M20A20 (Strength is 20.19/mm2 for 07 days) of Barrage Bay No-2 Gravity floor and M25A20 (Strength is23.95/mm2 for 07 days) of Pier No-15 (Starter) has done in presence of Client & PSS team.
74/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for LHS U/S Divide wall, 4th lift is under progress.
75/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering & Binding of reinforcement for RHS D/S Counerfort & Abutment wall, 4th lift is under progress.
76/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.5m.
77/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.01/mm2 for 28 days) of Pier No-1, 10th lift and (Strength is 30.88/mm2 for 28 days) of Flank wall Cut-off, 1st lift has done in presence of Client & PSS team.
78/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
79/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Flank wall, 6th lift at Block No-5 is under progress.
80/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flared out wall at Block No-5 is under progress.
81/100
Instream Storage Structure, Hamirpur
Chequered plate fixing work is in progress of hoist bridge platform
82/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-23, 15th lift at Block No-4 is under progress.
83/100
Instream Storage Structure, Khalpal
Binding of reinforcement for LHS D/S Divide wall, 3rd lift is under progress.
84/100
Instream Storage Structure, Khalpal
Testing of Compressive M25A20 (Strength is 35.72/mm2 for 28 days) of D/S Panel No-10 has done in presence of Client & PSS team.
85/100
UGPL, Left Lower Suktel Canal Division
33KV Transmission line LSP Double Pole - 66 (800Amp) isolator installation work is in progress near village Ghungi.
86/100
Instream Storage Structure, Gudvella
Welding and grinding work is under progress at mechanical yard on 01.07.2026
87/100
Instream Storage Structure, Gudvella
Plastering work is under progress at building area on 01.07.2026
88/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 01.07.2026
89/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 01.07.2026
90/100
Instream Storage Structure, Nandagaon
Monorail walkway erection work under progress on Undersluice gate 1&2 on 01.07.2026
91/100
Instream Storage Structure, Nandagaon
Undersluice gate no 2 Hoist bridge and gate erection work under progress on 01.07.2026
92/100
Instream Storage Structure, Nandagaon
Undersluice gate no 1 erection work under progress on 01.07.2026
93/100
Instream Storage Structure, Nandagaon
Shuttering for CC block at D/S right flared out wall is in progress on 01.07.2026
94/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI to HDPE pipe connection at J-454, RM -10, near village Budelbahali in presence of PMC team.
95/100
UGPL, Right Lower Suktel Canal Division
Internal drain bottom portion grading work is in progress in front of PLC room at Pump House in presence of PMC team.
96/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of D/S Flank wall Raft at Block No-1 done in presence of Client & PSS Team.
97/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flank wall Raft at Block No-1 is under progress in presence of Client & PSS Team.
98/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.06/mm2 for 28 days) of Pier No-3, 9th lift and (Strength is 30.94/mm2 for 28 days) of Flared out wall Raft and M15A40 (Strength is 20.35/mm2 for 28 days) of Flared out wall PCC and M30A20 (Strength is 37.78/mm2 for 28 days) of Groove 2nd stage, 3rd lift (Bay No-28) has done in presence of Client & PSS team.
99/100
Instream Storage Structure, Gudvella
• Today, the Irrigation Expert Sir and Quality Control Expert Sir from PMC visited ISS Gudvella. During their visit, the Department JE, PMC Site Engineer and Agency Engineers were present.
1. They inspected the overall site conditions and instructed the agency to start the electrical works immediately and complete them at the earliest without any delay.
2. They also directed the agency to expedite the erection of the stoplog gate so that the dry test can be conducted at the earliest on 30.06.2026
100/100
Instream Storage Structure, Gudvella
• Today, the Irrigation Expert Sir and Quality Control Expert Sir from PMC visited ISS Gudvella. During their visit, the Department JE, PMC Site Engineer and Agency Engineers were present.
1. They inspected the overall site conditions and instructed the agency to start the electrical works immediately and complete them at the earliest without any delay.
2. They also directed the agency to expedite the erection of the stoplog gate so that the dry test can be conducted at the earliest on 30.06.2026
❮
❯