1/100
UGPL, Right Lower Suktel Canal Division
1HA Outlet Pipe extension work is in progress of OCS no- 0201211-C02A at village Sindurbahal visited by DoWR SE & SDO, PMC team along with L&T personnel.
2/100
UGPL, Right Lower Suktel Canal Division
OCS erection work is in progress of 0213094 C06A at village Randa.
3/100
UGPL, Right Lower Suktel Canal Division
Joint verification is in progress of OCS No. 0201219-CO6A 4000 HA at village Kutumbtola village is in progress in presence of DOWR JE, PMC team and EPC staff.
4/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE pipe line Tee (75 X 125 ×75)mm connection at LO 199, LM -10, near village Jharmunda in presence of PMC team.
5/100
Instream Storage Structure, Gudvella
Floor tiles fitting under progress at control room building on 17.06.2026
6/100
Instream Storage Structure, Gudvella
Placement of GSB for approach road is under progress at site on 17.06.2026
7/100
Instream Storage Structure, Gudvella
Outside plastering is under progress at control room building on 17.06.2026
8/100
Instream Storage Structure, Gudvella
Stone pitching work at u/s side is under progress at site on 17.06.2026
9/100
Instream Storage Structure, Gudvella
Mechanical work is under progress at site on 17.06.2026
10/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 17.06.2026
11/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 17.06.2026
12/100
Instream Storage Structure, KansariGanda
Slump cone test conducted in progress.
13/100
Instream Storage Structure, KansariGanda
The first Girder placement IN PROGRESS
14/100
Instream Storage Structure, KansariGanda
The first Girder placement IN PROGRESS
15/100
Instream Storage Structure, Gudvella
Approach road construction is under progress at site on 16.06.2026
16/100
Instream Storage Structure, Gudvella
Placement of GSB for approach road is under progress at site on 16.06.2026
17/100
Instream Storage Structure, Gudvella
Outside plastering is under progress at control room building on 16.06.2026
18/100
Instream Storage Structure, Gudvella
Stone pitching work at u/s side is under progress at site on 16.06.2026
19/100
Instream Storage Structure, Gudvella
Mechanical work is under progress at site on 16.06.2026
20/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 16.06.2026
21/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 16.06.2026
22/100
Instream Storage Structure, Nandagaon
Witnessed the material testing of IS 2062 material. Tensile test, Bend test and Material composition tests were conducted at NABL Laboratory Balanagar Hyderabad on 17.06.2026
23/100
Instream Storage Structure, Nandagaon
Witnessed the material testing of IS 2062 material. Tensile test, Bend test and Material composition tests were conducted at NABL Laboratory Balanagar Hyderabad on 17.06.2026
24/100
Instream Storage Structure, Nandagaon
Witnessed the material testing of IS 2062 material. Tensile test, Bend test and Material composition tests were conducted at NABL Laboratory Balanagar Hyderabad on 17.06.2026
25/100
Instream Storage Structure, Nandagaon
De-Shuttering & Shuttering for 2nd stage concrete is in progress at pier no. 13&A2 on 17.06.2026
26/100
Instream Storage Structure, Nandagaon
There is no erection and painting work in progress at the site today due to labour issues on 17.06.2026
27/100
Instream Storage Structure, Nandagaon
River flood water reached at site U/S view on 17.06.2026
28/100
Instream Storage Structure, Nandagaon
De-Shuttering & Shuttering for CC block is in progress at D/S right flared out wall on 17.06.2026
29/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress at right abutment on 17.06.2026
30/100
Instream Storage Structure, Nandagaon
Shuttering for basement slab of office building is in progress on 17.06.2026
31/100
Instream Storage Structure, Nandagaon
• Today I inspected mechanical equipment as per approved drawing at Vasudeva Engineering Technics Hyderabad. The following components were inspected.
1. Gearbox frame details
2. Axle&shafts
3. Gears, pinion and Bushes
4. Ropedrum details
5. Central drive unit
6. position indicator panel details
7. Gearbox
8. Motors on 16.06.2026
32/100
Instream Storage Structure, Nandagaon
• Today I inspected mechanical equipment as per approved drawing at Vasudeva Engineering Technics Hyderabad. The following components were inspected.
1. Gearbox frame details
2. Axle&shafts
3. Gears, pinion and Bushes
4. Ropedrum details
5. Central drive unit
6. position indicator panel details
7. Gearbox
8. Motors on 16.06.2026
33/100
Instream Storage Structure, Nandagaon
• Today I inspected mechanical equipment as per approved drawing at Vasudeva Engineering Technics Hyderabad. The following components were inspected.
1. Gearbox frame details
2. Axle&shafts
3. Gears, pinion and Bushes
4. Ropedrum details
5. Central drive unit
6. position indicator panel details
7. Gearbox
8. Motors on 16.06.2026
34/100
Instream Storage Structure, Nandagaon
• Today I inspected mechanical equipment as per approved drawing at Vasudeva Engineering Technics Hyderabad. The following components were inspected.
1. Gearbox frame details
2. Axle&shafts
3. Gears, pinion and Bushes
4. Ropedrum details
5. Central drive unit
6. position indicator panel details
7. Gearbox
8. Motors on 16.06.2026
35/100
Instream Storage Structure, Nandagaon
• Today I inspected mechanical equipment as per approved drawing at Vasudeva Engineering Technics Hyderabad. The following components were inspected.
1. Gearbox frame details
2. Axle&shafts
3. Gears, pinion and Bushes
4. Ropedrum details
5. Central drive unit
6. position indicator panel details
7. Gearbox
8. Motors on 16.06.2026
36/100
Instream Storage Structure, Nandagaon
• Today I inspected mechanical equipment as per approved drawing at Vasudeva Engineering Technics Hyderabad. The following components were inspected.
1. Gearbox frame details
2. Axle&shafts
3. Gears, pinion and Bushes
4. Ropedrum details
5. Central drive unit
6. position indicator panel details
7. Gearbox
8. Motors on 16.06.2026
37/100
Instream Storage Structure, Nandagaon
• Today I inspected mechanical equipment as per approved drawing at Vasudeva Engineering Technics Hyderabad. The following components were inspected.
1. Gearbox frame details
2. Axle&shafts
3. Gears, pinion and Bushes
4. Ropedrum details
5. Central drive unit
6. position indicator panel details
7. Gearbox
8. Motors on 16.06.2026
38/100
Instream Storage Structure, Nandagaon
• Today I inspected mechanical equipment as per approved drawing at Vasudeva Engineering Technics Hyderabad. The following components were inspected.
1. Gearbox frame details
2. Axle&shafts
3. Gears, pinion and Bushes
4. Ropedrum details
5. Central drive unit
6. position indicator panel details
7. Gearbox
8. Motors on 16.06.2026
39/100
Instream Storage Structure, Nandagaon
Concrete casting with M20A20 grade for CC block at D/S right flared out wall is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 84mm on 16.06.2026
40/100
Instream Storage Structure, Nandagaon
Concrete casting with M20A20 grade for CC block at D/S right flared out wall is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 84mm on 16.06.2026
41/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no. 13&A2 is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 88mm on 16.06.2026
42/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no. 13&A2 is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 88mm on 16.06.2026
43/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at left abutment U/S side upto RL-247.00m is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 86mm on 16.06.2026
44/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at left abutment U/S side upto RL-247.00m is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 86mm on 16.06.2026
45/100
Instream Storage Structure, Nandagaon
• 3.The casting of the CC block at the following area has been checked in the presence of PM, EPC agency, Site Engineers of PMC & EPC Agency:
(i) Shuttering for CC block at D/S right Flared out wall of 37.50m length & 0.6m ht. from RL-240.00m to RL-240.60m is completed.
(ii). Filling of inverted filter materials covering with LDPE paper at adjacent to each CC block in earth side are done before placement.
(iii) Application of 2 coat bitumen paint at cj's concrete surface is done.
(iv). Area is ready and passed by SE KID, Bh. Patna to place concrete with PCC M20A20 grade on 16.06.2026
46/100
Instream Storage Structure, Nandagaon
• 2.Fixing & fittings and alignment of 2nd. stage embedded parts and numbers of dowel bars provided as per approved drawing at roller tracks of both stoplog & service gate grooves at bay no.14 of pier no.13 & right abutment 6th lift have been checked and found correct by HM Expert of PMC during his site visit on dt.01.06.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for M35A20 grade on 16.06.2026
47/100
Instream Storage Structure, Nandagaon
• 1.Checked the area of left abutment with following activities in presence of PM, EPC agency, Site Engineers of PMC & Site Engineer of EPC agency:-
(i).Checked the reinforcement in binding, tying n spacing of both vertical main & horiz. dist. bars of left abutment from RL-246.40m to RL-247.00m completed.
(ii).Rigid n smooth shuttering with 75mm clear cover using cover blocks of 75mm are done.
(iii).The concrete surface is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with RCC M25A20 grade on 16.06.2026
48/100
Instream Storage Structure, Nandagaon
De-Shuttering & Shuttering for 2nd stage concrete is in progress at pier no.13 & A2 on 16.06.2026
49/100
Instream Storage Structure, Nandagaon
Shuttering for basement slab of office building is in progress on 16.06.2026
50/100
Instream Storage Structure, Nandagaon
Shuttering for CC blocks at D/S right flared out wall on 16.06.2026
51/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-38 done in presence of Client & PSS Team.
52/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-38 is under progress in presence of Client & PSS Team.
53/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.41/mm2 for 28 days) of Pier No-27 & 28 pedestal and (M30A20 (Strength is 37.33/mm2 for 28 days) of Groove 2nd stage, 6th & 3rd lift (Bay No-9) and M15A40 (Strength is 13.18/mm2 for 07 days) of U/S Flared out wall at Block No-1 (PCC) has done in presence of Client & PSS team.
54/100
Instream Storage Structure, Hamirpur
R.D.U assembly set No-19 gear Box fixing work is in progress.
55/100
Instream Storage Structure, Hamirpur
Gantry Girder fixing is in progress in (Bay No-8).
56/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Deck slab (Bay No-10) is under progress.
57/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
58/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-3, 10th lift is under progress.
59/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-2, 10th lift is under progress.
60/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-4 & 5 is under progress.
61/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for U/S Flank wall at Block No-1 is under progress.
62/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Abutment (A1), 11th lift at Block No-1 is under progress.
63/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-2, 10th lift is under progress.
64/100
Instream Storage Structure, Jharbeda
Slump testing M25A20 (Value 90 mm) of Pier No-7 to Pier No-8 U/S Wearing coat done in presence of Client & PSS Team.
65/100
Instream Storage Structure, Jharbeda
Concreting M25A20 of Pier No-7 to Pier No-8 U/S Wearing coat is under progress in presence of Client & PSS Team.
66/100
Instream Storage Structure, Jharbeda
Slump testing M25A20 (Value 80 mm) of Pier No-7, pier Cap done in presence of Client & PSS Team.
67/100
Instream Storage Structure, Jharbeda
Concreting M25A20 of Pier No-7, pier Cap is under progress in presence of Client & PSS Team.
68/100
Instream Storage Structure, Jharbeda
Shuttering of (D2) Middle portion pier, 2nd lift is under progress.
69/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 85 mm) of Barrage Bay No-2 Gravity floor done in presence of Client & PSS Team.
70/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Barrage Bay No-2 Gravity floor is under progress in presence of Client & PSS Team.
71/100
Instream Storage Structure, Khalpal
Shuttering & Binding of reinforcement for Pier No-12 is under progress.
72/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 90 mm) of RHS D/S Counterfort & Wing wall, 2nd lift done in presence of Client & PSS Team.
73/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of RHS D/S Counterfort & Wing wall, 2nd lift is under progress in presence of Client & PSS Team.
74/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for LHS Barrage Bay No-3 (Deck slab) is under progress.
75/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of RHS D/S counter fort & wing wall 2nd lift is under progress.
76/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Abutment (A1), 10th lift at Block No-1 done in presence of Client & PSS Team.
77/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Abutment (A1), 10th lift at Block No-1 is under progress in presence of Client & PSS Team.
78/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-1, 11th lift done in presence of Client & PSS Team.
79/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-1, 11th lift is under progress in presence of Client & PSS Team.
80/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Deck slab is under progress.
81/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Pier No-4, 7th lift is under progress.
82/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-3, 10th lift is under progress.
83/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Abutment (A1), 8th lift at Block No-1 is under progress.
84/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-2, 10th lift is under progress.
85/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 85 mm) of Barrage Bay No-2 Gravity floor done in presence of Client & PSS Team.
86/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Barrage Bay No-2 Gravity floor is under progress in presence of Client & PSS Team.
87/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
88/100
Instream Storage Structure, Khalpal
Shuttering & Binding of reinforcement for Pier No-12 is under progress.
89/100
Instream Storage Structure, Gudvella
The installation of the monorail is currently in progress on 15.06.2026
90/100
Instream Storage Structure, Gudvella
The installation of the monorail is currently in progress on 15.06.2026
91/100
Instream Storage Structure, Gudvella
Outside plastering is under progress at control room building on 15.06.2026
92/100
Instream Storage Structure, Gudvella
Stone packing is under progress at u/s side on 15.06.2026
93/100
Instream Storage Structure, Gudvella
Mechanical work is under progress at site on 15.06.2026
94/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 15.06.2026
95/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 15.06.2026
96/100
Instream Storage Structure, Gudvella
Outside plaster is in progress on 14.06.2026
97/100
Instream Storage Structure, Gudvella
Stone pitching work is in progress at A2 d/s side on 14.06.2026
98/100
Instream Storage Structure, Gudvella
Rubber seal work and cutting for stair case is in progress on 14.06.2026
99/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 14.06.2026
100/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 14.06.2026
❮
❯