PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No- 0213021-C06B near village Chhatapipal in presence of PMC team.
2/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 350mm Dia DI pipeline laying and Gap closing from J -30 to J-413, LM-5 near Village Mandiapadar in presence of PMC team.
3/100
UGPL, Left Lower Suktel Canal Division
HDPE Tee (125 X 75 X 75)mm connection work is in progress at LO-101 LM-5, near village Mandiapadar in presence of PMC team.
4/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE to HDPE pipe Tee connection at RLO-6, LM-18 near village Maharpali in presence of PMC team.
5/100
Instream Storage Structure, Khalpal
Curing of Gravity floor is in progress.
6/100
Instream Storage Structure, Khalpal
Curing of Pier No-23 is in progress.
7/100
Instream Storage Structure, Jharbeda
Slump testing M20A20 (Value 60 mm) of RHS D/S Training wall, 2nd Layer done in presence of Client & PSS Team.
8/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of RHS D/S Training wall, 2nd Layer is under progress in presence of Client & PSS Team.
9/100
Instream Storage Structure, Jharbeda
Slump testing M25A20 (Value 60 mm) of RHS D/S (D2) portion Footing, Final lift done in presence of Client & PSS Team.
10/100
Instream Storage Structure, Jharbeda
Concreting M25A20 of RHS D/S (D2) portion Footing, Final lift is under progress in presence of Client & PSS Team.
11/100
Instream Storage Structure, Jharbeda
Shuttering & Binding of reinforcement for pier No-5 to Pier No-6 U/S Crest portion Wearing Coat is under progress.
12/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-6 is under progress.
13/100
Instream Storage Structure, Jharbeda
Cleaning work is under progress.
14/100
Instream Storage Structure, Jharbeda
Curing of RHS D/S Flank wall is under progress.
15/100
Instream Storage Structure, Jharbeda
Curing of End sill is under progress.
16/100
Instream Storage Structure, Jharbeda
Dewatering work is under progress.
17/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Gantry Girder No-24 done in presence of Client & PSS Team.
18/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-24 is under progress in presence of Client & PSS Team.
19/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.63/mm2 for 07 days) of Pier No-4, 2nd lift and (Strength is 21.33/mm2 for 28 days) of Pier No-21, 14th lift and M15A40 (Strength is 20.63/mm2 for 28 days) of Flared Cut-off wall at Block No-1 (PCC) and M35A20 (Strength is 41.93/mm2 for 28 days) of Cross Girder (Bay No-21) has done in presence of Client & PSS team.
20/100
Instream Storage Structure, Hamirpur
Excavation of D/S at Block No-1 is under progress.
21/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Deck slab (Bay No-16 & 17) is under progress.
22/100
Instream Storage Structure, Hamirpur
Shuttering & binding of reinforcement for Pier No-3, 7th lift is under progress.
23/100
Instream Storage Structure, Hamirpur
Shuttering & binding of reinforcement for Pier No-1, 6th lift is under progress.
24/100
Instream Storage Structure, Hamirpur
Shuttering & binding of reinforcement for Abutment (A1), 7th lift is under progress.
25/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall Raft at Block No-5 is under progress.
26/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
27/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M15A40 of LHS side Drainage pipe (PCC) is under progress in presence of Client & PSS Team.
28/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for Abutment & Counterfort wall is under progress.
29/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for LHS side Raft is under progress.
30/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 80 mm) of LHS U/S Divide wall, 3rd lift done in presence of Client & PSS Team.
31/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS U/S Divide wall, 3rd lift is under progress in presence of Client & PSS Team.
32/100
Instream Storage Structure, Gudvella
Cast of concrete RCC M25A20 grade of kerb from span -08 to span -10 is underprogress in the presence of Dept JE, site engineers of PMC n agency at site. The slump test value is 68mm on 22.04.2026
33/100
Instream Storage Structure, Gudvella
Cast of concrete RCC M25A20 grade of kerb from span -08 to span -10 is underprogress in the presence of Dept JE, site engineers of PMC n agency at site. The slump test value is 68mm on 22.04.2026
34/100
Instream Storage Structure, Gudvella
Casting of precast railing over parapet wall on the deck slab has been commenced with dimensions 1.424 m × 0.13 m × 0.17 m on 22.04.2026
35/100
Instream Storage Structure, Gudvella
Under-sluice gate assembly work is under progress on 22.04.2026
36/100
Instream Storage Structure, Gudvella
Barrage gate installation work is under progress in between P1 to P2 on 22.04.2026
37/100
Instream Storage Structure, Gudvella
Shuttering & centring is under progress for slab & beam at control room building on 22.04.2026
38/100
Instream Storage Structure, Gudvella
Shuttering work is under progress at Posts of deck slab on 22.04.2026
39/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of right kerb at deck slab no.8,9& middle double pier upto RL-247.30m is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 86mm on 22.04.2026
40/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of right kerb at deck slab no.8,9& middle double pier upto RL-247.30m is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 86mm on 22.04.2026
41/100
Instream Storage Structure, Nandagaon
• 1.The area before placement of concrete for right kerb of deck slab has been checked in presence of PM,EPC agency,Site Engineers of PMC & EPC agency as follows: (i)Binding of 8mm dia 2-legged stirrups for left kerb at deck slab of Span- 8,9 & middle double pier and fixing of rail posts bars are completed. (ii) Rigid and smooth shuttering with 40mm clear cover are completed. (iii)Fixing & placing of joint materials at pier-7&8 along the expansion gap is done. (iv) Area is cleaned using air water jet and passed by SE, KID, Bhawanipatna and ready to place concrete with RCC M35A20 grade upto RL-247.30m on 22.04.2026
42/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress on 22.04.2026
43/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for right kerb at deck slab on 22.04.2026
44/100
Instream Storage Structure, Nandagaon
Columns, Trestle, Stiffener painting work under progress on 22.04.2026
45/100
UGPL, Right Lower Suktel Canal Division
Outlet fixing work is in progress of OCS no 0201209- C01B at-Sadeipali in presence of PMC team.
46/100
UGPL, Right Lower Suktel Canal Division
Valve Chamber Pre-cast slab reinforcement binding work is in progress of Pump House.
47/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No- 0213021_C07A near village Chhatapipal in presence of PMC team.
48/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door & angle fixing work is in progress OCS No:-0213112-C02A at village Ainlasari in presence of PMC team.
49/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress of 75mm Dia HDPE pipe line from RO-43 to RO-43B, RM-3, near village Kushmel.
50/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No- 0213012-C04B near village Daspur in presence of PMC team.
51/100
UGPL, Left Lower Suktel Canal Division
HDPE Tee (160 X 125 X 125)mm connection work is in progress at J-121, RM-7, near village Fasad in presence of PMC team.
52/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress of 225mm Dia HDPE pipe node from J-547 to J-120, RM-7 near village Fasad.
53/100
Instream Storage Structure, Gudvella
Casting of precast railing over parapet wall on the deck slab has been commenced with dimensions 1.424 m × 0.13 m × 0.17 m on 21.04.2026
54/100
Instream Storage Structure, Gudvella
Paint work under progress on 21.04.2026
55/100
Instream Storage Structure, Gudvella
Under-sluice gate assembly work under progress on 21.04.2026
56/100
Instream Storage Structure, Gudvella
Trestle and column installation work under progress at A1 and P1 on 21.04.2026
57/100
Instream Storage Structure, Gudvella
Brick work and Shuttering work for slab is in progress at 1st floor building on 21.04.2026
58/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right divide wall for 5th lift upto RL-238.20m is in progress through concrete pump in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 88mm on 21.04.2026
59/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right divide wall for 5th lift upto RL-238.20m is in progress through concrete pump in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 88mm on 21.04.2026
60/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no. 9 upto RL-247.00m is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 87mm on 21.04.2026
61/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no. 9 upto RL-247.00m is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 87mm on 21.04.2026
62/100
Instream Storage Structure, Nandagaon
• 3.The area of placing concrete at U/S right divide wall has been checked before placement in presence of PM of EPC Agency, Site Engineer of PMC & EPC Agency as follows: (i).The reinforcement in binding, tying n spacing of both vertical main & horiz. dist. bar and tie bars for casting of U/S right divide wall for 5th lift from RL-236.80m to RL-238.20m are found completed. (ii).Rigid & smooth shuttering and maintained clear cover of 75mm from main bar to shutter plates are done. (iii).The area is cleaned properly through air water jetting and passed by SE, KID, Bhawanipatna for placing with RCC M25A20 grade on 21.04.2026
63/100
Instream Storage Structure, Nandagaon
• 2(i).Fixing & fittings and alignment of All trestle and columns foundation bolts measurements has been checked at left abutment for Blockout area of 6.8m length and found correct by HM Expert of PMC during his site visit on dt.16.04.2026 in presence of mechanical Site Engineers of PMC and EPC Agency. (ii) Rigid and smooth shuttering for Blockout area with M35A20 grade at pier no.9 from RL-246.30m to RL-247.00m are found completed. (iii).The area is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with M35A20 grade on 21.04.2026
64/100
Instream Storage Structure, Nandagaon
Gate no 14 both stoplog gate and barrage bay gate 2nd stage embedded parts erection work under progress on 21.04.2026
65/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress on 21.04.2026
66/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for left kerb at deck slab on 21.04.2026
67/100
Instream Storage Structure, Nandagaon
Placing of CC blocks is in progress at U/S side on 21.04.2026
68/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering is in progress at U/S right divide wall on 21.04.2026
69/100
Instream Storage Structure, Nandagaon
Trestle painting work under progress on 21.04.2026
70/100
Instream Storage Structure, Nandagaon
Columns sand blasting work is in progress on 21.04.2026
71/100
Instream Storage Structure, Jharbeda
Shuttering & Binding of reinforcement for Pier No-7 is under progress.
72/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-8 is under progress.
73/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-6 is under progress.
74/100
Instream Storage Structure, Jharbeda
Cleaning work is under progress.
75/100
Instream Storage Structure, Jharbeda
Curing of Pier No-8 is under progress.
76/100
Instream Storage Structure, Jharbeda
Curing of End sill is under progress.
77/100
Instream Storage Structure, Jharbeda
Dewatering work is under progress.
78/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Gantry Girder No-23 done in presence of Client & PSS Team.
79/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-23 is under progress in presence of Client & PSS Team.
80/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Deck slab (Bay No-17) at Block No-3 done in presence of Client & PSS Team.
81/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Deck slab (Bay No-17) at Block No-3 is under progress in presence of Client & PSS Team.
82/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of D/S Flared out wall, Raft at Block No-5 done in presence of Client & PSS Team
83/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flared out wall, Raft at Block No-5 is under progress in presence of Client & PSS Team.
84/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.02/mm2 for 28 days) of Pier No-4, 2nd lift and (Strength is 30.94/mm2 for 28 days) of Pier No-13, 13th lift and (Strength is 21.19/mm2 for 07 days) of Pier No-2, 5th lift and M35A20 (Strength is 42.81/mm2 for 28 days) of Gantry Girder No-5 has done in presence of Client & PSS team.
85/100
Instream Storage Structure, Hamirpur
Gantry girder's 1st stage embedded parts welding work is in progress.
86/100
Instream Storage Structure, Hamirpur
L.H.S Pier No-11 Stop-log groove 2nd stage embedded parts Roller track and side guide erection work is in progress at Bay No-10.
87/100
Instream Storage Structure, Hamirpur
Shuttering & binding of reinforcement for Abutment (A1), 5th lift at Block No-1 is under progress.
88/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4, 6th lift is under progress.
89/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-21, 14th lift is under progress.
90/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
91/100
Instream Storage Structure, Khalpal
Curing of Pier No-23 is in progress.
92/100
Instream Storage Structure, Khalpal
Curing of Barrage Bay No-2 at Block No-3 work is in progress.
93/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 80 mm) of LHS under sluice portion End sill (Gravity floor) done in presence of Client & PSS Team.
94/100
Instream Storage Structure, Khalpal
Concreting M20A20 of LHS under sluice portion End sill (Gravity floor) is under progress in presence of Client & PSS Team.
95/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 80 mm) of LHS Wing wall, 4th lift done in presence of Client & PSS Team.
96/100
Instream Storage Structure, Khalpal
Concreting M25A20 of LHS Wing wall, 4th lift is under progress in presence of Client & PSS Team.
97/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 85 mm) of Barrage Bay No-3 Gravity floor done in presence of Client & PSS Team.
98/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Barrage Bay No-3 Gravity floor is under progress in presence of Client & PSS Team.
99/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for Abutment & Counterfort wall is under progress.
100/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for LHS side Raft is under progress.