GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Nandagaon
Stiffener alignment erection work under progress on 10.07.2026
2/100
Instream Storage Structure, Nandagaon
Hoist bridge erection work under progress on Barrage bay gate no 6 on 10.07.2026
3/100
Instream Storage Structure, Nandagaon
Railing fixing is in progress on 10.07.2026
4/100
Instream Storage Structure, Nandagaon
5 numbers of Monorail girder erection work completed on 10.07.2026
5/100
Instream Storage Structure, Nandagaon
Shuttering for CC block at U/S left flared out wall is in progress on 10.07.2026
6/100
Instream Storage Structure, Gudvella
Erection of stoplog gate is under progress at site on 10.07.2026
7/100
Instream Storage Structure, Gudvella
Plastering work is under progress at building area on 10.07.2026
8/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 10.07.2026
9/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 10.07.2026
10/100
Instream Storage Structure, Gudvella
Night view of ISS Gudvella on 09.07.2026
11/100
Instream Storage Structure, Gudvella
Installation work of electrical pole is under progress at site on 09.07.2026
12/100
Instream Storage Structure, Gudvella
Erection of stoplog gate is under progress at site on 09.07.2026
13/100
Instream Storage Structure, Gudvella
Plastering work is under progress at building area on 09.07.2026
14/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 09.07.2026
15/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 09.07.2026
16/100
Instream Storage Structure, Nandagaon
Conducting cube test of 2nd stage concrete M35A20 grade for 28 day compressive strength at camp lab and results are satisfactory i.e. 44.00N/mm² (Avg) on 09.07.2026
17/100
Instream Storage Structure, Nandagaon
• Site visit of ISS Nandagaon by DTL, Tel Basin, Bhawanipatna along with SHEE and Sr. Site Engineer of PMC in presence of PM ,EPC Agency,Site Engineers of PMC and EPC Agency. During the visit the following activities are in progress: 1. Casting of RCC railing is in progress. 2. Earth works at D/S right near flank wall for back filling is in progress. 3. Stone pitching work at U/S right embankment using filter materials in progress. 4. Erection of trestles, Hoist Bridge and hoisting of main gates at 8 nos. Bays from block -1 to Block-2 are done. Rest for 6nos. the fixing process is in progress and will be done by the end of july 2026. 5. The river flows through barrage is very smooth and found normal. 6. Curing of the base slab at the office building is continuing. Progress of column work binding, tying is started for the next floor on 09.07.2026
18/100
Instream Storage Structure, Nandagaon
Barrage bay gate no 4 Monorail girder erection work completed on 09.07.2026
19/100
Instream Storage Structure, Nandagaon
Hoist bridge erection work under progress on Barrage bay gate no 5 on 09.07.2026
20/100
Instream Storage Structure, Nandagaon
Barrage bay gate no 6 erection work under progress on 09.07.2026
21/100
Instream Storage Structure, Nandagaon
De-shuttering & shuttering for CC block at U/S left flared out wall is in progress on 09.07.2026
22/100
UGPL, Left Lower Suktel Canal Division
OMS verification work is in progress of OMS LO-20B, LM-1, at village Pipili.
23/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.03/mm2 for 28 days) of Flank wall Cut-off and M15A40 (Strength is 20.37/mm2 for 07 days) of Flared out wall PCC has done in presence of Client & PSS team.
24/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flank wall, 3rd lift at Block No-5 is under progress.
25/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Reinforcement fixing work of Barrage Bay Middle Pier No..1 at Baitarani ISS in progress.
26/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Middle pier curing work of Baitarani ISS in Progress.
27/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
LHS abutment wall reinforcement fixing work of Baitarani ISS in progress.
28/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Sluice bay divide wall Hoist portion block out shuttering work of Baitarani ISS in progress.
29/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Renforcement fixing work of LHS abutment wall at Baitarani ISS in progress.
30/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Hoist portion blockout shuttering of Sluice bay divide wall of Baitarani ISS in progress.
31/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
4ih lift concrere pouring pouring work barrage bay middle pier No..5 of Baitarani ISS in progress.
32/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
33/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall, 9th lift at Block No-5 is under progress.
34/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-23, 16th lift at Block No-4 is under progress.
35/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.545 m.
36/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.3m.
37/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.3m.
38/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-46 is under progress in presence of Client & PSS Team. Slump testing M35A20 (Value 80 mm) of Gantry Girder No-46 done in presence of Client & PSS Team.
39/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-46 is under progress in presence of Client & PSS Team.
40/100
Instream Storage Structure, Hamirpur
Hoist bridge platform No-4 Shaft fixing and alignment work is in progress.
41/100
Instream Storage Structure, Hamirpur
Shuttering of Gantry Girder No-46 is under progress.
42/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flank wall, 3rd lift at Block No-5 is under progress.
43/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
44/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall, 9th lift at Block No-5 is under progress.
45/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-23, 16th lift at Block No-4 is under progress.
46/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.640 m.
47/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
RCC from RL 5.0m to 6.40m of Barrage bay middle pier No..1 in progress.
48/100
Instream Storage Structure, Khalpal
Binding of reinforcement for LHS Abutment Counterfort wall, 2nd lift is under progress.
49/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 54.985 m.
50/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 90 mm) of RHS Double pier, 4th lift done in presence of Client & PSS Team.
51/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of RHS Double pier, 4th lift is under progress in presence of Client & PSS Team.
52/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Shuttering work of LHS wing and Counterfort wall of Baitarani ISS in progress.
53/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Shuttering work of 4th lift of Barrage bay middle pier No..5 in progress.
54/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Curing work in progress at Baitarani ISS.
55/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Shuttering of Pier No..6 of Baitarani ISS in Progress.
56/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Barrage bay middle Pier No..1Shuttering work of Baitarani ISS in progress.
57/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Back filling of curtain wall area of Baitarani ISS in progress.
58/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
LHS wing wall and counterfort wall shuttering work of Baitarani ISs in progress.
59/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
3rd lift shuttering work of Barrage Bay middle Pier No..4of Baitarani ISS in progress.
60/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
RCC of barrage Bay middle pier No..6 from RL 6.35m to 7.75m of Baitarani ISS in progress.
61/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
RCC WORK OF barrage bay Middle Pter No ..2 from RL 6.45m to 7.90m of Baitarani ISS in progress.
62/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
LHS wing wall and Counterfort wall shuttering work of Baitarani ISS in progress
63/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
LHS wing and Counterfort wall reinforcement fixing work of Baitarani ISS in progress.
64/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
LHS abutment wall reinforcement fixing work of baitarani ISS in progress.
65/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Curtain wall Casting of Baitarani ISS in progress.
66/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
8th Lift reinforcement fixing Work of LHS abutment at BAitarani ISS in Progress.
67/100
Integrated Barrage across river Kochila and across river Baitarini
8th Lift Renforcement Fixing of 8th lift LHS abutmrnt wall of Baitarani ISS in progress.
68/100
Integrated Barrage across river Kochila and across river Baitarini
4th Lift Renforcement fixing work of pier No..6(Barrage Bay Middle Pier)of baitarani ISS in Progress.
69/100
Integrated Barrage across river Kochila and across river Baitarini
RCC of Upstream Divide wall from RL1.00m to 2.45m of Baitarani ISS in progress.
70/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay middle Pier No..2Renforcement fixing work of Baitarani ISS in Progress.
71/100
Integrated Barrage across river Kochila and across river Baitarini
LHS wing wall and counterfort wall renforcement fixing of Baitarani ISS in progress.
72/100
Integrated Barrage across river Kochila and across river Baitarini
RCC OF Barrage Bay Divide Wall from RL 6.30m to 7.70m of Baitarani ISS in Progress.
73/100
UGPL, Left Lower Suktel Canal Division
Pump House out side Road sub-base compaction work is in progress visited by CME (PSS).
74/100
Instream Storage Structure, Khalpal
Testing of Compressive M20A20 (Strength is 29.78/mm2 for 28 days) of Barrage Bay No-2 Gravity floor has done in presence of Client & PSS team.
75/100
Instream Storage Structure, Khalpal
Binding of reinforcement for LHS Abutment Counterfort wall, 2nd lift is under progress.
76/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 55.185 m.
77/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.3m.
78/100
Instream Storage Structure, Hamirpur
Slump testing M15A40 (Value 45 mm) of U/S Flared out wall, 11th lift at Block No-5 done in presence of Client & PSS Team.
79/100
Instream Storage Structure, Hamirpur
Concreting M15A40 of U/S Flared out wall, 11th lift at Block No-5 is under progress in presence of Client & PSS Team.
80/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Pier No-24, 16th lift done in presence of Client & PSS Team.
81/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-24, 16th lift is under progress in presence of Client & PSS Team.
82/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 37.48/mm2 for 07 days) of Gantry Girder No-43 and M30A20 (Strength is 28.15/mm2 for 07 days) of Groove 2nd stage, 3rd lift (Bay No-19) and M25A20 (Strength is 13.33/mm2 for 07 days) of Flared out wall, 10th lift and (Strength is 21.48/mm2 for 07 days) of Flank wall, 7th lift has done in presence of Client & PSS team.
83/100
Instream Storage Structure, Hamirpur
C.D.U frame stiffener grinding & welding work is in progress.
84/100
Instream Storage Structure, Hamirpur
Gantry girder's 1st stage embedded plate welding work is in progress.
85/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Flank wall, 3rd lift at Block No-5 is under progress.
86/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flared out wall at Block No-5 is under progress.
87/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
88/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Flank wall, 9th lift at Block No-5 is under progress.
89/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-23, 16th lift at Block No-4 is under progress.
90/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.615 m.
91/100
Instream Storage Structure, Kopsinga
Double storied building FIRST FLOOR Roof slab reinforcement work is under progress
92/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Checker plate fixing work is in progress of Hoist-bridge
93/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Shaft fixing work is in progress at CDU to ERU
94/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Railling fixing work is in progress of Hoist-bridge
95/100
Instream Storage Structure, Kopsinga
D/S side water flow views, Water level -215.800 against crest level-215.100
96/100
Instream Storage Structure, Kopsinga
U/S side water flow views
97/100
Instream Storage Structure, Kopsinga
Double storied building FIRST FLOOR Roof slab shuttering & reinforcement work is under progress
98/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Railing fixing work is in progress of Hoist-bridge
99/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Bracket fixing work is in progress of Barrage gates
100/100
Instream Storage Structure, Kopsinga
Double storied building slab Reinforcement work under progress