1/100
Instream Storage Structure, Kopsinga
20 Nos of Hand Rail Casting work Complete
2/100
Instream Storage Structure, Kopsinga
Hand Rail Casting work in progress at ISS Kudabaga
3/100
Instream Storage Structure, Kopsinga
Cube test ISS Kopsingha
4/100
Instream Storage Structure, Kushabhadra
Pier no.2 hoisting blockout shuttering is under progress.
5/100
Instream Storage Structure, Kushabhadra
28 days cube test done for CC M25A20 at field laboratory of the ISS.
6/100
Instream Storage Structure, Kushabhadra
Ongoing Curing at fish pass slab portion.
7/100
Instream Storage Structure, Kushabhadra
Left D/S Abutment parapet wall shuttering from RL 21.80m to 22.90m in progress.
8/100
Instream Storage Structure, Kushabhadra
Pier no.2 Monorail hoisting and Block out portion shuttering from RL 23.00m to 23.70m in progress.
9/100
Instream Storage Structure, Kushabhadra
Flood water level RL 11.75m.
10/100
Instream Storage Structure, Kuakhai
DTL, MKS observing the present situation of the ISS site.
11/100
UGPL, Right Lower Suktel Canal Division
Earth pit marking work is in progress of Pump House.
12/100
UGPL, Right Lower Suktel Canal Division
In the presence of TL, QC & QA (PSS), JE (DoWR ) Indian patent stone concrete floor work is in progress of Pump House.
13/100
UGPL, Right Lower Suktel Canal Division
Pump House street lighting 9meter tubular pole numbering work is in progress of Pump House.
14/100
UGPL, Right Lower Suktel Canal Division
Cable caller room ladder fixing work is in progress of Pump House.
15/100
UGPL, Right Lower Suktel Canal Division
Fire fighting system slab curing work is in progress of Pump House.
16/100
UGPL, Right Lower Suktel Canal Division
Indian patent stone concrete flooring (Grid A'8 to A'9)work is in progress near trash rack site of Pump House.
17/100
UGPL, Left Lower Suktel Canal Division
Boundary wall column final lift shuttering work is in progress of Pump House.
18/100
UGPL, Left Lower Suktel Canal Division
Instrumentation Cable laying and dressing work is in progress at pump house.
19/100
UGPL, Left Lower Suktel Canal Division
Boundary wall tie beam reinforcement binding work is in progress at Pump House.
20/100
Integrated Barrage across river Kochila and across river Baitarini
Superintending Engineer, Akhuapada Irrigation Division visited the ISS- Kochila & Baitarani and inspected the casting of CC block at camp area on dated 17.07.2025.
21/100
Instream Storage Structure, Gudvella
Cast of concrete 4th lift RCC M25A20 grade at left side U/s flank wall( A1) including returning wall from RL 152.70m to 154.00m is under progress in the presence of Dept JE , agency foreman and site engineers of PMC n agency at site. Slump achieved 91mm on 17.07.2025
22/100
Instream Storage Structure, Gudvella
Cast of concrete 4th lift RCC M25A20 grade at left side U/s flank wall( A1) including returning wall from RL 152.70m to 154.00m is under progress in the presence of Dept JE , agency foreman and site engineers of PMC n agency at site. Slump achieved 91mm on 17.07.2025
23/100
Instream Storage Structure, Gudvella
Cast of concrete 7th lift RCC M25A20 grade at left side u/s wing wall Pier including 2 nos of counter fort wall from RL155.35m to 156.65m is under progress through pump in the presence of Dept JE,site engineers of PMC n agency at site. Slump achieved 86mm on 17.07.2025
24/100
Instream Storage Structure, Gudvella
Cast of concrete 7th lift RCC M25A20 grade at left side u/s wing wall Pier including 2 nos of counter fort wall from RL155.35m to 156.65m is under progress through pump in the presence of Dept JE,site engineers of PMC n agency at site. Slump achieved 86mm on 17.07.2025
25/100
Instream Storage Structure, Gudvella
Cast of concrete 6th lift RCC M25A20 grade at left side D/s wing wall Pier including 5nos of counter fort wall from RL154.05m to 155.35 m is under progress through pump in the presence of Dept JE , site engineers of PMC n agency at site. Slump achieved 84mm on 17.07.2025
26/100
Instream Storage Structure, Gudvella
Cast of concrete 6th lift RCC M25A20 grade at left side D/s wing wall Pier including 5nos of counter fort wall from RL154.05m to 155.35 m is under progress through pump in the presence of Dept JE , site engineers of PMC n agency at site. Slump achieved 84mm on 17.07.2025
27/100
Instream Storage Structure, Gudvella
Shuttering at left side u/s wing wall including 2nos of counter fort wall for 6th lift RCC work is under progress on 17.07.2025
28/100
Instream Storage Structure, Nandagaon
Reinforcement binding, centring & Shuttering of RCC main girder is in progress on 17.07.2025
29/100
Instream Storage Structure, Nandagaon
Reinforcement binding at pier no.8, Block-2 is in progress on 17.07.2025
30/100
Instream Storage Structure, Nandagaon
Centring & Shuttering for RCC deck slab at span-3 of barrage bay-1, Block-1 is in progress on 17.07.2025
31/100
Instream Storage Structure, Nandagaon
Curing of RCC deck slab, Block-1 is in progress on 17.07.2025
32/100
Instream Storage Structure, Mahulpali
D/S view of ISS Mahulpali on 17.07.2025
33/100
Instream Storage Structure, Mahulpali
U/S view of ISS Mahulpali on 17.07.2025
34/100
Instream Storage Structure, Chhatamakhana
Wet test was conducted in the presence of Department ACE,SE,SDO,JE and PMC Staff DTL,HME PMU ,IE expert,QC Expert HME Telbasin,SHE Expert Electrical engineer on 17.07.2025
35/100
Instream Storage Structure, Chhatamakhana
Wet test was conducted in the presence of Department ACE,SE,SDO,JE and PMC Staff DTL,HME PMU ,IE expert,QC Expert HME Telbasin,SHE Expert Electrical engineer on 17.07.2025
36/100
Instream Storage Structure, KansariGanda
Cube test conducted at site.
37/100
Instream Storage Structure, KansariGanda
Curing continuing at Site.
38/100
Instream Storage Structure, KansariGanda
Pier no 2 shuttering and reinforcement binding is in progress
39/100
Instream Storage Structure, KansariGanda
Pier no 2 shuttering and reinforcement binding is in progress
40/100
Instream Storage Structure, KansariGanda
Pier no 2 shuttering and reinforcement binding is in progress
41/100
Instream Storage Structure, Khirasasan
The flow level is 212.000 m against the design
RL: 210.900, i.e.,1.1m flood lift.
42/100
Instream Storage Structure, Khirasasan
The flow level is 212.000 m against the design RL: 210.900, i.e.,1.1m flood lift.
43/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 193.200m.
44/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.48/mm2 for 07 days) of Abutment wall(A2), 11th lift at Block No-5 and M35A20 (Strength is 35.41/mm2 for 07 days) of Girder No-26 has done in presence of Client & PSS team.
45/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 180.905mt.
46/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Abutment wall(A2), 13th lift at Block No-5 is under progress.
47/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Girder No-32, 33 & 34 is under progress.
48/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
ISS-Chaudhurygada including camp area is totally submerged under flood water, due to swelling of river Mahanadi - 17.07.2025
49/100
Integrated Barrage across river Kochila and across river Baitarini
BAITARANI -ISS C.C Block casting work in site camp at Kochila Baitarani Iss.
50/100
UGPL, Right Lower Suktel Canal Division
Fire fighting system 200mm thickness grade slab shuttering works is under progress of Pump House.
51/100
UGPL, Right Lower Suktel Canal Division
Fire fighting system pump supporting pedestal reinforcement checking is in progress of Pump House.
52/100
Instream Storage Structure, Gudvella
Cast of concrete 3rd lift RCC M25A20 grade at left side D/s flank wall including returning wall from RL 151.45 m to 152.75m is under progress through pump in the presence of Dept JE, site engineers of PMC n agency senior site engineers at site. Slump achieved 82mm on 16.07.2025
53/100
Instream Storage Structure, Gudvella
Cast of concrete 3rd lift RCC M25A20 grade at left side D/s flank wall including returning wall from RL 151.45 m to 152.75m is under progress through pump in the presence of Dept JE, site engineers of PMC n agency senior site engineers at site. Slump achieved 82mm on 16.07.2025
54/100
Instream Storage Structure, Gudvella
Trestle base plate welding work under progress on 16.07.2025
55/100
Instream Storage Structure, Gudvella
Shuttering and reinforcement at left side u/s flank wall including returning wall for 4th lift RCC work is under progress on 16.07.2025
56/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at pier no.8 for 8th lift at D/S side and 7th at U/S floor area from RL-241.10m to RL-242.45m is in progress through concrete pump in presence of JE,KID, PM, EPC agency, Site engineers of PMC & EPC agency. Slump achieved 83mm on 16.07.2025
57/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at pier no.8 for 8th lift at D/S side and 7th at U/S floor area from RL-241.10m to RL-242.45m is in progress through concrete pump in presence of JE,KID, PM, EPC agency, Site engineers of PMC & EPC agency. Slump achieved 83mm on 16.07.2025
58/100
Instream Storage Structure, Nandagaon
Reinforcement binding, centring & Shuttering at pier no.8, Block-2 is in progress on 16.07.2025
59/100
Instream Storage Structure, Nandagaon
Reinforcement binding of RCC girder is in progress on 16.07.2025
60/100
Instream Storage Structure, Nandagaon
Centring & Shuttering for RCC deck slab at span-3 of barrage bay-1, Block-1 is in progress on 16.07.2025
61/100
Instream Storage Structure, Nandagaon
Curing of RCC deck slab, Block-1 is in progress on 16.07.2025
62/100
Instream Storage Structure, Mahulpali
D/S view of ISS Mahulpali on 16.07.2025
63/100
Instream Storage Structure, Mahulpali
U/S view of ISS Mahulpali on 16.07.2025
64/100
Instream Storage Structure, Chhatamakhana
D/S view of the ISS Chhatamakhana on 16.07.2025
65/100
Instream Storage Structure, Chhatamakhana
U/S view of the ISS Chhatamakhana on 16.07.2025
66/100
Instream Storage Structure, KansariGanda
Cube test conducted at site.
67/100
Instream Storage Structure, KansariGanda
Curing continuing at Site.
68/100
Instream Storage Structure, KansariGanda
Curing continuing at Site.
69/100
Instream Storage Structure, KansariGanda
Pier no 2 shuttering and reinforcement binding is in progress
70/100
Instream Storage Structure, KansariGanda
Pier no 2 shuttering and reinforcement binding is in progress
71/100
Instream Storage Structure, KansariGanda
Visit of Dy Team-leader, Irrigation Eng. Expert and QA&QC Expert along with Site Engineer to the ISS Site. Inspected the reinforcement binding and shuttering of Piers No 2 and 3 (2nd lift) which is in progress.
Advised the agency's Project Manager to allow river water through barrage bays no 5, 4 & 3 by removing coffer dam in order to have smooth flow. Also reminded for epoxy painting of exposed reinforcements of all the Piers.
72/100
Instream Storage Structure, KansariGanda
Visit of Dy Team-leader, Irrigation Eng. Expert and QA&QC Expert along with Site Engineer to the ISS Site. Inspected the reinforcement binding and shuttering of Piers No 2 and 3 (2nd lift) which is in progress.
Advised the agency's Project Manager to allow river water through barrage bays no 5, 4 & 3 by removing coffer dam in order to have smooth flow. Also reminded for epoxy painting of exposed reinforcements of all the Piers.
73/100
Instream Storage Structure, KansariGanda
Visit of Dy Team-leader, Irrigation Eng. Expert and QA&QC Expert along with Site Engineer to the ISS Site. Inspected the reinforcement binding and shuttering of Piers No 2 and 3 (2nd lift) which is in progress.
Advised the agency's Project Manager to allow river water through barrage bays no 5, 4 & 3 by removing coffer dam in order to have smooth flow. Also reminded for epoxy painting of exposed reinforcements of all the Piers.
74/100
Instream Storage Structure, Kudabega
Slump 50mm
75/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Mechanical material's ( ERU, CDU, PULLY, Mono Grader, Channel, Anchor bolt - 40) receiving at ISS Kudabaga
76/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Walk-Way work is in progress
77/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Trestle or Column's base-plate work is in progress
78/100
Instream Storage Structure across river Sapei near village Kinjirma
Visited by DTL sir &QCE of PMC Sambalpur & A. E. E, A. E., & J. E (SID).
79/100
Instream Storage Structure across river Sapei near village Kinjirma
Visited by DTL sir &QCE of PMC Sambalpur & A. E. E, A. E., & J. E (SID).
80/100
Instream Storage Structure across river Sapei near village Kinjirma
* Flow direction is straight flow is seen at RL-208.300against crest level RL-206.250 .
* ?Water is flowing 2.05m above the crest level .
81/100
Instream Storage Structure, Kopsinga
Slump 90mm Tm 2
82/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-216.600 mtr against design crest level RL- 215.000 mtr .i.e 1.600mtr flood lift .
83/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-216.600 mtr against design crest level RL- 215.000 mtr .i.e 1.600mtr flood lift .
84/100
Instream Storage Structure, Khirasasan
The flow level is 212.000 m against the design
RL: 210.900, i.e.,1.1m flood lift.
85/100
Instream Storage Structure, Khirasasan
The flow level is 212.000 m against the design
RL: 210.900, i.e.,1.1m flood lift.
86/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. Flow direction is straight. The direction of flow is seen in middle of the river. Now the flow level is 226.800mt against design crest level 225.500 i.e. flood lift 1.3mt.
87/100
Instream Storage Structure, Kopsinga
Slump 85mm tm 1
88/100
Instream Storage Structure, Kopsinga
Cube test ISS Kopsingha
89/100
Instream Storage Structure, Budharaja
The flow level is 209.650 m against the design RL: 206.700, i.e., 2.95 m flood lift.
90/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 60.150mt.
91/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 193.800m
92/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Abutment wall (A2), 12th lift at Block No-5 done in presence of Client & PSS Team.
93/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Abutment wall (A2), 12th lift at Block No-5 is under progress in presence of Client & PSS Team.
94/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Girder No-31 done in presence of Client & PSS Team.
95/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Girder No-31 is under progress in presence of Client & PSS Team.
96/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 36.15/mm2 for 07 days) of Girder No-25 has done in presence of Client & PSS team.
97/100
Instream Storage Structure, Hamirpur
Hoist bridge plat form No-2 welding work is in progress.
98/100
Instream Storage Structure, Hamirpur
Skin plate V-cut grinding work is in progress of under sluice gate No-8.
99/100
Instream Storage Structure, Hamirpur
Shuttering of Abutment wall(A2), 12th lift at Block No-5 is under progress.
100/100
Instream Storage Structure, Hamirpur
Shuttering of Girder No-33 is under progress.
❮
❯