1/100
Instream Storage Structure, Gudvella
Primer painting is under progress at staircase at mechanical yard on 30.07.2026
2/100
Instream Storage Structure, Gudvella
Placement of building tiles is under progress at site on 30.07.2026
3/100
Instream Storage Structure, Gudvella
Grinding and finishing work is under progress at site on 30.07.2026
4/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 30.07.2026
5/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 30.07.2026
6/100
Instream Storage Structure, Nandagaon
SDO ISS Nandagaon visit the site with DTL, CME, QC exp, site engineering of PMC & site engineering of EPC agency today flood level of river is 237.0m against bed level 234.0m yesterday flood level of river was 238.80m on 30.07.2026
7/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of precast railing is in progress in presence of DTL, Tel basin Bhawanipatna, CME & QAC Expert of PMC, SDO ISS Nandagaon, PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 80mm on 30.07.2026
8/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of precast railing is in progress in presence of DTL, Tel basin Bhawanipatna, CME & QAC Expert of PMC, SDO ISS Nandagaon, PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 80mm on 30.07.2026
9/100
Instream Storage Structure, Nandagaon
Monorail walkway railing work is under progress on 30.07.2026
10/100
Instream Storage Structure, Nandagaon
1st NOS of monorail girder erection work is under progress on 30.07.2026
11/100
Instream Storage Structure, Nandagaon
Hoist bridge alignment work is under progress over 1st under sluice gate on 30.07.2026
12/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for precast railing is in progress on 30.07.2026
13/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-51 done in presence of Client & PSS Team.
14/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-51 is under progress in presence of Client & PSS Team.
15/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 42.23/mm2 for 28 days) of Gantry Girder No-42 and M15A40 (Strength is 20.50/mm2 for 28 days) of U/S Flared wall, 10th lift at Block No-5 has done in presence of Client & PSS team.
16/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
17/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for D/S Flank wall, 5th lift at Block No-5 is under progress.
18/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for U/S Flank wall, 12th lift at Block No-5 is under progress.
19/100
Instream Storage Structure, Hamirpur
Trestle No-18 bracing welding work is in progress.
20/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 180.060m.
21/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Present status of river Samakoi at Santeibhanja site.
22/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at Telkoi site.
23/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 58m.
24/100
UGPL, Right Lower Suktel Canal Division
Reservoir water level at RL 199.731m
25/100
UGPL, Right Lower Suktel Canal Division
Reservoir water level at RL 201.570m
26/100
Instream Storage Structure, Gudvella
Placement of filler material is under progress before placing of building tiles on 29.07.2026
27/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 29.07.2026
28/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 28.07.2026
29/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 28.07.2026
30/100
Instream Storage Structure, Nandagaon
No work, due to heavy rain on 29.07.2026
31/100
Instream Storage Structure, Dhanei
Fixation of Anchor Bolts in Trestle blockout is in progress in presence of QA/QC expert along with site engineer mechanical.
32/100
Instream Storage Structure, Dhanei
Fixation of Anchor Bolts in Trestle blockout is in progress in presence of QA/QC expert along with site engineer mechanical.
33/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of 8nos. Post at deck slab no. 14 right side is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 83mm on 28.07.2026
34/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of 8nos. Post at deck slab no. 14 right side is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 83mm on 28.07.2026
35/100
Instream Storage Structure, Nandagaon
Hoist bridge erection work under progress over 1st under sluice gate on 28.07.2026
36/100
Instream Storage Structure, Dhanei
One side sand blasting and colouring of all three gates completed.
37/100
Instream Storage Structure, Dhanei
One side sand blasting and colouring of all three gates completed.
38/100
Instream Storage Structure, Nandagaon
Stone pitching work at U/S right embankment is in progress on 28.07.2026
39/100
Instream Storage Structure, Nandagaon
De-Shuttering & Shuttering for CC block at U/S left flared out wall on 28.07.2026
40/100
Instream Storage Structure, Dhanei
Inside and outside plastering completed of the O&M building.
41/100
Instream Storage Structure, Dhanei
Secondary concreting of the Under sluice bay achieved RL 56.9 meter out of 57.3 meter on sluice bay. 28.07.26
42/100
Instream Storage Structure, Gudvella
Placement of aggregate around transformer area is under progress on 27.07.2026
43/100
Instream Storage Structure, Dhanei
Palli Sabha meetings were conducted on 21.07.2026 at 11:00 AM in Nimina Village and at 2:00 PM in Sanabaragam Village. The required quorum was duly achieved in both meetings.
The meetings were attended by the BDO and WEO, Polasara Block, Sarpanch,PEO, Zilla Parishad Member,Ward Members of Nimina Gram Panchayat, the majority of the identified land losers, the SDO and AE from the department, as well as the Social Development Expert from the PMC.
44/100
Instream Storage Structure, Dhanei
Palli Sabha meetings were conducted on 21.07.2026 at 11:00 AM in Nimina Village and at 2:00 PM in Sanabaragam Village. The required quorum was duly achieved in both meetings.
The meetings were attended by the BDO and WEO, Polasara Block, Sarpanch,PEO, Zilla Parishad Member,Ward Members of Nimina Gram Panchayat, the majority of the identified land losers, the SDO and AE from the department, as well as the Social Development Expert from the PMC.
45/100
Instream Storage Structure, Dhanei
Palli Sabha meetings were conducted on 21.07.2026 at 11:00 AM in Nimina Village and at 2:00 PM in Sanabaragam Village. The required quorum was duly achieved in both meetings.
The meetings were attended by the BDO and WEO, Polasara Block, Sarpanch,PEO, Zilla Parishad Member,Ward Members of Nimina Gram Panchayat, the majority of the identified land losers, the SDO and AE from the department, as well as the Social Development Expert from the PMC.
46/100
Instream Storage Structure, Dhanei
Palli Sabha meetings were conducted on 21.07.2026 at 11:00 AM in Nimina Village and at 2:00 PM in Sanabaragam Village. The required quorum was duly achieved in both meetings.
The meetings were attended by the BDO and WEO, Polasara Block, Sarpanch,PEO, Zilla Parishad Member,Ward Members of Nimina Gram Panchayat, the majority of the identified land losers, the SDO and AE from the department, as well as the Social Development Expert from the PMC.
47/100
Instream Storage Structure, Dhanei
Palli Sabha meetings were conducted on 21.07.2026 at 11:00 AM in Nimina Village and at 2:00 PM in Sanabaragam Village. The required quorum was duly achieved in both meetings.
The meetings were attended by the BDO and WEO, Polasara Block, Sarpanch,PEO, Zilla Parishad Member,Ward Members of Nimina Gram Panchayat, the majority of the identified land losers, the SDO and AE from the department, as well as the Social Development Expert from the PMC.
48/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 27.07.2026
49/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 27.07.2026
50/100
Instream Storage Structure, Dhanei
Secondary concreting of the guide channel achieved 55.3 meter on Sluice bay. 17.07.26
51/100
Instream Storage Structure, Dhanei
Secondary concreting of the guide channel achieved 55.3 meter on Sluice bay. 17.07.26
52/100
Instream Storage Structure, Dhanei
Secondary concreting achieved RL 53.7meter out of 57.3 meter on Sluice bay
53/100
Instream Storage Structure, Gudvella
Due to heavy rainfall, no work is going on on 26.07.2026
54/100
Instream Storage Structure, Dhanei
Sand blasting and Priming of the gates ongoing at site.
55/100
Instream Storage Structure, Gudvella
The installation of barbed wire fencing with angle posts around the transformer area is in progress on 25.07.2026
56/100
Instream Storage Structure, Dhanei
Visit of DTL, IEE including Site Engineers to this Site.
Sluice Bay Stop log & Service gate groove 2nd stage Shuttering is continuing
57/100
Instream Storage Structure, Dhanei
Visit of DTL, IEE including Site Engineers to this Site.
Sluice Bay Stop log & Service gate groove 2nd stage Shuttering is continuing
58/100
Instream Storage Structure, Gudvella
Adjustment of rubber seal of mechanical gate is under progress at site on 25.07.2026
59/100
Instream Storage Structure, Gudvella
Curing of wearing coat at deck slab is under progress at site on 25.07.2026
60/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 25.07.2026
61/100
Instream Storage Structure, KansariGanda
Work stop due to heavy rainfall. 28.07.26
62/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 25.07.2026
63/100
Instream Storage Structure, KansariGanda
RHS GIRDER NO 40 RAINFORCEMENT BINDING CHECK AND AFTER THAT CONCRETING IS IN PROGRESS IN PRESENCE OF SITE ENGINEER PMC.
64/100
Instream Storage Structure, KansariGanda
RHS GIRDER NO 40 RAINFORCEMENT BINDING CHECK AND AFTER THAT CONCRETING IS IN PROGRESS IN PRESENCE OF SITE ENGINEER PMC.
65/100
Instream Storage Structure, Nandagaon
Concrete casting with M20A20 grade of CC block at U/S left flared out wall is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 83mm on 27.07.2026
66/100
Instream Storage Structure, Nandagaon
Concrete casting with M20A20 grade of CC block at U/S left flared out wall is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 83mm on 27.07.2026
67/100
Instream Storage Structure, Nandagaon
• 1.The casting of the CC block at the following area has been checked in the presence of PM, EPC agency, Site Engineers of PMC & EPC Agency:
(i) Shuttering for CC block at U/S left flared out wall of 27.75m length & 0.6m ht. from RL-244.80m to RL-245.40m is completed.
(ii). Filling of inverted filter materials covering with LDPE paper at adjacent to each CC block in earth side are done before placement.
(iii) Application of 2 coat bitumen paint at cj's concrete surface is done.
(iv). Area is ready and passed by SE KID, Bh. Patna to place concrete with PCC M20A20 grade on 27.07.2026
68/100
Instream Storage Structure, Nandagaon
Stone pitching work at U/S right embankment is in progress on 27.07.2026
69/100
Instream Storage Structure, KansariGanda
Gurder No 39 concreting in progress and slump cone test conducted at site in presence of Irr. Eng. Expert along with site engineer PMC
70/100
Instream Storage Structure, KansariGanda
Gurder No 39 concreting in progress and slump cone test conducted at site in presence of Irr. Eng. Expert along with site engineer PMC
71/100
Instream Storage Structure, Nandagaon
Shuttering for CC block is in progress at U/S left flared out wall on 27.07.2026
72/100
Instream Storage Structure, KansariGanda
24.07.26- Water Level RL 2.70 mt
73/100
Instream Storage Structure, KansariGanda
24.07.26- Water Level RL 2.70 mt
74/100
Instream Storage Structure, KansariGanda
23.07.26- Water level 2.5
75/100
Instream Storage Structure, Nandagaon
Work stopped due to heavy rainfall on 26.07.2026
76/100
Instream Storage Structure, KansariGanda
22.07.26- Water level 2.2
77/100
Instream Storage Structure, KansariGanda
22.07.26- Water level 2.2
78/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of 8nos. Post at deck slab no. 4 left side is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 85mm on 25.07.2026
79/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of 8nos. Post at deck slab no. 4 left side is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 85mm on 25.07.2026
80/100
Instream Storage Structure, KansariGanda
Gramakantha Settlement (Khatiaramachandrapur): Two stakeholders have yet to submit their settlement applications. The RI, Panibandha has assured that the settlement proceedings will be processed in accordance with the applicable rules upon receipt of the requisite applications from the concerned stakeholders
81/100
Instream Storage Structure, KansariGanda
22.07.26 -Water level 2.00
82/100
Instream Storage Structure, Nandagaon
Stone pitching work at U/S right embankment is in progress on 25.07.2026
83/100
Instream Storage Structure, KansariGanda
palli Sabha on 21.07.2026 at Barada village Sidheswar thakura Pujari committee ,in the presence Dep staff and agency.
84/100
Instream Storage Structure, KansariGanda
21.07.26
85/100
Instream Storage Structure, Nandagaon
De-Shuttering & Shuttering for CC block at U/S left flared out wall on 25.07.2026
86/100
Instream Storage Structure, KansariGanda
Water level 2.1
87/100
Instream Storage Structure, KansariGanda
Water level 2.1
88/100
Instream Storage Structure, KansariGanda
Water level 2.1
89/100
Instream Storage Structure, KansariGanda
Girder NO 37 concrete pouring is progress in presence of Irr. Eng. Expert along with site engineer PMC.
90/100
Instream Storage Structure, KansariGanda
18.07.26
91/100
Instream Storage Structure, KansariGanda
2nd palli Sabha on 17.07.2026 at Raulibandha in the presence of Tahasildar,Addl Tahasildar,BDO,ABDO ,Ganjam alongwith Sarapancha,PEO,Ward members of the Malada GP.
92/100
Instream Storage Structure, KansariGanda
2nd palli Sabha on 17.07.2026 at Raulibandha in the presence of Tahasildar,Addl Tahasildar,BDO,ABDO ,Ganjam alongwith Sarapancha,PEO,Ward members of the Malada GP.
93/100
Instream Storage Structure, KansariGanda
17.07.26
94/100
Instream Storage Structure, KansariGanda
Water Level RL 1.90
95/100
Instream Storage Structure, KansariGanda
.
96/100
Instream Storage Structure, KansariGanda
A meeting with temple land beneficiaries (ISS Kansariganda)conducted at Sidheswara temple campus for acquiring temple land.However,due to rain only few members gathered.So,it is decided to conduct next time.Tentatively 21.7.2026 is fixed for the meeting.
97/100
Instream Storage Structure, Hamirpur
Shuttering of Gantry Girder is under progress.
98/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
99/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall, 5th lift at Block No-5 is under progress.
100/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for U/S Flank wall, 12th lift at Block No-5 is under progress.
❮
❯