1/100
Integrated Barrage across river Kochila and across river Baitarini
Lateral pile load test is going on in presence of PMC , OCCL, PMU, department , quality assurance Cuttack and agency-20.04.2026.
2/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-16, 14th lift with pier Cap done in presence of Client & PSS Team.
3/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-16, 14th lift with pier Cap is under progress in presence of Client & PSS Team.
4/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Pier No-15, 13th lift with pier Cap done in presence of Client & PSS Team.
5/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-15, 13th lift with pier Cap is under progress in presence of Client & PSS Team.
6/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-22 done in presence of Client & PSS Team.
7/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-22 is under progress in presence of Client & PSS Team.
8/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-14, 15th lift done in presence of Client & PSS Team.
9/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-14, 15th lift is under progress in presence of Client & PSS Team.
10/100
Instream Storage Structure, Hamirpur
CE&BM, Brahmani Basin, Samal along with Addl. C.E, HWC, Rengali & S.E, Rourkela Irrigation Division visited the work site in presence of A.E.E & A.E, RID, IEE & Site Engineers of PSS team and representative of EPC agency and reviewed the Construction work progress as well as land acquisition status.
11/100
Instream Storage Structure, Hamirpur
MS plate marking and cutting for hoist platform girder's flange work is in progress.
12/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly welding work is in progress.
13/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall at Block No-1 is under progress.
14/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Deck slab (Bay No-16 & 17) is under progress.
15/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall at Block No-5 is under progress.
16/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Toe wall at Block No-5 is under progress.
17/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Abutment (A1) is under progress.
18/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
19/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for Abutment & Counterfort wall is under progress.
20/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for LHS side Raft is under progress.
21/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
LHS under sluice deck slab staging work is under progress.
22/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering & binding of reinforcement for RHS Mid-pier, 3rd lift is under progress.
23/100
Instream Storage Structure, Jharbeda
CE&BM, Brahmani Basin, Samal along with Addl. C.E, HWC, Rengali & S.E, Rourkela Irrigation Division visited the work site in presence of A.E.E & A.E, RID, IEE & Site Engineers of PSS team and representative of EPC agency and reviewed the on going Construction work.
24/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-8 is under progress.
25/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-6 is under progress.
26/100
Instream Storage Structure, Jharbeda
Curing of End sill is under progress.
27/100
Instream Storage Structure, Jharbeda
Curing of RHS D/S Flank wall is under progress.
28/100
Instream Storage Structure, Khalpal
Curing of Piers is in progress.
29/100
Instream Storage Structure, Khalpal
Curing of Gravity floor work is in progress.
30/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 80 mm) of Pier No-20, 1st lift done in presence of Client & PSS Team.
31/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-20, 1st lift is under progress in presence of Client & PSS Team.
32/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 80 mm) of Pier No-23, 1st lift done in presence of Client & PSS Team.
33/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-23, 1st lift is under progress in presence of Client & PSS Team.
34/100
Instream Storage Structure, Gudvella
Parapet railing casting under progress on 20.04.2026
35/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 80 mm) of Gravity floor Bay No-3 done in presence of Client & PSS Team.
36/100
Instream Storage Structure, Gudvella
Under-sluice bay top and bottom assembly work under progress on 20.04.2026
37/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Gravity floor Bay No-3 is under progress in presence of Client & PSS Team.
38/100
Instream Storage Structure, Khalpal
Concreting M15A40 of Barrage Bay No-2 PCC is under progress in presence of Client & PSS Team.
39/100
Instream Storage Structure, Gudvella
Trestle installation work under progress at A1 on 20.04.2026
40/100
Instream Storage Structure, Gudvella
Fixing of trestle at A1 is in progress on 20.04.2026
41/100
Instream Storage Structure, Gudvella
Shuttering work is underprogress at posting of span on 20.04.2026
42/100
Instream Storage Structure, Gudvella
Brick work is in progress at 1st floor building and Shuttering work started for slab on 20.04.206
43/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right divide wall for 4th lift upto RL-236.80m is in progress through concrete pump in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 82mm on 20.04.2026
44/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right divide wall for 4th lift upto RL-236.80m is in progress through concrete pump in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 82mm on 20.04.2026
45/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at foundation column no. 16 upto RL-240.95 is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 82mm on 20.04.2026
46/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at foundation column no. 16 upto RL-240.95 is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 82mm on 20.04.2026
47/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of left kerb at deck slab no.9&10 upto RL-247.30mbis in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 86mm on 20.04.2026
48/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of left kerb at deck slab no.9&10 upto RL-247.30mbis in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 86mm on 20.04.2026
49/100
Instream Storage Structure, Nandagaon
• 3.The area of placing concrete at U/S right divide wall has been checked before placement in presence of PM of EPC Agency, Site Engineer of PMC & EPC Agency as follows:
(i).The main vertical steel 25mm # @ 125mm c/c & horiz. dist. bar 16mm #@ 175 mm c/c and tie bars for casting of U/S right divide wall for 4th lift from RL-235.40m to RL-236.80m are found completed.
(ii).Rigid & smooth shuttering and maintained clear cover of 75mm from main bar to shutter plates are done.
(iii).The area is cleaned properly through air water jetting and passed by SE, KID, Bhawanipatna for placing with RCC M25A20 grade on 20.04.2026
50/100
Instream Storage Structure, Nandagaon
• 2.The area of placing concrete at foundation of column no.16 of building has been checked before placement in presence of PM of EPC Agency, Site Engineer of PMC & EPC Agency as follows:
(i).The reinforcement of foundation 12# @ 150 c/c in both direction, in column 4X20# & 4X16# & 8# stirrups @15mm c/c binding in column from RL-240.60m to RL-240.95m are found completed.
(ii).Rigid & smooth shuttering and maintained clear cover of 50mm from main bar to shutter plates are done.
(iii).The area is cleaned and passed by SE, KID, Bhawanipatna for placing with RCC M25A20 grade on 20.04.2026
51/100
Instream Storage Structure, Nandagaon
• 1.The area before placement of concrete for left kerb beam of deck slab has been checked in presence of PM,EPC agency,Site Engineers of PMC & EPC agency as follows:
(i)Binding of 8mm dia 2-legged stirrups @ 200 mm c/c for left kerb at deck slab of Span- 9 & 10 and fixing of rail posts bars are completed.
(ii) Rigid and smooth shuttering with 40mm clear cover are completed.
(iii)Fixing & placing of joint materials at pier-9&10 along the expansion gap is done.
(iv) Area is cleaned using air water jet and passed by SE, KID, Bhawanipatna and ready to place concrete with RCC M35A20 grade upto RL-247.30m on 20.04.2026
52/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for building column foundation is in progress on 20.04.2026
53/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress at pier no.9 on 20.04.2026
54/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering is in progress at U/S right divide wall on 20.04.2026
55/100
Barrage across river Turi & Guntat
Site inspection at the Turi–Guntat Barrage was carried out by the Chief Engineer sir, accompanied by SE (NID), SDO, JEs, and the agency representative.
56/100
Instream Storage Structure, Kudabega
Right under sluice bay fish of fish pass reinforcement & shuttering work in progress
57/100
Instream Storage Structure, Kudabega
Slump 80mm
58/100
Instream Storage Structure, Kudabega
Right under sluice bay wearing coat M25A20 casting work in progress
59/100
Instream Storage Structure, Kudabega
Right under sluice bay wearing coat M25A20 casting work in progress
60/100
Instream Storage Structure, Kudabega
Right under sluice bay wearing coat M25A20 casting work in progress
61/100
Instream Storage Structure, Kudabega
Casting of wearing coat of RUS
62/100
Instream Storage Structure, Kudabega
Slump 80mm of rus wearing coat
63/100
Instream Storage Structure, Kudabega
Slump 80mm of wearing coat (RUS)
64/100
Instream Storage Structure, Kudabega
Casting of U/S flared wall (RHS)
65/100
Instream Storage Structure, Kudabega
Slump 80mm of us flared wall
66/100
Instream Storage Structure, Kudabega
Casting of wearing coat of RUS
67/100
Instream Storage Structure, Kudabega
Casting of rus wearing coat
68/100
Instream Storage Structure, Kudabega
Slump 80mm of rus wearing coat
69/100
Instream Storage Structure, Kudabega
Wearing coat of rus
70/100
Instream Storage Structure, Kudabega
Slump 80mm of wearing coat (RUS)
71/100
Instream Storage Structure, Kudabega
Wearing coat raft(rus) casting
72/100
Instream Storage Structure, Kudabega
Slump 80mm of wearing coat(rus)
73/100
Instream Storage Structure, Kudabega
ISS Kudabaga - SS - plate fixing work is in progress in bottom Seal-beam
74/100
Instream Storage Structure, Kudabega
ISS Kudabaga - SS - plate fixing work is in progress in bottom Seal-beam
75/100
Instream Storage Structure, Kudabega
Earth filling (RHS)
76/100
Instream Storage Structure, Kudabega
Right under sluice bay fish of fish pass reinforcement & shuttering work in progress
77/100
Instream Storage Structure, Kudabega
Right under sluice bay fish of fish pass reinforcement & shuttering work in progress
78/100
Instream Storage Structure, Kudabega
Slump 80mm
79/100
Instream Storage Structure, Kudabega
Right under sluice bay fish pass portion denial M25A20 casting work in progress
80/100
Instream Storage Structure, Kudabega
Reinforcement of Daniel wall of fish pass.
81/100
Instream Storage Structure, Kudabega
Slump 85mm
82/100
Instream Storage Structure, Kudabega
Slump 80mm
83/100
Instream Storage Structure, Kudabega
Right under sluice bay wearing coat M25A20 casting work in progress
84/100
Instream Storage Structure, Kudabega
Right under sluice bay fish of fish pass reinforcement & shuttering & casting work in progress
85/100
Instream Storage Structure, Kudabega
Right under sluice bay fish of fish pass reinforcement & shuttering & casting work in progress
86/100
Instream Storage Structure, Kudabega
Slump 80mm
87/100
Instream Storage Structure, Kudabega
Right under sluice bay wearing coat M25A20 casting work in progress
88/100
Instream Storage Structure, Kudabega
Right under sluice bay wearing coat M25A20 casting work in progress
89/100
Instream Storage Structure, Kudabega
Double stored building for watchman & operator shed rooph beam reinforcement work in progress
90/100
Instream Storage Structure, Kudabega
Double stored building for watchman & operator shed rooph beam reinforcement work in progress
91/100
Instream Storage Structure, Kudabega
Casting of wearing coat DS gravity floor
92/100
Instream Storage Structure, Kudabega
Slump 80mm of D/S gravity floor (RUS)
93/100
Instream Storage Structure, Kudabega
Slump 85mm of RHS fish pass portion
94/100
Instream Storage Structure, Kudabega
Slump 80 mm of wearing coat of RHS D/S gravity floor
95/100
Instream Storage Structure, Kudabega
Casting in progress
96/100
Instream Storage Structure, Kudabega
Slump 80mm of RHS gravity floor D/S
97/100
Instream Storage Structure, Kudabega
Shuttering work of double stored Building for watchman shed and operators
98/100
Instream Storage Structure, Gochara
Hoist Platform railing painting work is in progress.
99/100
Instream Storage Structure, Gochara
Staff quarter building beam shuttering work is going on..
100/100
Instream Storage Structure, Gochara
View showing flow of river from D/S of river.
❮
❯