1/100
Instream Storage Structure, Gudvella
Visited by: SE , Balangir Irrigation Division
Location: ISS Gudvella Site
Present: Department JE, PMC Site Engineers, and Agency Representatives
Observations and Instructions
1. The agency was instructed to deploy additional manpower to expedite the ongoing construction works.
2. The agency was advised to immediately commence the second stage of mechanical works.
3. The agency was directed to submit the Afflux Survey Report and the approach road data of the site at the earliest.
4. The agency was instructed to start the building works without any further delay.
Remarks / Conclusion
The overall progress of the work was reviewed during the visit. The agency was advised to enhance the pace of execution and ensure timely submission of all required data and reports. The quality of work must be maintained strictly as per specifications under the close supervision of PMC and departmental officials on 28.11.2025
2/100
UGPL, Left Lower Suktel Canal Division
Outlet point extension work is in progress at LO-107A (LM-6), Z-6861 near village Gerdi.
3/100
Instream Storage Structure, Gudvella
Cast of concrete (10th lift / step PCC) M15A40 grade at left side D/s flard out wall from sec 1-1 to sec 2-2 with RL154.00m to 154.60m is under progress in the presence of Dept JE,site engineers of PMC n agency. Slump achieved 68mm on 28.11.2025
4/100
Instream Storage Structure, Gudvella
Cast of concrete (10th lift / step PCC) M15A40 grade at left side D/s flard out wall from sec 1-1 to sec 2-2 with RL154.00m to 154.60m is under progress in the presence of Dept JE,site engineers of PMC n agency. Slump achieved 68mm on 28.11.2025
5/100
UGPL, Left Lower Suktel Canal Division
MS Pipe to DI pipe Branch connection Pad plate Welding work is in progress, Dy-2 RM-08 at Village Khairpali.
6/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 1no of CC block at U/S right flared out wall from sec.4-4 to Sec.5-5 for 1st lift from RL-235.80m to RL-236.40m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 75mm on 28.11.2025
7/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 1no of CC block at U/S right flared out wall from sec.4-4 to Sec.5-5 for 1st lift from RL-235.80m to RL-236.40m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 75mm on 28.11.2025
8/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at U/S right flared out wall from sec.2-2 to Sec.4-4 for 5th lift from RL-236.40m to RL-237.00m is in progress in presence of JE,KID, Site Engineers of PMC & EPC agency. Slump achieved 71mm on 28.11.2025
9/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at U/S right flared out wall from sec.2-2 to Sec.4-4 for 5th lift from RL-236.40m to RL-237.00m is in progress in presence of JE,KID, Site Engineers of PMC & EPC agency. Slump achieved 71mm on 28.11.2025
10/100
Instream Storage Structure, Nandagaon
Columns fit up work and base plate welding under progress on 28.11.2025
11/100
Instream Storage Structure, Nandagaon
Gate no 3 both stop log gate and barrage bay gate erection work under progress on 28.11.2025
12/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering at pier no. 9, Block-2 is in progress on 28.11.2025
13/100
UGPL, Left Lower Suktel Canal Division
1Ha. outlet point fixing work is in progress of RO-150, RM-8 at village Bhainsa.
14/100
Integrated Barrage across river Kochila and across river Baitarini
BAITARANI -ISS Sluice bay divide wall cleaning is in progress
15/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
PMC MBBS, Chandikhol visited ISS- Chaudhurygada ISS project today. The PMC team discussed with the agency and instructed to complete the cofferdam work latest by 10th Dec 2025 and further chased to expedite the project work.
16/100
UGPL, Left Lower Suktel Canal Division
20mm Dia galvanized steel Conduit pipe laying and wiring work is in progress for outdoor roof lighting work at Pump House.
17/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 400mm Dia DI Pipeline Lm-11, from J-135 to J-136 at village Khairpali.
18/100
UGPL, Left Lower Suktel Canal Division
Outlet fixing work in progress of HDPE pipe line, LO-163B at village Taliudar in presence of DWOR AE and PMC team.
19/100
UGPL, Left Lower Suktel Canal Division
Excavation work in progress for connection of DI pipe line to HDPE pipe line from J-548 to RO-42, RM-3 Near Kusmel.
20/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for Dia 75mm HDPE pipeline LM - 17, LO330A OMS point at village Singhanimunda.
21/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Visited by Dy. TL, Brahmani Basin, Samal in presence of A.E.E & A.E, RDD, QAE and of PSS team along with Dy. PM of EPC agency regarding review the Concreting, Shuttering & Cleaning of reinforcement at Site.
22/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Visited of Forrest Range Officer, Pallahara for verification & Girth measurement and numbering of trees for forest land diversion in presence of Dy. TL, QAE of PSS team, A.E of RDD with EPC agency.
23/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Excavation of Gravity floor is under progress.
24/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of Divide wall, 3rd lift is under progress.
25/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Visited by Dy. TL, Brahmani Basin, Samal in presence of A.E.E & A.E, RDD, QAE and PSE of PSS team along with Dy. PM of EPC agency regarding review the Concreting, Shuttering & Cleaning of reinforcement at Site.
26/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Gramsabha conducted for Forest land Diversion in Telkoi Gram Panchyat in presence of Sarapanch, PEO, Forest Officials, AEE, RDD and SDE of PSS along with EPC Agency.
27/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M20A20 (Value 80 mm) of LHS D/S Gravity floor done in presence of Client & PSS Team.
28/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M20A20 of LHS D/S Gravity floor is under progress in presence of Client & PSS Team.
29/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS D/S Counter fort, 1st lift is under progress.
30/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning & Vertical straightening of reinforcement for LHS U/S Divide wall, 2nd lift is under progress.
31/100
UGPL, Right Lower Suktel Canal Division
Internal drain plastering work is in progress at Pump House.
32/100
Instream Storage Structure, Jharbeda
Inspection by A.E.E & A.E, QA&QC of RID along with PSS team at ISS Site regarding ongoing activities of construction work.
33/100
Instream Storage Structure, Jharbeda
Observed of Impact value test in presence of A.E.E & A.E, QA&QC of RID & PSS team along with EPC agency.
34/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-6, 3rd lift is under progress.
35/100
Instream Storage Structure, Jharbeda
Cleaning of Reinforcement for Pier No-7, 2nd lift is under progress.
36/100
Instream Storage Structure, Jharbeda
Cleaning of Floor area is under progress.
37/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.33/mm2 for 07 days) of Pier No-23, 10th lift has done in presence of Client & PSS team.
38/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Sill beam (Bay No-14) is under progress in presence of Client & PSS Team.
39/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-23, 11th lift done in presence of Client & PSS Team.
40/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-23, 11th lift is under progress in presence of Client & PSS Team.
41/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-31, 6th lift done in presence of Client & PSS Team.
42/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-31, 6th lift is under progress in presence of Client & PSS Team.
43/100
Instream Storage Structure, Hamirpur
Curing of Pier No-18, 8th lift is under progress.
44/100
Instream Storage Structure, Hamirpur
2st stage embedded parts seal beam erection work is in progress of bay No-12.
45/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-17, 9th lift is under progress.
46/100
Instream Storage Structure, Hamirpur
Double pier hoist bridge platform stiffener welding work is in progress.
47/100
Instream Storage Structure, Hamirpur
Seal beam installation work is in progress of bay No-11.
48/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-29, 12th lift is under progress.
49/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-22, 8th lift is under progress.
50/100
Instream Storage Structure, Khalpal
Hirakud Government Lab mix design trial mix conducted at site laboratory of M20A20, 14 days cube (Strength 26.93 N/mm²) and M20A40, 28 days cube (Strength 28.29 N/mm²)in presence of PSS Team.
51/100
Instream Storage Structure, Khalpal
Slump testing M20A40 (Value 65 mm) C.C Blocks done in presence of Client & PSS Team.
52/100
Instream Storage Structure, Khalpal
Casting of C.C Block (M20A40) is under progress in presence of Client & PSS Team.
53/100
UGPL, Left Lower Suktel Canal Division
Concrete pouring work is in progress for raft bottom area of internal drainage near boundary wall at Pump House.
54/100
UGPL, Left Lower Suktel Canal Division
Slump test is in progress for internal drainage near boundary wall at Pump House.
55/100
Instream Storage Structure, Khalpal
Hirakud Government Lab mix design trial mix conducted at site laboratory of M15A40, 14 days cube (Strength 20.56 N/mm²) in presence of PSS Team.
56/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering & binding of reinforcement for Counter fort is under progress.
57/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cleaning & Vertical straightening of reinforcement for Divide wall, 3rd lift is under progress.
58/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cleaning of Gravity floor is under progress.
59/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M20A20 (Value 85 mm) of Gravity floor done in presence of Client & PSS Team.
60/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M20A20 of Gravity floor is under progress in presence of Client & PSS Team.
61/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS D/S Counter fort, 1st lift is under progress.
62/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS D/S Divide wall, 1st lift is under progress.
63/100
Instream Storage Structure, Jharbeda
Cleaning of Reinforcement for Pier No-7, 2nd lift is under progress.
64/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-6, 3rd lift is under progress.
65/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-5, 3rd lift is under progress.
66/100
Instream Storage Structure, Jharbeda
Cleaning of Floor area is under progress.
67/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.62/mm2 for 07 days) of Pier No-29, 10th lift and M25A20(Strength is 21.04/mm2 for 07 days) of Pier No-18, 6th lift has done in presence of Client & PSS team.
68/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-18, 8th lift done in presence of Client & PSS Team.
69/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-18, 8th lift is under progress in presence of Client & PSS Team.
70/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-27, 13th lift done in presence of Client & PSS Team.
71/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-27, 13th lift is under progress in presence of Client & PSS Team.
72/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-10, 4th lift done in presence of Client & PSS Team.
73/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-10, 4th lift is under progress in presence of Client & PSS Team.
74/100
Instream Storage Structure, Hamirpur
Curing of Pier No-28 is under progress.
75/100
Instream Storage Structure, Hamirpur
2st stage embedded parts seal beam fixing work is in progress of bay No-12.
76/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Pier No-17, 8th lift is under progress.
77/100
Instream Storage Structure, Hamirpur
Double pier hoist bridge platform stiffener welding work is in progress.
78/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-23, 11th lift at Block No-4 is under progress.
79/100
Instream Storage Structure, Hamirpur
Column bracing welding work is in progress.
80/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-29, 12th lift is under progress.
81/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-31, 6th lift at Block No-5 is under progress.
82/100
Instream Storage Structure, Gudvella
Shuttering at right side U/s flank wall raft for final lift PCC work is under progress on 27.11.2025
83/100
Instream Storage Structure, Nandagaon
Gate no 3 both stop log gate and barrage bay gate embedded parts erection work under progress on 27.11.2025
84/100
Instream Storage Structure, Nandagaon
Sil beam SS plate welding under progress on 27.11.2025
85/100
Instream Storage Structure, Nandagaon
Cleaning of reinforcement using gunny bag at right abutment, Block-2 is in progress on 27.11.2025
86/100
Integrated Barrage across river Kochila and across river Baitarini
PMC MBBS, Chandikhol visited Kochila-Baitarani ISS project today. Discussed with the agency to expedite the project work- 28.11.2025
87/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Cofferdam work is going on at Tikhiri ISS project.
88/100
UGPL, Right Lower Suktel Canal Division
OCS fittings Installation work is in progress for OCS -2305010-C08B, at village Takarla in presence of Bermad Personnel and PMC team.
89/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for laying of 90mm Dia HDPE pipe from J-7178 to 0213118- C05 at village Bileisarda.
90/100
UGPL, Left Lower Suktel Canal Division
280mm Dia HDPE pipe laying work is in progress node from J-80 to J-440, LM-6 near village Gerdi in presence of PMC team.
91/100
Instream Storage Structure, Khalpal
Batching plant internal calibration at site in presence of A.E.E & PSS Team.
92/100
UGPL, Left Lower Suktel Canal Division
1Ha. outlet point fixing work is in progress of RO-224A, Z-2276 at village Budipadar.
93/100
UGPL, Left Lower Suktel Canal Division
20mm Dia galvanized steel Conduit pipe laying and wiring work is in progress for outdoor roof lighting work at Pump House.
94/100
UGPL, Left Lower Suktel Canal Division
Outlet point extension work is in progress of HDPE pipeline, Zone-2, LO-111B, Z-5524 LM-6 At village Gerdi.
95/100
Instream Storage Structure, Khalpal
Slump testing M20A40 (Value 55 mm) C.C Blocks done in presence of Client & PSS Team.
96/100
Instream Storage Structure, Khalpal
Casting of C.C Block (M20A40) is under progress in presence of Client & PSS Team.
97/100
UGPL, Right Lower Suktel Canal Division
Concreting work is in progress for internal approach RCC road of Pump House.
98/100
UGPL, Right Lower Suktel Canal Division
Slump test is in progress for internal approach RCC road concrete of Pump House.
99/100
UGPL, Right Lower Suktel Canal Division
Internal drain plastering work is in progress at Pump House.
100/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
❮
❯