PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Jharbeda
Dewatering work is in Progress.
2/100
Instream Storage Structure, Jharbeda
Curing work is under progress.
3/100
Instream Storage Structure, Jharbeda
Curing of RHS D/S Flank wall is under progress.
4/100
Instream Storage Structure, Hamirpur
Calibration test of weight is being conducted in Batching plant in Presence of A.E RID & PSS Team.
5/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.91/mm2 for 28 days) of Pier No-4, 4th lift and (Strength is 30.96/mm2 for 28 days) of Pier No-5, 5th lift and M35A20 (Strength is 42.30/mm2 for 28 days) of Gantry Girder No-13 and (Strength is 36.89/mm2 for 07 days) of Gantry Girder No-27 and M35A20 (Strength is 37.78/mm2 for 07 days) of Deck slab (Bay No-16) has done in presence of Client & PSS team.
6/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-4 welding work is in progress.
7/100
Instream Storage Structure, Hamirpur
MS plate marking and cutting for u/s hoist bridge girder's work is in progress.
8/100
Instream Storage Structure, Hamirpur
2nd stage embedded parts guide and roller track erection work is in progress at bay No-26.
9/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall at Block No-5 is under progress.
10/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Flank wall at Block No-1 is under progress.
11/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-2, 6th lift is under progress.
12/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Flank wall Cut-off at Block No-1 is under progress.
13/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Abutment (A1), 5th lift is under progress.
14/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
15/100
Instream Storage Structure, Khalpal
Inspection of Batching plant calibration by S.E, AID at site in presence of PSS Team & EPC Agency.
16/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 90 mm) of Pier No-22, 2nd lift done in presence of Client & PSS Team.
17/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-22, 2nd lift done in presence of Client & PSS Team
18/100
Instream Storage Structure, Khalpal
Curing of Wing wall is in progress.
19/100
Instream Storage Structure, Khalpal
Binding of reinforcement for Barrage Bay No-2, Raft is under progress.
20/100
Instream Storage Structure, Khalpal
Curing of Gravity floor & End sill is in progress.
21/100
Instream Storage Structure, Khalpal
Curing of Piers is in progress.
22/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering &Binding of reinforcement for RHS Divide wall, 3rd lift is under progress.
23/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of Double pier, 1st lift is under progress.
24/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for LHS side Raft is under progress.
25/100
Barrage across river Turi & Guntat
Work is in progress at Turi barrage site.
26/100
Barrage across river Turi & Guntat
Site visit of Chief Engineer, SE NID, SDO, JE's, PMC site engineers along with agency representatives to Turi guntat site.
27/100
UGPL, Right Lower Suktel Canal Division
OCS chamber piping work is in progress of OCS No-0213007-C01A at village Bairasar in presence of DoWR AE and PMC team.
28/100
UGPL, Right Lower Suktel Canal Division
Inspected of BFV and BFV Chamber is in progress for 200mm DIa HDPE pipe from J 7021 to J-7100 (p-7109) at village Bandanakata in presence of PMC team.
29/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Gantry Girder No-30 done in presence of Client & PSS Team.
30/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No- 0213124- C02A near village Jamsara in presence of DoWR JE and PMC team.
31/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-30 is under progress in presence of Client & PSS Team.
32/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of D/S Flared out wall, Raft at Block No-5 done in presence of Client & PSS Team.
33/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flared out wall, Raft at Block No-5 is under progress in presence of Client & PSS Team.
34/100
UGPL, Right Lower Suktel Canal Division
1ha Outlet RCC hume pipe fixing work is in progress of OCS No- 0201211- C12B - SC 03 at village Barkani in presence of DoWR JE and PMC team.
35/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 90 mm) of Barrage Bay No3 Gravity floor done in presence of Client & PSS Team.
36/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Barrage Bay No3 Gravity floor done in presence of Client & PSS Team
37/100
Instream Storage Structure, Khalpal
Curing of Piers & Gravity floor is in progress.
38/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M20A20 (Value 90 mm) of LHS side Gravity floor PCC done in presence of Client & PSS Team.
39/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for LHS side Raft is under progress.
40/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Testing of Compressive M20A20 (Strength is 17.89/mm2 for 07 days) of RHS D/S Gravity floor and M25A20 (Strength is 29.79/mm2 for 28 days) of RHS Mid-pier, 1st lift has done in presence of Client & PSS team.
41/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering &Binding of reinforcement for RHS Double pier, 1st lift is under progress.
42/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for RHS Divide wall, 3rd lift is under progress.
43/100
Instream Storage Structure, Jharbeda
Slump testing M20A20 (Value 50 mm) of RHS D/S Training wall, Footing, 3rd Layer done in presence of Client & PSS Team.
44/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of RHS D/S Training wall, Footing, 3rd Layer is under progress in presence of Client & PSS Team.
45/100
Instream Storage Structure, Jharbeda
Dewatering work is in Progress.
46/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-6 is under progress.
47/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-8, 5th lift is under progress.
48/100
Instream Storage Structure, Jharbeda
Curing of RHS (A2) Footing is under progress.
49/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
50/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.33/mm2 for 07 days) of Pier No-1, 6th lift and (Strength is 30.95/mm2 for 28 days) of D/S Flank wall, Raft at Block No-5 and (Strength is 31.04/mm2 for 28 days) of Abutment (A1), 6th lift and (Strength is 30.81/mm2 for 28 days) of Pier No-21, 11th lift and M35A20 (Strength is 42.15/mm2 for 28 days) of Gantry Girder No-12 has done in presence of Client & PSS team.
51/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-30, 12th lift with pier Cap done in presence of Client & PSS Team.
52/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-30, 12th lift with pier Cap is under progress in presence of Client & PSS Team.
53/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank Cut-off wall at Block No-1 is under progress.
54/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-2, 5th lift is under progress.
55/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall, Raft at Block No-5 is under progress.
56/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Abutment (A1), 5th lift is under progress.
57/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
58/100
Instream Storage Structure, Sirigida
Joint verification conducted for Govt. land alienation as well as felling of trees for O&M building construction by R.I, Godibandha, FRO, OFDC along with A.E.E & A.E, AID and PSS team.
59/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 85 mm) of Barrage Bay No-3 Gravity floor done in presence of Client & PSS Team.
60/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Barrage Bay No-3 Gravity floor done in presence of Client & PSS Team.
61/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 165 mm) of D/S Panel No-11 at Barrage Bay No-1 done in presence of Client & PSS Team.
62/100
Instream Storage Structure, Khalpal
Concreting M25A20 of D/S Panel No-11 at Barrage Bay No-1 done in presence of Client & PSS Team
63/100
Instream Storage Structure, Khalpal
Diaphragm wall cage placing for D/S Panel No-11 at Barrage Bay No-1 in presence of Client & PSS Team.
64/100
Instream Storage Structure, Khalpal
Excavation of Diaphragm wall D/S Panel No-11 at Barrage Bay No-1 is under progress in presence of Client & PSS Team.
65/100
Instream Storage Structure, Khalpal
Curing of Gravity floor is in progress.
66/100
Instream Storage Structure, Khalpal
Curing of Piers is in progress.
67/100
Instream Storage Structure, Gudvella
Shuttering work of Post is under progress at site on 03.05.2026
68/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 03.05.2026
69/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 03.05.2026
70/100
Instream Storage Structure, Gudvella
Cast of posts of U/s side of span -7 on 02.05.2026
71/100
Instream Storage Structure, Gudvella
Shuttering work of Post is under progress at site on 02.05.2026
72/100
Instream Storage Structure, Gudvella
Curing work at site on 02.05.2026
73/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 02.05.2026
74/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 02.05.2026
75/100
Instream Storage Structure, Gudvella
Cast of posts of U/s side of span -8 and span -9 on 01.05.2026
76/100
Instream Storage Structure, Gudvella
Cast of concrete M25A20 GRADE at 1st floor slab building is in progress in the presence of Dept JE , site engineer of PMC and agency at site. The slump test value is 75mm on 01.05.2026
77/100
Instream Storage Structure, Gudvella
Cast of concrete M25A20 GRADE at 1st floor slab building is in progress in the presence of Dept JE , site engineer of PMC and agency at site. The slump test value is 75mm on 01.05.2026
78/100
Instream Storage Structure, Gudvella
The 1st floor slab of the control room building is ready for concreting with M25A20 grade concrete on 01.05.2026
79/100
UGPL, Left Lower Suktel Canal Division
300mm Dia DI pipe line Air vàlve fixing work is in progress of Lm-9 from J-73 to J-293 at village Bhadra
80/100
Instream Storage Structure, Gudvella
Shuttering work of Post is under progress at site on 01.05.2026
81/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 01.05.2026
82/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 01.05.2026
83/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete at pier no. 11 on 03.05.2026
84/100
Instream Storage Structure, Nandagaon
Curing at U/S right divide wall on 03.05.2026
85/100
Instream Storage Structure, Nandagaon
Shuttering for Block out portion at pier no.10 on 03.05.2026
86/100
Instream Storage Structure, Nandagaon
Curing is in progress at U/S right divide wall on 02.05.2026
87/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no.9&10 on 02.05.2026
88/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress on 02.05.2026
89/100
Instream Storage Structure, Nandagaon
Monorail walkway painting work under progress on 02.05.2026
90/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no.8,9&10 on 01.05.2026
91/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress on 01.05.2026
92/100
Instream Storage Structure, Nandagaon
Barrage bay gate painting work is under progress on 01.05.2026
93/100
Instream Storage Structure, Nandagaon
Monorail walkway primer painting work is under progress on 01.05.2026
94/100
UGPL, Right Lower Suktel Canal Division
External drain brick masonry work is in progress at Pump House.
95/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No- 0213124 - C09B near village Khamarmunda in presence of DoWR JE and PMC team.
96/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door and angle fixing work is in progress OCS No:-0201297-C03B at village Rinabachan in presence of PMC team.
97/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI branch Tee(350X150X 350) connection at j-482, RM-9, near village Pandarani in presence of DoWR AE and PMC team.
98/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for laying of 125mm Dia HDPE pipeline from node J-461 to LO-218, LM11 near village Khandajuri in presence of PMC team.
99/100
UGPL, Left Lower Suktel Canal Division
Butt fusion jointing work is in progress for 125mm Dia HDPE pipe of J-461 to LO-218 LM-11 Near village Kandajuri in presence of PMC team.
100/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI to HDPE pipe connection at J-72, LM-9 near village Bhadra in presence of PMC team.