GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Gudvella
Cast of concrete final lift PCC M20A20 grade at U/s curtain wall from A2 to P8 with RL 148.20m to 148.60m is under progress in the presence of Dept JE, site engineer of PMC and agency. The slump test value is found 75mm on 09.03.2026
2/100
Instream Storage Structure, Gudvella
Cast of concrete final lift PCC M20A20 grade at U/s curtain wall from A2 to P8 with RL 148.20m to 148.60m is under progress in the presence of Dept JE, site engineer of PMC and agency. The slump test value is found 75mm on 09.03.2026
3/100
Instream Storage Structure, Gudvella
Roller fit up work at barrage gate is under progress on 09.03.2026
4/100
Instream Storage Structure, Gudvella
Final alignment (block out area) work at A1 & P1 is under progress on 09.03.2026
5/100
Instream Storage Structure, Gudvella
Reinforcement and shuttering work at block out area of pier -6 is under progress on 09.03.2026
6/100
Instream Storage Structure, Gudvella
Shuttering at u/s curtain wall is under progress on 09.03.2026
7/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
PMC team-Chandikhole visited ISS- Chaudhurygada today to monitor Barragebay casting work.
8/100
Instream Storage Structure, Gudvella
Brick work at building area is under progress on 09.03.2026
9/100
Integrated Barrage across river Kochila and across river Baitarini
PMC team-Chandikhole visited ISS – Kochila & Baitarani today to monitor RCC work.
10/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 2nos. Cross girders at pier no.13 & right abutment is in progress through concrete pump in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is mm on 09.03.2026
11/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 2nos. Cross girders at pier no.13 & right abutment is in progress through concrete pump in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is mm on 09.03.2026
12/100
Instream Storage Structure, Nandagaon
• 2.Reinforcement works including shuttering for casting of 2nos. cross girders with RCC M35A20 grade at Pier No.:-13 & right abutment for span-14 of undersluice bay-4 is completed and checked in presence of PM,EPC agency, Site Engineers of PMC and Site Engineer of EPC Agency as follows: (i)Laying & placing in proper position of 2 layers 16mm dia bottom main bars @ 3nos. at 1st.layer & 2nos. at 2nd layer tied with 10mm dia 2-Legged stirrups @150mm C/C including binding 10mm dia dist. bars on both sides of vertical faces of girders are completed. (ii) Rigid and smooth shuttering with 40mm clear cover at bottom and both vertical faces are completed. (iii) Fixing & placing of 8mm dia B-type mesh bars @ 2 layers at both end points of girder is completed. (iv)The area is ready and passed by SE KID Bhawanipatna for placing with RCC M35A20 grade on 09.03.2026
13/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of 3nos. CC blocks at D/S left Flared out wall i.e 1no. of size 6.0x1.5x0.6m at sec.2-2 for 15th lift and 1no. of size 6.0x1.5x0.6m from sec. 4-4 to sec. 5-5 for 16th lift and 1no. of size 1.5x1.5x0.6m from sec.5-5 to sec.6-6 for 17th lift of 0.6m hight upto RL-244.80m is in progress in presence of PM EPC agency Site Engineers of PMC & EPC agency. The slump test value is 77mm on 09.03.2026
14/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of 3nos. CC blocks at D/S left Flared out wall i.e 1no. of size 6.0x1.5x0.6m at sec.2-2 for 15th lift and 1no. of size 6.0x1.5x0.6m from sec. 4-4 to sec. 5-5 for 16th lift and 1no. of size 1.5x1.5x0.6m from sec.5-5 to sec.6-6 for 17th lift of 0.6m hight upto RL-244.80m is in progress in presence of PM EPC agency Site Engineers of PMC & EPC agency. The slump test value is 77mm on 09.03.2026
15/100
Instream Storage Structure, Nandagaon
• 1.The casting of CC blocks at following area has been checked in presence of PM,EPC agency, Site Engineer of PMC & EPC Agency: (i)3Nos. CC blocks at D/S left Flared out wall i.e 1no. of size 6.0x1.5x0.6m at sec.2-2 for 15th lift and 1no. of size 6.0x1.5x0.6m from sec. 4-4 to sec. 5-5 for 16th lift and 1no. of size 1.5x1.5x0.6m from sec.5-5 to sec.6-6 for 17th lift of 0.6m hight upto RL-244.80m is completed. (ii). Filling of inverted filter materials covering with LDPE paper at adjacent to each CC block in earth side are done before placement. (iii) Application of 2 coat bitumen paint at cj's concrete surface is done. (iv). Area is ready and passed by SE KID, Bh. Patna to place concrete with PCC M20A20 grade on 09.03.2026
16/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of Reinforcement for RHS Divide wall, 3rd lift slope portion is under progress.
17/100
Instream Storage Structure, Nandagaon
Barrage bay gate no. 9 sill beam erection work under progress on 09.03.2026
18/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering & Binding of Reinforcement for LHS D/S Divide wall, 3rd lift is under progress.
19/100
Instream Storage Structure, Jharbeda
Slump testing M20A20 (Value 40 mm) of D/S Pier No-7 to Pier No-8 Gravity floor, 2nd lift done in presence of Client & PSS Team.
20/100
Instream Storage Structure, Nandagaon
Monorail walkway MIG welding under progress on 09.03.2026
21/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of D/S Pier No-7 to Pier No-8 Gravity floor, 2nd lift is under progress in presence of Client & PSS Team.
22/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for cross girder at right abutment & pier no.13 is in progress on 09.03.2026
23/100
Instream Storage Structure, Nandagaon
Shuttering for RCC deck slab at span-14 is in progress on 09.03.2026
24/100
Instream Storage Structure, Nandagaon
Curing at RCC deck slab. wall is in progress on 09.03.2026
25/100
Integrated Barrage across river Kochila and across river Baitarini
AEE and AE of Akhuapada irrigation Division visited ISS- Kochila & Baitarani today. PMC team- Chandikhole and representatives of Agency were also present at site.
26/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Installation of first-stage embedded parts (stoplog and service gate seal beams) is in progress at the Choudhary Gada ISS Project.
27/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay raft PCC work in progress at baitarani iss project.
28/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Site Visit of OCCL S.M and PMC MBBS chandikhol today to TIKHIRI ISS PROJECT and CHOUDHARY GADA ISS PROJECT Discussion about project work with agency.
29/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site.
30/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and Irr. Eng. Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site and U/S right side diaphragm wall panel no -57 casting, Right side pile no-144, 123 casting and Rhs under-sluice panel no- R61 concrete pouring.
31/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and Irr. Eng. Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site and U/S right side diaphragm wall panel no -57 casting, Right side pile no-144, 123 casting and Rhs under-sluice panel no- R61 concrete pouring.
32/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-7, 6th lift is under progress.
33/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-8, 3rd lift is under progress.
34/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
35/100
Instream Storage Structure, Jharbeda
Placing of CC Blocks for D/S Barrage portion work is under progress.
36/100
Instream Storage Structure, Jharbeda
Curing of Wearing coat is under progress.
37/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of D/S Flank wall Cut-off, 2nd lift at Block No-5 done in presence of Client & PSS Team.
38/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flank wall Cut-off, 2nd lift at Block No-5 is under progress in presence of Client & PSS Team.
39/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
40/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
41/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
42/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
43/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
44/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-6, 10th lift at Block No-2 done in presence of Client & PSS Team.
45/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-6, 10th lift at Block No-2 is under progress in presence of Client & PSS Team.
46/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
47/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
48/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
49/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
50/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
51/100
Instream Storage Structure, Hamirpur
Cleaning of reinforcement for U/S Abutment (A1) at Block No-1 is under progress by Sand blasting method.
52/100
Instream Storage Structure, Hamirpur
R.D.U assembly No-6 work is in progress.
53/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Cross Girder (Bay No-23) is under progress.
54/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Abutment (A1), 5th lift is under progress.
55/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-15, 6th lift is under progress.
56/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-16, 8th lift is under progress.
57/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-20, 15th lift is under progress.
58/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-21, 6th lift is under progress.
59/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Girder is under progress.
60/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flared out wall, 2nd lift at Block No-5 is under progress.
61/100
Instream Storage Structure, Khalpal
Curing of piers is under progress.
62/100
Instream Storage Structure, Khalpal
Curing of counterfort & abutment wall is under progress.
63/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
64/100
UGPL, Right Lower Suktel Canal Division
Floor finishing concrete pouring work is in progress at fire fighting system of Pump House.
65/100
UGPL, Left Lower Suktel Canal Division
Air Vacuum valve installation work is in progress at LM-7 LO-140B near village Uperuda .
66/100
UGPL, Right Lower Suktel Canal Division
25mm bitumen sealing filling work is in progress for expansion joint of RCC road of 20mm at Pump House in presence of PMC team.
67/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 85 mm) of LHS Mid-pier, 8th lift done in presence of Client & PSS Team.
68/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS Mid-pier, 8th lift is under progress in presence of Client & PSS Team.
69/100
Instream Storage Structure, Jharbeda
Dewatering work is under progress.
70/100
Instream Storage Structure, Jharbeda
Curing work is under progress.
71/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-30, 10th lift done in presence of Client & PSS Team.
72/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-30, 10th lift is under progress in presence of Client & PSS Team.
73/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Girder is under progress.
74/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-21, 6th lift is under progress.
75/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-20 with pedestal is under progress.
76/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-6, 10th lift is under progress.
77/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-7, 14th lift is under progress.
78/100
Instream Storage Structure, Khalpal
Curing of piers is under progress.
79/100
Instream Storage Structure, Khalpal
Gravity Floor Inverted Filter work in progress.
80/100
Instream Storage Structure, Khalpal
Binding of reinforcement for Barrage bay Raft at Block No-4 is under progress.
81/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 80 mm) of LHS Double pier, 7th lift done in presence of Client & PSS Team.
82/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS Double pier, 7th lift is under progress in presence of Client & PSS Team.
83/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering & binding of reinforcement for RHS Counterfort with Abutment wall, 1st lift is under Progress.
84/100
Instream Storage Structure, Jharbeda
INSPECTED BY ISS SITE ALONG WITH A.E, S.D.O, RID & PSS TEAM DISCUSSED WITH LOCAL PEOPLE REGARDING LAND AQUISITION.
85/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of D/S Flank wall, Cut-off at Block No-5 done in presence of Client & PSS Team.
86/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flank wall, Cut-off at Block No-5 is under progress in presence of Client & PSS Team.
87/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 95 mm) of Pier No-9, 16th lift with pedestal done in presence of Client & PSS Team.
88/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-22, 16th lift Pier No-9, 16th lift with pedestal is under progress in presence of Client & PSS Team.
89/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for OCS chamber of OCS No-0213028-C02A at village Bhadrapali.
90/100
Instream Storage Structure, Hamirpur
Slump testing M15A40 (Value 40 mm) of D/S Toe wall, 1st lift at Block No-5 done in presence of Client & PSS Team.
91/100
Instream Storage Structure, Hamirpur
Concreting M15A40 of D/S Toe wall, 1st lift at Block No-5 is under progress in presence of Client & PSS Team.
92/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-22, 16th lift at Block No-4 done in presence of Client & PSS Team.
93/100
Instream Storage Structure, Gudvella
Cast of concrete PCC M20A20 grade at u/s curtain wall of grade M20A20 from RL 147.70 m to 148.20 m is completed in the presence of Dept JE, site engineer of PMC and agency. The slump test value is found 74mm on 08.03.2026
94/100
Instream Storage Structure, Gudvella
Cast of concrete PCC M20A20 grade at u/s curtain wall of grade M20A20 from RL 147.70 m to 148.20 m is completed in the presence of Dept JE, site engineer of PMC and agency. The slump test value is found 74mm on 08.03.2026
95/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-22, 16th lift at Block No-4 is under progress in presence of Client & PSS Team.
96/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS no- 0213040-C10B at village Dumerbahal in presence of PMC team.
97/100
Instream Storage Structure, Gudvella
The final inspection/checking work is in progress at the blockout areas of the undersluice bay and barrage bay to ensure proper alignment and readiness for further work on 08.03.2026
98/100
Instream Storage Structure, Gudvella
The final inspection/checking work is in progress at the blockout areas of the undersluice bay and barrage bay to ensure proper alignment and readiness for further work on 08.03.2026
99/100
Instream Storage Structure, Gudvella
The final inspection/checking work is in progress at the blockout areas of the undersluice bay and barrage bay to ensure proper alignment and readiness for further work on 08.03.2026
100/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Deck slab (Bay No-24) at Block No-4 done in presence of Client & PSS Team.

Enter Login Details

Forgot Password ?