1/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door fixing work is in progress OCS No:-0213133-C01B at village Sauntpur in presence of PMC team.
2/100
UGPL, Right Lower Suktel Canal Division
Valve Chamber Pre-cast slab concrete pouring work is in progress of Pump House in presence of PMC team.
3/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No- 0213055- C04B near village Bubel in presence of PMC team.
4/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for Gap closing of 350mm Dia DI pipeline from node J-511 to J-285, RM-11 near village Burda in presence PMC team.
5/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress of 90mm Dia HDPE pipeline from RO-56 to RO-56B, RM-3 near village Dhamanasar in presence of DoWR SDO and PMC team.
6/100
UGPL, Left Lower Suktel Canal Division
Butt fusion jointing work is in progress of 280mm Dia HDPE pipe from J- 512 to J-513 near village Sakhma in presence of PMC.
7/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for laying of 140mm Dia HDPE pipe line at RLO- 6, LM-18 near village Maharpali in presence of PMC team.
8/100
Instream Storage Structure, Dhanei
Visit the ISS Sanabaragam- PMC team consisting of HME and Site Engineer Mechanical. The following observations made
on HM Equipment -2nd Stage embedded parts placement in both Barrage Bays- Stop-log gate Grooves:
1. The placement of Roller cum Side Seal tracks , Guide tracks completed as per Approved drawing, checked alignment of
items, on parameters like C/C Roller track, C/C of Side Seal Seats and F/F dimension of Side Guide tracks, found OK.
2. Instructed the agency on cleaning of rust on the above mentioned items placed in grooves, after rust cleaning, clearance
will be given for concreting.
9/100
Instream Storage Structure, Dhanei
Visit the ISS Sanabaragam- PMC team consisting of HME and Site Engineer Mechanical. The following observations made
on HM Equipment -2nd Stage embedded parts placement in both Barrage Bays- Stop-log gate Grooves:
1. The placement of Roller cum Side Seal tracks , Guide tracks completed as per Approved drawing, checked alignment of
items, on parameters like C/C Roller track, C/C of Side Seal Seats and F/F dimension of Side Guide tracks, found OK.
2. Instructed the agency on cleaning of rust on the above mentioned items placed in grooves, after rust cleaning, clearance
will be given for concreting.
10/100
Instream Storage Structure, Dhanei
Visit of SD Expert along with site engineer mechanical to the Iss Site. Inspected the overall progress of mechanical work
and Erection of mechanical gate components in progress.
11/100
Instream Storage Structure, Dhanei
Visit of SD Expert along with site engineer mechanical to the Iss Site. Inspected the overall progress of mechanical work
and Erection of mechanical gate components in progress.
12/100
Instream Storage Structure, Dhanei
Visit of SD Expert along with site engineer mechanical to the Iss Site. Inspected the overall progress of mechanical work
and Erection of mechanical gate components in progress.
13/100
Instream Storage Structure, Dhanei
Visit of SD Expert along with site engineer mechanical to the Iss Site. Inspected the overall progress of mechanical work
and Erection of mechanical gate components in progress.
14/100
Instream Storage Structure, Dhanei
A joint inspection of ISS Sanabaragrama was carried out by a team comprising the Chief Engineer of RBVN Basin, Additional
Chief Engineer, Superintending Engineer, SDO, AE, and the Deputy Team Leader of PMC along with their team.
During the visit, the team not only inspected the site but also assessed the overall progress of the works.
Observing the works at site, the agency has been directed to immediately initiate and carry out all work simultaneously on
multiple fronts, including mechanical works, gate works, establishment of the electrical substation, completion of the
O&M building, initiation of the afflux bond, and progress of land acquisition.
15/100
Instream Storage Structure, Dhanei
A joint inspection of ISS Sanabaragrama was carried out by a team comprising the Chief Engineer of RBVN Basin, Additional
Chief Engineer, Superintending Engineer, SDO, AE, and the Deputy Team Leader of PMC along with their team.
During the visit, the team not only inspected the site but also assessed the overall progress of the works.
Observing the works at site, the agency has been directed to immediately initiate and carry out all work simultaneously on
multiple fronts, including mechanical works, gate works, establishment of the electrical substation, completion of the
O&M building, initiation of the afflux bond, and progress of land acquisition.
16/100
Instream Storage Structure, Dhanei
Visit of Hydro-mechanical Expert along with Mechanical Site Engineer PMC to the lSS Site. Inspected the overall progress of site, 1. the placement of Sill Beam in Left Abutment Barrage Bay Stop-log gate groove completed as per Approved drawing, checked alignment and found ok. 2. Instructed the agency on rust cleaning of this particular Sill Beam, after cleaning, clearance will be given for concreting. 3. Hoist trestles anchor bolts and plates placement work is started in block outs in Left Abutment pier.
17/100
Instream Storage Structure, Dhanei
Visit of Hydro-mechanical Expert along with Mechanical Site Engineer PMC to the lSS Site. Inspected the overall progress of site, 1. the placement of Sill Beam in Left Abutment Barrage Bay Stop-log gate groove completed as per Approved drawing, checked alignment and found ok. 2. Instructed the agency on rust cleaning of this particular Sill Beam, after cleaning, clearance will be given for concreting. 3. Hoist trestles anchor bolts and plates placement work is started in block outs in Left Abutment pier.
18/100
Instream Storage Structure, Dhanei
Visit of Hydro-mechanical Expert along with Mechanical Site Engineer PMC to the lSS Site. Inspected the overall progress of site, 1. the placement of Sill Beam in Left Abutment Barrage Bay Stop-log gate groove completed as per Approved drawing, checked alignment and found ok. 2. Instructed the agency on rust cleaning of this particular Sill Beam, after cleaning, clearance will be given for concreting. 3. Hoist trestles anchor bolts and plates placement work is started in block outs in Left Abutment pier.
19/100
Instream Storage Structure, Dhanei
Visit of DyTL and QA/QC Expert along with Site Engineer PMC to the lSS Site. Inspected the overall progress of site, 1. Barrage bay stop log gate sill beam fixing continuing. 2. O & M building staircase room brick work in progress. 3. Earth work of Left Afflux Bond continues and alignment of right Afflux Bond Inspected by Team.
20/100
Instream Storage Structure, Dhanei
Visit of DyTL and QA/QC Expert along with Site Engineer PMC to the lSS Site. Inspected the overall progress of site, 1. Barrage bay stop log gate sill beam fixing continuing. 2. O & M building staircase room brick work in progress. 3. Earth work of Left Afflux Bond continues and alignment of right Afflux Bond Inspected by Team.
21/100
Instream Storage Structure, Dhanei
Visit of DyTL and QA/QC Expert along with Site Engineer PMC to the lSS Site. Inspected the overall progress of site, 1. Barrage bay stop log gate sill beam fixing continuing. 2. O & M building staircase room brick work in progress. 3. Earth work of Left Afflux Bond continues and alignment of right Afflux Bond Inspected by Team.
22/100
Instream Storage Structure, Dhanei
Visit of Addl CE RB Basin, SE BeID along with SDO & AE including DTL accompanied by PMC Team to the lSS Site. The team inspected various ongoing civil & mechanical activities at Site. Reviewed regarding expeditious execution of remaining works and to complete the same without further delay.
23/100
Instream Storage Structure, Dhanei
Visit of Addl CE RB Basin, SE BeID along with SDO & AE including DTL accompanied by PMC Team to the lSS Site. The team inspected various ongoing civil & mechanical activities at Site. Reviewed regarding expeditious execution of remaining works and to complete the same without further delay.
24/100
Instream Storage Structure, Dhanei
Visit of Addl CE RB Basin, SE BeID along with SDO & AE including DTL accompanied by PMC Team to the lSS Site. The team inspected various ongoing civil & mechanical activities at Site. Reviewed regarding expeditious execution of remaining works and to complete the same without further delay.
25/100
Integrated Barrage across river Kochila and across river Baitarini
AEE of Akhuapada irrigation division, PMC and representative of Agency visited ISS-Kochila today. LHS Abutment wall Casting from level 3.55m to 4.9m. work in progress at baitarani iss project.
26/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
LHS under sluice end Pier 1st lift casting work in progress at choudhary gada iss project.
27/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.96/mm2 for 28 days) of Pier No-5, 4th lift and (Strength is 30.99/mm2 for 28 days) of Pier No-16, 12th lift and (Strength is 30.79/mm2 for 28 days) of Fish pass Raft at Block No-1 and M35A20 (Strength is 37.19/mm2 for 07 days) of Gantry Girder No-25 and M15A40 (Strength is 13.18/mm2 for 07 days) of D/S Toe wall, 3rd lift at Block No-5 has done in presence of Client & PSS team.
28/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Abutment (A1), 5th lift is under progress.
29/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-2, 7th lift is under progress.
30/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 90 mm) of U/S under sluice End sill, Final lift done in presence of Client & PSS Team.
31/100
Instream Storage Structure, Khalpal
Concreting M20A20 of U/S under sluice End sill, Final lift is under progress in presence of Client & PSS Team.
32/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 85 mm) of Barrage Bay No-3 Gravity floor done in presence of Client & PSS Team.
33/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Barrage Bay No-3 Gravity floor is under progress in presence of Client & PSS Team.
34/100
Instream Storage Structure, Khalpal
Curing of Piers, End sill & Gravity floor is in progress.
35/100
UGPL, Right Lower Suktel Canal Division
DI to HDPE pipe connection work is in progress at J-512 in presence of PMC team near village Sakma.
36/100
UGPL, Right Lower Suktel Canal Division
Butt fusion jointing work is in progress of 280mm Dia HDPE pipe from J- 512 to J-513 in presence of PMC Team near village Sakhma.
37/100
UGPL, Right Lower Suktel Canal Division
Bermad's instruments installation work is in progress of OCS No- 0201345-C06A in presence of SE, SDO of DoWR & PMC team near village Madhiapali.
38/100
UGPL, Right Lower Suktel Canal Division
HDPE pipe fixing work is in progress of OCS No- 0201206-C09A near village Dhubaudar.
39/100
Instream Storage Structure, Gudvella
• Today visited ACE, Balangir Irrigation Circle at ISS Gudvella.
1. He checked the overall site conditions and instructed the agency to procure stone for stone pitching without delay.
2. He also inspected the shuttering and reinforcement work of the 1st floor slab of the control room on 30.04.2026
40/100
Instream Storage Structure, Gudvella
• Visited IE Expert, QC Expert at ISS Gudvella site . Dept JE , site engineers of PMC n agency were present.
1. Checked the site condition and reinforcement work of slab at 1st floor building at site on 30.04.2026
41/100
Instream Storage Structure, Gudvella
• Visited IE Expert, QC Expert at ISS Gudvella site . Dept JE , site engineers of PMC n agency were present.
1. Checked the site condition and reinforcement work of slab at 1st floor building at site on 30.04.2026
42/100
Instream Storage Structure, Gudvella
Shuttering work of Post is under progress at site on 30.04.2026
43/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 30.04.2026
44/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 30.04.2026
45/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 29.04.2026
46/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 29.04.2026
47/100
Instream Storage Structure, Gudvella
No work at both civil and mechanical site due to labour issue on 29.04.2026
48/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No- 0213052- C09B near village Jhara Balangir in presence of PMC team.
49/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 75mm Dia HDPE pipe Gap closing node from RO-56 to RO-56B RM-3 near village Ramsingha in presence of PMC team.
50/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 28.04.2026
51/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 28.04.2026
52/100
Instream Storage Structure, Gudvella
No civil work is going on at the site. Only curing of posts and railing is going on at site on 28.04.2026
53/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI Tee (350X140X350) connection at J-231 in presence of PMC team near village Kutenpali.
54/100
Instream Storage Structure, Gudvella
No work due to labour issue at mechanical site on 28.04.2026
55/100
Instream Storage Structure, Nandagaon
Monorail walkway sand blasting work under progress on 30.04.2026
56/100
Instream Storage Structure, Nandagaon
Gate no 14 both stoplog gate and barrage bay gate 2nd stage embedded parts erection work under progress on 30.04.2026
57/100
Instream Storage Structure, Nandagaon
Curing work is in progress on 30.04.2026
58/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress on 30.04.2026
59/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress on 29.04.2026
60/100
Instream Storage Structure, Nandagaon
Curing work progress on 29.04.2026
61/100
Instream Storage Structure, Nandagaon
Barrage bay gate painting work under progress on 29.04.2026
62/100
Instream Storage Structure, Nandagaon
Gate no 14 both stoplog gate and barrage bay gate 2nd stage embedded parts erection work under progress on 29.04.2026
63/100
Instream Storage Structure, Nandagaon
Barrage bay gate sand blasting work under progress on 28.04.2026
64/100
Instream Storage Structure, Nandagaon
Barrage bay gate primer painting work under progress on 28.04.2026
65/100
Instream Storage Structure, Nandagaon
Gate no 14 both stoplog gate and barrage bay gate 2nd stage embedded parts erection work under progress on 28.04.2026
66/100
Instream Storage Structure, Nandagaon
Curtain wall shuttering is in progress on 28.04.2026
67/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering is in progress at U/S right divide wall on 28.04.2026
68/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for LHS side Raft is under progress.
69/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M25A20 (Value 95 mm) of Divide wall, 9th lift done in presence of Client & PSS Team.
70/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of Divide wall, 9th lift is under progress in presence of Client & PSS Team.
71/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 85 mm) of LHS D/S End sill under sluice & Barrage Bay portion done in presence of Client & PSS Team.
72/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS D/S End sill under sluice & Barrage Bay portion is under progress in presence of Client & PSS Team.
73/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering & Staging of LHS under sluice Deck slab is under progress.
74/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for RHS Divide wall, 3rd lift is under progress.
75/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Excavation of RHS D/S Divide wall is under progress.
76/100
Instream Storage Structure, Jharbeda
Slump testing M25A20 (Value 85 mm) of Pier No-5, 7th lift done in presence of Client & PSS Team.
77/100
Instream Storage Structure, Jharbeda
Concreting M25A20 of Pier No-5, 7th lift is under progress in presence of Client & PSS Team.
78/100
Instream Storage Structure, Jharbeda
Shuttering of RHS D/S Flank wall is under progress.
79/100
Instream Storage Structure, Jharbeda
Shuttering of RHS D/S Training wall is under progress.
80/100
Instream Storage Structure, Jharbeda
Shuttering & Binding of reinforcement for Pier No-8 is under progress.
81/100
Instream Storage Structure, Jharbeda
Shuttering & Binding of reinforcement for RHS (A2) wall, 1st lift is under progress.
82/100
Instream Storage Structure, Jharbeda
Curing of RHS D/S under sluice Gravity floor is under progress.
83/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
84/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-13, 15th lift done in presence of Client & PSS Team.
85/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-13, 15th lift is under progress in presence of Client & PSS Team.
86/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-29 done in presence of Client & PSS Team.
87/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-29 is under progress in presence of Client & PSS Team.
88/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.96/mm2 for 28 days) of Pier No-5, 4th lift and (Strength is 30.99/mm2 for 28 days) of Pier No-16, 12th lift and (Strength is 30.79/mm2 for 28 days) of Fish pass Raft at Block No-1 and M35A20 (Strength is 37.19/mm2 for 07 days) of Gantry Girder No-25 and M15A40 (Strength is 13.18/mm2 for 07 days) of D/S Toe wall, 3rd lift at Block No-5 has done in presence of Client & PSS team.
89/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-3 welding work is in progress.
90/100
Instream Storage Structure, Hamirpur
MS plate marking and cutting for hoist platform stiffener work is in progress.
91/100
Instream Storage Structure, Hamirpur
Shuttering of Deck slab is under progress.
92/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall, Raft at Block No-5 is under progress.
93/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Abutment (A1), 5th lift is under progress.
94/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
95/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 80 mm) of Barrage Bay No-3 Gravity floor done in presence of Client & PSS Team.
96/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Barrage Bay No-3 Gravity floor is under progress in presence of Client & PSS Team.
97/100
Instream Storage Structure, Khalpal
Curing of Gravity floor is in progress.
98/100
Instream Storage Structure, Khalpal
Curing of Piers & End sill is in progress.
99/100
Instream Storage Structure, Khalpal
Testing of Compressive M20A20 (Strength is 20.09/mm2 for 07 days) of Barrage Bay No-3 Gravity floor has done in presence of Client & PSS team.
100/100
Barrage across river Turi & Guntat
Gates and columns installation is in progress at guntat site.
❮
❯