GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of D/S Flank wall Cut-off, 1st lift at Block No-1 done in presence of Client & PSS Team.
2/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flank wall Cut-off, 1st lift at Block No-1 is under progress in presence of Client & PSS Team.
3/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-1, 10th lift done in presence of Client & PSS Team.
4/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-1, 10th lift is under progress in presence of Client & PSS Team.
5/100
Instream Storage Structure, Hamirpur
MS plate marking and cutting for column work is in progress.
6/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-8 fixing work is in progress.
7/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
8/100
Instream Storage Structure, Hamirpur
Shuttering of Deck slab (Bay No-10 & 11) is under progress.
9/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 42.44/mm2 for 28 days) of Gantry Girder No-32 and M25A20 (Strength is 30.96/mm2 for 28 days) of Pier No-2, 6th lift and (Strength is 21.04/mm2 for 07 days) of Pier No-6, 14th lift and (Strength is 21.63/mm2 for 07 days) of Pier No-26, 13th lift and (Strength is 30.86/mm2 for 28 days) of D/S Flared out wall Raft (Bank side) has done in presence of Client & PSS team.
10/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4, 5th lift is under progress.
11/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall at Block No-1 is under progress.
12/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flank wall Cut-off at Block No-1 is under progress.
13/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Abutment (A1), 7th lift at Block No-1 is under progress.
14/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Abutment (A1), 10th lift at Block No-1 is under progress.
15/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M25A20 (Value 95 mm) of LHS Barrage Bay Raft, Final layer done in presence of Client & PSS Team.
16/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of LHS Barrage Bay Raft, Final layer is Completed in presence of Client & PSS Team.
17/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering & alignment of Gate groove is under progress.
18/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
De-Shuttering of Pier Cap is under progress.
19/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering & binding of reinforcement for RHS D/S Counterfort & Wing wall, 1st lift is under progress.
20/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-8, 6th lift is under progress.
21/100
Instream Storage Structure, Jharbeda
Shuttering of LHS U/S (D2) portion footing is under progress.
22/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-6, pier Cap is under progress.
23/100
Instream Storage Structure, Jharbeda
Curing of RHS U/S Flank wall is under progress.
24/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 160 mm) of D/S Panel No-10 at Barrage Bay No-1 done in presence of Client & PSS Team.
25/100
Instream Storage Structure, Khalpal
Concreting M25A20 of D/S Panel No-10 at Barrage Bay No-1 done in presence of Client & PSS Team.
26/100
Instream Storage Structure, Khalpal
Diaphragm wall cage placing for D/S Panel No-10 at Barrage Bay No-1 in presence of Client & PSS Team.
27/100
Instream Storage Structure, Khalpal
Excavation of Diaphragm wall D/S Panel No-10 at Barrage Bay No-1 is under progress.
28/100
Instream Storage Structure, Khalpal
Shuttering & Binding of reinforcement for RHS Double Pier No-25, 1st lift is under progress.
29/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
30/100
Instream Storage Structure, Gudvella
Overhead tank fitting work is in progress on 03.06.2026
31/100
Instream Storage Structure, Gudvella
The door, window and grill fitting work is under progress at ground floor of the building on 03.06.2026
32/100
Instream Storage Structure, Gudvella
Mechanical work is under progress at site on 03.06.2026
33/100
Instream Storage Structure, Gudvella
Filter media laying at the A1 d/s area is in progress before stone pitching of the slope on 03.06.2026
34/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 03.06.2026
35/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 03.06.2026
36/100
Instream Storage Structure, Nandagaon
Placing of CC blocks is in progress at D/S side on 03.06.2026
37/100
Instream Storage Structure, Nandagaon
Curing work is in progress on 03.06.2026
38/100
Instream Storage Structure, Nandagaon
Gate no 14 Undersluice both barrage bay and stoplog gate 2nd stage embedded parts erection work is under progress on 03.06.2026
39/100
UGPL, Right Lower Suktel Canal Division
Joint verification is in progress for outlet of OCS 0201215-CO3A at village Chandanbhati in presence of DoWR JE and PMC team.
40/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for 75mm Dia HDPE pipe of OCS no-0213116-C06A-03 1HA subchak at village Padiabahal,
41/100
UGPL, Left Lower Suktel Canal Division
HDD machine road pushing work is in progress (road crossing) of 75mm Dia HDPE pipe between RO-164 to RO-164B, RM-9 near village Manhira in presence of PMC team.
42/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 75mm Dia HDPE pipe line Extension of 1hactet outlet point LO-44A Z- 4289, LM-3 near village Baghapali in presence of DoWR JE and PMC team.
43/100
UGPL, Left Lower Suktel Canal Division
Approach channel bell mouth portion stone pitching work is in progress at Pump House.
44/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI to HDPE connection and 225mm Dia HDPE pipe line gap closing work is in progress Node from J-74 to J-70, LM-9 near village Kusang.
45/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Pier No-3, 9th lift at Block No-1 done in presence of Client & PSS Team.
46/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-3, 9th lift at Block No-1 is under progress in presence of Client & PSS Team.
47/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of U/S Flared out wall Raft at Block No-1 (River side) done in presence of Client & PSS Team.
48/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of U/S Flared out wall Raft at Block No-1 (River side) is under progress in presence of Client & PSS Team.
49/100
Instream Storage Structure, Hamirpur
Stop-log groove 2nd stage embedded parts roller track alignment work is in progress at (Bay No-12).
50/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 42.59/mm2 for 28 days) of Gantry Girder No-31 has done in presence of Client & PSS team.
51/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-3, 9th lift is under progress.
52/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for U/S Flank wall at Block No-1 is under progress.
53/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Abutment (A1), 10th lift at Block No-1 is under progress.
54/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for Abutment Counterfort and Shuttering of LHS Barrage Bay Raft (Gate groove) is under progress.
55/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 90 mm) of RHS Divide wall, 4th lift done in presence of Client & PSS Team.
56/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of RHS Divide wall, 4th lift is under progress in presence of Client & PSS Team.
57/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering & binding of reinforcement for RHS D/S Counterfort & Wing wall, 1st lift is under progress.
58/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-8, 6th lift is under progress.
59/100
Instream Storage Structure, Jharbeda
Shuttering of LHS U/S (D2) portion footing is under progress.
60/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-6, pier Cap is under progress.
61/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency
62/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of LHS Double pier No-25, 4th lift done in presence of Client & PSS Team.
63/100
Instream Storage Structure, Khalpal
Concreting M25A20 of LHS Double pier No-25, 4th lift is under progress in presence of Client & PSS Team.
64/100
Instream Storage Structure, Khalpal
Testing of Compressive M25A20 (Strength is 35.36/mm2 for 28 days) of U/S Panel No-9 has done in presence of Client & PSS team.
65/100
Instream Storage Structure, Khalpal
Binding of reinforcement for lift side Double Pier No-25, 4th lift is under progress.
66/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
67/100
Instream Storage Structure, Gudvella
The door, window and grill fitting work has started on the ground floor of the building on 02.06.2026
68/100
Instream Storage Structure, Gudvella
Earthwork excavation for stone packing under progress at u/s A1 slope porting on 02.06.2026
69/100
Instream Storage Structure, Gudvella
Fixing of posts at walk way is under progress at site on 02.06.2026
70/100
Instream Storage Structure, Gudvella
Stone pitching work at D/s side of site is under progress on 02.06.2026
71/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 02.06.2026
72/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 02.06.2026
73/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.10,12&13 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 84mm on 02.06.2026
74/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.10,12&13 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 84mm on 02.06.2026
75/100
Instream Storage Structure, Nandagaon
• 3. Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay no.10 of pier no.10 for 10th lift and bay no.11 of pier no.10 for 9th lift and bay no. 13 of pier no. 12&13 for 6th lift at stoplog gate and 5th lift at main gate grooves have been checked and found correct by HM Expert of PMC during his site visit on dt.01.06.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs. (i) Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows: (ii) Chipping of old vertical concrete surface is done. (iii) The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for M35A20 grade on 02.06.2026
76/100
Instream Storage Structure, Nandagaon
Site visit of ISS Nandagaon by Chief Engineer, Subarnarekha Irr. Project(Jala Prabhari), Nuapada on dt. 02.06.2026 in presence of SE, KID, Bhawanipatna, SDO, ISS Nandagaon, Sr. Site Engineer of PMC, GM& PM of EPC Agency and other technical staff of PMC and EPC Agency. Discussion made about the salient feature of the project and the progress of work towards completion of construction works on 02.06.2026
77/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no.13 upto RL-247.0m is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency on 02.06.2026
78/100
Instream Storage Structure, Nandagaon
• 1(i).Fixing & fittings and alignment of All trestle and columns foundation bolts measurements has been checked at pier No.13 for Blockout area of 6.8m length and found correct by HM Expert of PMC during his site visit on dt.1.06.2026 in presence of mechanical Site Engineers of PMC and EPC Agency. (ii) Rigid and smooth shuttering for Blockout area with M35A20 grade at Pier No.13 from RL-246.30m to RL-247.00m are found completed. (iii).The area is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with M35A20 grade on 02.06.2026
79/100
Instream Storage Structure, Nandagaon
Brick work in CM 1:6 using well burnt CB Bricks for construction of walls in superstructure at Office Building of ISS, Nandagaon is in progress. The water used in mortar is found cleaned and free from silt, visible materials and within the permissible temperatures during mixing manually at sire. The area may be passed by SE, KID, Bhawanipatna on 02.06.2026
80/100
Instream Storage Structure, Nandagaon
Curing work is in progress on 02.06.2026
81/100
Instream Storage Structure, Nandagaon
Gate no 14 Undersluice both barrage bay and stoplog gate 2 stage embedded parts erection work under progress on 02.06.2026
82/100
UGPL, Right Lower Suktel Canal Division
OCS chamber above GL work is in progress of OCS No:- 0213109-C02A at village Kulthipali in presence of DoWR AE, JE and PMC team.
83/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for 75mm Dia HDPE pipe of OCS no-0213116-C06A-02, 1Ha. subchak at village Padiabahal in presence of DoWR SDO and PMC team.
84/100
UGPL, Left Lower Suktel Canal Division
HDD machine road pushing work is in progress (road crossing) of 75mm Dia HDPE pipe between RO-164 to RO-164B.(Z-265,Z-552,Z-354,Z-239,Z-234, RM-9 near village Manhira in presence of PMC team.
85/100
UGPL, Left Lower Suktel Canal Division
Stone pitching work is in progress of Approach channel at Pump House visited by DoWR CCE, TL (PSS) and QA/QC (PMC).
86/100
UGPL, Left Lower Suktel Canal Division
laying work is in progress of 75mm Dia HDPE pipe node from LO-180 to LO -180B at village Bhadra.
87/100
UGPL, Left Lower Suktel Canal Division
OMS manifold installation work is in progress at LO-180B, LM-9 near village Bhadra.
88/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 350mm Dia DI pipe line gap closing in between J-518 to J-247 at RM-13 near village Kushang village in presence of PMC team.
89/100
Instream Storage Structure, KansariGanda
Pier no.10 RHS pile cap reinforcement binding work in progress,
90/100
Instream Storage Structure, KansariGanda
Pier no.10 RHS pile cap reinforcement binding work in progress,
91/100
Instream Storage Structure, KansariGanda
Pier no.10 RHS pile cap reinforcement binding work in progress,
92/100
Instream Storage Structure, KansariGanda
Pier no.10 RHS pile cap reinforcement binding work in progress,
93/100
Instream Storage Structure, KansariGanda
Visit the ISS Kansariganda site by PMC team consisting of QA/QC Expert, HME, Site Engineers Civil & Mechanical - The work was completed as per requirement and points mentioned during inspection dated 14.05.2026 on Sill Beams placed in Barrage Bays number 3,4 & 5 and cleared for 2nd stage concreting in these Gate grooves Sill Beams area
94/100
Instream Storage Structure, KansariGanda
Pile cap concrete completed in presence of IRR. Eng. Expert along with Site engineer PMC.
95/100
Instream Storage Structure, KansariGanda
Pile cap concrete completed in presence of IRR. Eng. Expert along with Site engineer PMC.
96/100
Instream Storage Structure, KansariGanda
Slump cone test done at site
97/100
Instream Storage Structure, KansariGanda
Prepare for Pile cap concrete, Pier number 10 pile cap reinforcement binding progress and C C block placing D/S LHS Barrage bay & filter filling in presence of AE,AEE dept. and Site engineer PMC.
98/100
Instream Storage Structure, KansariGanda
Prepare for Pile cap concrete, Pier number 10 pile cap reinforcement binding progress and C C block placing D/S LHS Barrage bay & filter filling in presence of AE,AEE dept. and Site engineer PMC.
99/100
Instream Storage Structure, KansariGanda
Prepare for Pile cap concrete, Pier number 10 pile cap reinforcement binding progress and C C block placing D/S LHS Barrage bay & filter filling in presence of AE,AEE dept. and Site engineer PMC.
100/100
Instream Storage Structure, KansariGanda
Slump cone test done at site