1/100
Instream Storage Structure, Khalpal
Testing of Compressive M20A20 (Strength is 29.78/mm2 for 28 days) of Barrage Bay No-2 Gravity floor has done in presence of Client & PSS team.
2/100
Instream Storage Structure, Khalpal
Binding of reinforcement for LHS Abutment Counterfort wall, 2nd lift is under progress.
3/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 55.185 m.
4/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.3m.
5/100
Instream Storage Structure, Hamirpur
Slump testing M15A40 (Value 45 mm) of U/S Flared out wall, 11th lift at Block No-5 done in presence of Client & PSS Team.
6/100
Instream Storage Structure, Hamirpur
Concreting M15A40 of U/S Flared out wall, 11th lift at Block No-5 is under progress in presence of Client & PSS Team.
7/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Pier No-24, 16th lift done in presence of Client & PSS Team.
8/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-24, 16th lift is under progress in presence of Client & PSS Team.
9/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 37.48/mm2 for 07 days) of Gantry Girder No-43 and M30A20 (Strength is 28.15/mm2 for 07 days) of Groove 2nd stage, 3rd lift (Bay No-19) and M25A20 (Strength is 13.33/mm2 for 07 days) of Flared out wall, 10th lift and (Strength is 21.48/mm2 for 07 days) of Flank wall, 7th lift has done in presence of Client & PSS team.
10/100
Instream Storage Structure, Hamirpur
C.D.U frame stiffener grinding & welding work is in progress.
11/100
Instream Storage Structure, Hamirpur
Gantry girder's 1st stage embedded plate welding work is in progress.
12/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Flank wall, 3rd lift at Block No-5 is under progress.
13/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flared out wall at Block No-5 is under progress.
14/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
15/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Flank wall, 9th lift at Block No-5 is under progress.
16/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-23, 16th lift at Block No-4 is under progress.
17/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.615 m.
18/100
Instream Storage Structure, Kopsinga
Double storied building FIRST FLOOR Roof slab reinforcement work is under progress
19/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Checker plate fixing work is in progress of Hoist-bridge
20/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Shaft fixing work is in progress at CDU to ERU
21/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Railling fixing work is in progress of Hoist-bridge
22/100
Instream Storage Structure, Kopsinga
D/S side water flow views, Water level -215.800
against crest level-215.100
23/100
Instream Storage Structure, Kopsinga
U/S side water flow views
24/100
Instream Storage Structure, Kopsinga
Double storied building FIRST FLOOR Roof slab shuttering & reinforcement work is under progress
25/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Railing fixing work is in progress of Hoist-bridge
26/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Bracket fixing work is in progress of Barrage gates
27/100
Instream Storage Structure, Kopsinga
Double storied building slab Reinforcement work under progress
28/100
Instream Storage Structure, Kopsinga
Water level -215.900
against crest level-215.100
29/100
Instream Storage Structure, Kudabega
Leveling for fixing stone Boulder
30/100
Instream Storage Structure, Kudabega
RHS Site control building & double stored building slab shuttering work in progress
31/100
Instream Storage Structure, Kudabega
Drainage Spouts chipping work in progress.
32/100
Instream Storage Structure, Kudabega
Drainage spouts fixing work is in progress
33/100
Instream Storage Structure, Kudabega
Water level 206.850m
34/100
Instream Storage Structure, Kudabega
Stone boulder packing at us afflux bond
35/100
Instream Storage Structure, Kudabega
Expansion joint cleaning
36/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Top Guide fixing work is in progress
37/100
Instream Storage Structure, Kudabega
Water level 206.900m
38/100
Instream Storage Structure, Kudabega
Drainage Spouts chipping work in progress
39/100
Instream Storage Structure, Kudabega
Double stored building staging work in progress
40/100
Instream Storage Structure, Kudabega
Water level 206.950m
41/100
Instream Storage Structure, Kudabega
Control room Building at Belaigarh
42/100
Instream Storage Structure, Kudabega
Left side us afflux bond stone boulder packing
43/100
Instream Storage Structure, Kudabega
Drainage spouts chipping work in progress
44/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Top Guide fixing work is in progress
45/100
Instream Storage Structure, Kudabega
Water level R/L -207.350
46/100
Instream Storage Structure, Kudabega
Stone Boulder pitching of us afflux bund
47/100
Instream Storage Structure across river Sapei near village Kinjirma
* Flow direction is straight flow is seen at RL- 206.55 against crest level RL- 206.25 .
* Water is flowing 0.3m above the crest level .
48/100
Instream Storage Structure across river Sapei near village Kinjirma
View showing Flow direction is straight flow is seen at RL- 206.65 against crest level RL- 206.25 .
* Water is flowing 0.4m above the crest level .
49/100
Instream Storage Structure across river Sapei near village Kinjirma
* Flow direction is straight flow is seen at RL- 206.75 against crest level RL- 206.25 .
* Water is flowing 0.5m above the crest level .
50/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-215.000 mtr against design crest level RL- 215.000 mtr .i.e 0.000 mtr flood lift .
51/100
Instream Storage Structure Across Bheden near village Saida
Cross beam & top Hoist column final welding work is in progress.
52/100
Instream Storage Structure Across Bheden near village Saida
Guide shoes fixing work is in progress of Barrage Bay Gate no-4.
53/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-215.000 mtr against design crest level RL- 215.000 mtr .i.e 0.000mtr flood lift .
54/100
Instream Storage Structure Across Bheden near village Saida
Guide shoes fixing work is in progress of Barrage Bay Gate no-1.
55/100
Instream Storage Structure Across Bheden near village Saida
Monorail Girder's fasteners tightening work is in progress.
56/100
Instream Storage Structure Across Bheden near village Saida
Cross beam & top Hoist column final welding work is in progress.
57/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-215.100 mtr against design crest level RL- 215.000 mtr .i.e 0.100mtr flood lift
58/100
Instream Storage Structure Across Bheden near village Saida
Railing fixing work is in progress of top of the Hoist bridge platform.
59/100
Instream Storage Structure Across Bheden near village Saida
Monorail Trestle nut tightening work is in progress
60/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S to U/S of river
61/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-215.700 mtr against design crest level RL- 215.000 mtr .i.e 0.7 mtr flood lift .
62/100
Instream Storage Structure, Khirasasan
No Mechanical work activity at site
63/100
Instream Storage Structure, Khirasasan
Staff Quarter plastering work and 1 St floor slab shuttering work under Progress.
64/100
Instream Storage Structure, Khirasasan
The water level - 210.700 Against design crest level-210.900
65/100
Instream Storage Structure, Khirasasan
Staff Quarter plastering work and 1 St floor slab shuttering work under Progress.
66/100
Instream Storage Structure, Khirasasan
The water level - 210.700 Against design crest level-210.900
67/100
Instream Storage Structure, Khirasasan
CDU, RDU cover fixing work in progress
68/100
Instream Storage Structure, Khirasasan
Staff Quarter plastering work is in Progress.
69/100
Instream Storage Structure, Khirasasan
The water level - 211.000 Against design crest level-210.900
70/100
Instream Storage Structure, Khirasasan
Staff Quarter plastering work is in Progress.
71/100
Instream Storage Structure, Khirasasan
The water level - 211.000 Against design crest level-210.900
72/100
Instream Storage Structure, Budharaja
Staff Quarter plastering work is in Progress.
73/100
Instream Storage Structure, Budharaja
The flow level is 207.050 m against the design RL: 206.700, i.e., 0.350 m flood lift.
74/100
Instream Storage Structure, Budharaja
Coloring work is in progress on the interior of the staff quarters.
75/100
Instream Storage Structure, Budharaja
The flow level is 207.450 m against the design RL: 206.700, i.e., 0.75 m flood lift.
76/100
Instream Storage Structure, Budharaja
Coloring work is in progress on the exterior of the staff quarters.
77/100
Instream Storage Structure, Budharaja
The flow level is 208.00 m against the design RL: 206.700, i.e., 1.3 m flood lift.
78/100
Instream Storage Structure, Budharaja
The flow level is 208.050 m against the design RL: 206.700, i.e., 1.35 m flood lift.
79/100
Instream Storage Structure, Gochara
No work activity at Site.
80/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
81/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. The flow level is 225.650mt against design crest level 225.500 i.e. flood lift 0.150mt.
82/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
83/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. The flow level is 225.750mt against design crest level 225.500 i.e. flood lift 0.250mt.
84/100
Instream Storage Structure, Gochara
Staff quarter 1st floor out side brick wall work in progress.
85/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river)
86/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. The flow level is 225.750mt against design crest level 225.500 i.e. flood lift 0.250mt.
87/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
88/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. Flow direction is straight. The direction of flow is seen in middle of the river. Now the flow level is 226.100mt against design crest level 225.500 i.e. flood lift 0.6mt
89/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Flood water entered in to the working area at Choudhury gada ISS project inundated the site. Both U/S and D/S coffer dams is not yet removed for free flow of flood water.
90/100
Instream Storage Structure, Hamirpur
Slump testing M15A40 (Value 45 mm) of D/S Flared out wall, 1st lift at Block No-5 done in presence of Client & PSS Team.
91/100
Instream Storage Structure, Hamirpur
Concreting M15A40 of D/S Flared out wall, 1st lift at Block No-5 is under progress in presence of Client & PSS Team.
92/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Gantry Girder No-45 done in presence of Client & PSS Team.
93/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Right side U/S devide Wall raft casting is going on
94/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-45 is under progress in presence of Client & PSS Team.
95/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of RHS U/S Flank wall, 8th lift at Block No-5 done in presence of Client & PSS Team.
96/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of RHS U/S Flank wall, 8th lift at Block No-5 is under progress in presence of Client & PSS Team.
97/100
Instream Storage Structure, Hamirpur
Hoist bridge platform No-3 Shaft fixing and alignment work is in progress.
98/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
No work at choudhary gada iss project due to heavy rain.
99/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flared out wall at Block No-5 is under progress.
100/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Gantry Girder is under progress.
❮
❯