1/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of D/S Flank wall Raft at Block No-1 done in presence of Client & PSS Team.
2/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flank wall Raft at Block No-1 is under progress in presence of Client & PSS Team.
3/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.06/mm2 for 28 days) of Pier No-3, 9th lift and (Strength is 30.94/mm2 for 28 days) of Flared out wall Raft and M15A40 (Strength is 20.35/mm2 for 28 days) of Flared out wall PCC and M30A20 (Strength is 37.78/mm2 for 28 days) of Groove 2nd stage, 3rd lift (Bay No-28) has done in presence of Client & PSS team.
4/100
Instream Storage Structure, Gudvella
• Today, the Irrigation Expert Sir and Quality Control Expert Sir from PMC visited ISS Gudvella. During their visit, the Department JE, PMC Site Engineer and Agency Engineers were present. 1. They inspected the overall site conditions and instructed the agency to start the electrical works immediately and complete them at the earliest without any delay. 2. They also directed the agency to expedite the erection of the stoplog gate so that the dry test can be conducted at the earliest on 30.06.2026
5/100
Instream Storage Structure, Gudvella
• Today, the Irrigation Expert Sir and Quality Control Expert Sir from PMC visited ISS Gudvella. During their visit, the Department JE, PMC Site Engineer and Agency Engineers were present. 1. They inspected the overall site conditions and instructed the agency to start the electrical works immediately and complete them at the earliest without any delay. 2. They also directed the agency to expedite the erection of the stoplog gate so that the dry test can be conducted at the earliest on 30.06.2026
6/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flared out wall at Block No-1 is under progress.
7/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall Raft at Block No-1 is under progress.
8/100
Instream Storage Structure, Gudvella
The cover work of the roller drum is under progress at the mechanical yard on 30.06.2026
9/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Gantry Girder is under progress.
10/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-4 & 5, 5th lift is under progress.
11/100
Instream Storage Structure, Gudvella
Plastering work of parapet wall is under progress at building on 30.06.2026
12/100
Instream Storage Structure, Hamirpur
Shuttering of Abutment (A1), 12th lift at Block No-1 is under progress.
13/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-1, 14th lift is under progress.
14/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 30.06.2026
15/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-3, 13th lift at Block No-1 is under progress.
16/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 30.06.2026
17/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M25A20 (Value 90 mm) of RHS Deck slab done in presence of Client & PSS Team.
18/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of RHS Deck slab is under progress in presence of Client & PSS Team.
19/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 70 mm) of RHS D/S End-sill, 1st lift done in presence of Client & PSS Team.
20/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering & Binding of reinforcement for RHS D/S Counerfort & Wing wall, 3rd lift is under progress.
21/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-8, 7th lift is under progress.
22/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for RHS U/S (D2) wall, 1st lift is under progress.
23/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of RHS Double pier No-25, 3rd lift done in presence of Client & PSS Team.
24/100
Instream Storage Structure, Khalpal
Concreting M25A20 of RHS Double pier No-25, 3rd lift is under progress in presence of Client & PSS Team.
25/100
Instream Storage Structure, Khalpal
Testing of Compressive M25A20 (Strength is 33.98/mm2 for 28 days) of LHS Double pier No-25, 4th lift has done in presence of Client & PSS team.
26/100
Instream Storage Structure, Nandagaon
Shuttering for CC block at D/S right flared out wall is in progress on 30.06.2026
27/100
Instream Storage Structure, Nandagaon
1st gate erection is in progress on 30.06.2026
28/100
Instream Storage Structure, Nandagaon
Crane has arrived at the site, due to water ejection the erection work has been stopped, it may takes more then 5 to 6 hours on 30.06.2026
29/100
Instream Storage Structure, Gudvella
• Today CE & BM, Tel Basin, Bhawanipatna, SE, SDO and AE, Balangir Irrigation Division, Balangir visited ISS Gudvella. During their visit, the Department JE, PMC Site Engineer and Agency representative were present. 1. The officials inspected the overall site conditions and reviewed the progress of the ongoing works. They instructed the agency to expedite and complete all remaining works without any further delay on 29.06.2026
30/100
Instream Storage Structure, Gudvella
• Today CE & BM, Tel Basin, Bhawanipatna, SE, SDO and AE, Balangir Irrigation Division, Balangir visited ISS Gudvella. During their visit, the Department JE, PMC Site Engineer and Agency representative were present. 1. The officials inspected the overall site conditions and reviewed the progress of the ongoing works. They instructed the agency to expedite and complete all remaining works without any further delay on 29.06.2026
31/100
Instream Storage Structure, Gudvella
Coverage work of roller drum is under progress at mechanical yard on 29.06.2026
32/100
Instream Storage Structure, Gudvella
Brick work is under progress at parapet wall of building on 29.06.2026
33/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 29.06.2026
34/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 29.06.2026
35/100
Instream Storage Structure, Nandagaon
Concrete casting with M20A20 grade of CC block at D/S right flared out wall is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency and found slump test value is 84mm at placing site on 29.06.2026
36/100
Instream Storage Structure, Nandagaon
Concrete casting with M20A20 grade of CC block at D/S right flared out wall is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency and found slump test value is 84mm at placing site on 29.06.2026
37/100
Instream Storage Structure, Nandagaon
• 1.The casting of the CC block at the following area has been checked in the presence of PM, EPC agency, Site Engineers of PMC & EPC Agency: (i) Shuttering for CC block at D/S right Flared out wall of 37.50m length & 0.6m ht. from RL-242.40m to RL-243.00m is completed. (ii). Filling of inverted filter materials covering with LDPE paper at adjacent to each CC block in earth side are done before placement. (iii) Application of 2 coat bitumen paint at cj's concrete surface is done. (iv). Area is ready and passed by SE KID, Bh. Patna to place concrete with PCC M20A20 grade on 29.06.2026
38/100
Instream Storage Structure, Nandagaon
The erection work and painting work has been stopped at the site today due to labour issues on 29.06.2026
39/100
UGPL, Right Lower Suktel Canal Division
OCS chamber above GL work is in progress of OCS No:- 0213094-C06A at village Mehermunda in presence of PMC team and L&T personnel.
40/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door and angle fixing work is in progress OCS No-: 0213127-C09B at village Raksimunda in presence of DoWR AE, PMC team and L&T official.
41/100
UGPL, Right Lower Suktel Canal Division
Approach channel 2nd slope and 3rd berm joint portion concreting work is in progress at Pump House.
42/100
UGPL, Left Lower Suktel Canal Division
Butt Fusion jointing work is in progress for 160mm Dia HDPE pipeline from J-301 to J - 582, RM-6 near village Baghapali in presence of PMC team..
43/100
UGPL, Left Lower Suktel Canal Division
Excavation work in progress for 160mm Dia HDPE pipe laying node from J-301 to J-582, RM-6 near village Baghapali in presence of PMC team.
44/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Gantry Girder No-41 done in presence of Client & PSS Team.
45/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-41 is under progress in presence of Client & PSS Team.
46/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-2, 11th lift done in presence of Client & PSS Team.
47/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-2, 11th lift is under progress in presence of Client & PSS Team.
48/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.17/mm2 for 28 days) of Pier No-1, 9th lift and (Strength is 21.78/mm2 for 07 days) of Pier No-1, 12th lift and M15A40 (Strength is 20.44/mm2 for 28 days) of Flared out wall PCC and M30A20 (Strength is 38.15/mm2 for 28 days) of Groove 2nd stage (Bay No-26, 27 & 28) has done in presence of Client & PSS team.
49/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Gantry Girder is under progress.
50/100
Instream Storage Structure, Hamirpur
Gantry girder's 1st stage embedded plate welding work is in progress.
51/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall Raft at Block No-1 is under progress.
52/100
Instream Storage Structure, Hamirpur
Shuttering of Abutment (A1), 12th lift at Block No-1 is under progress.
53/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for RHS D/S Counerfort & Abutment wall, 4th lift is under progress.
54/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for RHS D/S Counerfort & Wing wall, 3rd lift is under progress.
55/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of Pier No-17 (Starter) done in presence of Client & PSS Team.
56/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-17 (Starter) is under progress in presence of Client & PSS Team.
57/100
Instream Storage Structure, Khalpal
Site inspection by QC&QA Expert, PMU in presence of A.E.E & A.E, AID, Dy. TL, QAE, IEE of PSS team along with EPC agency and observed inside the gravity floor of Barrage Bay-2.
58/100
Instream Storage Structure, Khalpal
Shuttering of RHS Double Pier No-25, 3rd lift is under progress.
59/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
60/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for laying of 75mm Dia HDPE pipe of OCS No- 0201214-C05B for sub chak No-9 At village Buxiudar in presence of PMC team.
61/100
Instream Storage Structure, Gudvella
Brick work at headroom area of building is under progress at site on 28.06.2026
62/100
Instream Storage Structure, Gudvella
Minor mechanical grinding works are currently in progress on 28.06.2026
63/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 28.06.2026
64/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 28.06.2026
65/100
Instream Storage Structure, Gudvella
Today officials from the Gudvella Forest Section visited the ISS Gudvella site to inspect the sal trees located along the proposed approach road. The inspection was conducted to assess the tree and submit a report to their higher authorities for further necessary action on 27.06.2026
66/100
Instream Storage Structure, Gudvella
Brick work at the head room of building area is under progress at site on 27.06.2026
67/100
Instream Storage Structure, Gudvella
Staircase work at mechanical yard is under progress at site on 27.06.2026
68/100
Instream Storage Structure, Gudvella
Fittup work electrical pole is under progress at site on 27.06.2026
69/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 27.06.2026
70/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 27.06.2026
71/100
Instream Storage Structure, Gudvella
Staircase work is under progress at mechanical yard on 26.06.2026
72/100
Instream Storage Structure, Gudvella
Plastering work at building area is under progress at site on 26.06.2026
73/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 26.06.2026
74/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 26.06.2026
75/100
Instream Storage Structure, Nandagaon
Shuttering for CC block is in progress at D/S right flared out wall on 28.06.2026
76/100
Instream Storage Structure, Nandagaon
Shuttering for CC block at D/S right flared out wall is in progress on 27.06.2026
77/100
Instream Storage Structure, Nandagaon
The erection work has been stopped at the site today due to labour issues on 26.06.2026
78/100
Instream Storage Structure, Nandagaon
Curing is in progress at right abutment on 26.06.2026
79/100
Instream Storage Structure, Nandagaon
Shuttering for CC block at D/S right flared out wall is in progress on 26.06.2026
80/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of LHS D/S Divide wall, 2nd lift done in presence of Client & PSS Team.
81/100
Instream Storage Structure, Khalpal
Concreting M25A20 of LHS D/S Divide wall, 2nd lift is under progress in presence of Client & PSS Team.
82/100
Instream Storage Structure, Khalpal
Shuttering of RHS Double Pier No-25, 3rd lift is under progress.
83/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
84/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 85 mm) of RHS D/S Divide wall, 4th lift done in presence of Client & PSS Team.
85/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of RHS D/S Divide wall, 4th lift is under progress in presence of Client & PSS Team.
86/100
Instream Storage Structure, Hamirpur
Testing of Compressive M15A40 (Strength is 20.23/mm2 for 28 days) of Flared out wall Raft PCC and (Strength is 20.89/mm2 for 28 days) of Flank wall Cut-off PCC has done in presence of Client & PSS team.
87/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-40 done in presence of Client & PSS Team.
88/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-40 is under progress in presence of Client & PSS Team.
89/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.04/mm2 for 07 days) of Pier No-3, 11th lift and (Strength is 21.63/mm2 for 07 days) of Pier No-5, 4th lift and M35A20 (Strength is 37.63/mm2 for 07 days) of Deck slab (Bay No-10 &11) and M30A20 (Strength is 37.78/mm2 for 28 days) of Groove 2nd stage, 9th and 1st lift (Bay No-26 & 28) has done in presence of Client & PSS team.
90/100
Instream Storage Structure, Hamirpur
Barrage bay Gate No-25 lifting trial operation work is in progress.
91/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
92/100
Instream Storage Structure, Hamirpur
Gantry girder's 1st stage embedded plate fixing and welding work is in progress.
93/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall Raft at Block No-1 is under progress.
94/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-4 & 5, 5th lift is under progress.
95/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-1, 14th lift is under progress.
96/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-3, 13th lift is under progress.
97/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Abutment (A1), 12th lift at Block No-1 is under progress.
98/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Flank wall, 4th lift at Block No-1 is under progress.
99/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M25A20 (Value 85 mm) of LHS Divide wall, 1st lift done in presence of Client & PSS Team.
100/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of LHS Divide wall, 1st lift is under progress in presence of Client & PSS Team.