GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
UGPL, Right Lower Suktel Canal Division
OCS chamber piping work is in progress of OCS No-0213007-C01A at village Bairasar in presence of DoWR AE and PMC team.
2/100
UGPL, Right Lower Suktel Canal Division
Inspected of BFV and BFV Chamber is in progress for 200mm DIa HDPE pipe from J 7021 to J-7100 (p-7109) at village Bandanakata in presence of PMC team.
3/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Gantry Girder No-30 done in presence of Client & PSS Team.
4/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No- 0213124- C02A near village Jamsara in presence of DoWR JE and PMC team.
5/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-30 is under progress in presence of Client & PSS Team.
6/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of D/S Flared out wall, Raft at Block No-5 done in presence of Client & PSS Team.
7/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flared out wall, Raft at Block No-5 is under progress in presence of Client & PSS Team.
8/100
UGPL, Right Lower Suktel Canal Division
1ha Outlet RCC hume pipe fixing work is in progress of OCS No- 0201211- C12B - SC 03 at village Barkani in presence of DoWR JE and PMC team.
9/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 90 mm) of Barrage Bay No3 Gravity floor done in presence of Client & PSS Team.
10/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Barrage Bay No3 Gravity floor done in presence of Client & PSS Team
11/100
Instream Storage Structure, Khalpal
Curing of Piers & Gravity floor is in progress.
12/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M20A20 (Value 90 mm) of LHS side Gravity floor PCC done in presence of Client & PSS Team.
13/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for LHS side Raft is under progress.
14/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Testing of Compressive M20A20 (Strength is 17.89/mm2 for 07 days) of RHS D/S Gravity floor and M25A20 (Strength is 29.79/mm2 for 28 days) of RHS Mid-pier, 1st lift has done in presence of Client & PSS team.
15/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering &Binding of reinforcement for RHS Double pier, 1st lift is under progress.
16/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for RHS Divide wall, 3rd lift is under progress.
17/100
Instream Storage Structure, Jharbeda
Slump testing M20A20 (Value 50 mm) of RHS D/S Training wall, Footing, 3rd Layer done in presence of Client & PSS Team.
18/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of RHS D/S Training wall, Footing, 3rd Layer is under progress in presence of Client & PSS Team.
19/100
Instream Storage Structure, Jharbeda
Dewatering work is in Progress.
20/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-6 is under progress.
21/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-8, 5th lift is under progress.
22/100
Instream Storage Structure, Jharbeda
Curing of RHS (A2) Footing is under progress.
23/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
24/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.33/mm2 for 07 days) of Pier No-1, 6th lift and (Strength is 30.95/mm2 for 28 days) of D/S Flank wall, Raft at Block No-5 and (Strength is 31.04/mm2 for 28 days) of Abutment (A1), 6th lift and (Strength is 30.81/mm2 for 28 days) of Pier No-21, 11th lift and M35A20 (Strength is 42.15/mm2 for 28 days) of Gantry Girder No-12 has done in presence of Client & PSS team.
25/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-30, 12th lift with pier Cap done in presence of Client & PSS Team.
26/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-30, 12th lift with pier Cap is under progress in presence of Client & PSS Team.
27/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank Cut-off wall at Block No-1 is under progress.
28/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-2, 5th lift is under progress.
29/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall, Raft at Block No-5 is under progress.
30/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Abutment (A1), 5th lift is under progress.
31/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
32/100
Instream Storage Structure, Sirigida
Joint verification conducted for Govt. land alienation as well as felling of trees for O&M building construction by R.I, Godibandha, FRO, OFDC along with A.E.E & A.E, AID and PSS team.
33/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 85 mm) of Barrage Bay No-3 Gravity floor done in presence of Client & PSS Team.
34/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Barrage Bay No-3 Gravity floor done in presence of Client & PSS Team.
35/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 165 mm) of D/S Panel No-11 at Barrage Bay No-1 done in presence of Client & PSS Team.
36/100
Instream Storage Structure, Khalpal
Concreting M25A20 of D/S Panel No-11 at Barrage Bay No-1 done in presence of Client & PSS Team
37/100
Instream Storage Structure, Khalpal
Diaphragm wall cage placing for D/S Panel No-11 at Barrage Bay No-1 in presence of Client & PSS Team.
38/100
Instream Storage Structure, Khalpal
Excavation of Diaphragm wall D/S Panel No-11 at Barrage Bay No-1 is under progress in presence of Client & PSS Team.
39/100
Instream Storage Structure, Khalpal
Curing of Gravity floor is in progress.
40/100
Instream Storage Structure, Khalpal
Curing of Piers is in progress.
41/100
Instream Storage Structure, Gudvella
Shuttering work of Post is under progress at site on 03.05.2026
42/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 03.05.2026
43/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 03.05.2026
44/100
Instream Storage Structure, Gudvella
Cast of posts of U/s side of span -7 on 02.05.2026
45/100
Instream Storage Structure, Gudvella
Shuttering work of Post is under progress at site on 02.05.2026
46/100
Instream Storage Structure, Gudvella
Curing work at site on 02.05.2026
47/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 02.05.2026
48/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 02.05.2026
49/100
Instream Storage Structure, Gudvella
Cast of posts of U/s side of span -8 and span -9 on 01.05.2026
50/100
Instream Storage Structure, Gudvella
Cast of concrete M25A20 GRADE at 1st floor slab building is in progress in the presence of Dept JE , site engineer of PMC and agency at site. The slump test value is 75mm on 01.05.2026
51/100
Instream Storage Structure, Gudvella
Cast of concrete M25A20 GRADE at 1st floor slab building is in progress in the presence of Dept JE , site engineer of PMC and agency at site. The slump test value is 75mm on 01.05.2026
52/100
Instream Storage Structure, Gudvella
The 1st floor slab of the control room building is ready for concreting with M25A20 grade concrete on 01.05.2026
53/100
UGPL, Left Lower Suktel Canal Division
300mm Dia DI pipe line Air vàlve fixing work is in progress of Lm-9 from J-73 to J-293 at village Bhadra
54/100
Instream Storage Structure, Gudvella
Shuttering work of Post is under progress at site on 01.05.2026
55/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 01.05.2026
56/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 01.05.2026
57/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete at pier no. 11 on 03.05.2026
58/100
Instream Storage Structure, Nandagaon
Curing at U/S right divide wall on 03.05.2026
59/100
Instream Storage Structure, Nandagaon
Shuttering for Block out portion at pier no.10 on 03.05.2026
60/100
Instream Storage Structure, Nandagaon
Curing is in progress at U/S right divide wall on 02.05.2026
61/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no.9&10 on 02.05.2026
62/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress on 02.05.2026
63/100
Instream Storage Structure, Nandagaon
Monorail walkway painting work under progress on 02.05.2026
64/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no.8,9&10 on 01.05.2026
65/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress on 01.05.2026
66/100
Instream Storage Structure, Nandagaon
Barrage bay gate painting work is under progress on 01.05.2026
67/100
Instream Storage Structure, Nandagaon
Monorail walkway primer painting work is under progress on 01.05.2026
68/100
UGPL, Right Lower Suktel Canal Division
External drain brick masonry work is in progress at Pump House.
69/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No- 0213124 - C09B near village Khamarmunda in presence of DoWR JE and PMC team.
70/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door and angle fixing work is in progress OCS No:-0201297-C03B at village Rinabachan in presence of PMC team.
71/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI branch Tee(350X150X 350) connection at j-482, RM-9, near village Pandarani in presence of DoWR AE and PMC team.
72/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for laying of 125mm Dia HDPE pipeline from node J-461 to LO-218, LM11 near village Khandajuri in presence of PMC team.
73/100
UGPL, Left Lower Suktel Canal Division
Butt fusion jointing work is in progress for 125mm Dia HDPE pipe of J-461 to LO-218 LM-11 Near village Kandajuri in presence of PMC team.
74/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI to HDPE pipe connection at J-72, LM-9 near village Bhadra in presence of PMC team.
75/100
UGPL, Left Lower Suktel Canal Division
Butt fusion jointing work is in progress of 140mm Dia HDPE pipe of J-72 LM-9 near village Bhadra in presence of PMC team.
76/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door fixing work is in progress OCS No:-0213133-C01B at village Sauntpur in presence of PMC team.
77/100
UGPL, Right Lower Suktel Canal Division
Valve Chamber Pre-cast slab concrete pouring work is in progress of Pump House in presence of PMC team.
78/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No- 0213055- C04B near village Bubel in presence of PMC team.
79/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for Gap closing of 350mm Dia DI pipeline from node J-511 to J-285, RM-11 near village Burda in presence PMC team.
80/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress of 90mm Dia HDPE pipeline from RO-56 to RO-56B, RM-3 near village Dhamanasar in presence of DoWR SDO and PMC team.
81/100
UGPL, Left Lower Suktel Canal Division
Butt fusion jointing work is in progress of 280mm Dia HDPE pipe from J- 512 to J-513 near village Sakhma in presence of PMC.
82/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for laying of 140mm Dia HDPE pipe line at RLO- 6, LM-18 near village Maharpali in presence of PMC team.
83/100
Instream Storage Structure, Dhanei
Visit the ISS Sanabaragam- PMC team consisting of HME and Site Engineer Mechanical. The following observations made on HM Equipment -2nd Stage embedded parts placement in both Barrage Bays- Stop-log gate Grooves: 1. The placement of Roller cum Side Seal tracks , Guide tracks completed as per Approved drawing, checked alignment of items, on parameters like C/C Roller track, C/C of Side Seal Seats and F/F dimension of Side Guide tracks, found OK. 2. Instructed the agency on cleaning of rust on the above mentioned items placed in grooves, after rust cleaning, clearance will be given for concreting.
84/100
Instream Storage Structure, Dhanei
Visit the ISS Sanabaragam- PMC team consisting of HME and Site Engineer Mechanical. The following observations made on HM Equipment -2nd Stage embedded parts placement in both Barrage Bays- Stop-log gate Grooves: 1. The placement of Roller cum Side Seal tracks , Guide tracks completed as per Approved drawing, checked alignment of items, on parameters like C/C Roller track, C/C of Side Seal Seats and F/F dimension of Side Guide tracks, found OK. 2. Instructed the agency on cleaning of rust on the above mentioned items placed in grooves, after rust cleaning, clearance will be given for concreting.
85/100
Instream Storage Structure, Dhanei
Visit of SD Expert along with site engineer mechanical to the Iss Site. Inspected the overall progress of mechanical work and Erection of mechanical gate components in progress.
86/100
Instream Storage Structure, Dhanei
Visit of SD Expert along with site engineer mechanical to the Iss Site. Inspected the overall progress of mechanical work and Erection of mechanical gate components in progress.
87/100
Instream Storage Structure, Dhanei
Visit of SD Expert along with site engineer mechanical to the Iss Site. Inspected the overall progress of mechanical work and Erection of mechanical gate components in progress.
88/100
Instream Storage Structure, Dhanei
Visit of SD Expert along with site engineer mechanical to the Iss Site. Inspected the overall progress of mechanical work and Erection of mechanical gate components in progress.
89/100
Instream Storage Structure, Dhanei
A joint inspection of ISS Sanabaragrama was carried out by a team comprising the Chief Engineer of RBVN Basin, Additional Chief Engineer, Superintending Engineer, SDO, AE, and the Deputy Team Leader of PMC along with their team. During the visit, the team not only inspected the site but also assessed the overall progress of the works. Observing the works at site, the agency has been directed to immediately initiate and carry out all work simultaneously on multiple fronts, including mechanical works, gate works, establishment of the electrical substation, completion of the O&M building, initiation of the afflux bond, and progress of land acquisition.
90/100
Instream Storage Structure, Dhanei
A joint inspection of ISS Sanabaragrama was carried out by a team comprising the Chief Engineer of RBVN Basin, Additional Chief Engineer, Superintending Engineer, SDO, AE, and the Deputy Team Leader of PMC along with their team. During the visit, the team not only inspected the site but also assessed the overall progress of the works. Observing the works at site, the agency has been directed to immediately initiate and carry out all work simultaneously on multiple fronts, including mechanical works, gate works, establishment of the electrical substation, completion of the O&M building, initiation of the afflux bond, and progress of land acquisition.
91/100
Instream Storage Structure, Dhanei
Visit of Hydro-mechanical Expert along with Mechanical Site Engineer PMC to the lSS Site. Inspected the overall progress of site, 1. the placement of Sill Beam in Left Abutment Barrage Bay Stop-log gate groove completed as per Approved drawing, checked alignment and found ok. 2. Instructed the agency on rust cleaning of this particular Sill Beam, after cleaning, clearance will be given for concreting. 3. Hoist trestles anchor bolts and plates placement work is started in block outs in Left Abutment pier.
92/100
Instream Storage Structure, Dhanei
Visit of Hydro-mechanical Expert along with Mechanical Site Engineer PMC to the lSS Site. Inspected the overall progress of site, 1. the placement of Sill Beam in Left Abutment Barrage Bay Stop-log gate groove completed as per Approved drawing, checked alignment and found ok. 2. Instructed the agency on rust cleaning of this particular Sill Beam, after cleaning, clearance will be given for concreting. 3. Hoist trestles anchor bolts and plates placement work is started in block outs in Left Abutment pier.
93/100
Instream Storage Structure, Dhanei
Visit of Hydro-mechanical Expert along with Mechanical Site Engineer PMC to the lSS Site. Inspected the overall progress of site, 1. the placement of Sill Beam in Left Abutment Barrage Bay Stop-log gate groove completed as per Approved drawing, checked alignment and found ok. 2. Instructed the agency on rust cleaning of this particular Sill Beam, after cleaning, clearance will be given for concreting. 3. Hoist trestles anchor bolts and plates placement work is started in block outs in Left Abutment pier.
94/100
Instream Storage Structure, Dhanei
Visit of DyTL and QA/QC Expert along with Site Engineer PMC to the lSS Site. Inspected the overall progress of site, 1. Barrage bay stop log gate sill beam fixing continuing. 2. O & M building staircase room brick work in progress. 3. Earth work of Left Afflux Bond continues and alignment of right Afflux Bond Inspected by Team.
95/100
Instream Storage Structure, Dhanei
Visit of DyTL and QA/QC Expert along with Site Engineer PMC to the lSS Site. Inspected the overall progress of site, 1. Barrage bay stop log gate sill beam fixing continuing. 2. O & M building staircase room brick work in progress. 3. Earth work of Left Afflux Bond continues and alignment of right Afflux Bond Inspected by Team.
96/100
Instream Storage Structure, Dhanei
Visit of DyTL and QA/QC Expert along with Site Engineer PMC to the lSS Site. Inspected the overall progress of site, 1. Barrage bay stop log gate sill beam fixing continuing. 2. O & M building staircase room brick work in progress. 3. Earth work of Left Afflux Bond continues and alignment of right Afflux Bond Inspected by Team.
97/100
Instream Storage Structure, Dhanei
Visit of Addl CE RB Basin, SE BeID along with SDO & AE including DTL accompanied by PMC Team to the lSS Site. The team inspected various ongoing civil & mechanical activities at Site. Reviewed regarding expeditious execution of remaining works and to complete the same without further delay.
98/100
Instream Storage Structure, Dhanei
Visit of Addl CE RB Basin, SE BeID along with SDO & AE including DTL accompanied by PMC Team to the lSS Site. The team inspected various ongoing civil & mechanical activities at Site. Reviewed regarding expeditious execution of remaining works and to complete the same without further delay.
99/100
Instream Storage Structure, Dhanei
Visit of Addl CE RB Basin, SE BeID along with SDO & AE including DTL accompanied by PMC Team to the lSS Site. The team inspected various ongoing civil & mechanical activities at Site. Reviewed regarding expeditious execution of remaining works and to complete the same without further delay.
100/100
Integrated Barrage across river Kochila and across river Baitarini
AEE of Akhuapada irrigation division, PMC and representative of Agency visited ISS-Kochila today. LHS Abutment wall Casting from level 3.55m to 4.9m. work in progress at baitarani iss project.

Enter Login Details

Forgot Password ?