1/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Rust cleaning of reinforcement for RHS Divide wall is under progress.
2/100
Instream Storage Structure, Hamirpur
Curing of Piers is under progress.
3/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-31, 5th lift at Block No-5 is under progress.
4/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-27, 12th lift at Block No-4 is under progress.
5/100
Instream Storage Structure, Hamirpur
Shuttering of RHS U/S Flank wall, 5th lift at Block No-5 is under progress.
6/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-31, 4th lift at Block No-5 is under progress.
7/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-29, 10th lift is under progress.
8/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-23, 10th lift is under progress.
9/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Observed of Silt content test (Value 1.95%) in presence of Client & PSS team along with EPC agency.
10/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Recalibration of Batching plant in presence of A.E.E, RDD & PSS team along with EPC agency.
11/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Observed of Sieve analysis of Coarse & Fine aggregate in presence of A.E.E, RDD & A.E/ JE, Rengali Dam Division and JE Quality Assurance Division, Samal and DPM of EPC Agency.
12/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Checking of Reinforcement at Divided wall by Quality Assurance Export PSS Angul, Site Engineer in presence of A.E.E, RDD & A.E/ JE, Rengali Dam Division and JE Quality Assurance Division, Samal and DPM of EPC Agency.
13/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Chiseling & cleaning of old concrete surfaces at the divide wall is under progress in presence of A.E.E, RDD & Q.A.E of PSS team.
14/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Excavation of foundation for Office building is under progress.
15/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning of debris for Middle pier is under progress.
16/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning of reinforcement is under progress.
17/100
Instream Storage Structure, Jharbeda
Cleaning of D/S Pier No-4 to Pier No-7 is under progress.
18/100
Instream Storage Structure, Jharbeda
Cleaning of Pier No-7 is under progress.
19/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-29, 9th lift at Block No-4 done in presence of Client & PSS Team.
20/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-29, 9th lift at Block No-4 is under progress in presence of Client & PSS Team.
21/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-17, 7th lift at Block No-3 is under progress.
22/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-27, 12th lift at Block No-4 is under progress.
23/100
Instream Storage Structure, Hamirpur
Shuttering of RHS U/S Flank wall, 5th lift at Block No-5 is under progress.
24/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-31, 4th lift at Block No-5 is under progress.
25/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-28, 14th lift at Block No-4 is under progress.
26/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-23, 10th lift is under progress.
27/100
Instream Storage Structure Across Bheden near village Saida
IEE , QCE, E&A of PMC Sambalpur visited ISS Saida.Checked centering , shuttering & reinforcement of Deck slab in between LHS Abutment & Divide wall. The requisite tests of construction materials such as FA & CA , cement to be performed before casting .
28/100
Instream Storage Structure Across Bheden near village Saida
LHS Abutment to LHS Divide wall between mid portion Deck slab shuttering work is in progress .
29/100
Instream Storage Structure Across Bheden near village Saida
LHS U/S Flared out wall mud cleaning work is going on .
30/100
Instream Storage Structure, Khalpal
Hirakud Government Lab mix design trial mix conducted at site laboratory of M25A20, 14 days cube (Strength 38.34 N/mm²) in presence of Client & PSS Team.
31/100
Instream Storage Structure, Khalpal
Slump testing M20A40 (Value 60 mm) C.C Blocks done in presence of Client & PSS Team.
32/100
Instream Storage Structure, Gochara
Deck slab cleaning work in progress.
33/100
Instream Storage Structure, Gudvella
Coffer dam making at u/s side is under progress on 16.11.2025
34/100
Instream Storage Structure, Khalpal
Casting of C.C Block (M20A40) is under progress in presence of Client & PSS Team.
35/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
36/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. Flow direction is straight. The direction of flow is seen in middle of the river. Now the flow level is 225.600mt against design crest level 225.500 i.e. flood lift 0.1mt.
37/100
Instream Storage Structure, Gudvella
Erection of pylon at deck slab no -8 in between P7 and P8 is in progress on 15.11.2025
38/100
Instream Storage Structure, Budharaja
Inspected alignment of LHS u/s flared out wall. Instructed to provide expansion joint at max every 9.00mt interval.
39/100
Instream Storage Structure, Budharaja
Inspected Staff Quatres which is under construction.
40/100
Instream Storage Structure, Budharaja
IEE ,QCE , E&A visited ISS Budharaja. The required space for DG seems to be inadequate in the specified DG room. It may require to modify DG room & control room after procurement of DG set& MDB by the Agency.
41/100
Instream Storage Structure, Budharaja
De-Shuttering work is in Progress at Pier No: 2, Hoist Gate Portion.
42/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 2no. of CC blocks at U/S left flared out wall i.e. 1no. of size 6.0x1.5x0.6m at sec-4-4 for 9th lift & 1no. at sec2-2 for 6th lift upto RL-242.40m is in progress in presence of JE,KID, PM, EPC agency n Site Engineers of PMC & EPC agency. Slump achieved 73mm on 16.11.2025
43/100
Instream Storage Structure, Budharaja
De-Shuttering work is in Progress at Pier No: 1, Hoist Gate Portion.
44/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at LHS Divided wall, Hoist Gate Portion.
45/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 2no. of CC blocks at U/S left flared out wall i.e. 1no. of size 6.0x1.5x0.6m at sec-4-4 for 9th lift & 1no. at sec2-2 for 6th lift upto RL-242.40m is in progress in presence of JE,KID, PM, EPC agency n Site Engineers of PMC & EPC agency. Slump achieved 73mm on 16.11.2025
46/100
Instream Storage Structure, Budharaja
The flow level is 206.800 m against the design RL: 206.700, i.e., 0.100 m flood lift.
47/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 3no. of CC blocks of size 6.0x1.5x0.6m. at U/S flared out wall i.e. 1no. from sec-5-5 to sec-4-4 for 11th lift, 1no. from sec-4-4 to sec-2-2 for 9th lift & 1no. from sec2-2 to sec-1-1 for 6th lift upto RL-242.40m is in progress in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 75mm on 15.11.2025
48/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 3no. of CC blocks of size 6.0x1.5x0.6m. at U/S flared out wall i.e. 1no. from sec-5-5 to sec-4-4 for 11th lift, 1no. from sec-4-4 to sec-2-2 for 9th lift & 1no. from sec2-2 to sec-1-1 for 6th lift upto RL-242.40m is in progress in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 75mm on 15.11.2025
49/100
Instream Storage Structure, Khirasasan
Inspected LHS Guide Bund.
50/100
Instream Storage Structure, Khirasasan
Inspected RHS D/S Flared out wall.Instructed to provide expansion joint max at 9.00mt interval. Necessary back filling work to be done with good quality earth from approved borrow area.
51/100
Instream Storage Structure, Nandagaon
2nd stage embedded parts of both stop log gate and barrage bay gate of gate no 5 erection work under progress on 15.11.2025
52/100
Instream Storage Structure, Khirasasan
IEE ,QCE , E&A visited ISS Kirasason. The required space for DG seems to be inadequate in the specified DG room. It may require to modify DG room & control room after procurement of DG set& MDB by the Agency.
53/100
Instream Storage Structure, Khirasasan
LHS D/S Flared out wall 7th lift shuttering work under progress
54/100
Instream Storage Structure, Khirasasan
Pier no 5 Hoist portion shuttering work under progress
55/100
Instream Storage Structure, Khirasasan
View showing flow of river from D/S of river
56/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
57/100
Instream Storage Structure, Kudabega
Casting of concrete M30A20 for Stop log for service gate groove 2nd stage 6th lift RL-213.650 to 215.00 span 25 pier no 25
58/100
Instream Storage Structure, Kudabega
Slump 85 mm
59/100
Instream Storage Structure, Kudabega
Pier no-9, 10 RHS side gate groove chipping work in progress
60/100
Instream Storage Structure, Kudabega
Span 23,25 deshuttering work in progress
61/100
Instream Storage Structure, Kudabega
Span 30 gate grooving deshuttering and shuttering work in progress
62/100
Instream Storage Structure, Kudabega
Wing wall 4th lft steel Binding work in progress
63/100
Instream Storage Structure, Kopsinga
FDD test of LHS approach road 14th layer in presence of dept.JE (QC) .
64/100
Instream Storage Structure, Kopsinga
FDD test of LHS D/S guide bond 25th layer in presence of dept. JE (QC)
65/100
Instream Storage Structure, Kopsinga
Concrete work under progress of LHS u/s flared wall 9th lift (M20A20) in presence of dept. JE madam .
66/100
Instream Storage Structure, Kopsinga
Slump-80mm, LHS u/s flared wall 9th lift (M20A20)
67/100
Instream Storage Structure, Kopsinga
28 days Cube test of U/S P(8-7) & P(17-16) and 7 days cube test of d/s post P(10-11) & P(12-13) .
68/100
Instream Storage Structure, Kopsinga
Completed RHS d/s divide wall 7th lift .
69/100
Instream Storage Structure, Kopsinga
90mm,tm-6
70/100
Instream Storage Structure, Kopsinga
FDD test of LHS D/S guide bond 24th layer in presence of dept. JE madam.
71/100
Instream Storage Structure, Kopsinga
90mm,tm-5
72/100
Instream Storage Structure, Kopsinga
95mm,tm-4
73/100
Instream Storage Structure, Kopsinga
95mm,tm-3
74/100
Instream Storage Structure, Kopsinga
Concrete work under progress of RHS d/s divide wall 7th lift(M25A20) in presence of dept. JE madam.
75/100
Instream Storage Structure, Kopsinga
90mm,tm-2
76/100
Instream Storage Structure, Kopsinga
Slump-90mm,tm-1, RHS d/s divide wall 7th lift (M25A20) .
77/100
Instream Storage Structure, KansariGanda
Cleaning work in progress at site.
78/100
Instream Storage Structure, KansariGanda
Cleaning work in progress at site.
79/100
Instream Storage Structure, KansariGanda
Cleaning work in progress at site.
80/100
Instream Storage Structure, KansariGanda
Cleaning work in progress at site.
81/100
Instream Storage Structure, KansariGanda
Cleaning work in progress at site.
82/100
Instream Storage Structure, KansariGanda
Cleaning work in progress at site.
83/100
Instream Storage Structure, KansariGanda
Cleaning work in progress at site.
84/100
Instream Storage Structure, KansariGanda
Cleaning work in progress at site.
85/100
Instream Storage Structure, KansariGanda
Cleaning work in progress at site.
86/100
Instream Storage Structure, KansariGanda
Cleaning work in progress at site.
87/100
UGPL, Right Lower Suktel Canal Division
Valve verification work is in progress of Pipe DN - 350, Valve DN - 80 at village bhalar.
88/100
UGPL, Right Lower Suktel Canal Division
Valve verification work is in progress of Pipe DN - 300, Junction- in between J5081 & J5091 Valve DN - 80 at village Nilajpali.
89/100
UGPL, Right Lower Suktel Canal Division
Pump House internal drain inside plastering work is in progress.
90/100
UGPL, Left Lower Suktel Canal Division
Trench Excavation work is in progress for Dia 225mm HDPE pipe line node from J-467 to J-25 (zone-2) pipe at village Chhatabahal.
91/100
UGPL, Left Lower Suktel Canal Division
Boundary wall outer side plastering work is in progress at Pump House.
92/100
UGPL, Left Lower Suktel Canal Division
Butt fusion jointing work and Gap closing work is in progress for Dia 200mm HDPE pipe line from node J-411 to J-412, (Zone-1) at village Amamunda .
93/100
Instream Storage Structure, Gudvella
Erection of pylon at deck slab no -8 in between P7 and P8 at site is under progress on 14.11.2025
94/100
Instream Storage Structure, Nandagaon
M15 A20 grade concrete casting left side D/S flared out wall at sec.2-2 to sec.4-41st lift casting on date 17.10.25 & date of testing 14.11.25(28 days) in presence of DTL, QC exp.Sr site engineering, site engineering of Pmc & pm of aged average value23.56N/mm2 on 14.11.2025
95/100
Instream Storage Structure, Nandagaon
Embedded parts welding work is in progress on 14.11.2025
96/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 1no. of CC blocks of size 6.0x1.5x0.6m. at D/S left flared out wall for 3rd lift at sec.5-5 upto RL-237.00m is in progress in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 73mm on 14.11.2025
97/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 1no. of CC blocks of size 6.0x1.5x0.6m. at D/S left flared out wall for 3rd lift at sec.5-5 upto RL-237.00m is in progress in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 73mm on 14.11.2025
98/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at D/S left flared out wall from sec.1-1 to sec.2-2 for 10th lift from RL-239.40m to RL-240.00m is in progress in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 78mm on 14.11.2025
99/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at D/S left flared out wall from sec.1-1 to sec.2-2 for 10th lift from RL-239.40m to RL-240.00m is in progress in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 78mm on 14.11.2025
100/100
Integrated Barrage across river Kochila and across river Baitarini
BAITARANI -ISS C.C Block casting work in progress at site camp of ISS Kochila Baitarani- 15.11.2025
❮
❯