1/100
Instream Storage Structure, Nandagaon
R/S U/s stone pitching is in progress
2/100
Instream Storage Structure, Gudvella
REPAIRING WORK OF VERTICAL RUBBER SEAL OF GATE NO-9 IS IN PROGRESS.
3/100
Instream Storage Structure, Gudvella
CHIPPING WORK OF STOPLOG GROOVE OF GATE NO-5 IS IN PROGRESS.
4/100
Instream Storage Structure, Gudvella
D/S OF ISS GUDVELLA.
5/100
Instream Storage Structure, Gudvella
U/S OF ISS GUDVELLA.
6/100
Instream Storage Structure, Gudvella
Inspected by SE, SDO, AE & JE. Instructed to agency to complete the balance work earlier so that the dry & wet testing of the barrage can be carried out & further necessary action for inauguration can be taken.
7/100
Instream Storage Structure, Gudvella
Inspected by SE, SDO, AE & JE. Instructed to agency to complete the balance work earlier so that the dry & wet testing of the barrage can be carried out & further necessary action for inauguration can be taken.
8/100
Instream Storage Structure, Nandagaon
Drone Photos of Nandagaon ISS
9/100
Instream Storage Structure, Nandagaon
Drone Photos of Nandagaon ISS
10/100
Instream Storage Structure, Nandagaon
Drone Photos of Nandagaon ISS
11/100
Instream Storage Structure, Nandagaon
Drone Photos of Nandagaon ISS
12/100
Instream Storage Structure, Gudvella
RUBBER SEAL ADJUSTMENT IS IN PROGRESS AT GATE NO.08
13/100
Instream Storage Structure, Gudvella
STOPLOG ADJUSTMENT IS IN PROGRESS AT GATE NO.10
14/100
Instream Storage Structure, Gudvella
D/S SIDE OF ISS GUDVELLA ON 06.10.2026
15/100
Instream Storage Structure, Gudvella
U/S SIDE OF ISS GUDVELLA ON 06.10.2026
16/100
Instream Storage Structure, Gudvella
Sir ????
Checked the ISS Gudvella work. The horizontal rubber seal adjustment work for Bay No 1 to 7 has been successfully completed. As informed by the agency personnel, the remaining 3 gates are expected to be completed within the next two days. (05-10-26)
17/100
Instream Storage Structure, Gudvella
Sir ????
Checked the ISS Gudvella work. The horizontal rubber seal adjustment work for Bay No 1 to 7 has been successfully completed. As informed by the agency personnel, the remaining 3 gates are expected to be completed within the next two days. (05-10-26)
18/100
Instream Storage Structure, Gudvella
Repairing work of the rubber seal at Barrage Bay Gate No. 8 is currently in progress.(05-10-26)
19/100
Instream Storage Structure, Gudvella
Chipping work at the stoplog groove of Barrage Bay No. 9 is currently in progress. (05-10-26)
20/100
Instream Storage Structure, Gudvella
D/s of ISS Gudvella 05-10-26
21/100
Instream Storage Structure, Gudvella
U/s of ISS Gudvella
22/100
Instream Storage Structure, Nandagaon
Plastering work is currently underway in the basement of the control room building.
23/100
Instream Storage Structure, Dholapita
Documents Handing over of all deliverables at RBVN Basin, PMC office
24/100
Instream Storage Structure, Jakameripalli
Documents Handing over of all deliverables at RBVN Basin, PMC office
25/100
Instream Storage Structure, Dhanei
Documents Handing over of all deliverables at RBVN Basin, PMC office
26/100
Instream Storage Structure, Dhanei
Documents Handing over of all deliverables at RBVN Basin, PMC office
27/100
Instream Storage Structure, KansariGanda
Documents Handing over of all deliverables at RBVN Basin, PMC office
28/100
Instream Storage Structure, KansariGanda
Documents Handing over of all deliverables at RBVN Basin, PMC office
29/100
Instream Storage Structure, KansariGanda
29/09/2026
30/100
Instream Storage Structure, Nandagaon
Brick work at office building is in progress on 29.09.2026
31/100
Instream Storage Structure, Gudvella
Chipping work of stoplog groove is under progress on 29.09.2026
32/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 29.09.2026
33/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 29.09.2026
34/100
Instream Storage Structure, Gudvella
Chipping work of stoplog groove is under progress on 28.09.2026
35/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 28.09.2026
36/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 28.09.2026
37/100
Barrage across river Turi & Guntat
Guntat site status.
38/100
Barrage across river Turi & Guntat
Turi site status.
39/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 27.09.2026
40/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 27.09.2026
41/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 26.09.2026
42/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 26.09.2026
43/100
Instream Storage Structure, Gudvella
• Visited the Deputy Team Leader of the Tel Basin at the ISS Gudvella site, accompanied by the PMC site engineers.
1. Instructed the agency to expedite and complete all pending site works.
2. The installation and charging of the transformer by TPWODL were successfully completed at the site on 25.09.2026
44/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 25.09.2026
45/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 25.09.2026
46/100
Instream Storage Structure, Khalpal
Present flow condition of Rainfall at ISS khalpal site.
47/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
DCAC meeting conducted by supervision of Deputy Collector, keonjhar, S. E & S D. O, Rengali Dam Division, Tahasildar Telkoi, L. A. O, keonjhar, all landlord & R. S. A staff for ISS Santeibhanja.
48/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
DCAC meeting conducted by supervision of Deputy Collector, keonjhar, S. E & S D. O, Rengali Dam Division, Tahasildar Telkoi, L. A. O, keonjhar, all landlord & R. S. A staff for ISS Telkoi.
49/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Watchman building foundation is under progress in presence of Client & PSS Team.
50/100
Instream Storage Structure, Hamirpur
Binding of Reinforcement for Building footing vertical is under progress.
51/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.440m.
52/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 37.04/mm2 for 07 days) of Cross Girder (Bay No-13 & 14) and M25A20 (Strength is 21.48/mm2 for 07 days) of Precast Hand Railing has done in presence of Client & PSS team.
53/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Watchman building foundation is under progress in presence of Client & PSS Team.
54/100
Instream Storage Structure, Hamirpur
Column guide line welding work is in progress.
55/100
Instream Storage Structure, Hamirpur
MS plate marking and cutting for column base plate work is in progress.
56/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 95 mm) of Deck slab (Bay No-14) done in presence of Client & PSS Team.
57/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Deck slab (Bay No-14) is under progress in presence of Client & PSS Team.
58/100
Instream Storage Structure, Jakameripalli
Visit of QA/QC Expert, Mechanical site engineer and support staffs of PMC to the ISS Site for Routine inspection during Defect liability period.
59/100
Instream Storage Structure, Jakameripalli
Visit of QA/QC Expert, Mechanical site engineer and support staffs of PMC to the ISS Site for Routine inspection during Defect liability period.
60/100
Instream Storage Structure, Jakameripalli
02/01/2026 -Visit to ISS Jakmarapalli by PMC team consisting of QA/QC Expert, SDE, HME and Site Engineer Mechanical. The following observations made on Hydro Mechanical Equipment - Yearly Maintenance work.
1. Rope Drum Hoists Worm Reducers Oil change completed.
2. Greasing completed for Rope Drum Hoists gear assembly and other items.
3. Cardium compound applied for all Wire ropes of Hoists and Under Slung Hoist (for Stop log operation)
4. The painting work completed on Hoists Assembly Covers.
5. Greasing completed for Pulley Blocks and Gate Rollers.
61/100
Instream Storage Structure, Jakameripalli
02/01/2026 -Visit to ISS Jakmarapalli by PMC team consisting of QA/QC Expert, SDE, HME and Site Engineer Mechanical. The following observations made on Hydro Mechanical Equipment - Yearly Maintenance work.
1. Rope Drum Hoists Worm Reducers Oil change completed.
2. Greasing completed for Rope Drum Hoists gear assembly and other items.
3. Cardium compound applied for all Wire ropes of Hoists and Under Slung Hoist (for Stop log operation)
4. The painting work completed on Hoists Assembly Covers.
5. Greasing completed for Pulley Blocks and Gate Rollers.
62/100
Instream Storage Structure, Jakameripalli
02/01/2026 -Visit to ISS Jakmarapalli by PMC team consisting of QA/QC Expert, SDE, HME and Site Engineer Mechanical. The following observations made on Hydro Mechanical Equipment - Yearly Maintenance work.
1. Rope Drum Hoists Worm Reducers Oil change completed.
2. Greasing completed for Rope Drum Hoists gear assembly and other items.
3. Cardium compound applied for all Wire ropes of Hoists and Under Slung Hoist (for Stop log operation)
4. The painting work completed on Hoists Assembly Covers.
5. Greasing completed for Pulley Blocks and Gate Rollers.
63/100
Instream Storage Structure, Jakameripalli
02/01/2026 -Visit to ISS Jakmarapalli by PMC team consisting of QA/QC Expert, SDE, HME and Site Engineer Mechanical. The following observations made on Hydro Mechanical Equipment - Yearly Maintenance work.
1. Rope Drum Hoists Worm Reducers Oil change completed.
2. Greasing completed for Rope Drum Hoists gear assembly and other items.
3. Cardium compound applied for all Wire ropes of Hoists and Under Slung Hoist (for Stop log operation)
4. The painting work completed on Hoists Assembly Covers.
5. Greasing completed for Pulley Blocks and Gate Rollers.
64/100
Instream Storage Structure, Jakameripalli
02/01/2026 -Visit to ISS Jakmarapalli by PMC team consisting of QA/QC Expert, SDE, HME and Site Engineer Mechanical. The following observations made on Hydro Mechanical Equipment - Yearly Maintenance work.
1. Rope Drum Hoists Worm Reducers Oil change completed.
2. Greasing completed for Rope Drum Hoists gear assembly and other items.
3. Cardium compound applied for all Wire ropes of Hoists and Under Slung Hoist (for Stop log operation)
4. The painting work completed on Hoists Assembly Covers.
5. Greasing completed for Pulley Blocks and Gate Rollers.
65/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 24.09.2026
66/100
MMIP, Bankatira Barrage Project
Bankatira Barrage site inspection of PSS consultants.
67/100
MMIP, Bankatira Barrage Project
Flood water situation on river Budhabalanga at bankatira Barrage Site.
68/100
MMIP, Bankatira Barrage Project
Budhabalanga Flood water ( Submerged Nuagan - Shankarpur Road ) cutting off the Bankatira Barrage site Access.
69/100
MMIP, Bankatira Barrage Project
Bankatira Barrage site on 1- 07-2026.
70/100
MMIP, Bankatira Barrage Project
Site inspected by Superintending Engineer in the presence of PMC Consultants.
71/100
MMIP, Bankatira Barrage Project
Inspection of sheet pile drawing work by Irrigation Expert PMC S.B. Basin Baripada.
72/100
MMIP, Bankatira Barrage Project
Inspection of sheet pile driving work at site by S.E. & PMC staff.
73/100
Instream Storage Structure, Dhanei
Visit of SD Expert, PMC to RI Laxmana Pali, RI Chirikipada and SDO, Dhanei during the visit to ISS Sanabargam today (24.9.2026). Updated them on the latest status of land acquisition and made discussion on re-demarcation of private land scheduled for 01.10.2026, and the Collector’s letter(letter no:619 dt:1.9.26) to the Tahasildar, Polasara regarding demarcation of Government land by deploying revenue team.
74/100
Instream Storage Structure, Dhanei
Visit of SD Expert, PMC to RI Laxmana Pali, RI Chirikipada and SDO, Dhanei during the visit to ISS Sanabargam today (24.9.2026). Updated them on the latest status of land acquisition and made discussion on re-demarcation of private land scheduled for 01.10.2026, and the Collector’s letter(letter no:619 dt:1.9.26) to the Tahasildar, Polasara regarding demarcation of Government land by deploying revenue team.
75/100
Instream Storage Structure, Dhanei
Visit of SD Expert, PMC to RI Laxmana Pali, RI Chirikipada and SDO, Dhanei during the visit to ISS Sanabargam today (24.9.2026). Updated them on the latest status of land acquisition and made discussion on re-demarcation of private land scheduled for 01.10.2026, and the Collector’s letter(letter no:619 dt:1.9.26) to the Tahasildar, Polasara regarding demarcation of Government land by deploying revenue team.
76/100
Instream Storage Structure, KansariGanda
24.09.26
77/100
Instream Storage Structure, KansariGanda
24.09.26
78/100
Instream Storage Structure, KansariGanda
24.09.26
79/100
Instream Storage Structure, KansariGanda
24.09.26
80/100
Instream Storage Structure, KansariGanda
22.09.26
81/100
Instream Storage Structure, KansariGanda
Mechanical Gate and Trestle fabrication work in progress
82/100
Instream Storage Structure, KansariGanda
11.09.26
83/100
Instream Storage Structure, KansariGanda
Demarcation Update – UDS pur Mauja
Date: 09.09.2026
Demarcation for UDS pur Mauja continued today in the presence of Sarapancha and the villagers. During re-demarcation, it was observed that certain government lands have been converted into private patta land on the ground.
As these latest ground-level changes are not yet reflected in revenue records/maps, such discrepancies surfaced during spot verification, carried out in the presence of the land holders.
As per standard practice, boundary pegs with red flags have been fixed at the demarcation points.
84/100
Instream Storage Structure, KansariGanda
Demarcation Update – UDS pur Mauja
Date: 09.09.2026
Demarcation for UDS pur Mauja continued today in the presence of Sarapancha and the villagers. During re-demarcation, it was observed that certain government lands have been converted into private patta land on the ground.
As these latest ground-level changes are not yet reflected in revenue records/maps, such discrepancies surfaced during spot verification, carried out in the presence of the land holders.
As per standard practice, boundary pegs with red flags have been fixed at the demarcation points.
85/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 23.09.2026
86/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 23.09.2026
87/100
Instream Storage Structure, Nandagaon
• Visited the ISS Nandagaon site with CME, QC exp in presence of site engineers. The work position of project site is as follows.
1.Basement slab & basement flooring PCC of control room building completed. No further work done since last one month.
2. No manpower for mechanical gate balance works.
3. Stone pitching work done for 300mtrs only on u/s right side & no further work is going on.
4. Wearing coat over the bridge slab haven’t taken off till now on 22.09.2026
88/100
Instream Storage Structure, Nandagaon
• Visited the ISS Nandagaon site with CME, QC exp in presence of site engineers. The work position of project site is as follows.
1.Basement slab & basement flooring PCC of control room building completed. No further work done since last one month.
2. No manpower for mechanical gate balance works.
3. Stone pitching work done for 300mtrs only on u/s right side & no further work is going on.
4. Wearing coat over the bridge slab haven’t taken off till now on 22.09.2026
89/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 22.09.2026
90/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 22.09.2026
91/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 21.09.2026
92/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 19.09.2026
93/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 19.09.2026
94/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 18.09.2026
95/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 18.09.2026
96/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 17.09.2026
97/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 17.09.2026
98/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 16.09.2026
99/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 16.09.2026
100/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 15.09.2026
❮
❯