1/100
UGPL, Left Lower Suktel Canal Division
Air valve is installing and stem pipe encasement work is in progress of Lm-16, chainage-3750m, at village Kusang.
2/100
UGPL, Left Lower Suktel Canal Division
Stem pipe Encasing work is in progress at LO-167 LM-9 Near village Banjari In Presence of DoWR AE and PMC team.
3/100
UGPL, Left Lower Suktel Canal Division
1 Hector chamber fixing work in progress of OMS LO-307B Z-6536 (LM-16) near village Singhanimunda.
4/100
UGPL, Left Lower Suktel Canal Division
Internal Approach road block concrete pouring work is in progress at Pump House In presence of PMC team.
5/100
UGPL, Left Lower Suktel Canal Division
Slump testing work is in progress for internal approach road block casting at Pump House in presence of DoWR AEE and PMC team.
6/100
UGPL, Left Lower Suktel Canal Division
HDD machine road pushing work is in progress for road crossing work of 75mm Dia HDPE pipe line between at RO-251B(Z-4565),RM-14 near village Birkel.
7/100
UGPL, Left Lower Suktel Canal Division
Internal Approach road block shuttering board fixing work is in progress of Pump House area in presence of PMC team.
8/100
UGPL, Left Lower Suktel Canal Division
Internal Approach road block concrete pouring work is in progress at Pump House In presence of PMC team.
9/100
UGPL, Left Lower Suktel Canal Division
Slump testing work is in progress for internal approach road block casting at Pump House in presence of PMC team.
10/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE pipe connection work in progress road crossing lines jointing of OMS LO-307A Z(6741,6371,6469) LM-17 at Birkel.
11/100
UGPL, Left Lower Suktel Canal Division
Internal Approach road block shuttering board fixing work is in progress of Pump House area in presence of PMC team.
12/100
UGPL, Left Lower Suktel Canal Division
Stem pipe Encasing work is in progress at LO-157B LM-8 Near Talidur In Presence of DoWR AE and PMC team.
13/100
UGPL, Left Lower Suktel Canal Division
HDD machine road pushing work is in progress for road crossing work of 75mm Dia HDPE pipe line between at LO-327A(Z-5439), LM-17 near village Birkel.
14/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., SD expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site, CC block concreting, LHS divide wall pier cap RCC work, Pile cage lowering and Divide wall pile no 113 concreting.
15/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., SD expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site, CC block concreting, LHS divide wall pier cap RCC work, Pile cage lowering and Divide wall pile no 113 concreting.
16/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., SD expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site, CC block concreting, LHS divide wall pier cap RCC work, Pile cage lowering and Divide wall pile no 113 concreting.
17/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., SD expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site, CC block concreting, LHS divide wall pier cap RCC work, Pile cage lowering and Divide wall pile no 113 concreting.
18/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., SD expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site, CC block concreting, LHS divide wall pier cap RCC work, Pile cage lowering and Divide wall pile no 113 concreting.
19/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., QA/QC expert and along with Site engineers PMC to the ISS Site. Inspected the overall progress of site, RHS barrage bay mid. pier -06, pile cap concrete pouring and Divide wall Pile no - 147 Concreting.
20/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., QA/QC expert and along with Site engineers PMC to the ISS Site. Inspected the overall progress of site, RHS barrage bay mid. pier -06, pile cap concrete pouring and Divide wall Pile no - 147 Concreting.
21/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., QA/QC expert and along with Site engineers PMC to the ISS Site. Inspected the overall progress of site, RHS barrage bay mid. pier -06, pile cap concrete pouring and Divide wall Pile no - 147 Concreting.
22/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., QA/QC expert and along with Site engineers PMC to the ISS Site. Inspected the overall progress of site, RHS barrage bay mid. pier -06, pile cap concrete pouring and Divide wall Pile no - 147 Concreting.
23/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., QA/QC expert and along with Site engineers PMC to the ISS Site. Inspected the overall progress of site, RHS barrage bay mid. pier -06, pile cap concrete pouring and Divide wall Pile no - 147 Concreting.
24/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay gravity flow area bed preparation work in progress at baitarani iss project.
25/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Inspection of SE, QAD division Cuttack, AEE and JE of KDP irr division manager OCCL and PMC chandikhol at choudhary gada iss project-06.03.2026
26/100
Instream Storage Structure, Gudvella
• Today DTL visited ISS Gudvella along with HME & SHE experts.
He instructed the agency to complete the following works before submission of the 2nd EOT:
1. Remaining A2 d/s wing wall
2. Parapet & kerb of deck slab
3. Start building work without further delay
4. Complete land acquisition process
5. Start blockout area concrete
6. To submit the design & drawing of afflux bund & road.
He also instructed the agency to increase manpower to complete the above works without delay on 05.03.2026
27/100
Instream Storage Structure, Gudvella
• Today DTL visited ISS Gudvella along with HME & SHE experts.
He instructed the agency to complete the following works before submission of the 2nd EOT:
1. Remaining A2 d/s wing wall
2. Parapet & kerb of deck slab
3. Start building work without further delay
4. Complete land acquisition process
5. Start blockout area concrete
6. To submit the design & drawing of afflux bund & road.
He also instructed the agency to increase manpower to complete the above works without delay on 05.03.2026
28/100
Instream Storage Structure, Gudvella
Inspected the foundation bolts installation work as per approved drawing. All foundation bolts installed as per approved drawing. Final alignment work under progress. Instructed to agency to complete the foundation bolts alignment work as early as possible to allow the concrete casting in blackout portion. Till now pending painting work was not started. Instructed to agency to start the painting work then only gate erection work will be complete with in the Schedule time on 05.03.2026
29/100
Instream Storage Structure, Gudvella
Inspected the foundation bolts installation work as per approved drawing. All foundation bolts installed as per approved drawing. Final alignment work under progress. Instructed to agency to complete the foundation bolts alignment work as early as possible to allow the concrete casting in blackout portion. Till now pending painting work was not started. Instructed to agency to start the painting work then only gate erection work will be complete with in the Schedule time on 05.03.2026
30/100
Instream Storage Structure, Gudvella
Foundation bolt rectify work completed as per approval drawing at A1 & P1 blockout area on 05.03.2026
31/100
Instream Storage Structure, Gudvella
De-shuttering work at deck slab no 9 is under progress on 05.03.2026
32/100
Instream Storage Structure, Gudvella
Placement of CC block at D/s is under progress on 05.03.2026
33/100
Instream Storage Structure, Gudvella
Curing at building column is under progress on 05.03.2026
34/100
Instream Storage Structure, Nandagaon
Monorail walkway assembly work is under progress on 05.03.2026
35/100
Instream Storage Structure, Nandagaon
Foundation bolts installation work at Pier No-07 is in progress on 05.03.2026
36/100
Instream Storage Structure, Nandagaon
Curing at RCC deck slab is in progress on 05.03.2026
37/100
Instream Storage Structure, Nandagaon
Shuttering for RCC deck slab at span-13 is in progress on 05.03.2026
38/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for LHS D/S Divide wall, 3rd lift is under progress.
39/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-1, 6th lift at Block No-1 done in presence of Client & PSS Team.
40/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-1, 6th lift at Block No-1 is under progress in presence of Client & PSS Team.
41/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.26/mm2 for 28 days) of Pier No-13, 7th lift and (Strength is 31.31/mm2 for 28 days) of Pier No-10, 17th lift and (Strength is 21.78/mm2 for 07 days) of Pier No-6, 8th lift and (Strength is 21.04/mm2 for 07 days) of Pier No-13, 10th lift and M15A40 (Strength is 20.48/mm2 for 28 days) of D/S Toe wall, 1st lift and M15A40 (Strength is 20.07/mm2 for 28 days) of Core wall, 7th lift has done in presence of Client & PSS team.
42/100
Instream Storage Structure, Hamirpur
2nd stage embedded parts side guide, roller track erection work is in progress at Bay No-10.
43/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Deck slab (Bay No-24 & 25) is under progress.
44/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall Raft at Block no-5 is under progress.
45/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-22, 15th lift is under progress.
46/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-21, 6th lift is under progress.
47/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-16, 7th lift is under progress.
48/100
Instream Storage Structure, Khalpal
Curing of Piers is under progress.
49/100
UGPL, Right Lower Suktel Canal Division
Backfilling and levelling work is in progress at external drain site of Pump House.
50/100
UGPL, Right Lower Suktel Canal Division
Gap closing work is in progress 225mm Dia HDPE pipe in between J-3061 to J- 3143 at village Bhaler in presence of PMC team and L&T official.
51/100
UGPL, Right Lower Suktel Canal Division
OCS chamber piping work is in progress of OCS No-0213090-C03A at village Kurlupali in presence of PMC team and L&T personnel.
52/100
UGPL, Right Lower Suktel Canal Division
OCS chamber above GL work is in progress of OCS No:- 0213090-C04A at village Malmunda in presence of DoWR staff and PMC team.
53/100
UGPL, Right Lower Suktel Canal Division
External drain gap concrete pouring and stone pitching surface cleaning work is in progress at Pump House.
54/100
UGPL, Right Lower Suktel Canal Division
OCS chamber piping work is in progress of OCS No-0213090-C04A at village Kurlupali in presence of PMC team and L&T personnel.
55/100
UGPL, Right Lower Suktel Canal Division
Butterfly Valve and Butterfly valve Chamber verification work is in progress for 250mm Dia HDPE Pipe from J-7009 to J-7073(P-7067) village Umuria.
56/100
UGPL, Right Lower Suktel Canal Division
OCS chamber backfilling work is in progress of OCS no. 0201214-C07A At village Khamarmunda.
57/100
UGPL, Right Lower Suktel Canal Division
External drain stone pitching work is in progress at Pump House.
58/100
UGPL, Left Lower Suktel Canal Division
Stem pipe Encasing Reinforcement binding and Shuttering work is in progress at LO-8A LM-152A Near village Talidur In Presence of DoWR AE and PMC team .
59/100
UGPL, Left Lower Suktel Canal Division
Internal Approach road block concrete pouring work is in progress at Pump House In presence of PMC team.
60/100
UGPL, Left Lower Suktel Canal Division
Slump testing work is in progress for internal approach road block casting at Pump House in presence of PMC team.
61/100
UGPL, Left Lower Suktel Canal Division
HDD machine road pushing work is in progress of 75mm Dia HDPE pipe line between OMS LO-288A(Z-5201) near village Singhanimunda.
62/100
UGPL, Left Lower Suktel Canal Division
Inspected Stem pipe Encasing work is in progress at LO-8A LM-1 Near village Kusmel In Presence of DoWR AE and PMC team.
63/100
UGPL, Left Lower Suktel Canal Division
Internal Approach road block shuttering board fixing work is in progress of Pump House area in presence of PMC team.
64/100
UGPL, Left Lower Suktel Canal Division
Internal Approach road block concrete pouring work is in progress at Pump House In presence of PMC team.
65/100
UGPL, Left Lower Suktel Canal Division
Slump testing work is in progress for internal approach road block casting at Pump House in presence of PMC team.
66/100
UGPL, Left Lower Suktel Canal Division
Internal Approach road block shuttering board fixing work is in progress of Pump House area in presence of PMC team.
67/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
SM-OCCL and PMC-MBBS,Chandikhol visited choudhary gada iss project today. Discussion was held about Raft concrete casting work with agency. SM, OCCL instructed to PM of the Agency to engage more 1st class mason and helpers for raft casting and fixing of template in slope portion in order to achieve a smooth surface. SM also instructed agency to procure sufficient gunny bags for covering the top surface and ensure proper curing.
68/100
Integrated Barrage across river Kochila and across river Baitarini
PMC Team- Chandikhole visited ISS- Kochila & Baitarani today and inspected the different construction activities in presence of Agency representatives.
69/100
Instream Storage Structure, Gudvella
Cast of concrete final lift PCC M20A20 grade at 2nd row D/s curtain wall from A2 to P6 with RL148.20m to 148.60m is underprogress in the presence of Dept JE,site engineers of PMC n agency. The slump test value is 76mm on 03.03.2026
70/100
Instream Storage Structure, Gudvella
Cast of concrete final lift PCC M20A20 grade at 2nd row D/s curtain wall from A2 to P6 with RL148.20m to 148.60m is underprogress in the presence of Dept JE,site engineers of PMC n agency. The slump test value is 76mm on 03.03.2026
71/100
Instream Storage Structure, Gudvella
Area of 2nd d/s curtain wall is ready for concreting of grade M20A20 (final lift PCC) from RL 148.20 m to 148.60 m (P6 to A2). It is approved by SE, SDO and AE on 03.03.2026
72/100
Instream Storage Structure, Gudvella
Foundation bolt rectify work at Block out area P2 is under progress on 03.03.2026
73/100
Instream Storage Structure, Gudvella
Foundation bolt rectify at P3 blockout area completed on 03.03.2026
74/100
Instream Storage Structure, Gudvella
De-shuttering work at deck slab no-9 is under progress on 03.03.2026
75/100
Instream Storage Structure, Gudvella
• 1. Shuttering work at 2nd row d/s curtain wall is under progress.
2. Placement of CC block at site is under progress on 03.03.2026
76/100
Instream Storage Structure, Nandagaon
Shuttering works at span-13 at right block -2 is in progress on 03.03.2026
77/100
Instream Storage Structure, Nandagaon
Conducted one set cube test(3 nos. cubes) of M15A20 grade at Site Lab in presence of CME, Sr. Site Engineer of PMC other site Engineers PMC and EPC Agency, ISS Nandagaon. Found the result is compressive strength was 23.41N/mm²( Avg) on 03.03.2026
78/100
Instream Storage Structure, Nandagaon
Conducted one set cube test(3 nos. cubes) of M15A20 grade at Site Lab in presence of CME, Sr. Site Engineer of PMC other site Engineers PMC and EPC Agency, ISS Nandagaon. Found the result is compressive strength was 23.41N/mm²( Avg) on 03.03.2026
79/100
Instream Storage Structure, Nandagaon
Conducted one set cube test(3 nos. cubes) of M15A20 grade at Site Lab in presence of CME, Sr. Site Engineer of PMC other site Engineers PMC and EPC Agency, ISS Nandagaon. Found the result is compressive strength was 23.41N/mm²( Avg) on 03.03.2026
80/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for RCC deck slab at span-12 upto RL-247.0m is in progress through concrete pump & using plate vibrator for proper compaction in presence CME,Sr. Site Engineer of PMC,PM,EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 90mm on 03.03.2026
81/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for RCC deck slab at span-12 upto RL-247.0m is in progress through concrete pump & using plate vibrator for proper compaction in presence CME,Sr. Site Engineer of PMC,PM,EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 90mm on 03.03.2026
82/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for RCC deck slab at span-12 upto RL-247.0m is in progress through concrete pump & using plate vibrator for proper compaction in presence CME,Sr. Site Engineer of PMC,PM,EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 90mm on 03.03.2026
83/100
Instream Storage Structure, Nandagaon
Checked & measured the spacing of 8mm 2-legged strriups of kerb and found 200mm c/c on 03.03.2026
84/100
Instream Storage Structure, Nandagaon
Checking the spacing of 10mm top distribution bar of RCC deck slab and found 200mm c/c on 03.03.2026
85/100
Instream Storage Structure, Nandagaon
Checking the spacing of 16mm top main bar of RCC deck slab and found 150mm c/c on 03.03.2026
86/100
Instream Storage Structure, Nandagaon
• 1) Site visit of ISS Nandagaon by CME,Sr. Site Engineer of PMC in presence of PM,EPC Agency, Site Engineers of PMC and site Engineer of EPC Agency. Found the area in binding, placing of reinforcements works including shuttering at RCC Deck slab of span-12 at barrage bay-10 of block-2 are completed as follows :
(i) Binding of main n dist. bars at both bottom & top layers including binding of 8mm dia 2-legged stirrups for kerb at both sides of slab and fixing of rail posts bars & 100mm dia MS pipes for drainage system are completed.
(ii) Binding & placing of bentup/ hunch bar of 12mm dia 200 C/C at both side of cantilever portions are completed.
(iii) Placing of clear cover 40mm at bottom and both sides using cover blocks are done.
(iv) Rigid and Smooth shuttering & maintaining 40mm gap along the expansion joints are done by fixing of MS angles.
(v) Area is cleaned using air water pressure and passed by SE, KID, Bhawanipatna and ready to place concrete with RCC M35A20 grade upto RL-247.00m on 03.03.2026
87/100
Instream Storage Structure, Nandagaon
Curing at RCC deck slab is in progress on 03.03.2026
88/100
Instream Storage Structure, Nandagaon
Monorail walkway assembly work is under progress on 03.03.2026
89/100
Instream Storage Structure, Nandagaon
Foundation bolts installation work at Pier No-06 is in progress on 03.03.2026
90/100
Instream Storage Structure, Nandagaon
Shuttering for CC blocks at D/S left flared out wall, Block-2 is in progress on 03.03.2026
91/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for RCC deck slab at sapn-12 is in progress on 03.03.2026
92/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for LHS D/S Divide wall, 3rd lift is under progress.
93/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of RHS Divide wall slope portion, 3rd lift is under Progress.
94/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-7 is under Progress.
95/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-6 is under Progress.
96/100
Instream Storage Structure, Jharbeda
D/S CC BLOCK PLACING WORK IS IN PROGRESS.
97/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-8, 16th lift with pedestal at Block No-2 done in presence of Client & PSS Team.
98/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-8, 16th lift with pedestal at Block No-2 is under progress in presence of Client & PSS Team.
99/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-13, 11th lift done in presence of Client & PSS Team.
100/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall Raft at Block no-5 is under progress.
❮
❯