GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure , Tustapalli
The DGPS survey work has been successfully completed up to the axis of ISS Tustapali. The survey work is currently in progress towards the upstream side for afflux assessment in the presence of the SE Sir, JE and the agency's survey team.
2/100
Instream Storage Structure , Tustapalli
The DGPS survey work has been successfully completed up to the axis of ISS Tustapali. The survey work is currently in progress towards the upstream side for afflux assessment in the presence of the SE Sir, JE and the agency's survey team.
3/100
Instream Storage Structure , Tustapalli
The DGPS survey work has been successfully completed up to the axis of ISS Tustapali. The survey work is currently in progress towards the upstream side for afflux assessment in the presence of the SE Sir, JE and the agency's survey team.
4/100
Instream Storage Structure , Tustapalli
The DGPS survey work has been successfully completed up to the axis of ISS Tustapali. The survey work is currently in progress towards the upstream side for afflux assessment in the presence of the SE Sir, JE and the agency's survey team.
5/100
Instream Storage Structure , Tustapalli
The DGPS survey work has been successfully completed up to the axis of ISS Tustapali. The survey work is currently in progress towards the upstream side for afflux assessment in the presence of the SE Sir, JE and the agency's survey team.
6/100
Instream Storage Structure , Tustapalli
The DGPS survey work has been successfully completed up to the axis of ISS Tustapali. The survey work is currently in progress towards the upstream side for afflux assessment in the presence of the SE Sir, JE and the agency's survey team.
7/100
Instream Storage Structure, Gudvella
D/S OF ISS GUDVELLA.
8/100
Instream Storage Structure, Gudvella
U/S OF ISS GUDVELLA.
9/100
Instream Storage Structure, Nandagaon
Gate Erection is in progress.
10/100
Instream Storage Structure, Nandagaon
Building 2nd floor Slab Shuttering is in progress.
11/100
Instream Storage Structure, Hamirpur
Hoist Column stiffner plate fixing work is in progress
12/100
Instream Storage Structure, Hamirpur
Bay no 9 Deckslab railing beam post fixing and shuttering work is in progress
13/100
Instream Storage Structure, Hamirpur
Block No-5 d/s Flared out wall curing work & deshuttering is in progress
14/100
Instream Storage Structure, Dhanei
Painting work of the Under-Sluice gate ongoing at site
15/100
Instream Storage Structure, Dhanei
The RI, Chirikipada Sasan, along with the sub division team, revisited the ISS Sanabaragam site to address the grievances raised by villagers following the land demarcation carried out in October 2026 for private land acquisition. The team reviewed the issues raised by the affected villagers and took necessary steps towards their resolution.
16/100
Instream Storage Structure, Dhanei
The Superintending Engineer, Mechanical Division, Brahmapur visited the ISS Sanabaragam site on our request and inspected the progress of the work in detail, particularly the mechanical gate components. He also provided valuable technical guidance regarding the erection procedure and the materials required for successful completion of the gate erection work.
17/100
Instream Storage Structure, Near Village Basantpur across River Daya
collection of pilling materials for construction of coffer dam
18/100
Instream Storage Structure, Near Village Basantpur across River Daya
Coffer dam work in progress
19/100
Instream Storage Structure, Kuakhai
Reinforcements and the area ready for casting observed by SDO, ISS Kuakhai (I/C) . Today R/S D/S Flank wall 3rd lift from RL 11.10m to 12.50m M25 A20 casting to be commenced .
20/100
Instream Storage Structure, Hamirpur
Block no 5 d/s flared out wall boulder pitching work in progress
21/100
Instream Storage Structure, Hamirpur
By no 5 cross girder casting work progress
22/100
Instream Storage Structure, Hamirpur
Bay no - 18, gate groove 2nd stage 8th lift concreting is in progress
23/100
Instream Storage Structure , Tustapalli
The DGPS survey work is currently in progress from Saintala towards the Tustapali ISS site.
24/100
Instream Storage Structure, Gudvella
D/S OF ISS GUDVELLA.
25/100
Instream Storage Structure, Gudvella
U/S OF ISS GUDVELLA.
26/100
Instream Storage Structure, Kushabhadra
Barrage gate installation.
27/100
Instream Storage Structure, Kushabhadra
O&M Building 1st Floor Electrifications work is under progress.
28/100
Instream Storage Structure, Kushabhadra
Right side u/s guide bond area c&g with slope cutting work is progressing.
29/100
Instream Storage Structure, Kuakhai
AE,Prachi observing ongoing casting of RCC M30 A20 at right side counterfort (zone- 5) 5th lift from RL 11.45m to 12.80m is in progress.
30/100
Instream Storage Structure, Dhanei
Sand Blasting and Painting work ongoing of the gates at site
31/100
Barrage across river Turi & Guntat
Turi Barrage control room slab casting is going on
32/100
Barrage across river Turi & Guntat
Before slab casting on the control room of Turi Barrage
33/100
Barrage across river Turi & Guntat
Present status of Turi Barrage
34/100
Instream Storage Structure, Hamirpur
Bay no - 17, gate groove 2nd stage concreting is in progress
35/100
Instream Storage Structure, Hamirpur
Bay no-06 Deck slab concreting work in progress
36/100
Instream Storage Structure, Hamirpur
Bay no 10 - 2nd stage groove Wall concrete work in progress
37/100
Instream Storage Structure, Kuakhai
Casting of RCC M30 A20 at right side counterfort (zone- 5) 5th lift from RL 11.45m to 12.80m is in progress.
38/100
Instream Storage Structure , Tustapalli
The leveling survey using an Auto Level was completed on 06.11.2026. Following a break in the survey work, the DGPS survey has been resumed today i.e. on 17.11.2026, from Deogaon PWD IB in the presence of the Departmental Junior Engineer and the agency's survey team.
39/100
Instream Storage Structure , Tustapalli
The leveling survey using an Auto Level was completed on 06.11.2026. Following a break in the survey work, the DGPS survey has been resumed today i.e. on 17.11.2026, from Deogaon PWD IB in the presence of the Departmental Junior Engineer and the agency's survey team.
40/100
Instream Storage Structure , Tustapalli
The leveling survey using an Auto Level was completed on 06.11.2026. Following a break in the survey work, the DGPS survey has been resumed today i.e. on 17.11.2026 from Deogaon PWD IB in the presence of the Departmental Junior Engineer and the agency's survey team.
41/100
Instream Storage Structure, Gudvella
D/S SIDE OF ISS GUDVELLA ON 17.11.2026
42/100
Instream Storage Structure, Gudvella
U/S SIDE OF ISS GUDVELLA ON 17.11.2026
43/100
Instream Storage Structure, Gudvella
D/S SIDE OF ISS GUDVELLA ON 16.11.2026
44/100
Instream Storage Structure, Gudvella
U/S SIDE OF ISS GUDVELLA ON 16.11.2026
45/100
Instream Storage Structure, Gudvella
D/S SIDE OF ISS GUDVELLA ON 15.11.2026
46/100
Instream Storage Structure, Gudvella
DECKSLAB OF ISS GUDVELLA ON 15.11.2026
47/100
Instream Storage Structure, Gudvella
U/S SIDE OF ISS GUDVELLA ON 15.11.2026
48/100
Instream Storage Structure, Kushabhadra
Walkway bridge hand railing fixing work is under progress.
49/100
Instream Storage Structure, Kushabhadra
Making bed preparation for backfilling.
50/100
Instream Storage Structure, Kushabhadra
O&M Building 1st Floor Inside plastering work is under progress.
51/100
Instream Storage Structure, Kushabhadra
Canal Road 2nd layer laying work is under progress.
52/100
Instream Storage Structure, Hamirpur
Bay no - 17, gate groove 2nd stage 6th lift concreting is in progress
53/100
Instream Storage Structure, Hamirpur
Bay no-06 Deck slab shuttering with reinforcement binding work is in progress
54/100
Instream Storage Structure, Hamirpur
Bay no - 7/8, slab curing work is in progress
55/100
Instream Storage Structure, Dhanei
All three gates have been inverted to facilitate Sand blasting and painting of the opposite sides.
56/100
Instream Storage Structure, Dhanei
12 nos electrical Poles installation completed at site.
57/100
Instream Storage Structure, Dhanei
Electrical Pole installation started at site. Four nos of poles installed on that day.
58/100
Instream Storage Structure, Near Village Basantpur across River Daya
Coffer dam work is in progress
59/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning of Reinforcement in progress ISS Telkoi on 16.11.2026
60/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
ISS Santeibhanja 16.11.2026
61/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
cleaning work in progress ISS Santeibhanja on 16.11.2026
62/100
Instream Storage Structure, Nandagaon
Control Room construction work is in progress,
63/100
Instream Storage Structure, Kushabhadra
Right side Guide bund development is under progress.
64/100
Instream Storage Structure, Kushabhadra
Canal road second layer compaction is in progress.
65/100
Instream Storage Structure, Hamirpur
Bay no 6 Deckslab reinforcement binding work is in progress.
66/100
Instream Storage Structure, Hamirpur
Abutment A2 under sluice column erection with fitting work in progress
67/100
Instream Storage Structure, Hamirpur
Bay no 21stoplog side guide alignment with fitting work in progress
68/100
Instream Storage Structure, Kushabhadra
Hoist Bridge Alignement Work is in Progress
69/100
Instream Storage Structure, Kushabhadra
Building Electrification work is in Progress.
70/100
Instream Storage Structure, Kushabhadra
Laying of second layer for River embankment road.
71/100
Instream Storage Structure, Near Village Basantpur across River Daya
Coffee dam work is in progress.
72/100
Instream Storage Structure, Gudvella
D/S OF ISS GUDVELLA ON 14.11.2026
73/100
Instream Storage Structure, Gudvella
U/S OF ISS GUDVELLA ON 14.11.2026
74/100
Instream Storage Structure, Gudvella
D/S OF ISS GUDVELLA ON 13.11.2026
75/100
Instream Storage Structure, Gudvella
U/S OF ISS GUDVELLA. ON 13.11.2026.
76/100
Instream Storage Structure, Hamirpur
Block no 5 d/s flared out wall boulder pitching work in progress
77/100
Instream Storage Structure, Hamirpur
Bay no-06 Deck slab reinforcement placing work is in progress
78/100
Instream Storage Structure, Hamirpur
Bay no-12 gate groove 2nd stage concreting work in progress
79/100
Instream Storage Structure, Kuakhai
SE, Prachi along with G.M.( Civil), H.O. OCCL visited the ISS Kuakhai site in presence of concerned site engineers and PM, DDBL and instructed to expedite the progress as per the work programme submitted for timely completion of work by stipulated date i. e by March-27.
80/100
Instream Storage Structure, Kushabhadra
Embankment Road 2nd layer laying work is under progress.
81/100
Instream Storage Structure, Kushabhadra
O&M Building 1st Floor Inside plastering & Finishing work is under progress.
82/100
Instream Storage Structure, Gudvella
D/s of ISS Gudvella.
83/100
Instream Storage Structure, Gudvella
U/s of ISS Gudvella.
84/100
Instream Storage Structure, Hamirpur
Bay no - 22, gate groove 2nd stage 1st lift concreting is in progress
85/100
Instream Storage Structure, Hamirpur
Block no 5 d/s flared out wall 9th lift boulder spreading in progress
86/100
Instream Storage Structure, Hamirpur
Deck slab curing work is in progress
87/100
Instream Storage Structure, Kudabega
Unloading Stone at site
88/100
Instream Storage Structure, Kudabega
Electrical Lightening work in progress
89/100
Instream Storage Structure, Near Village Basantpur across River Daya
Site visit by Assistant Engineer to the confluence point of Daya & Bhargavi River to plan for the construction of Coffee dam.
90/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Dewatering in progress at ISS Santeibhanja on 11.11.2026
91/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Inspection of Control Room Building works at ISS Telkoi on 11.11.2026
92/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Joint Inspection of land at Telkoi (currently under the occupation of RWSS) by SE, RWSS Division and AEE, Rengali Dam Division in presence of field engineers and the agency on 11.11.2026
93/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Joint Inspection of land at Telkoi (currently under the occupation of RWSS) by SE, RWSS Division and AEE, Rengali Dam Division in presence of field engineers and the agency on date 11.11.2026
94/100
Instream Storage Structure, Gudvella
D/s of ISS Gudvella.
95/100
Instream Storage Structure, Gudvella
U/s of ISS Gudvella.
96/100
Instream Storage Structure, Hamirpur
Bay no - 17, gate groove 2nd stage 2nd lift concreting is in progress
97/100
Instream Storage Structure, Hamirpur
Bay no 21 LHS column erection work in progress
98/100
Instream Storage Structure, Kushabhadra
Fixation of alignment of Guide bund by SDO Balianta & Manager,OCCL and other field engineerd.
99/100
Instream Storage Structure, Kushabhadra
Rolling of GSB is ongoing.
100/100
Instream Storage Structure, Kopsinga
First floor of double storey building plastering is under progress

Enter Login Details

Forgot Password ?