GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, KansariGanda
Visit of PMC team comprising Irrigation experts, Social expert, safety expert to the ISS Kansariganda. Interacted with the site incharge, site Engineers of the agency with respect to check list prepared for post monsoon preparations at site. Cleaning of debris from different components of barrage was in progress. Grinding of rusted exposed rods were in progress. Sand blasting was also initiated where ever possible. The agency was instructed to increase sufficient labourers for early cleaning. AEE and AE of the department were also present during discussion during the visit. Maintenance works were taken up to all transport vehicles, DGs, pumps . Labour camps are yet to ready for staying and sanitary arrangements are to be restored.
2/100
Instream Storage Structure, KansariGanda
Visit of PMC team comprising Irrigation experts, Social expert, safety expert to the ISS Kansariganda. Interacted with the site incharge, site Engineers of the agency with respect to check list prepared for post monsoon preparations at site. Cleaning of debris from different components of barrage was in progress. Grinding of rusted exposed rods were in progress. Sand blasting was also initiated where ever possible. The agency was instructed to increase sufficient labourers for early cleaning. AEE and AE of the department were also present during discussion during the visit. Maintenance works were taken up to all transport vehicles, DGs, pumps . Labour camps are yet to ready for staying and sanitary arrangements are to be restored.
3/100
Instream Storage Structure, KansariGanda
Visit of PMC team comprising Irrigation experts, Social expert, safety expert to the ISS Kansariganda. Interacted with the site incharge, site Engineers of the agency with respect to check list prepared for post monsoon preparations at site. Cleaning of debris from different components of barrage was in progress. Grinding of rusted exposed rods were in progress. Sand blasting was also initiated where ever possible. The agency was instructed to increase sufficient labourers for early cleaning. AEE and AE of the department were also present during discussion during the visit. Maintenance works were taken up to all transport vehicles, DGs, pumps . Labour camps are yet to ready for staying and sanitary arrangements are to be restored.
4/100
Instream Storage Structure, KansariGanda
Visit of PMC team comprising Irrigation experts, Social expert, safety expert to the ISS Kansariganda. Interacted with the site incharge, site Engineers of the agency with respect to check list prepared for post monsoon preparations at site. Cleaning of debris from different components of barrage was in progress. Grinding of rusted exposed rods were in progress. Sand blasting was also initiated where ever possible. The agency was instructed to increase sufficient labourers for early cleaning. AEE and AE of the department were also present during discussion during the visit. Maintenance works were taken up to all transport vehicles, DGs, pumps . Labour camps are yet to ready for staying and sanitary arrangements are to be restored.
5/100
Instream Storage Structure, KansariGanda
Visit of PMC team comprising Irrigation experts, Social expert, safety expert to the ISS Kansariganda. Interacted with the site incharge, site Engineers of the agency with respect to check list prepared for post monsoon preparations at site. Cleaning of debris from different components of barrage was in progress. Grinding of rusted exposed rods were in progress. Sand blasting was also initiated where ever possible. The agency was instructed to increase sufficient labourers for early cleaning. AEE and AE of the department were also present during discussion during the visit. Maintenance works were taken up to all transport vehicles, DGs, pumps . Labour camps are yet to ready for staying and sanitary arrangements are to be restored.
6/100
Instream Storage Structure, KansariGanda
Visit of PMC team comprising Irrigation experts, Social expert, safety expert to the ISS Kansariganda. Interacted with the site incharge, site Engineers of the agency with respect to check list prepared for post monsoon preparations at site. Cleaning of debris from different components of barrage was in progress. Grinding of rusted exposed rods were in progress. Sand blasting was also initiated where ever possible. The agency was instructed to increase sufficient labourers for early cleaning. AEE and AE of the department were also present during discussion during the visit. Maintenance works were taken up to all transport vehicles, DGs, pumps . Labour camps are yet to ready for staying and sanitary arrangements are to be restored.
7/100
UGPL, Left Lower Suktel Canal Division
Gap closing work is in progress at RM-7, J-412 Hdpe pipe near village Amamunda .
8/100
UGPL, Left Lower Suktel Canal Division
Joint verification is in progress of HDPE pipe line OMS point and outlet points of LO-140A(LM-7)in presence of PMC team at village Uparudar.
9/100
Instream Storage Structure, Gudvella
Erection of pylon at deck slab no -8 in between P7 and P8 at site is under progress on 13.11.2025
10/100
Instream Storage Structure, Nandagaon
Monorail's fitup welding work is in progress on 13.11.2025
11/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 2nos. of CC blocks of size 6.0x1.5x0.6m. at D/S left flared out wall for 3rd lift from sec.5-5 to sec.6-6 & 2nd lift from sec.4-4 to sec.5-5 upto RL-237.00m is in progress through concrete pump in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 88mm on 13.11.2025
12/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 2nos. of CC blocks of size 6.0x1.5x0.6m. at D/S left flared out wall for 3rd lift from sec.5-5 to sec.6-6 & 2nd lift from sec.4-4 to sec.5-5 upto RL-237.00m is in progress through concrete pump in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 88mm on 13.11.2025
13/100
UGPL, Right Lower Suktel Canal Division
Valve verification work is in progress In between junction J-7038 & J-7042 at village Bandhankata.
14/100
UGPL, Right Lower Suktel Canal Division
Pump House internal drain bricks masonry work is in progress.
15/100
Integrated Barrage across river Kochila and across river Baitarini
CC Block shifting is ongoing at camp.-14.11.2025
16/100
UGPL, Left Lower Suktel Canal Division
Boundary wall outer side plastering work is in progress of Pump House.
17/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cleaning of reinforcement for Raft area is under progress.
18/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning of reinforcement for Raft area is under progress.
19/100
Instream Storage Structure, Jharbeda
Cleaning of Pier No-7 is under progress.
20/100
Instream Storage Structure, Jharbeda
Cleaning of Sand & mud at Raft area is under progress.
21/100
Instream Storage Structure, Jharbeda
Dewatering work is under progress.
22/100
Instream Storage Structure, Jharbeda
Cleaning of Pier No-6 is under progress.
23/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 20.74/mm2 for 07 days) of Pier No-28, 12th lift and (Strength is 30.30/mm2 for 28 days) of Pier No-29, 6th lift has done in presence of Client & PSS team.
24/100
Instream Storage Structure, Hamirpur
Hoist bridge platform assembly No-15 welding work is in progress.
25/100
Instream Storage Structure, Hamirpur
Curing of Piers is under progress.
26/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-30 & 31, 3rd lift at Block No-5 is under progress.
27/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-28, 13th lift at Block No-4 is under progress.
28/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-29, 9th lift at Block No-4 is under progress.
29/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-23, 9th lift at Block No-4 is under progress.
30/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for RHS U/S Flank wall, 5th lift at Block No-5 is under progress.
31/100
Instream Storage Structure, Khalpal
M15A20 Hirakud Government Lab mix design trial mix conducted at site laboratory, Slump test (Value 60 mm) and cube casting in presence of J.E, Quality Control, Samal and PSS Team of Angul.
32/100
Instream Storage Structure, Khalpal
Slump testing M20A40 (Value 60 mm) C.C Blocks done in presence of Client & PSS Team.
33/100
Instream Storage Structure, Khalpal
Casting of C.C Block (M20A40) is under progress in presence of Client & PSS Team.
34/100
UGPL, Left Lower Suktel Canal Division
The Gap closing work is in progress for laying of 600mm Dia DI pipeline, DY-2, from node J-642 to J-245 near village Dumdumi.
35/100
Instream Storage Structure, Gudvella
Shuttering at left side u/s flared out wall for 8th lift PCC work is under progress on 12.11.2025
36/100
Instream Storage Structure, Nandagaon
2nd stage embedded parts and roller track all measurements checked as per drawing erection work completed on 6th stoplog gate on 12.11.2025
37/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 10nos. of CC blocks at U/S left flared out wall upto RL-241.80m is in progress in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 71mm on 12.11.2025
38/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 10nos. of CC blocks at U/S left flared out wall upto RL-241.80m is in progress in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 71mm on 12.11.2025
39/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at D/S left flared out wall from sec.1-1 to sec.2-2 for 9th lift from RL-238.80m to RL-239.40m is in progress in presence of JE,KID, PM, EPC agency n Site Engineers of PMC & EPC agency. Slump achieved 73mm on 12.11.2025
40/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at D/S left flared out wall from sec.1-1 to sec.2-2 for 9th lift from RL-238.80m to RL-239.40m is in progress in presence of JE,KID, PM, EPC agency n Site Engineers of PMC & EPC agency. Slump achieved 73mm on 12.11.2025
41/100
UGPL, Right Lower Suktel Canal Division
Internal drain plastering work is in progress at Pump House.
42/100
UGPL, Right Lower Suktel Canal Division
AMS verification work is in progress of DI pipe Dia - 500mm In between Junction - J-0011 & J-0510 at village Khuntpali.
43/100
UGPL, Left Lower Suktel Canal Division
DYCO panel testing is in progress by JAYASHREE service ENGINEER at Pump House.
44/100
UGPL, Left Lower Suktel Canal Division
Trench excavation work in progress for outlet point extension at LO-127A (Z-6032) village Lankabahal.
45/100
UGPL, Left Lower Suktel Canal Division
Joint verification is in progress of HDPE pipe line OMS point and outlet points at village Lankabahal of LO-127A(LM-7)in presence of PMC team.
46/100
UGPL, Left Lower Suktel Canal Division
Boundary wall outer side plastering work is in progress of Pump House.
47/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cleaning of debris & mud at Raft area is under progress.
48/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Excavation of Foundation for Office building is under progress.
49/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Observed of Sieve analysis of Coarse & Fine aggregate in presence of S.E, RDD, A.E.E, RDD & PSS team along with EPC agency.
50/100
Instream Storage Structure, Jharbeda
Cleaning of Sand & mud at Raft area is under progress.
51/100
Instream Storage Structure, Jharbeda
Dewatering work is under progress.
52/100
Instream Storage Structure, Jharbeda
Cleaning of Pier No-6 is under progress.
53/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.18/mm2 for 07 days) of Pier No-30, 2nd lift has done in presence of Client & PSS team.
54/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Flank wall, 4th lift at Block No-5 done in presence of Client & PSS Team.
55/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Flank wall, 4th lift at Block No-5 is under progress in presence of Client & PSS Team.
56/100
Instream Storage Structure, Hamirpur
Curing of Piers is under progress.
57/100
Instream Storage Structure, Hamirpur
Observed of Sieve analysis of Fine aggregate in presence of A.E.E, RID & PSS team along with EPC agency.
58/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-30 & 31, 3rd lift at Block No-5 is under progress.
59/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-27, 12th lift at Block No-4 is under progress.
60/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-29, 9th lift at Block No-4 is under progress.
61/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-23, 9th lift at Block No-4 is under progress.
62/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-17, 6th lift at Block No-3 is under progress.
63/100
Instream Storage Structure, Khalpal
M30A20 Hirakud Government Lab mix design trial mix conducted in site laboratory, Slump test (Value 120 mm) and cube casting in presence of PSS Team.
64/100
Instream Storage Structure, Khalpal
Samal Mix Design trial mix conducted at site laboratory of M25A20, 7 days cube (Strength 31.21 N/mm²) & M20A40 7 days cube (Strength 28.10 N/mm²) in presence of PSS Team.
65/100
Instream Storage Structure, Khalpal
Slump testing M20A40 (Value 60 mm) C.C Blocks done in presence of Client & PSS Team.
66/100
Instream Storage Structure, Khalpal
Casting of C.C Block (M20A40) is under progress in presence of Client & PSS Team.
67/100
Instream Storage Structure, Gudvella
Cast of concrete 8th lift PCC M15A40 grade at left side D/s flard out wall from sec 1-1 to sec 2 - 2 with RL 152.80m to 153.40m is under progress the presence of Dept JE, site engineers of PMC n agency. Slump achieved 70mm on 11.11.2025
68/100
Instream Storage Structure, Gudvella
Cast of concrete 8th lift PCC M15A40 grade at left side D/s flard out wall from sec 1-1 to sec 2 - 2 with RL 152.80m to 153.40m is under progress the presence of Dept JE, site engineers of PMC n agency. Slump achieved 70mm on 11.11.2025
69/100
UGPL, Left Lower Suktel Canal Division
Trench Excavation work is in progress from node J-642 to J-245, DY-2 for laying of DI pipeline 600mm Dia near village Dumdumi.
70/100
Instream Storage Structure, Gudvella
Cast of concrete 7th lift PCC M15A40 grade at left side D/s flard out wall from sec 1-1 to sec 2a - 2a with RL 152.20m to 152.80m is under progress the presence of Dept JE, site engineers of PMC n agency. Slump achieved 71mm on 10.11.2025
71/100
Instream Storage Structure, Gudvella
Cast of concrete 7th lift PCC M15A40 grade at left side D/s flard out wall from sec 1-1 to sec 2a - 2a with RL 152.20m to 152.80m is under progress the presence of Dept JE, site engineers of PMC n agency. Slump achieved 71mm on 10.11.2025
72/100
Instream Storage Structure, Nandagaon
2nd stage embedded parts erection work under progress on 6th stoplog gate on 11.11.2025
73/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at D/S left flared out wall from sec.1-1 to sec.2-2 for 8th lift from RL-238.20m to RL-238.80m is in progress in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 71mm on 11.11.2025
74/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at D/S left flared out wall from sec.1-1 to sec.2-2 for 8th lift from RL-238.20m to RL-238.80m is in progress in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 71mm on 11.1.2025
75/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 10nos. of CC blocks at U/S left flared out wall upto RL-241.80m is in progress in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 76mm on 11.11.2025
76/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 10nos. of CC blocks at U/S left flared out wall upto RL-241.80m is in progress in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 76mm on 11.11.2025
77/100
Instream Storage Structure, Nandagaon
Column fit up work under progress on 10.11.2025
78/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 6nos. of CC blocks at D/S left flared out wall for 1st lift from sec.4-4 to sec.5-5 and 2nd lift from sec.5-5 to sec.6-6 upto RL-236.40m is in progress through concrete pump in presence of JE,KID, PM,EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 81mm on 10.11.2025
79/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 6nos. of CC blocks at D/S left flared out wall for 1st lift from sec.4-4 to sec.5-5 and 2nd lift from sec.5-5 to sec.6-6 upto RL-236.40m is in progress through concrete pump in presence of JE,KID, PM,EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 81mm on 10.11.2025
80/100
UGPL, Left Lower Suktel Canal Division
Filtration unit main distribution panel installation work is in progress at left command Pump House Zone- 2 .
81/100
Instream Storage Structure, Gudvella
Cast of concrete 7th lift PCC M20A20 grade at left side U/s flard out wall CC block from sec 2-2 to sec 4-4 with RL 152.20m to 152.80m is under progress the presence of Dept JE, site engineers of PMC n agency at site. Slump achieved 71mm on 09.11.2025
82/100
Instream Storage Structure, Gudvella
Cast of concrete 7th lift PCC M20A20 grade at left side U/s flard out wall CC block from sec 2-2 to sec 4-4 with RL 152.20m to 152.80m is under progress the presence of Dept JE, site engineers of PMC n agency at site. Slump achieved 71mm on 09.11.2025
83/100
Instream Storage Structure, Gudvella
Cast of concrete 6th lift PCC M15A40 grade at left side D/s flard out wall from sec 1-1 to sec 3-3 with RL151.60m to 152.20 m is under progress through chute in the presence of Dept JE, site engineers of PMC n agency at site. Slump achieved 70mm on 08.11.2025
84/100
Instream Storage Structure, Gudvella
Cast of concrete 6th lift PCC M15A40 grade at left side D/s flard out wall from sec 1-1 to sec 3-3 with RL151.60m to 152.20 m is under progress through chute in the presence of Dept JE, site engineers of PMC n agency at site. Slump achieved 70mm on 08.11.2025
85/100
Instream Storage Structure, Gudvella
De shuttering at deck slab no -1 in between A1 and P1 is under progress on 07.11.2025
86/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade at bay no.3 & 6 gate grooves sill beam is in progress in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 73mm on 09.11.2025
87/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade at bay no.3 & 6 gate grooves sill beam is in progress in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 73mm on 09.11.2025
88/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade at bay no.4 & 5 gate grooves sill beam is in progress in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 71mm on 08.11.2025
89/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade at bay no.4 & 5 gate grooves sill beam is in progress in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 71mm on 08.11.2025
90/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at D/S left flared out wall from sec.2-2 to sec.4-4 of length 4.68m measure from sec.2-2 for 6th lift from RL-237.00m to RL-237.00m is in progress through concrete pump in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 86mm on 08.11.2025
91/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at D/S left flared out wall from sec.2-2 to sec.4-4 of length 4.68m measure from sec.2-2 for 6th lift from RL-237.00m to RL-237.00m is in progress through concrete pump in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 86mm on 08.11.2025
92/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at D/S left flared out wall from sec.1-1 to sec.2-2 for 7th lift from RL-237.60m to RL-238.20m is in progress through concrete pump in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 84mm on 08.11.2025
93/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at D/S left flared out wall from sec.1-1 to sec.2-2 for 7th lift from RL-237.60m to RL-238.20m is in progress through concrete pump in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 84mm on 08.11.2025
94/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 6nos. of CC blocks at D/S left flared out wall for 1st lift from sec.4-4 to sec.5-5 and 2nd lift from sec.5-5 to sec.6-6 upto RL-236.40m is in progress through concrete pump in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 87mm on 08.11.2025
95/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 6nos. of CC blocks at D/S left flared out wall for 1st lift from sec.4-4 to sec.5-5 and 2nd lift from sec.5-5 to sec.6-6 upto RL-236.40m is in progress through concrete pump in presence of JE,KID, PM n Site Engineers of PMC & EPC agency. Slump achieved 87mm on 08.11.2025
96/100
Instream Storage Structure, Nandagaon
First barrage bay gate sil beam water level checked, all measurements checked as per drawing, spirit level checked on 08.11.2025
97/100
Instream Storage Structure, Nandagaon
De- Shuttering & Shuttering at D/S left flared out wall is in progress on 08.11.2025
98/100
Instream Storage Structure, Nandagaon
Chequer plate welding on hoist bridge under progress on 07.11.2025
99/100
Instream Storage Structure, Nandagaon
1st barrage bay gate erection work under progress on 07.11.2025
100/100
UGPL, Right Lower Suktel Canal Division
Soil filling and levelling work is in progress near free space area of filtration unit of Pump House.

Enter Login Details

Forgot Password ?