1/100
Barrage across river Turi & Guntat
Compressive strength test of concrete cubes conducted atTuri Barrage Site. Grade of concrete M25A20.
2/100
Barrage across river Turi & Guntat
Slump Test conducted at Location Guntat site.
Grade:- M15 A40
Slump:- 60mm
It is in admissible limit.
3/100
Barrage across river Turi & Guntat
PCC concreting underway in D/S flaredout wall R/S at Guntat site.
4/100
Barrage across river Turi & Guntat
Slump Test conducted at Location Turi site.
Grade:- M25 A20
Slump:- 85mm
It is in admissible limit.
5/100
Barrage across river Turi & Guntat
RCC concreting underway in D/S counterfort wall at Turi site.
6/100
Barrage across river Turi & Guntat
Slump Test conducted at Location Guntat site.
Grade:- M25 A20
Slump:- 88mm
It is in admissible limit.
7/100
Barrage across river Turi & Guntat
RCC concreting underway at D/S flank wall at Guntat site.
8/100
Barrage across river Turi & Guntat
Slump Test conducted at Location Turi site.
Grade:- M25 A20
Slump:- 80mm
It is in admissible limit.
9/100
Barrage across river Turi & Guntat
RCC concreting underway at U/ S flank wall and return wall at Turi site.
10/100
Barrage across river Turi & Guntat
Gradation test of Coarse aggregate and Fine Aggregate conducted in presence of WRD QC SE, JE, NID JE and PMC Site engineers and agency representatives at Turi site.
11/100
Barrage across river Turi & Guntat
FDD core cutting test has been done in the presence of WRD JE, PMC Site engineers and agency representatives at Turi site.
12/100
Barrage across river Turi & Guntat
FDD core cutting test has been done in the presence of WRD JE, PMC Site engineers and agency representatives at Turi site.
13/100
Barrage across river Turi & Guntat
RCC concreting underway at D/S flankwall and return wall Turi site.
14/100
Barrage across river Turi & Guntat
Slump Test conducted at Location Turi site.
Grade:- M25 A20
Slump:- 83mm
It is in admissible limit.
15/100
Instream Storage Structure, Khirasasan
Slump 85mm
16/100
Instream Storage Structure, Khirasasan
Sand
17/100
Instream Storage Structure, Khirasasan
Chips 10 mm
18/100
Instream Storage Structure, Khirasasan
Material procured Chips 20 mm
19/100
Instream Storage Structure, Khirasasan
Sir, checked placing and positioning of steel reinforcement, supporting bars and alignment of shuttering work in LHS d/s flared out 7th lift RL- 213.500 to 214.100 Now the area is ready for concrete casting M20 A20. So recommended for the purpose. Approved by AEE sir SID Sambalpur in presence of JE
20/100
Instream Storage Structure, Khirasasan
Pier no. 5 hoist portion shuttering work completed and ready for casting.
21/100
Instream Storage Structure, Khirasasan
View showing flow of river from D/S of river
22/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
23/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at LHS U/S FLAIRED-OUT WALL.
24/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at Pier No: 4, Hoist Gate Portion.
25/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at Pier No: 3, Hoist Gate Portion.
26/100
Instream Storage Structure, Budharaja
Curing work is in Progress at Pier No: 2, Hoist Gate Portion.
27/100
Instream Storage Structure, Budharaja
Curing work is in Progress at Pier No: 1, Hoist Gate Portion.
28/100
Instream Storage Structure, Budharaja
The flow level is 206.800 m against the design RL: 206.700, i.e., 0.100 m flood lift.
29/100
Instream Storage Structure across river Sapei near village Kinjirma
shuttering work under progress of R.H.S counter fort wing Wall 4th lift
30/100
Instream Storage Structure across river Sapei near village Kinjirma
Control room plinth beam reinforcement work under progress
31/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
32/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. Flow direction is straight. The direction of flow is seen in middle of the river. Now the flow level is 225.600mt against design crest level 225.500 i.e. flood lift 0.1mt.
33/100
Instream Storage Structure Across Bheden near village Saida
Shuttering work progress in LHS d/s flank wall final lift
34/100
Instream Storage Structure, Kopsinga
LHS U/S Guided bond 23th layer FDD check
35/100
Instream Storage Structure, Kopsinga
LHS D/S 28 th layer Guided bond FDD test
36/100
Instream Storage Structure, Kopsinga
LHS Approach road 17th layer FDD test
37/100
Instream Storage Structure, Kopsinga
Flared wall LHS U/ S 8th lift casting under progress M20 A20
38/100
Instream Storage Structure, Kopsinga
FDD test of LHS D/S guide bond 27th layer in presence of dept. JE madam
39/100
Instream Storage Structure, Kopsinga
FDD test of LHS approach road 16th layer in presence of dept.JE madam
40/100
Instream Storage Structure, Kopsinga
RHS d/s divide wall final lift shuttering work under progress.
41/100
Instream Storage Structure, Kopsinga
Slump-80mm, P(5-6) span u/s kerb (M35A20) .
42/100
Instream Storage Structure, Kudabega
Slump 80mm
43/100
Instream Storage Structure, Kudabega
Slump 85mm
44/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Sand-blasting work is in progress of Barrage gate or service gate
45/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Guide Fixing work is in progress of Stop-log gate at Span no 19
46/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Roller track fixing work is in progress of Stop log gate at Span no 21 & 20
47/100
Instream Storage Structure, Kudabega
ISS Kudabaga - 'Walk-Way' work is in progress
48/100
Instream Storage Structure, Kudabega
RHS d/s wing wall 5th lift shuttering & reinforcement cleaning work in progress.
49/100
Instream Storage Structure, Kudabega
Pier no-23, side gate groove second stage Deshuttering & shuttering work in progress.
50/100
Instream Storage Structure, Kudabega
Pier no-24,25 side gate groove second stage Deshuttering & shuttering work in progress.
51/100
UGPL, Right Lower Suktel Canal Division
OCS fittings Installation work is in progress of OCS -0213064-C19B at village Bhaler in presence of L&T personnel, Bermad team and PMC team.
52/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for extension of Outlet from Ro-280B, Z-6311, RM-15 at village Luchkibahal.
53/100
Instream Storage Structure, Kushabhadra
Slump test done at site, slump value is 83mm.
54/100
Instream Storage Structure, Kushabhadra
Laying of CC M25A20 in left D/S flank Wall and Return wall (Sec A-A to B-B) form RL 16.65m to 17.95m in progress.
55/100
Instream Storage Structure, Kushabhadra
Soil compaction test conducted at Right U/S flared out wall portion.
56/100
Instream Storage Structure, Kuakhai
Cleaning of rust from the piers.
57/100
Instream Storage Structure, Kuakhai
Rust cleaning work is under progress from the reinforcement bars of Pier no.7B and 8.
58/100
Instream Storage Structure, Kuakhai
Curing on casted girders in progress.
59/100
Instream Storage Structure, Kuakhai
Casting of RCC M35A20 in pre-cast main girder (No.20) for the bridge is under progress.
60/100
Instream Storage Structure, Kuakhai
PSS Team observing the ongoing girder casting at ISS site.
61/100
Instream Storage Structure, Kuakhai
Casting of RCC M35A20 in pre-cast main girder (No.19) for the bridge is under progress.
62/100
Instream Storage Structure, Kuakhai
Curing on casted girders in progress.
63/100
Instream Storage Structure, Kuakhai
Cutting, Bending & Binding of steel reinforcement for pre-cast girder of the bridge is under progress.
64/100
UGPL, Left Lower Suktel Canal Division
Trench Excavation work is in progress for Gap closing of 450mm Dia DI pipeline from node J-254 to J-38, RM-15 near Village Birkel.
65/100
Instream Storage Structure, Kuakhai
Curing on casted girders in progress.
66/100
Instream Storage Structure, Kuakhai
Cleaning of sand and silt from left under sluice bay.
67/100
Instream Storage Structure, Kuakhai
PSS Team observing the ongoing sand blasting at right side pier.
68/100
Instream Storage Structure, Kuakhai
Curing in progress.
69/100
Instream Storage Structure, Kuakhai
Casting of RCC M35A20 in pre-cast main girder (No.18) for the bridge is completed.
70/100
Instream Storage Structure, Kuakhai
Casting of RCC M35A20 in pre-cast main girder (No.17) for the bridge is completed.
71/100
Instream Storage Structure, Kuakhai
Slump test done at site, slump value is 90mm.
72/100
Instream Storage Structure, Kuakhai
Casting of RCC M35A20 in pre-cast main girder for the bridge is started.
73/100
Instream Storage Structure, Kuakhai
Concreting in progress.
74/100
Instream Storage Structure, Kuakhai
Casting of RCC M35A20 in pre-cast main girder (No.17 & 18) for the bridge is started.
75/100
Instream Storage Structure, Kuakhai
Curing of girders in progress.
76/100
Instream Storage Structure, Kushabhadra
Area excavation for CC Block at Right U/S side.
77/100
Instream Storage Structure, Kushabhadra
Pier no.6 (left side) second stage concreting work in progress.
78/100
Instream Storage Structure, Kushabhadra
Slump test done at site, slump value is 84mm.
79/100
Instream Storage Structure, Kushabhadra
Laying of CC M25A20 in column footing of O&M building of the ISS is in progress.
80/100
Instream Storage Structure, Kushabhadra
Pier no.6 second stage concreting work is under progress.
81/100
Instream Storage Structure, Kushabhadra
7 days cube test for CC M25A20 done at field laboratory of the ISS, Average compressive strength is 22.39 N/mm2.
82/100
Instream Storage Structure, Kushabhadra
Slump test done at site, slump value is 85mm.
83/100
Instream Storage Structure, Kushabhadra
Excavation under progress for U/S CC Blocks.
84/100
Instream Storage Structure, Kushabhadra
Pier no-6 (Left) from RL 14.80m to 17.10m Barrage gate secondary gate groove concrete laying in progress.
85/100
Instream Storage Structure, Kushabhadra
Slump test done at site, slump value is 85mm.
86/100
Instream Storage Structure, Kushabhadra
Laying of CC M25A20 in column footing of O&M building of the ISS is in progress.
87/100
Instream Storage Structure, Kushabhadra
Laying of CC M25A20 in left D/S flank Wall and Return wall (Sec A-A to B-B) form RL 15.25m to 16.65m in progress.
88/100
UGPL, Right Lower Suktel Canal Division
Internal drain bricks masonry work is in progress at Pump House.
89/100
UGPL, Right Lower Suktel Canal Division
Internal drain inside plastering work is in progress at Pump House.
90/100
UGPL, Left Lower Suktel Canal Division
Boundary wall outer side plastering work is in progress at Pump House.
91/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of RHS Divide wall is under progress.
92/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cleaning & Vertical straightening of reinforcement for RHS Divide wall is under progress in presence of Client & PSS team along with EPC agency.
93/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Recalibration of Batching Plant Engg. of rengali dam division, Dy. TL, QAE & PSS team of angul along with PM of EPC agency.
94/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning & Vertical straightening of reinforcement for LHS Divide wall is under progress in presence of Client & PSS team along with EPC agency.
95/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Observed of Sieve analysis of Coarse aggregate of 20mm & 10mm in presence of Dy. TL, QAE & PSS team of angul along with PM of EPC agency.
96/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate and Fine aggregate in presence of Client & PSS team along with EPC agency.
97/100
Instream Storage Structure, Jharbeda
Cleaning of old concrete surface at Pier No-6 is under progress.
98/100
Instream Storage Structure, Jharbeda
De-shuttering of shutter plates for Pier No-7 is under progress.
99/100
Instream Storage Structure, Jharbeda
Excavation for LHS Abutment wall to RHS Abutment wall is under progress.
100/100
Instream Storage Structure, Jharbeda
Cleaning of Pier No-6 is under progress.
❮
❯