GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No- 0213012-C04B near village Daspur in presence of PMC team.
2/100
UGPL, Left Lower Suktel Canal Division
HDPE Tee (160 X 125 X 125)mm connection work is in progress at J-121, RM-7, near village Fasad in presence of PMC team.
3/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress of 225mm Dia HDPE pipe node from J-547 to J-120, RM-7 near village Fasad.
4/100
Instream Storage Structure, Gudvella
Casting of precast railing over parapet wall on the deck slab has been commenced with dimensions 1.424 m × 0.13 m × 0.17 m on 21.04.2026
5/100
Instream Storage Structure, Gudvella
Paint work under progress on 21.04.2026
6/100
Instream Storage Structure, Gudvella
Under-sluice gate assembly work under progress on 21.04.2026
7/100
Instream Storage Structure, Gudvella
Trestle and column installation work under progress at A1 and P1 on 21.04.2026
8/100
Instream Storage Structure, Gudvella
Brick work and Shuttering work for slab is in progress at 1st floor building on 21.04.2026
9/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right divide wall for 5th lift upto RL-238.20m is in progress through concrete pump in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 88mm on 21.04.2026
10/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right divide wall for 5th lift upto RL-238.20m is in progress through concrete pump in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 88mm on 21.04.2026
11/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no. 9 upto RL-247.00m is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 87mm on 21.04.2026
12/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no. 9 upto RL-247.00m is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 87mm on 21.04.2026
13/100
Instream Storage Structure, Nandagaon
• 3.The area of placing concrete at U/S right divide wall has been checked before placement in presence of PM of EPC Agency, Site Engineer of PMC & EPC Agency as follows: (i).The reinforcement in binding, tying n spacing of both vertical main & horiz. dist. bar and tie bars for casting of U/S right divide wall for 5th lift from RL-236.80m to RL-238.20m are found completed. (ii).Rigid & smooth shuttering and maintained clear cover of 75mm from main bar to shutter plates are done. (iii).The area is cleaned properly through air water jetting and passed by SE, KID, Bhawanipatna for placing with RCC M25A20 grade on 21.04.2026
14/100
Instream Storage Structure, Nandagaon
• 2(i).Fixing & fittings and alignment of All trestle and columns foundation bolts measurements has been checked at left abutment for Blockout area of 6.8m length and found correct by HM Expert of PMC during his site visit on dt.16.04.2026 in presence of mechanical Site Engineers of PMC and EPC Agency. (ii) Rigid and smooth shuttering for Blockout area with M35A20 grade at pier no.9 from RL-246.30m to RL-247.00m are found completed. (iii).The area is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with M35A20 grade on 21.04.2026
15/100
Instream Storage Structure, Nandagaon
Gate no 14 both stoplog gate and barrage bay gate 2nd stage embedded parts erection work under progress on 21.04.2026
16/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress on 21.04.2026
17/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for left kerb at deck slab on 21.04.2026
18/100
Instream Storage Structure, Nandagaon
Placing of CC blocks is in progress at U/S side on 21.04.2026
19/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering is in progress at U/S right divide wall on 21.04.2026
20/100
Instream Storage Structure, Nandagaon
Trestle painting work under progress on 21.04.2026
21/100
Instream Storage Structure, Nandagaon
Columns sand blasting work is in progress on 21.04.2026
22/100
Instream Storage Structure, Jharbeda
Shuttering & Binding of reinforcement for Pier No-7 is under progress.
23/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-8 is under progress.
24/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-6 is under progress.
25/100
Instream Storage Structure, Jharbeda
Cleaning work is under progress.
26/100
Instream Storage Structure, Jharbeda
Curing of Pier No-8 is under progress.
27/100
Instream Storage Structure, Jharbeda
Curing of End sill is under progress.
28/100
Instream Storage Structure, Jharbeda
Dewatering work is under progress.
29/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Gantry Girder No-23 done in presence of Client & PSS Team.
30/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-23 is under progress in presence of Client & PSS Team.
31/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Deck slab (Bay No-17) at Block No-3 done in presence of Client & PSS Team.
32/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Deck slab (Bay No-17) at Block No-3 is under progress in presence of Client & PSS Team.
33/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of D/S Flared out wall, Raft at Block No-5 done in presence of Client & PSS Team
34/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flared out wall, Raft at Block No-5 is under progress in presence of Client & PSS Team.
35/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.02/mm2 for 28 days) of Pier No-4, 2nd lift and (Strength is 30.94/mm2 for 28 days) of Pier No-13, 13th lift and (Strength is 21.19/mm2 for 07 days) of Pier No-2, 5th lift and M35A20 (Strength is 42.81/mm2 for 28 days) of Gantry Girder No-5 has done in presence of Client & PSS team.
36/100
Instream Storage Structure, Hamirpur
Gantry girder's 1st stage embedded parts welding work is in progress.
37/100
Instream Storage Structure, Hamirpur
L.H.S Pier No-11 Stop-log groove 2nd stage embedded parts Roller track and side guide erection work is in progress at Bay No-10.
38/100
Instream Storage Structure, Hamirpur
Shuttering & binding of reinforcement for Abutment (A1), 5th lift at Block No-1 is under progress.
39/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4, 6th lift is under progress.
40/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-21, 14th lift is under progress.
41/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
42/100
Instream Storage Structure, Khalpal
Curing of Pier No-23 is in progress.
43/100
Instream Storage Structure, Khalpal
Curing of Barrage Bay No-2 at Block No-3 work is in progress.
44/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 80 mm) of LHS under sluice portion End sill (Gravity floor) done in presence of Client & PSS Team.
45/100
Instream Storage Structure, Khalpal
Concreting M20A20 of LHS under sluice portion End sill (Gravity floor) is under progress in presence of Client & PSS Team.
46/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 80 mm) of LHS Wing wall, 4th lift done in presence of Client & PSS Team.
47/100
Instream Storage Structure, Khalpal
Concreting M25A20 of LHS Wing wall, 4th lift is under progress in presence of Client & PSS Team.
48/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 85 mm) of Barrage Bay No-3 Gravity floor done in presence of Client & PSS Team.
49/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Barrage Bay No-3 Gravity floor is under progress in presence of Client & PSS Team.
50/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for Abutment & Counterfort wall is under progress.
51/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for LHS side Raft is under progress.
52/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering & binding of reinforcement for RHS Mid-pier, 3rd lift is under progress.
53/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for fixing of 1ha outlet for OCS no 0201209- C01B at village Sadeipali in presence of DoWR JE and PMC team.
54/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door & angle fixing and above GL work is in progress OCS No:-0213119-C15A at village Bileisarda in presence of DoWR JE and PMC team.
55/100
UGPL, Right Lower Suktel Canal Division
Joint verification for outlet of OCS No-0213001-C03B is in progress at village Ainlasari in presence of DOWR JE and PMC team.
56/100
UGPL, Right Lower Suktel Canal Division
OCS chamber above GL work is in progress of OCS No:- 0213094-C15B at village Randa in presence of PMC team.
57/100
UGPL, Left Lower Suktel Canal Division
DI to HDPE pipeline connection work is in progress at LM-18, J-302 near village Kuturapali in presence of DoWR SDO and PMC team.
58/100
UGPL, Left Lower Suktel Canal Division
HDPE Tee (225X 140X 180)mm connection work is in progress at J-290,LM-9, near village Banjari in presence of PMC team.
59/100
UGPL, Left Lower Suktel Canal Division
HDD machine road pushing work is in progress of 125mmDia HDPE pipe at J-542 to LO-182 ( LM-9) near village Ambapali in presence of DoWR SDO and PMC team.
60/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI to HDPE pipeline connection at J-302, LM-18 near village Kuturapali in presence of PMC team.
61/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for laying and gap closing of 350mm Dia DI pipe from J- 30 to J- 413, LM -5 near village Mandiapadar.
62/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE Tee connection at J-225 LM-9, near village Banjari in presence of PMC team.
63/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress node from J-225 to J-290 225mm Dia HDPE pipe LM-9 near village Banjari in presence of PMC team.
64/100
Integrated Barrage across river Kochila and across river Baitarini
Lateral pile load test is going on in presence of PMC , OCCL, PMU, department , quality assurance Cuttack and agency-20.04.2026.
65/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-16, 14th lift with pier Cap done in presence of Client & PSS Team.
66/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-16, 14th lift with pier Cap is under progress in presence of Client & PSS Team.
67/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Pier No-15, 13th lift with pier Cap done in presence of Client & PSS Team.
68/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-15, 13th lift with pier Cap is under progress in presence of Client & PSS Team.
69/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-22 done in presence of Client & PSS Team.
70/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-22 is under progress in presence of Client & PSS Team.
71/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-14, 15th lift done in presence of Client & PSS Team.
72/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-14, 15th lift is under progress in presence of Client & PSS Team.
73/100
Instream Storage Structure, Hamirpur
CE&BM, Brahmani Basin, Samal along with Addl. C.E, HWC, Rengali & S.E, Rourkela Irrigation Division visited the work site in presence of A.E.E & A.E, RID, IEE & Site Engineers of PSS team and representative of EPC agency and reviewed the Construction work progress as well as land acquisition status.
74/100
Instream Storage Structure, Hamirpur
MS plate marking and cutting for hoist platform girder's flange work is in progress.
75/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly welding work is in progress.
76/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall at Block No-1 is under progress.
77/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Deck slab (Bay No-16 & 17) is under progress.
78/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall at Block No-5 is under progress.
79/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Toe wall at Block No-5 is under progress.
80/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Abutment (A1) is under progress.
81/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
82/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for Abutment & Counterfort wall is under progress.
83/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for LHS side Raft is under progress.
84/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
LHS under sluice deck slab staging work is under progress.
85/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering & binding of reinforcement for RHS Mid-pier, 3rd lift is under progress.
86/100
Instream Storage Structure, Jharbeda
CE&BM, Brahmani Basin, Samal along with Addl. C.E, HWC, Rengali & S.E, Rourkela Irrigation Division visited the work site in presence of A.E.E & A.E, RID, IEE & Site Engineers of PSS team and representative of EPC agency and reviewed the on going Construction work.
87/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-8 is under progress.
88/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-6 is under progress.
89/100
Instream Storage Structure, Jharbeda
Curing of End sill is under progress.
90/100
Instream Storage Structure, Jharbeda
Curing of RHS D/S Flank wall is under progress.
91/100
Instream Storage Structure, Khalpal
Curing of Piers is in progress.
92/100
Instream Storage Structure, Khalpal
Curing of Gravity floor work is in progress.
93/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 80 mm) of Pier No-20, 1st lift done in presence of Client & PSS Team.
94/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-20, 1st lift is under progress in presence of Client & PSS Team.
95/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 80 mm) of Pier No-23, 1st lift done in presence of Client & PSS Team.
96/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-23, 1st lift is under progress in presence of Client & PSS Team.
97/100
Instream Storage Structure, Gudvella
Parapet railing casting under progress on 20.04.2026
98/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 80 mm) of Gravity floor Bay No-3 done in presence of Client & PSS Team.
99/100
Instream Storage Structure, Gudvella
Under-sluice bay top and bottom assembly work under progress on 20.04.2026
100/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Gravity floor Bay No-3 is under progress in presence of Client & PSS Team.