PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure across river Sapei near village Kinjirma
85mm Tm-17
2/100
Instream Storage Structure across river Sapei near village Kinjirma
RHS U/S divide wall raft M25A20 casting work in progress
3/100
Instream Storage Structure across river Sapei near village Kinjirma
80mm Tm-15
4/100
Instream Storage Structure across river Sapei near village Kinjirma
85mm Tm-14
5/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 80mm,tm-13
6/100
Instream Storage Structure across river Sapei near village Kinjirma
80mm Tm-12
7/100
Instream Storage Structure across river Sapei near village Kinjirma
80mm Tm-11
8/100
Instream Storage Structure across river Sapei near village Kinjirma
RHS U/S divide wall raft M25A20 casting work in progress
9/100
Instream Storage Structure across river Sapei near village Kinjirma
Tm-10 85mm
10/100
Instream Storage Structure across river Sapei near village Kinjirma
Concrete work under progress of u/s divide wall raft(M25A20) in presence of dept. AEE,AE & JE .
11/100
Instream Storage Structure across river Sapei near village Kinjirma
90mm,tm-9
12/100
Instream Storage Structure across river Sapei near village Kinjirma
Casting of raft foundation witnessed by IEE and QCE in presence of AEE.
13/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 80mm,tm-8
14/100
Instream Storage Structure across river Sapei near village Kinjirma
Raft Foundation casting of RHS U/S divide wall is in progress.
15/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 85mm,tm-7
16/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 85mm,tm-6
17/100
Instream Storage Structure across river Sapei near village Kinjirma
Concrete work under progress of u/s divide wall raft(M25A20) in presence of dept.AEE , IEE & QCE of PMC Sambalpur.
18/100
Instream Storage Structure across river Sapei near village Kinjirma
Concrete work under progress of u/s divide wall raft(M25A20) in presence of dept. AEE , IEE & QCE of PMC Sambalpur.
19/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 75mm,tm-5
20/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 90mm,tm-4
21/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 80mm,tm-3
22/100
Instream Storage Structure across river Sapei near village Kinjirma
D-shuttering work under progress of pier no 4 .
23/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 80mm,tm-2
24/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump-80mm,tm-1 (M25A20)
25/100
Instream Storage Structure, Budharaja
Staff Quarter ground floor plastering work is in Progress.
26/100
Instream Storage Structure, Budharaja
Rock Breaking and Cleaning work is in Progress at LHS Under sluice bay Portion.
27/100
Instream Storage Structure, Budharaja
View showing flow of river from U/S to D/S of river.
28/100
Instream Storage Structure, Kopsinga
Pier no 22 Expansion joint chipping work under progress
29/100
Instream Storage Structure, Kopsinga
Double storied building curing work under progress
30/100
Instream Storage Structure, Kopsinga
Double storied building Brick work under progress ISS Kopsingha
31/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - 5th Under-sluice gate's work is in progress out of - 6
32/100
Instream Storage Structure, Khirasasan
Slump 80mm
33/100
Instream Storage Structure, Khirasasan
checked placing supporting bars and alignment of shuttering work in RHS U/S flared out profile 8th step RL- 214.100 to 214.700 Now the area is ready for concrete casting M20 A20. So recommended for the purpose. Approved by AEE sir SID Sambalpur in presence of JE
34/100
Instream Storage Structure, Khirasasan
RHS U/S FLARED out wall profile 8th lift shuttering work under progress
35/100
Instream Storage Structure, Khirasasan
View showing flow of river from D/S of the river.
36/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
37/100
Instream Storage Structure, Gochara
E & A of PMC Sambalpur visited ISS Gochhra.
38/100
Instream Storage Structure, Gochara
P1 cement washing work in progress.
39/100
Instream Storage Structure, Gochara
Electric panel fixing work is in progress to the top of the Hoist bridge's Platform.
40/100
Instream Storage Structure, Gochara
Lifting bracket fixing work is in progress of Barrage Bay Gate no-1.
41/100
Instream Storage Structure, Kudabega
Casting of D/S gravity floor RHS sluice bay
42/100
Instream Storage Structure, Kudabega
Slump 80mm of ds gravity floor of right sluice Bay
43/100
Instream Storage Structure, Kudabega
Casting of RHS sluice bay D/S gravity floor
44/100
Instream Storage Structure, Kudabega
Slump 80mm (RHS ds wearing coat)
45/100
Instream Storage Structure, Kudabega
Cleaning the D/S RHS Gravity floor
46/100
Instream Storage Structure, Kudabega
Preparation for wearing coat for D/S gravity floor
47/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Panting work is in progress of CDU & ERU
48/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Chakkar - Plate's fixing work is in progress
49/100
Instream Storage Structure Across Bheden near village Saida
LHS U/S Flared out wall curing work is going on .
50/100
Instream Storage Structure Across Bheden near village Saida
P-5 gate groves chipping work is in progress .
51/100
Instream Storage Structure Across Bheden near village Saida
De-Shuttering work progress in RHS u/s flared out wall step-10
52/100
Instream Storage Structure Across Bheden near village Saida
De-Shuttering work progress in RHS d/s flared out wall step-4 & shuttering work progress in step-5
53/100
UGPL, Left Lower Suktel Canal Division
HDPE Tee (75X 125 X 75)mm connection work is in progress at RO-78, RM-4, near village Semelia in presence of PMC team.
54/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-15, 11th lift done in presence of Client & PSS Team.
55/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-15, 11th lift is under progress in presence of Client & PSS Team.
56/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-15 done in presence of Client & PSS Team.
57/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-15 is under progress in presence of Client & PSS Team.
58/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.96/mm2 for 28 days) of Abutment (A1), 4th lift at Block No-1 and (Strength is 21.48/mm2 for 07 days) of Pier No-5, 4th lift and (Strength is 21.04/mm2 for 07 days) of Fish pass Raft at Block No-1 has done in presence of Client & PSS team.
59/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform No-3 girder's welding work is in progress.
60/100
Instream Storage Structure, Hamirpur
Single Pier hoist bridge platform assembly No-17 welding work is in progress.
61/100
Instream Storage Structure, Hamirpur
MS plate marking and cutting for hoist bridge platform stiffener work is in progress.
62/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4, 5th lift is under progress.
63/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-3, 6th lift is under progress.
64/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Abutment (A1), 7th lift at Block No-1 is under progress.
65/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Flank wall at Block No-1 is under progress.
66/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-1, 4th lift is under progress.
67/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-15, 11th lift is under progress.
68/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall at Block no-5 is under progress.
69/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Gantry Girder is under progress.
70/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Pier no-21, 12th lift is under progress.
71/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Testing of Compressive M25A20 (Strength is 30.25/mm2 for 28 days) of RHS Double Pier, 3rd lift has done in presence of Client & PSS team.
72/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Excavation of D/S Divide wall for Cut-off and Shuttering of Middle pier and binding of reinforcement for Double pier is under progress.
73/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M25A20 (Value 95 mm) of Divide wall, 8th lift done in presence of Client & PSS Team.
74/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of Divide wall, 8th lift is under progress in presence of Client & PSS Team.
75/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Testing of Compressive M25A20 (Strength is 23.25/mm2 for 07 days) of LHS D/S Wing wall, 2nd lift and M25A20 (Strength is 29.51/mm2 for 28 days) of RHS Divide wall has done in presence of Client & PSS team.
76/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering & binding of reinforcement for RHS Divide wall, 2nd lift is under progress.
77/100
Instream Storage Structure, Jharbeda
Slump testing M25A20 (Value 85 mm) of Pier No-9, 9th lift done in presence of Client & PSS Team.
78/100
Instream Storage Structure, Jharbeda
Concreting M25A20 of Pier No-9, 9th lift is under progress in presence of Client & PSS Team.
79/100
Instream Storage Structure, Jharbeda
Cutting & bending for reinforcement is under progress.
80/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for RHS under sluice D/S Cut-off wall is under progress.
81/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for RHS Divide wall D/S portion Footing Top Layer is under progress.
82/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-8 to RHS (D2) End sill, 2nd Layer is under progress.
83/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
84/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 80 mm) of LHS D/S Wing wall, 3rd lift done in presence of Client & PSS Team.
85/100
Instream Storage Structure, Khalpal
Concreting M25A20 of LHS D/S Wing wall, 3rd lift is under progress in presence of Client & PSS Team.
86/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 80 mm) of Pier No-20 (Crest portion) done in presence of Client & PSS Team.
87/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-20 (Crest portion) is under progress in presence of Client & PSS Team.
88/100
Instream Storage Structure, Khalpal
Excavation of Barrage Bay No-3, Gravity floor is under progress.
89/100
Instream Storage Structure, Khalpal
Shuttering of Pier No-20 and binding of reinforcement for Pier No-21 & 22, 1st lift is under progress.
90/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door & angle fixing work is in progress OCS No:-2305093-C06B at village Ghatkaintara in presence of PMC team.
91/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS-0213094-C14A at village Randa in presence of PMC team.
92/100
UGPL, Right Lower Suktel Canal Division
External drain Hume pipe joint concrete filling work is in progress at Pump House.
93/100
UGPL, Left Lower Suktel Canal Division
laying work is in progress of 75mm Dia HDPE pipe main line at RLO-1A(LM-17) near village Sargard.
94/100
UGPL, Left Lower Suktel Canal Division
Butt fusion joint work in progress of 125mm Dia HDPE pipe node from J-542 to LO-184 near village Ambapali.
95/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 160mm Dia HDPE pipe line from J-50 to J-83, RM-4, near village Semelia in presence of DOWR JE and PMC team.
96/100
Instream Storage Structure, Gudvella
Casting of CC BLOCK PCC M20A40 grade is under progress in the presence of Dept JE, site engineer of PMC and agency. The slump test value is 73mm on 09.04.2026
97/100
Instream Storage Structure, Gudvella
Casting of CC BLOCK PCC M20A40 grade is under progress in the presence of Dept JE, site engineer of PMC and agency. The slump test value is 73mm on 09.04.2026
98/100
Instream Storage Structure, Gudvella
Casting of precast railing over the parapet wall is in progress with dimensions 1.424 m × 0.13 m × 0.17 m on 09.04.2026
99/100
Instream Storage Structure, Gudvella
Sand blasting work is under progress on 09.04.2026
100/100
Instream Storage Structure, Gudvella
Shuttering and reinforcement work of precast railing for parapet wall of deck slab is ready for concreting on 09.04.2026