1/100
Instream Storage Structure, Gudvella
Stone pitching and dumping work is under progress at D/s side of site on 28.05.2026
2/100
Instream Storage Structure, Gudvella
Electrical pipe installation work at building area is under progress on 28.05.2026
3/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 28.05.2026
4/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 28.05.2026
5/100
Instream Storage Structure, Gudvella
Earthwork excavation is under progress for stone dumping at D/s side on 27.05.2026
6/100
Instream Storage Structure, Gudvella
Fixing of posts at walk way is under progress at site on 27.05.2026
7/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 27.05.2026
8/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 27.05.2026
9/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.10,11,12&13 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 87mm on 28.05.2026
10/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.10,11,12&13 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 87mm on 28.05.2026
11/100
Instream Storage Structure, Nandagaon
• 1.Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay No.-11 of Pier No.10 for 7th lift and bay no.12 of pier no. 11 for 5th lift & pier no.12 for 6th lift and bay no. 13 for pier no.12&13 for 3rd lift have been checked and found correct by HM Expert of PMC during his site visit on dt.20.05.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for M35A20 grade on 28.05.2026
12/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.11 for 7th lift of bay no.11 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 86mm on 27.05.2026
13/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.11 for 7th lift of bay no.11 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 86mm on 27.05.2026
14/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade of Dirt wall at right abutment upto RL-246.70m is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 85mm on 27.05.2026
15/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade of Dirt wall at right abutment upto RL-246.70m is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 85mm on 27.05.2026
16/100
Instream Storage Structure, Nandagaon
• 3.Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay No.-11 of Pier No.11 for 7th lift have been checked and found correct by HM Expert of PMC during his site visit on dt.20.05.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
{i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for M35A20 grade on 27.05.2026
17/100
Instream Storage Structure, Nandagaon
• 2.The Area of placing concrete of Dirt Wall at right abutment has been checked before placement as follows:
(i) Reinforcement in binding, tying and spacing of both vertical main & horiz. dist. bar of Dirt Wall at right abutment of 9.1m length at D/S side from RL-245.40m to RL-246.70m are found completed in presence JE, ISS Nandgaon, PM of EPC agency, ISS Nandagaon, Site Engineers of PMC & EPC agency , ISS Nandgaon.
(ii)Rigid & smooth shuttering with 75mm clear cover from main bar to shutter plates are completed.
(iii).The area is cleaned properly through air water jetting and passed by SE, KID, Bhawanipatna for placing with RCC M25A20 grade,ISS Nandagaon on 27.05.2026
18/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade of 5nos. Columns of building is completed in presence of PM EPC agency, Site Engineers of PMC & EPC agency on 27.05.2026
19/100
Instream Storage Structure, Nandagaon
• 1.The area of placing concrete of 5 nos. column of Office building have been checked before placement in presence of PM of EPC Agency, Site Engineers of PMC & EPC Agency as follows:
(i).The reinforcement in binding,placing and tying with 4-legged stirrups of 5nos. column,i.e. No.3,6,7, 10 & 11 are found completed
(ii).Rigid & smooth shuttering and maintained clear cover of 40mm from main bar to shutter plates for column are done.
(iii).The area is cleaned and passed by SE, KID, Bhawanipatna for placing with RCC M25A20 grade on 27.05.2026
20/100
Instream Storage Structure, Nandagaon
Curing work is in progress on 27.05.2026
21/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress at pier no.14 on 27.05.2026
22/100
Instream Storage Structure, Nandagaon
1st under sluice barrage bay gate groove cleaning process under progress on 27.05.2026
23/100
Instream Storage Structure, Nandagaon
Trestle and columns erection work under progress on 27.05.2026
24/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 42.22/mm2 for 28 days) of Ganty Girder No-28, M25A20 (Strength is 21.48/mm2 for 7 days) Pier No-2, 7th lift, M25A20 (Strength is 21.63/mm2 for 07 days) of Flared out wall Raft has done in presence of Client & PSS team.
25/100
Instream Storage Structure, Hamirpur
U/s hoist bridge platform assembly No-7 fit-up work is in progress.
26/100
Instream Storage Structure, Hamirpur
Drive unit & shaft fixing work is in progress of hoist bridge platform assembly No-2.
27/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-1, 9th lift is under progress.
28/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Flared out wall Raft at Block No-1 is under progress.
29/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-4, 4th lift is under progress.
30/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of Barrage Bay No-2, Raft Crest portion done in presence of Client & PSS Team.
31/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Barrage Bay No-2, Raft Crest portion is under progress.
32/100
Instream Storage Structure, Khalpal
Binding of reinforcement for Double Pier No-25, 2nd lift is under progress.
33/100
Instream Storage Structure, Khalpal
Curing of Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
34/100
Instream Storage Structure, Jharbeda
Slump testing M25A20 (Value 50 mm) of RHS Divide wall D2, Pier portion, 1st lift done in presence of Client & PSS Team.
35/100
Instream Storage Structure, Jharbeda
Concreting M25A20 of RHS Divide wall D2, Pier portion, 1st lift is under progress in presence of Client & PSS Team.
36/100
Instream Storage Structure, Jharbeda
Curing of RHS Training wall is under progress.
37/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-7 is under progress.
38/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
39/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Testing of Compressive M25A20 (Strength is 20.89/mm2 for 7 days) of LHS Raft has done in presence of Client & PSS team.
40/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M20A20 (Value 90 mm) of LHS U/S Raft, Top layer done in presence of Client & PSS Team.
41/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of LHS U/S Raft, Top layer is under progress in presence of Client & PSS Team.
42/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 80 mm) of RHS D/S Counterfort & Wing wall done in presence of Client & PSS Team.
43/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of RHS D/S Counterfort & Wing wall is under progress in presence of Client & PSS Team.
44/100
UGPL, Left Lower Suktel Canal Division
140mm Dia HDPE pipe butt fusion jointing work is in progress of node from J-239 to LO-251 LM-13 village Kutenpali in presence of PMC team.
45/100
UGPL, Right Lower Suktel Canal Division
OCS chamber above GL finishing work is in progress of OCS No:- 0213080-C16A at village Puitala in presence of PMC team.
46/100
UGPL, Right Lower Suktel Canal Division
Valve Chamber Pre-cast cover slab shifting work is in progress of Pump House in presence of PMC team.
47/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door and angle fixing work is in progress OCS No-: 0213117-C07A at village Pipirda in presence of PMC team.
48/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE Tee (125 X 75×75)mm connection at LO-347, LM-18, near village Kutrapali in presence of PMC team.
49/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress of 75mm Dia HDPE pipe line from LO-174 to LO-174A LM-9 near village Bhadra in presence of PMC team.
50/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress of Gap closing 450mm Dia DI pipe line of Lm-17 from J-622 to J-366 near village Birkel in presence of PMC team.
51/100
UGPL, Left Lower Suktel Canal Division
DI to HDPE connection work is in progress of Rm-4, J-83 at village Dhamanasar in presence of PMC team.
52/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 450mm Dia DI pipe line of Lm-17 from J-622 to J-366 near village Birkel in presence of PMC team.
53/100
UGPL, Right Lower Suktel Canal Division
A video conference meeting was held under the chairmanship of PMU TL in the office chamber of the CCE regarding the progress and balance work of Pump House, Pipe laying, all valves fitting of pipe line network, OCS instrumentation installation, chamber erection, outlet fixing, kilometre marking, Scada system and formation of Pani panchayat in presence of SE, SDO and other departmental of DoWR, TL (PES & PSS), ARE of PSS, PMC team along with representative of Agency.
54/100
UGPL, Left Lower Suktel Canal Division
A video conference meeting was held under the chairmanship of PMU TL in the office chamber of the CCE regarding the progress and balance work of Pump House, Pipe laying, all valves fitting of pipe line network, OMS instrumentation installation, chamber erection, outlet fixing, kilometre marking, Scada system and formation of Pani panchayat in presence of SE, SDO and other departmental of DoWR,TL (PES & PSS), ARE of PSS, PMC team along with representative of Agency.
55/100
Instream Storage Structure, Gudvella
Joint verification for a new electrical connection at ISS Gudvella was conducted with the Electrical JE , Electrical SDO, EE (Management), Network Planning Engineer and the Connection Management Group of the Electrical Department, Tata Power, Balangir. The agency representative and the PMC site engineer were also present during the verification on 26.05.2026
56/100
Instream Storage Structure, Gudvella
Joint verification for a new electrical connection at ISS Gudvella was conducted with the Electrical JE , Electrical SDO, EE (Management), Network Planning Engineer and the Connection Management Group of the Electrical Department, Tata Power, Balangir. The agency representative and the PMC site engineer were also present during the verification on 26.05.2026
57/100
Instream Storage Structure, Gudvella
Stone packing under progress at d/s side of ISS Gudvella on 26.05.2026
58/100
Instream Storage Structure, Gudvella
Mechanical work is under progress at site on 26.05.2026
59/100
Instream Storage Structure, Gudvella
Rolling work for the approach road is in progress on the left side on 26.05.2026
60/100
Instream Storage Structure, Gudvella
Piping work for building electrification is in progress on 26.05.2026
61/100
Instream Storage Structure, Nandagaon
2. Brick work in CM 1:6 using well burnt CB Bricks for construction of walls in superstructure at Office Building of ISS, Nandagaon is in progress . The water used in mortar is found cleaned and free from silt, visible materials and within the permissible temperatures during mixing manually at sire. The area may be passed by SE, KID, Bhawnipatna on 26.05.2026
62/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.10,11&12 is completed in presence of PM EPC agency, Site Engineer of PMC & EPC agency on 26.05.2026
63/100
Instream Storage Structure, Nandagaon
• 1.Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay No.- of Pier No.10,11&12have been checked and found correct by HM Expert of PMC during his site visit on dt.20.05.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 26.05.2026
64/100
Instream Storage Structure, Nandagaon
Hoist bridge sand blasting under progress on 26.05.2026
65/100
Instream Storage Structure, Nandagaon
Placing of CC blocks is in progress at U/S side on 26.05.2026
66/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress at pier no.14 on 26.05.2026
67/100
Instream Storage Structure, Nandagaon
Curing work is in progress on 26.05.2026
68/100
Instream Storage Structure, Nandagaon
Sand blasting of hoist bridge under progress on 26.05.2026
69/100
Instream Storage Structure, Nandagaon
Undersluice and barrage bay gate roller and guide shoe fixing and fitting under progress on 26.05.2026
70/100
Instream Storage Structure, Nandagaon
Latching arrangement on hoist bridge under progress on 26.05.2026
71/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for laying of 450mm Dia DI pipe line from node J-366 to J-212, LM-17 near village Birkel in presence of PMC team.
72/100
UGPL, Right Lower Suktel Canal Division
500mm Dia DI pipe AMS 223 installation work is in progress from J-2510 to J-2512 at village Dhubaudar in presence of DOWR AE, JE and PMC team.
73/100
UGPL, Right Lower Suktel Canal Division
External drain stone pitching work is in progress at Pump House.
74/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for laying of DN 75 mm Dia HDPE pipe of OCS No. 0213080-C19A for 1 Ha Sub-Chak at village Gaintala in presence of PMC team.
75/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI to HDPE pipe connection at J-127, RM-3 near village Kushmel in presence of PMC team.
76/100
UGPL, Left Lower Suktel Canal Division
HDD machine road pushing work is in progress (road crossing) of 125mm Dia HDPE pipe between J-436 to LO-236 LM-12 near village Pandarani in presence of PMC team.
77/100
UGPL, Left Lower Suktel Canal Division
125mm Dia HDPE pipe butt fusion jointing work is in progress of node from J-436 to LO-236, LM-12 at village Pandarani in presence of PMC team.
78/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for laying of DN 75 mm Dia HDPE pipe for 1 Ha Sub-Chak of OCS No. 0213126-C01A at village Junapadar in presence of DoWR JE and PMC team.
79/100
UGPL, Right Lower Suktel Canal Division
75mm Dia HDPE Pipe jointing work is in Progress of OCS no-0213119-C01B at village Bileisarda in presence of PMC team.
80/100
Instream Storage Structure, Gudvella
Stone packing work on river bed is in progress at d/s side on 25.05.2026
81/100
Instream Storage Structure, Gudvella
Fixing of posts at walk way is under progress at site on 25.05.2026
82/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 25.05.2026
83/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 25.05.2026
84/100
Instream Storage Structure, Gudvella
Stone dumping is currently in progress at the downstream site on 24.05.2026
85/100
Instream Storage Structure, Gudvella
Mechanical work is under progress at site on 24.05.2026
86/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 24.05.2026
87/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 24.05.2026
88/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no.12 upto RL-247.0m is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 85mm on 25.05.2026
89/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no.12 upto RL-247.0m is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 85mm on 25.05.2026
90/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade of 8nos. Columns of building is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 82mm on 25.05.2026
91/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade of 8nos. Columns of building is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 82mm on 25.05.2026
92/100
Instream Storage Structure, Nandagaon
• 2(i).Fixing & fittings and alignment of All trestle and columns foundation bolts measurements has been checked at pier no.12 for Blockout area of 6.8m length and found correct by HM Expert of PMC during his site visit on dt.20.05.2026 in presence of mechanical Site Engineers of PMC and EPC Agency.
(ii) Rigid and smooth shuttering for Blockout area with M35A20 grade at pier no.12 from RL-246.30m to RL-247.00m are found completed.
(iii).The area is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with M35A20 grade on 25.05.2026
93/100
Instream Storage Structure, Nandagaon
• 1.The area of placing concrete of 8nos. column of Office building have been checked before placement in presence of PM of EPC Agency, Site Engineers of PMC & EPC Agency as follows:
(i).The reinforcement in binding,placing and tying with 4-legged stirrups of 8nos. column,i.e. No.1,2,5,9,13,14,15 & 16 are found completed
(ii).Rigid & smooth shuttering and maintained clear cover of 40mm from main bar to shutter plates for column are done.
(iii).The area is cleaned and passed by SE, KID, Bhawanipatna for placing with RCC M25A20 grade on 25.05.2026
94/100
Instream Storage Structure, Nandagaon
Hoist bridge plate painting work under progress on 25.05.2026
95/100
Instream Storage Structure, Nandagaon
Monorail walkway and monorail girder painting work under progress on 25.05.2026
96/100
Instream Storage Structure, Nandagaon
Pier 1 to pier 8 all trestle and columns proper alignment and erection work completed on 25.05.2026
97/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.9,10 & 11 is completed on 24.05.2026
98/100
Instream Storage Structure, Gudvella
Stone pitching work is under progress at d/s side of ISS Gudvella on 23.05.2026
99/100
Instream Storage Structure, Gudvella
Mechanical work is under progress at site on 23.05.2026
100/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 23.05.2026
❮
❯