1/100
Instream Storage Structure, Nandagaon
Control Room construction work is in progress,
2/100
Instream Storage Structure, Kushabhadra
Right side Guide bund development is under progress.
3/100
Instream Storage Structure, Kushabhadra
Canal road second layer compaction is in progress.
4/100
Instream Storage Structure, Hamirpur
Bay no 6 Deckslab reinforcement binding work is in progress.
5/100
Instream Storage Structure, Hamirpur
Abutment A2 under sluice column erection with fitting work in progress
6/100
Instream Storage Structure, Hamirpur
Bay no 21stoplog side guide alignment with fitting work in progress
7/100
Instream Storage Structure, Kushabhadra
Hoist Bridge Alignement Work is in Progress
8/100
Instream Storage Structure, Kushabhadra
Building Electrification work is in Progress.
9/100
Instream Storage Structure, Kushabhadra
Laying of second layer for River embankment road.
10/100
Instream Storage Structure, Near Village Basantpur across River Daya
Coffee dam work is in progress.
11/100
Instream Storage Structure, Gudvella
D/S OF ISS GUDVELLA ON 14.11.2026
12/100
Instream Storage Structure, Gudvella
U/S OF ISS GUDVELLA ON 14.11.2026
13/100
Instream Storage Structure, Gudvella
D/S OF ISS GUDVELLA ON 13.11.2026
14/100
Instream Storage Structure, Gudvella
U/S OF ISS GUDVELLA. ON 13.11.2026.
15/100
Instream Storage Structure, Hamirpur
Block no 5 d/s flared out wall boulder pitching work in progress
16/100
Instream Storage Structure, Hamirpur
Bay no-06 Deck slab reinforcement placing work is in progress
17/100
Instream Storage Structure, Hamirpur
Bay no-12 gate groove 2nd stage concreting work in progress
18/100
Instream Storage Structure, Kuakhai
SE, Prachi along with G.M.( Civil), H.O. OCCL visited the ISS Kuakhai site in presence of concerned site engineers and PM, DDBL and instructed to expedite the progress as per the work programme submitted for timely completion of work by stipulated date i. e by March-27.
19/100
Instream Storage Structure, Kushabhadra
Embankment Road 2nd layer laying work is under progress.
20/100
Instream Storage Structure, Kushabhadra
O&M Building 1st Floor Inside plastering & Finishing work is under progress.
21/100
Instream Storage Structure, Gudvella
D/s of ISS Gudvella.
22/100
Instream Storage Structure, Gudvella
U/s of ISS Gudvella.
23/100
Instream Storage Structure, Hamirpur
Bay no - 22, gate groove 2nd stage 1st lift concreting is in progress
24/100
Instream Storage Structure, Hamirpur
Block no 5 d/s flared out wall 9th lift boulder spreading in progress
25/100
Instream Storage Structure, Hamirpur
Deck slab curing work is in progress
26/100
Instream Storage Structure, Kudabega
Unloading Stone at site
27/100
Instream Storage Structure, Kudabega
Electrical Lightening work in progress
28/100
Instream Storage Structure, Near Village Basantpur across River Daya
Site visit by Assistant Engineer to the confluence point of Daya & Bhargavi River to plan for the construction of Coffee dam.
29/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Dewatering in progress at ISS Santeibhanja on 11.11.2026
30/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Inspection of Control Room Building works at ISS Telkoi on 11.11.2026
31/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Joint Inspection of land at Telkoi (currently under the occupation of RWSS) by SE, RWSS Division and AEE, Rengali Dam Division in presence of field engineers and the agency on 11.11.2026
32/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Joint Inspection of land at Telkoi (currently under the occupation of RWSS) by SE, RWSS Division and AEE, Rengali Dam Division in presence of field engineers and the agency on date 11.11.2026
33/100
Instream Storage Structure, Gudvella
D/s of ISS Gudvella.
34/100
Instream Storage Structure, Gudvella
U/s of ISS Gudvella.
35/100
Instream Storage Structure, Hamirpur
Bay no - 17, gate groove 2nd stage 2nd lift concreting is in progress
36/100
Instream Storage Structure, Hamirpur
Bay no 21 LHS column erection work in progress
37/100
Instream Storage Structure, Kushabhadra
Fixation of alignment of Guide bund by SDO Balianta & Manager,OCCL and other field engineerd.
38/100
Instream Storage Structure, Kushabhadra
Rolling of GSB is ongoing.
39/100
Instream Storage Structure, Kopsinga
First floor of double storey building plastering is under progress
40/100
Instream Storage Structure, Kopsinga
Welding work of RHS D/S handrail is under progress
41/100
Instream Storage Structure, Kopsinga
Staircase welding work at RHS
42/100
Instream Storage Structure, Kopsinga
LHS D/S River view on Dt.11.11.2026
43/100
Instream Storage Structure, Dhanei
O&M building Coloring, Door/window, Tiles and Railing works completed.
44/100
Instream Storage Structure, Dhanei
O&M building Coloring, Door/window, Tiles and Railing works completed.
45/100
Barrage across river Turi & Guntat
Link channel TGIP
46/100
Barrage across river Turi & Guntat
Maintenance building work status at Turi Barrage
47/100
Barrage across river Turi & Guntat
Turi Barrage Gate
48/100
Barrage across river Turi & Guntat
Turi Barrage Down stream status
49/100
Integrated Barrage across river Kochila and across river Baitarini
Coffer dam & Approach road work started
50/100
Instream Storage Structure, Near Village Basantpur across River Daya
Labour shed preparation is ongoing.
51/100
Instream Storage Structure, Near Village Basantpur across River Daya
Development of Camp site work is in progress.
52/100
Instream Storage Structure, Kushabhadra
Canal Road GSB Preparations Work RD- 00+250M to 00+500M.
53/100
Instream Storage Structure, Kushabhadra
fabrication and mechanical installation work on the operating platform of barrage hoist gate system
54/100
Instream Storage Structure, Kushabhadra
Compaction of GSB by Vibro Roller at canal road
55/100
Instream Storage Structure, Kushabhadra
Making soil bond work is progressing at u/s river area ( for de watering purpose)
56/100
Instream Storage Structure, Hamirpur
Batching plant Calibration
57/100
Instream Storage Structure, Hamirpur
Mechanical SE site visit
58/100
Instream Storage Structure, Hamirpur
Column erection work in progress
59/100
Instream Storage Structure, Hamirpur
60/100
Instream Storage Structure, Hamirpur
61/100
Instream Storage Structure, Hamirpur
gate groove 2nd stage concreting is in progress
62/100
Instream Storage Structure, Dhanei
6 nos of electrical poles procured and shifted to the site.
63/100
Instream Storage Structure, Dhanei
64/100
Instream Storage Structure, Dhanei
65/100
Instream Storage Structure, Dhanei
O&M building Hand Railing work ongoing
66/100
Instream Storage Structure, Hamirpur
Bay no 24 LHS column erection work is in progress
67/100
Instream Storage Structure, Hamirpur
By no 9/10 slab expansion joint concrete work
68/100
Instream Storage Structure, Hamirpur
Bay no 10 railing beam concrete work
69/100
Instream Storage Structure, Kudabega
Roof slab casting
70/100
Instream Storage Structure, Kudabega
roof slab cating 1st floor watcman cum operator shed
71/100
Instream Storage Structure, Kudabega
Roof slab casting 1st floor watchman cum operator hed
72/100
Instream Storage Structure, Kudabega
slump no-5 of roof slab 1st floor watchman cum operator shed
73/100
Instream Storage Structure, Kudabega
slump no-4 of roof slab of watchman cum operator shed
74/100
Instream Storage Structure, Kudabega
Slump No-3 of roof slab casting of watch man cum operator shed
75/100
Instream Storage Structure, Kudabega
Slump No-2 of 1st floor roof slab of watchman cum operator shed
76/100
Instream Storage Structure, Kudabega
Slump No-1 of Roof Slab
77/100
Integrated Barrage across river Kochila and across river Baitarini
ISS over Baitarani on 09.11.2026
78/100
Instream Storage Structure, Kudabega
Reinforcement checking of first floor slab by departmental Engineers
79/100
Instream Storage Structure, Jamutpali
Discussion with villagers nearby regarding land demarcation
80/100
Instream Storage Structure, Jamutpali
Land demarcation at site
81/100
Instream Storage Structure, Jamutpali
Geotechnical Site Investigation
82/100
Instream Storage Structure, Kuakhai
The SE, QAAD, Bhubaneswar, along with his team, inspected the ongoing concrete casting work of U/S Right side Devide wall.
83/100
Instream Storage Structure, Kuakhai
The SE, QAAD, Bhubaneswar, along with his team, inspected the ongoing concrete casting work of U/S Right side Devide wall.
84/100
Instream Storage Structure, Kuakhai
Casting of U/S Devide wall (R/S) from RL 16.65m to 18.05m with M25A20 concrete commenced in presence of AEE, ISS Kuakhai (I/C), QAAD team, OCCL.
85/100
Instream Storage Structure, Kuakhai
Casting of U/S Devide wall (R/S) from RL 16.65m to 18.05m with M25A20 concrete commenced in presence of AEE, ISS Kuakhai (I/C), QAAD team, OCCL.
86/100
Instream Storage Structure, Kushabhadra
Stop log gat gantry track alignment.
87/100
Instream Storage Structure, Kuakhai
Inspection and calibration of batching plant and sieve in presence of QAAD, Bhubaneswar team.
88/100
Instream Storage Structure, Kuakhai
Inspection and calibration of batching plant and sieve in presence of QAAD, Bhubaneswar team.
89/100
Instream Storage Structure, Kuakhai
Inspection and calibration of batching plant and sieve in presence of QAAD, Bhubaneswar team.
90/100
Instream Storage Structure, Near Village Basantpur across River Daya
Installation of Batching Plant completed.
91/100
Instream Storage Structure, Jamutpali
Pillar Posting at the banks of Jamutpali
92/100
Instream Storage Structure, Jamutpali
S/I work at ISS JAMUTPALI
93/100
Instream Storage Structure, Jamutpali
Drilling of Bore inside the river at Jamutpali
94/100
Instream Storage Structure, Kushabhadra
Compaction of GSB for the River Embankment Road
95/100
Instream Storage Structure, Jamutpali
Setting up of labour camp at Jamutpali
96/100
Instream Storage Structure, Kuakhai
Drone photos of ISS site before flood.
97/100
Instream Storage Structure, Near Village Basantpur across River Daya
Present Site condition.
98/100
Instream Storage Structure, Kuakhai
Drone photo of ISS before flood.
99/100
Instream Storage Structure, Near Village Basantpur across River Daya
Installation of Labour shed and material testing lab is under progress.
100/100
Instream Storage Structure, Jharbeda
Site clearing work is initiated
❮
❯