1/100
Instream Storage Structure across river Sapei near village Kinjirma
Complete to the casting of L.S double pier 6th lift
2/100
Instream Storage Structure across river Sapei near village Kinjirma
T.m 08
80mm
3/100
Instream Storage Structure across river Sapei near village Kinjirma
T.M 07
90mm
4/100
Instream Storage Structure across river Sapei near village Kinjirma
T.M 06
Slump 80mm
(L.S double Pier 6th lift casting of continue)
5/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 80mm
T.m 01
6/100
Instream Storage Structure, Budharaja
De-Shuttering work is in Progress LHS Divided Wall, Hoist Gate Portion.
7/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at Pier No: 7, Hoist Gate Portion.
8/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at Pier No: 6, Hoist Gate Portion.
9/100
Instream Storage Structure, Budharaja
De-Shuttering work is in Progress at Pier No: 1, Hoist Gate Portion.
10/100
Instream Storage Structure, Budharaja
Staff Quarter Brick work in progress and Curing .
11/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
12/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. Flow direction is straight. The direction of flow is seen in middle of the river. Now the flow level is 225.600mt against design crest level 225.500 i.e. flood lift 0.0mt.
13/100
Instream Storage Structure Across Bheden near village Saida
Reinforcement work progress in P-5, 10th lift.
Rl-223.4 to 224.3
14/100
Instream Storage Structure, Kopsinga
LHS U/S Guided bond 37th layer FDD Check .
15/100
Instream Storage Structure, Kopsinga
28days cube test of P(13-14) u/s kerb and P(9-10) u/s kerb & LHS d/s flared wall 8th lift 7 days cube test of LHS flared wall 8th lift u/s and D/S divide wall final lift RHS .
16/100
Instream Storage Structure, Kopsinga
Slump-75mm, tm-2
17/100
Instream Storage Structure, Kopsinga
Slump-80mm ,LHS D/S flared wall 14th lift M20A20 .
18/100
Instream Storage Structure, Kopsinga
Chipping work under progress .
19/100
Instream Storage Structure, Kopsinga
Chipping work under progress .
20/100
Instream Storage Structure, Kopsinga
Chipping work under progress .
21/100
Instream Storage Structure, Kopsinga
LHS U/S Guided bond 35th layer FDD Check
22/100
Instream Storage Structure, Kopsinga
LHS D/S Guided bond 39th layer FDD Check
23/100
Instream Storage Structure, Khirasasan
Slump 80 mm
24/100
Instream Storage Structure, Khirasasan
Sir, checked placing and positioning of steel reinforcement, supporting bars and alignment of shuttering work in LHS d/s flared out 9th lift RL- 214.700 to 215.300 Now the area is ready for concrete casting M20 A20. So recommended for the purpose. Approved by AEE sir SID Sambalpur in presence of JE
25/100
Instream Storage Structure, Khirasasan
LHS D/S FLARED OUT wall 9th lift shuttering work completed and ready for concrete casting
26/100
Instream Storage Structure, Khirasasan
LHS U/S FLARED OUT WALL EXCAVATION WORK UNDER PROGRESS
27/100
Instream Storage Structure, Khirasasan
Pier no 3 Hoist portion shuttering work under progress.
28/100
Instream Storage Structure, Khirasasan
Pier no 2 Hoist portion shuttering work under progress.
29/100
Instream Storage Structure, Kudabega
Slump 85mm
30/100
Instream Storage Structure, Kudabega
Barrage bay-2 span no- 19 p-19 & p-18 for stoplog & service gate groove 2nd stage 2th lift M30A20 casting work in progress
31/100
Instream Storage Structure, Kudabega
Slump 80mm
32/100
Instream Storage Structure, Kudabega
Barrage bay-2 span no- 21 p-21R & p-20 for stoplog & service gate groove 2nd stage 5th lift M30A20 casting work in progress
33/100
Instream Storage Structure, Kudabega
Slump 85mm
34/100
Instream Storage Structure, Kudabega
Barrage bay-2 pier no-14 deck strip seal expansion joint M35A20 casting work in progress
35/100
Instream Storage Structure, Kudabega
ISS Kudabaga - 'Guide' fixing work is in progress for Span no - 16
36/100
Instream Storage Structure, Kudabega
Span no-12 kerb shuttering work in progress
37/100
Instream Storage Structure, Kudabega
ISS Kudabaga - 'Guide' fixing work is in progress for Span no - 20
38/100
Instream Storage Structure, Kudabega
Span no- 04 gate groove chipping work in progress.
39/100
Instream Storage Structure, Kudabega
Span no-14 raft gate groove bottom seal cleaning work in progress.
40/100
Instream Storage Structure, Kudabega
Span no-22 gate groove deshuttering & shuttering work in progress
41/100
Instream Storage Structure, Kudabega
RHS downstream Wing Wall deshuttering work in progress
42/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Trestle or Column's work is in progress
43/100
UGPL, Left Lower Suktel Canal Division
1Ha. outlet point fixing work is in progress of RO-290B,Z-5622 near village Pardhiapali.
44/100
Instream Storage Structure, Gudvella
Reinforcement at deck slab no 8 in between P7 & P8 is in progress on 25.11.2025
45/100
Instream Storage Structure, Gudvella
Reinforcement and shuttering at end sill portion from P5 to P9 is in progress on 25.11.2025
46/100
Instream Storage Structure, Nandagaon
Monorail fit up and welding under progress on 25.11.2025
47/100
Instream Storage Structure, Nandagaon
Gate no 3 both stoplog gate and barrage bay gate erection of 2nd stage embedded parts under progress on 25.11.2025
48/100
Integrated Barrage across river Kochila and across river Baitarini
Sluice Bay Abutment wall Reinforcement binding work is in progress at Baitarani ISS Project-26.11.2025
49/100
UGPL, Right Lower Suktel Canal Division
OCS fittings Installation work is in progress for OCS -0213119-C21A, at village Kasurpali in presence of AE, JE (DoWR) and PMC team.
50/100
UGPL, Right Lower Suktel Canal Division
Slump test is in progress for internal RCC road concreting of Pump House.
51/100
UGPL, Right Lower Suktel Canal Division
Internal RCC road reinforcement binding work is in progress at Pump House.
52/100
UGPL, Right Lower Suktel Canal Division
Internal drain wall inside plastering work is in progress at Pump House.
53/100
UGPL, Left Lower Suktel Canal Division
Butt fusion jointing work is in progress for 225mm Dia HDPE pipe line from node J-166 to J-188, (Zone-1) at Village Ramsingha.
54/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 280mm Dia HDPE pipeline from J-80 to J-440 (LM-6) at Village Gerdi.
55/100
UGPL, Left Lower Suktel Canal Division
Joint verification work is in progress for HDPE pipe line OMS point and outlet points of RO-56B(RM-3) at Village Ramshingha in presence of PMC team .
56/100
UGPL, Left Lower Suktel Canal Division
20mm Dia galvanized steel Conduit pipe laying is in progress for outdoor roof 90wt. & 150wt. lighting work at Pump House.
57/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 350mm Dia DI pipeline LM-10 from J-85 to J-17 at Village Khairpali.
58/100
Instream Storage Structure, Kuakhai
Slump test done at site, slump value is 100mm.
59/100
Instream Storage Structure, Kuakhai
Casting of RCCM25A20 in pier no.8 from RL 20.993m to 22.286m in progress.
60/100
Instream Storage Structure, Kuakhai
Removal of rust from the reinforcement of left barrage bay piers using sand blasting.
61/100
Instream Storage Structure, Kuakhai
Manager, OCCL verifying the arrangement of pier cap bar at pier no.8.
62/100
Instream Storage Structure, Kuakhai
Irrigation expert, PSS with Manager OCCL checking the reinforcement, shuttering work in pier no.8 before casting.
63/100
Instream Storage Structure, Kuakhai
Earthwork excavation at Right U/S side of the ISS is under progress.
64/100
Instream Storage Structure, Kuakhai
Reinforcement bar arrangement at Pier No.10 is under progress from RL 21.086m to 22.286m, including pier cap bars.
65/100
Instream Storage Structure, Kuakhai
Casting of RCC M35A20 in pre-cast main girder (no.24 & 25) for the bridge is completed.
66/100
Instream Storage Structure, Kuakhai
Casting of RCC M35A20 in pre-cast main girder (no.25) for the bridge is under progress.
67/100
Instream Storage Structure, Kuakhai
Curing on casted girders in progress.
68/100
Instream Storage Structure, Kuakhai
Casting of RCC M35A20 in pre-cast main girder (no.24 & 25) for the bridge is under progress.
69/100
Instream Storage Structure, Kuakhai
Curing on casted girders in progress.
70/100
Instream Storage Structure, Kushabhadra
Left D/S Flank wall and Return wall (sec A-A to B-B) concrete laying in progress (from RL 19.15m to 20.53m).
71/100
Instream Storage Structure, Kushabhadra
Ongoing Excavation of earth for right U/S side curtain wall.
72/100
Instream Storage Structure, Kushabhadra
Ongoing Reinforcement binding at Right D/S Abutment and Counterfort.
73/100
Instream Storage Structure, Kushabhadra
Laying of CCM25A20 in right abutment & counter-fort from RL 15.20m to 16.60m in progress.
74/100
Instream Storage Structure, Kushabhadra
Laying of CC M25A20 in Right side Abutment & Counterfort from 15.20M to 16.60M in progress.
75/100
Instream Storage Structure, Kushabhadra
Inspection of PSS Team to Right D/S Abutment & Counterfort area.
76/100
Instream Storage Structure, Kushabhadra
Right U/S side curtain wall concrete work in progress.
77/100
Instream Storage Structure, Kushabhadra
Pier no.6 (left) Stop log gate and right side barrage gate second stage concreting work is completed.
78/100
Instream Storage Structure, Kushabhadra
Chief Engineer, Superintending Engineer of QAQC, BBSR & team visited the ISS site.
79/100
Instream Storage Structure, Kushabhadra
Gradation for coarse aggregates & fine aggregates conducted at site office in presence of Quality Control team, BBSR along with PSS Team, OCCL & the Agency.
80/100
Instream Storage Structure, Kushabhadra
Inspection of Right U/S curtain wall shuttering work by PSS Team.
81/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cube casting & Slump testing M25A20 (Value 80mm) of Divide wall, 2nd lift is under progress done in presence of Client & PSS Team.
82/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of Divide wall, 2nd lift is under progress in presence of Client & PSS Team.
83/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cube casting & Slump testing M25A20 (Value 80mm) of LHS D/S Counter fort, 1st lift is under progress done in presence of Client & PSS Team.
84/100
Instream Storage Structure, Kushabhadra
Inspection of Right abutment & counterfort shuttering work by PSS team.
85/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS D/S Counter fort, 1st lift is under progress in presence of Client & PSS Team.
86/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS D/S Counter fort, 1st lift is under progress.
87/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
De-shuttering of LHS U/S & D/S Divide wall, 1st lift is under progress.
88/100
Instream Storage Structure, Kushabhadra
Inspection of PSS Team to O&M Building site.
89/100
Instream Storage Structure, Jharbeda
Dewatering work is under progress.
90/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-6, 3rd lift is under progress.
91/100
Instream Storage Structure, Kushabhadra
Right U/S side curtain wall shuttering work in progress.
92/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-5, 3rd lift is under progress.
93/100
Instream Storage Structure, Kushabhadra
Pier no.7 stop log gate groove 2nd stage concrete pouring work in progress.
94/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-7, 2nd lift is under progress.
95/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 20.74/mm2 for 07 days) of Pier No-27, 12th lift and M25A20(Strength is 21.04/mm2 for 07 days) of Flank wall at Block No-5 has done in presence of Client & PSS team.
96/100
Instream Storage Structure, Kushabhadra
7 days cube test for CC M30A20 done at our field laboratory of the ISS.
97/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Sill beam (Bay No-15) is under progress in presence of Client & PSS Team.
98/100
Instream Storage Structure, Kushabhadra
Soil compaction test conducted at Right U/S Abutment and Counterfort area.
99/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-17, 7th lift at Block No-3 done in presence of Client & PSS Team.
100/100
Instream Storage Structure, Kushabhadra
Right U/S side curtain wall shuttering work in progress.
❮
❯