1/100
Instream Storage Structure, Gudvella
Cast of concrete 13th lift PCC M20A20 grade at left side D/s flard out wall from sec 1-1 to 4-4 with RL 155.80m to 156.40m is under progress in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 73mm on 21.12.2025
2/100
Instream Storage Structure, Gudvella
Cast of concrete 13th lift PCC M20A20 grade at left side D/s flard out wall from sec 1-1 to 4-4 with RL 155.80m to 156.40m is under progress in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 73mm on 21.12.2025
3/100
Instream Storage Structure, Gudvella
Reinforcement at right side d/s flank wall raft RCC work is under progress on 20.12.2025
4/100
Instream Storage Structure, Gudvella
Roller track and guide installation barrage bay no 4 under progress on 20.12.2025
5/100
Instream Storage Structure, Gudvella
Cast of concrete 1st lift PCC M15A40 grade at right side u/s flard out wall raft from RL 143.85m to 144.65m was going on from 1:30pm to 3:15 pm in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 78mm on 20.12.2025
6/100
Instream Storage Structure, Gudvella
Cast of concrete 1st lift PCC M15A40 grade at right side u/s flard out wall raft from RL 143.85m to 144.65m was going on from 1:30pm to 3:15 pm in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 78mm on 20.12.2025
7/100
Instream Storage Structure, Gudvella
Cast of concrete RCC M25A20 grade at right side u/s flank wall raft from RL 147.10m to 148.60m is under progress through pump in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 88mm on 20.12.2025
8/100
Instream Storage Structure, Gudvella
Cast of concrete RCC M25A20 grade at right side u/s flank wall raft from RL 147.10m to 148.60m is under progress through pump in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 88mm on 20.12.2025
9/100
Instream Storage Structure, Gudvella
Cast of concrete 15th lift PCC M20A20 grade at left side u/s flard out wall from sec 1-1 to 4-4 with RL 157.00m to 157.60m is under progress in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 71mm on 20.12.2025
10/100
Instream Storage Structure, Gudvella
Cast of concrete 15th lift PCC M20A20 grade at left side u/s flard out wall from sec 1-1 to 4-4 with RL 157.00m to 157.60m is under progress in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 71mm on 20.12.2025
11/100
Instream Storage Structure, KansariGanda
Curing continuing at site.
12/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.5 of bay no.5 for 2nd lift is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 76mm on 21.12.2025
13/100
Instream Storage Structure, KansariGanda
Cube test done at site.
14/100
Instream Storage Structure, KansariGanda
Slump test at site in presence of AEE & AE of dept., Geologist and Irrigation Eng. Expert along with Site engineer PMC.
15/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.5 of bay no.5 for 2nd lift is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 76mm on 21.12.2025
16/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., QA&QC Expert along with Site engineer of PMC to the ISS site. Inspected the overall progress of work, LHS Pier no.4 7th lift concreting is going on, Shuttering and reinforcement binding for fish pass is going on, Grabbing for 2nd test pile is going on, grabbing is done up to 5.0m.
17/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., QA&QC Expert along with Site engineer of PMC to the ISS site. Inspected the overall progress of work, LHS Pier no.4 7th lift concreting is going on, Shuttering and reinforcement binding for fish pass is going on, Grabbing for 2nd test pile is going on, grabbing is done up to 5.0m.
18/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., QA&QC Expert along with Site engineer of PMC to the ISS site. Inspected the overall progress of work, LHS Pier no.4 7th lift concreting is going on, Shuttering and reinforcement binding for fish pass is going on, Grabbing for 2nd test pile is going on, grabbing is done up to 5.0m.
19/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., QA&QC Expert along with Site engineer of PMC to the ISS site. Inspected the overall progress of work, LHS Pier no.4 7th lift concreting is going on, Shuttering and reinforcement binding for fish pass is going on, Grabbing for 2nd test pile is going on, grabbing is done up to 5.0m.
20/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., QA&QC Expert along with Site engineer of PMC to the ISS site. Inspected the overall progress of work, LHS Pier no.4 7th lift concreting is going on, Shuttering and reinforcement binding for fish pass is going on, Grabbing for 2nd test pile is going on, grabbing is done up to 5.0m.
21/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right flank wall for 6th lift from RL-239.10m to RL-240.30m is in progress through concrete pump in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 87mm on 21.12.2025
22/100
Instream Storage Structure, KansariGanda
Slump test at site in presence of AEE & AE of dept., Geologist and Irrigation Eng. Expert along with Site engineer PMC.
23/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right flank wall for 6th lift from RL-239.10m to RL-240.30m is in progress through concrete pump in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 87mm on 21.12.2025
24/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert along with Site engineer of PMC to the ISS site. Inspected the overall progress of work, LHS under sluice fish pass pier concrete work in progress.
25/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert along with Site engineer of PMC to the ISS site. Inspected the overall progress of work, LHS under sluice fish pass pier concrete work in progress.
26/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert along with Site engineer of PMC to the ISS site. Inspected the overall progress of work, LHS under sluice fish pass pier concrete work in progress.
27/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert along with Site engineer of PMC to the ISS site. Inspected the overall progress of work, LHS under sluice fish pass pier concrete work in progress.
28/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert along with Site engineer of PMC to the ISS site. Inspected the overall progress of work, LHS under sluice fish pass pier concrete work in progress.
29/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.4 of bay no.5 for 1st lift is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency,ISS Nandgaon. Slump achieved 75mm on 21.12.2025
30/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.4 of bay no.5 for 1st lift is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency,ISS Nandgaon. Slump achieved 75mm on 21.12.2025
31/100
Instream Storage Structure, KansariGanda
Slump test and cube cast at site in presence of AEE & AE of dept., Geologist and Irrigation Eng. Expert along with Site engineer PMC.
32/100
Instream Storage Structure, KansariGanda
Slump test and cube cast at site in presence of AEE & AE of dept., Geologist and Irrigation Eng. Expert along with Site engineer PMC.
33/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert along with Site engineer of PMC to the ISS site. Inspected the overall progress of work and Middle pier 4th lift concrete work in progress.
34/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert along with Site engineer of PMC to the ISS site. Inspected the overall progress of work and Middle pier 4th lift concrete work in progress.
35/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering at D/S right flank wall, Block-2 is in progress on 21.12.2025
36/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.5 of bay no.5 for 1st lift is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 73mm on 20.12.2025
37/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.5 of bay no.5 for 1st lift is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 73mm on 20.12.2025
38/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.3 of bay no.3 for 3rd lift is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved75mm on 20.12.2025
39/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.3 of bay no.3 for 3rd lift is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved75mm on 20.12.2025
40/100
Instream Storage Structure, Nandagaon
Angle cutting for bracing of columns by using gas cutter under progress on 20.12.2025
41/100
Instream Storage Structure, Nandagaon
Gate no 6 both stoplog gate and barrage bay gate 2nd stage embedded parts erection work under progress on 20.12.2025
42/100
Instream Storage Structure, Hamirpur
Engineer-in-Chief, Planning & Design, Department of Water Resources (DoWR) with C.E & BM, Brahmani Basin Samal visited and inspect the ISS Construction Site in presence of Addl.CE, HWC, Rengali, S.E, QA&QC, RID, A.E.E & A.E, RID and I.E.E, Site Engineer of PSS team along with representative of EPC Agency.
43/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-23, 14th lift with Pedstal done in presence of Client & PSS Team.
44/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering at pier no.10,Block-2 is in progress on 20.12.2025
45/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-23, 14th lift with Pedstal is under progress in presence of Client & PSS Team.
46/100
Instream Storage Structure, Hamirpur
Radiographic test conducted today on double pier hoist bridge Platform No-3 is under progress.
47/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-10, 8th lift is under progress.
48/100
Instream Storage Structure, Nandagaon
Curing at U/S right flared out wall, Block-2 is in progress on 20.12.2025
49/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-30, 3rd lift is under progress.
50/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-31, 11th lift is under progress.
51/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cube casting for LHS D/S Double Pier, 1st lift 2nd step done in presence of Client & PSS Team
52/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 90 mm) of LHS D/S Double Pier, 1st lift 2nd step done in presence of Client & PSS Team.
53/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS D/S Double Pier, 1st lift 2nd step is under progress in presence of Client & PSS Team.
54/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cube casting for LHS D/S Mid Pier, 1st lift 3rd step done in presence of Client & PSS Team.
55/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 80 mm) of LHS D/S Mid Pier, 1st lift 3rd step done in presence of Client & PSS Team.
56/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS D/S Mid Pier, 1st lift 3rd step is completed in presence of Client & PSS Team.
57/100
Instream Storage Structure, Jharbeda
Engineer-in-Chief, Planning & Design, Department of Water Resources (DoWR) with C.E & BM, Brahmani Basin Samal visited and inspect the ISS Construction Site in presence of Addl.CE, HWC, Rengali, S.E, QA&QC, RID, A.E.E & A.E, RID and PSS team along with representative of EPC Agency.
58/100
Instream Storage Structure, Jharbeda
Excavation from Pier No-7 to RHS Abutments area is under progress.
59/100
Instream Storage Structure, Jharbeda
Cleaning from Pier No-6 to Pier No-7 U/S Gravity floor area is under progress.
60/100
Instream Storage Structure, Jharbeda
De-Shuttering of Pier No-1 is under progress.
61/100
Instream Storage Structure, Khalpal
Slump testing M35A20 (Value 90 mm) of Girder No-7 done in presence of Client & PSS Team.
62/100
Instream Storage Structure, Khalpal
Concreting M35A20 of Girder No-7 is under progress in presence of Client & PSS Team.
63/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Barrage bay Cross Cut-off Panel No-9 done in presence of Client & PSS Team.
64/100
Instream Storage Structure, Khalpal
Diaphragm wall cage placing for Barrage bay Cross cut-off Panel No-9 in presence of Client & PSS Team.
65/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-18, 12th lift is under progress in presence of Client & PSS Team.
66/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 88 mm) of Pier No-31, 10th lift done in presence of Client & PSS Team.
67/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-31, 10th lift is under progress in presence of Client & PSS Team.
68/100
Instream Storage Structure, Hamirpur
Central drive unit assembly drilling work is in progress.
69/100
Instream Storage Structure, Hamirpur
Cleaning of Barrage gate by sand blasting method is under progress.
70/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-10, 8th lift is under progress.
71/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-30, 3rd lift is under progress.
72/100
UGPL, Right Lower Suktel Canal Division
Bermad fixing work is in progress of OCS NO-0213120-C08B at village Budhisindhol .
73/100
Instream Storage Structure, Jharbeda
De-Shuttering work is under progress.
74/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M25A20 (Value 90 mm) of Abutment counterfort, 2nd lift done in presence of Client & PSS Team.
75/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of Abutment counterfort, 2nd lift is under progress in presence of Client & PSS Team.
76/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of Double Pier, 1st lift is under progress.
77/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS Midpier, 1st lift is under progress.
78/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning of RHS Raft is under progress.
79/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Barrage bay Cross Cut-off Panel No-6 done in presence of Client & PSS Team.
80/100
Instream Storage Structure, Khalpal
Concreting M35A20 of Girder No-6 is under progress in presence of Client & PSS Team.
81/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 160 mm) of Barrage bay Cross Cut-off Panel No-18 done in presence of Client & PSS Team.
82/100
Instream Storage Structure, Khalpal
Concreting M25A20 of D/S Barrage bay Cross Cut-off Panel No-18 done in presence of Client & PSS Team.
83/100
Instream Storage Structure, Khalpal
Binding of reinforcement for Diaphragm wall D/S Barrage bay Cross Cut-off Panel No-18 in presence of Client & PSS Team.
84/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
85/100
UGPL, Right Lower Suktel Canal Division
Pipe fitting work is in progress for OCS NO- 0213128-C06B at village Durgapali In presence of PMC team.
86/100
UGPL, Left Lower Suktel Canal Division
TEE connection work is in progress to HDPE pipeline at Rm-14 Ro-256 near village Jharmunda.
87/100
UGPL, Left Lower Suktel Canal Division
OMS installation work is in progress of RO-239A ,RM-13 near village Kushang.
88/100
Integrated Barrage across river Kochila and across river Baitarini
CE, ACE, SE and AEE of Quality Assurance Division Chandikhol, AEE and AE of Akhuapada irrigation Division visited ISS- Baitarani & Kochila today. PMC experts including DTL were present at site with the representatives of Agency-22.12.2025
89/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Over burden cutting at structure area work is going on at chaudharygada iss project.
90/100
UGPL, Left Lower Suktel Canal Division
Excavation work in progress for 75mm Dia HDPE pipeline from node RO-239 to RO-239A, RM-13 near village Kushang.
91/100
UGPL, Left Lower Suktel Canal Division
Internal drainage-2 wall shuttering board fixing work is in progress at Pump House in presence of PMC team.
92/100
UGPL, Right Lower Suktel Canal Division
Proceeding of Pani panchayat awareness meeting in presence of DoWR staff and PMC team at village Bahalbuka.
93/100
UGPL, Right Lower Suktel Canal Division
150mm Dia Air valve Tee fixing work is in progress on 700mm Dia DI pipe in between junction J-0212 and J-0122 at village Chareimara.
94/100
Instream Storage Structure, Gudvella
Cast of concrete 2nd lift RCC M25A20 grade at right side u/s wing wall including 2nos CF wall from RL 148.80m to 150.15m is under progress through pump in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 87mm on 19.12.2025
95/100
Instream Storage Structure, Gudvella
Cast of concrete 2nd lift RCC M25A20 grade at right side u/s wing wall including 2nos CF wall from RL 148.80m to 150.15m is under progress through pump in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 87mm on 19.12.2025
96/100
Instream Storage Structure, Gudvella
Cast of concrete 2nd lift RCC M25A20 grade at right side u/s wing wall including 2nos CF wall from RL 148.80m to 150.15m is under progress through pump in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 87mm on 19.12.2025
97/100
Instream Storage Structure, Gudvella
Cast of concrete 2nd lift RCC M25A20 grade at right side u/s wing wall including 2nos CF wall from RL 148.80m to 150.15m is under progress through pump in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 87mm on 19.12.2025
98/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 1no. CC block of size 5.0x1.5x0.6m at U/S right flared out wall at sec.2-2 for 5th lift from RL-239.40m to RL-240.00m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 76mm on 19.12.2025
99/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 1no. CC block of size 5.0x1.5x0.6m at U/S right flared out wall at sec.2-2 for 5th lift from RL-239.40m to RL-240.00m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 76mm on 19.12.2025
100/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of stoplog & main gate grooves sill beam at bay-7 (barrage bay no.5) block-1 is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 74mm on 19.12.2025
❮
❯