Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Gudvella
Erection of stoplog gate is under progress at site on 14.07.2026
2/100
Instream Storage Structure, Gudvella
Earth filling work for the A2-side approach road is in progress. Due to a litigation issue affecting a portion of the road alignment, the work faced some obstruction. However, after discussions and coordination with the local villagers, the work has resumed and is continuing smoothly on 14.07.2026
3/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 14.07.2026
4/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 14.07.2026
5/100
Instream Storage Structure, Nandagaon
Stone pitching work at U/S right embankment is in progress on 14.07.2026
6/100
Instream Storage Structure, Nandagaon
Monorail walkway erection work is under progress on pier no 9 on 14.07.2026
7/100
Instream Storage Structure, Nandagaon
6 NOS of monorail girder erection work is under progress on 14.07.2026
8/100
Instream Storage Structure, Nandagaon
Column , trestle and barrage bay gate erection work is completed on pier no 10 on 14.07.2026
9/100
Instream Storage Structure, Gochara
Staff quarter 1st floor out side brick wall work in progress..
10/100
Instream Storage Structure, Gochara
Staff quarter 1st floor out side brick wall work in progress..
11/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
12/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. The flow level is 225.500mt against design crest level 225.500 i.e. flood lift 0.000mt.
13/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
14/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.94/mm2 for 28 days) of Pier No-1, 11th lift and (Strength is 30.69/mm2 for 28 days) of Abutment wall (A1), 10th lift and M15A40 (Strength is 20.30/mm2 for 07 days) of Flank cut-off wall PCC has done in presence of Client & PSS team.
15/100
Instream Storage Structure, Gochara
The RDU and CDU base frame have been directly welded without installing or tightening the required nuts and bolts, which may affect proper installation and future maintenance.
16/100
Instream Storage Structure, Gochara
All Gates are being lowered to stop the water.
17/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
18/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. The flow level is 225.600mt against design crest level 225.500 i.e. flood lift 0.100mt.
19/100
Instream Storage Structure, Hamirpur
E.M brake & reducer fixing work is in progress Of C.D.U assembly No-21.
20/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flank wall, 3rd lift at Block No-5 is under progress.
21/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flank wall, 3rd lift at Block No-5 is under progress.
22/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flared out wall at Block No-5 is under progress.
23/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder No-48 is under progress.
24/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-25, 14th lift at Block No-4 is under progress.
25/100
Instream Storage Structure, Khalpal
Testing of Compressive M20A20 (Strength is 29.90/mm2 for 28 days) of Barrage Bay No-2 Gravity floor has done in presence of Client & PSS team.
26/100
Instream Storage Structure, Khalpal
Shuttering & Binding of reinforcement for LHS Abutment Counterfort wall, 2nd lift is under progress.
27/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 54.935 m.
28/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.00m.
29/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M25A20 (Value 90 mm) of LHS D/S Divide wall, 6th lift done in presence of Client & PSS Team.
30/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of LHS D/S Divide wall, 6th lift is under progress in presence of Client & PSS Team.
31/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Casting of C.C Block (M15A40) is under progress in presence of Client & PSS Team.
32/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of CC Blocks is under progress.
33/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Present status of river Samakoi at Santeibhanja site.
34/100
Instream Storage Structure, Gudvella
Septic tank work is in progress on 13.07.2026
35/100
Instream Storage Structure, Gudvella
Erection of stoplog gate is under progress at site on 13.07.2026
36/100
Instream Storage Structure, Gudvella
Shuttering work is under progress for headroom of building slab on 13.07.2026
37/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 13.07.2026
38/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 13.07.2026
39/100
Instream Storage Structure, Gudvella
Finishing and grinding work is under progress at mechanical yard on 12.07.2026
40/100
Instream Storage Structure, Gudvella
Plastering work is under progress at building area on 12.07.2026
41/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 12.07.2026
42/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 12.07.2026
43/100
Instream Storage Structure, Gudvella
Erection of stoplog gate is under progress at site on 11.07.2026
44/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 11.07.2026
45/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 11.07.2026
46/100
Instream Storage Structure, Hamirpur
Slump testing M15A40 (Value 45 mm) of U/S Flared out wall, 11th lift at Block No-5 done in presence of Client & PSS Team.
47/100
Instream Storage Structure, Hamirpur
Concreting M15A40 of U/S Flared out wall, 11th lift at Block No-5 is under progress in presence of Client & PSS Team.
48/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Gantry Girder No-46 done in presence of Client & PSS Team.
49/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-46 is under progress in presence of Client & PSS Team.
50/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-23, 15th lift at Block No-5 done in presence of Client & PSS Team.
51/100
Instream Storage Structure, Nandagaon
Column erection work is under progress at pier no 10 on 13.07.2026
52/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-23, 15th lift at Block No-5 is under progress in presence of Client & PSS Team.
53/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.63/mm2 for 07 days) of Pier No-18, 16th lift and M15A40 (Strength is 20.27/mm2 for 28 days) of Flared out wall PCC and M35A20 (Strength is 42.52/mm2 for 28 days) of Gantry Girder No-37 has done in presence of Client & PSS team.
54/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flank wall, 3rd lift at Block No-5 is under progress.
55/100
Instream Storage Structure, Nandagaon
Shuttering for CC block at U/S left flared out wall is in progress on 12.07.2026
56/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flared out wall at Block No-5 is under progress.
57/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flared out wall at Block No-5 is under progress.
58/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
59/100
Instream Storage Structure, Nandagaon
M20A20 grade of CC block at D/S right flared out wall is completed on 11.07.2026
60/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall, 9th lift at Block No-5 is under progress.
61/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-24, 14th lift at Block No-4 is under progress.
62/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.645 m.
63/100
Instream Storage Structure, Khalpal
Testing of Compressive M20A20 (Strength is 29.60/mm2 for 28 days) of Barrage Bay No-2 Gravity floor and M25A20 (Strength is 34.02/mm2 for 28 days) of Pier No-23, 2nd lift has done in presence of Client & PSS team.
64/100
Instream Storage Structure, Khalpal
Binding of reinforcement for LHS Abutment Counterfort wall, 2nd lift is under progress.
65/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 54.685 m.
66/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.1m.
67/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Present status of river Samakoi at Santeibhanja site.
68/100
Integrated Barrage across river Kochila and across river Baitarini
M25A20 Grade7days and 28 days compressive strength test conducted at Baitarani ISS site Labaratory in presence of PMC and representative of Agency Quality Engineer.
69/100
Integrated Barrage across river Kochila and across river Baitarini
FLood water in the river Baitarani
70/100
Integrated Barrage across river Kochila and across river Baitarini
All work stop due to rain at baitarani iss project.
71/100
Integrated Barrage across river Kochila and across river Baitarini
All work stop due to rain at baitarani iss project.
72/100
Integrated Barrage across river Kochila and across river Baitarini
All work stop due to rain at baitarani iss project.
73/100
Integrated Barrage across river Kochila and across river Baitarini
CE, MBBS, Addl. CE, Chandikhol inspecting Baitarani ISS work in presence of concerned AEE, PMC and PM of agency.
74/100
Integrated Barrage across river Kochila and across river Baitarini
All work stop due to Rain at baitarani iss project.
75/100
Integrated Barrage across river Kochila and across river Baitarini
Meeting held at PMU Bhubaneswar in presence of Chief Engineer, MBBS , The EPC agency and experts from PMU/PMC regarding land acquisition matter of Kochila Baitarani ISS projects.
76/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay middle pier no 4 shuttering work in progress at baitarani iss project.
77/100
Integrated Barrage across river Kochila and across river Baitarini
Abutment wall10 lift RL13.1 to 13.8and counterfort wall 13.1 to 13.5concrete pouring work in progress .
78/100
Integrated Barrage across river Kochila and across river Baitarini
M25A20 Grade 28Days&7days Compressive strength test.Baitarani ISS Site laboratory in presence of PMC and representatives of Agency QC&QA Engineer.
79/100
Integrated Barrage across river Kochila and across river Baitarini
M25A20 Grade 28Days Compressive strength test.Baitarani ISS Site laboratory in presence of PMC and representatives of Agency QC&QA Engineer.
80/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay middle pier no 5 shuttering work in progress at baitarani iss project.
81/100
Integrated Barrage across river Kochila and across river Baitarini
Wing Wall LHS Wing wall 10 lift RL13.1 to 13.8and counterfort wall 13.1 to 13.5 de shuttering work of Baitarani ISS project in progress .
82/100
Integrated Barrage across river Kochila and across river Baitarini
Upstream divide wall de shuttering work in progress at baitarani iss project.
83/100
Integrated Barrage across river Kochila and across river Baitarini
M25A20 Grade 7days and M20 A20 Grade 7days Compressive strength test of upstream divide wall , LHS Abutment wall,Pier no 3, C C block and Fish pass Area at Baitarani ISS Site laboratory in presence of PMC and representatives of Agency QC&QA Engineer.
84/100
Integrated Barrage across river Kochila and across river Baitarini
(Baitarani ISS) LHS Wing wall 10 th lift RL13.1 to 13.80m and counterfort wall RL 13.10m to 13.50m concrete pouring work in progress .
85/100
Integrated Barrage across river Kochila and across river Baitarini
Pier no - 4 of Baitarani ISS 6th lift concrete pouring work in progress (RL 9.3 to 10.75).
86/100
Integrated Barrage across river Kochila and across river Baitarini
Today Site Visit of AEE of Akhuapada irrigation Division, in presence of PMC and representatives of Agency also ISS Project at Kochila-Baitarani.
87/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay middle pier curing work in progress at Baitarani ISS project.
88/100
Integrated Barrage across river Kochila and across river Baitarini
Upstream divide wall 8th lift shuttering work in progress at Baitarani ISS project.
89/100
Integrated Barrage across river Kochila and across river Baitarini
LHS Abutment wall hoist portion RCC casting (from Reduced level 13.0m to 13.3m) work in progress at baitarani ISS project.
90/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay middle pier no 5 (5th lift) casting work in progress at baitarani ISS project.
91/100
Integrated Barrage across river Kochila and across river Baitarini
Upstream divide wall steel work in progress at Baitarani ISS project.
92/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay middle pier no 1 (5th lift) shuttering work in progress at baitarani ISS project.
93/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay middle pier no 1 (5th lift)) RCC casting from RL 7.80m to 9.20m work in progress at baitarani ISS project.
94/100
Integrated Barrage across river Kochila and across river Baitarini
C C block shifting from site camp of Baitarani ISS to Construction site at baitarani ISS project.
95/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay middle pier no 5 (5th lift) steel work in progress at baitarani ISS project.
96/100
Integrated Barrage across river Kochila and across river Baitarini
M25A20 Grade 28Days Compressive strength test at Baitarani ISS Site laboratory in presence of PMC and representatives of Agency QC&QA Engineer.
97/100
Integrated Barrage across river Kochila and across river Baitarini
Upstream divide wall 7th lift RCC casting work in progress at baitarani ISS project
98/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay middle pier no 4 (5th Lift) RCC casting work in progress at baitarani iss.
99/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay middle pier no 3 shuttering work in progress at baitarani iss project.
100/100
Integrated Barrage across river Kochila and across river Baitarini
M25A20 Grade, 7Days and 28days Compressive strength test of Pier no 5 ,LHS Abutment wall and upstream divide wall at Baitarani ISS Site laboratory in presence of PMC and representatives of Agency QC&QA Engineer.