PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 450mm Dia DI pipe gap closing from J-254 to J-38 near village Birkel in presence of AE DoWR and PMC team.
2/100
UGPL, Left Lower Suktel Canal Division
1ha outlet point fixing work is in progress at LO-198B(Z-2730),LM-10 near village Jharmunda in presence of PMC team.
3/100
Instream Storage Structure, Gudvella
Cast of concrete at endseal portion from in between A1 to P1 under sluice bay of grade M25A20 RCC with RL 147.45m to 148.60m is under progress through chute in the presence of Dept JE, site engineer of PMC and agency. The slump test value is 76mm on 07.04.2026
4/100
Instream Storage Structure, Gudvella
Cast of concrete at endseal portion from in between A1 to P1 under sluice bay of grade M25A20 RCC with RL 147.45m to 148.60m is under progress through chute in the presence of Dept JE, site engineer of PMC and agency. The slump test value is 76mm on 07.04.2026
5/100
Instream Storage Structure, Gudvella
Column, trestle final allignment work under progress on 07.04.2026
6/100
Instream Storage Structure, Gudvella
Paint work under progress on 07.04.2026
7/100
Instream Storage Structure, Gudvella
Stoplog ss plate welding work under progress on 07.04.2026
8/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no.7&8 is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 85mm on 07.04.2026
9/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no.7&8 is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 85mm on 07.04.2026
10/100
Instream Storage Structure, Nandagaon
• 1 (i).Fixing & fittings and alignment of All trestle and columns foundation bolts measurements has been checked at pier no.-7&8 for Blockout area of 6.8m length and found correct by HM Expert of PMC during his site visit on dt.01.04.2026 in presence of mechanical Site Engineers of PMC and EPC Agency. (ii) Rigid and smooth shuttering for Blockout area with M35A20 grade at pier no.-7&8 from RL-245.40m to RL-246.30m are found completed. (iii).The area is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with M35A20 grade on 07.04.2026
11/100
Instream Storage Structure, Nandagaon
Gate no 13 both barrage bay gate and stoplog gate 2nd stage embedded parts erection work completed and it is ready for concrete on 07.04.2026
12/100
Instream Storage Structure, Nandagaon
Gate no 13 both barrage bay gate and stoplog gate 2nd stage embedded parts erection work completed and it is ready for concrete on 07.04.2026
13/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no. 1 on 07.04.2026
14/100
Instream Storage Structure, Nandagaon
Placing of CC blocks is in progress at U/s side on 07.04.2026
15/100
Instream Storage Structure, Nandagaon
• 1) De-Shuttering is in progress at U/S right divide wall. 2) De-watering is in progress through well point system on 07.04.2026
16/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Fish pass, Raft at Block No-1 done in presence of Client & PSS Team.
17/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Fish pass, Raft at Block No-1 is under progress in presence of Client & PSS Team.
18/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-1, 3rd lift done in presence of Client & PSS Team.
19/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-1, 3rd lift is under progress in presence of Client & PSS Team.
20/100
Instream Storage Structure, Hamirpur
Column base plate drilling work is in progress.
21/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-2 girder's fit up work is in progress.
22/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-1 welding work is in progress.
23/100
Instream Storage Structure, Hamirpur
MS plate marking and cutting for stiffener of hoist bridge work is in progress.
24/100
Instream Storage Structure, Hamirpur
Shuttering of Fish pass raft at Block no-1 is under progress.
25/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Abutment wall (A1), 7th lift at Block No-1 is under progress.
26/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-1, 3rd lift is under progress.
27/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Flank wall at Block no-1 is under progress.
28/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
29/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Right side under sluice raft area concrete casting work in progress at choudhurygada iss projects on 08.04.2026
30/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay Raft Casting work is in progress in presence of Chief Engineer-MBBS, Chandikhol, OCCL GM, SE, AEE, AE of Akhuapada irrigation division, PMC-Chandikhole and representatives of Agency of Baitarani ISS- 08.04.2026
31/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-15, 12th lift is under progress.
32/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-16, 13th lift is under progress.
33/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Pier no-21, 12th lift is under progress.
34/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M25A20 (Value 80 mm) of Double pier, 4th lift done in presence of Client & PSS Team.
35/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of Double pier, 4th lift is under progress in presence of Client & PSS Team.
36/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 85 mm) of U/S Divide wall, Raft done in presence of Client & PSS Team.
37/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of U/S Divide wall, Raft is under progress in presence of Client & PSS Team.
38/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 85 mm) of RHS Counterfort with Abutment wall, 1st lift done in presence of Client & PSS Team.
39/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of RHS Counterfort with Abutment wall, 1st lift is under progress in presence of Client & PSS Team.
40/100
Instream Storage Structure, Jharbeda
Slump testing M25A20 (Value 80 mm) of RHS D/S (D2) portion Footing, 1st lift done in presence of Client & PSS Team.
41/100
Instream Storage Structure, Jharbeda
Concreting M25A20 of RHS D/S (D2) portion Footing, 1st lift is under progress in presence of Client & PSS Team.
42/100
Instream Storage Structure, Jharbeda
LHS (A1) GROOVES CHIPPING WORK IS IN PROGRESS.
43/100
Instream Storage Structure, Jharbeda
D/S CC BLOCK PLACING WORK IS IN PROGRESS.
44/100
Instream Storage Structure, Jharbeda
Cutting & bending for reinforcement is under progress.
45/100
Instream Storage Structure, Jharbeda
Shuttering of D/S End sill Pier No-8 to RHS (D2) is under progress.
46/100
Instream Storage Structure, Jharbeda
Shuttering of PierNo-8, 4th lift is under progress.
47/100
Instream Storage Structure, Jharbeda
Shuttering of PierNo-7, 7th lift is under progress.
48/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
49/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of Barrage Bay No-2 Mid Cut-off wall, 1st lift done in presence of Client & PSS Team.
50/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Barrage Bay No-2 Mid Cut-off wall, 1st lift is under progress in presence of Client & PSS Team.
51/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 90 mm) of Pier No-21 (Crest portion) done in presence of Client & PSS Team.
52/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-21 (Crest portion) is under progress in presence of Client & PSS Team.
53/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of Wing wall with Counterfort, 2nd lift is under progress.
54/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering & Binding of reinforcement for RHS Counterfort with Abutment wall, 1st lift is under progress.
55/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Testing of Compressive M25A20 (Strength is 31.09/mm2 for 28 days) of LHS Mid-pier, 8th lift and M20A20 (Strength is 20.66/mm2 for 07 days) of RHS Gravity floor has done in presence of Client & PSS team.
56/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M20A20 (Value 85 mm) of RHS Gravity floor done in presence of Client & PSS Team.
57/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M20A20 of RHS Gravity floor is under progress in presence of Client & PSS Team.
58/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Gantry Girder No-13 done in presence of Client & PSS Team.
59/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-13 is under progress in presence of Client & PSS Team.
60/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-5, 5th lift done in presence of Client & PSS Team.
61/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-5, 5th lift is under progress in presence of Client & PSS Team.
62/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Pier No-4, 4th lift done in presence of Client & PSS Team.
63/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-4, 4th lift is under progress in presence of Client & PSS Team.
64/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.33/mm2 for 07 days) of Pier No-4, 3rd lift and (Strength is 21.93/mm2 for 07 days) of Pier no-6 with Pedestal and (Strength is 31.04/mm2 for28 days) of Flared out Cut-off wall, 2nd lift has done in presence of Client & PSS team.
65/100
Instream Storage Structure, Hamirpur
RHS side Pier No-12 vertical Groove barrage bay and stop-log groove 2nd stage embedded parts roller track and side guide erection work is in progress.
66/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
67/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Pier No-3, 5th lift is under progress.
68/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Pier No-2, 4th lift is under progress.
69/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Flank wall at Block No-1 is under progress.
70/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for D/S Abutment (A1), 7th lift is under progress.
71/100
Instream Storage Structure, Khalpal
Observed of Sieve analysis of Fine aggregate in presence of Client & PSS team along with EPC agency.
72/100
Instream Storage Structure, Khalpal
Testing of Compressive M25A20 (Strength is 23.66/mm2 for 07 days) of LHS U/S Divide wall Raft and M25A20 (Strength is 24.13/mm2 for 07 days) of Barrage Bay No-2 has done in presence of Client & PSS team.
73/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 85 mm) of LHS sluice Bay Gravity floor (PCC) done in presence of Client & PSS Team.
74/100
Instream Storage Structure, Khalpal
Concreting M20A20 of LHS sluice Bay Gravity floor (PCC) is under progress in presence of Client & PSS Team.
75/100
UGPL, Left Lower Suktel Canal Division
HDPE connection work is in progress at J-194 of RM-6 at village Kirabahal.
76/100
UGPL, Left Lower Suktel Canal Division
Excavation work is under progress for 450mm Dia DI pipeline laying and Gap closing from node J-254 to J-38, RM-15 near vilage Birkel.
77/100
UGPL, Right Lower Suktel Canal Division
External drain brick masonry work is in progress at Pump House.
78/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS-0213124-C13A at village Baxiudar in presence of PMC team.
79/100
UGPL, Right Lower Suktel Canal Division
Inspected of Butterfly valve and Butterfly valve Chamber is in progress for 280mm DIa HDPE pipe from J-8020 to J-8037 (p-8037) at village Rakshimunda.
80/100
UGPL, Right Lower Suktel Canal Division
Air valve installation work is in progress of 600mm Dia DI pipe in between J-1354 to J-1345 at village Kharjura in presence of DoWR SDO, AE and PMC team.
81/100
UGPL, Right Lower Suktel Canal Division
OCS chamber above GL work is in progress of OCS No:- 0213014-C02B at village Charpali in presence of DoWR SDO and PMC team.
82/100
UGPL, Right Lower Suktel Canal Division
HDPE Pipe laying work is in progress of OCS No. 0213130-C09B at village Laderbahal in presence of PMC team.
83/100
UGPL, Right Lower Suktel Canal Division
OCS chamber Below NGL footing levelling work is in progress of OCS No. 0213126- C03B at village Padampur in presence of PMC team.
84/100
UGPL, Right Lower Suktel Canal Division
External drain brick masonry work is in progress at Pump House.
85/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS-0213078-C05A at village Bhaler in presence of PMC team.
86/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for 800mm Dia DI pipe of 800mm Dia valve chamber in between junction J-0030- to J-0040 at village Sauntpur.
87/100
UGPL, Right Lower Suktel Canal Division
External drain stone pitching gaps concrete filing work is in progress at Pump House.
88/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 450 mm Dia DI pipe line Laying & Gap closing of Rm-15, from J-254 to J-38 at village Birkel.
89/100
Instream Storage Structure, Gudvella
Paint work is under progress on 06.04.2026
90/100
Instream Storage Structure, Gudvella
Brick work is in progress at 1st floor building of control room on 06.04.2026
91/100
Instream Storage Structure, Gudvella
Gate installation work under progress at P2 on 06.04.2026
92/100
Instream Storage Structure, Gudvella
Placement of CC block is under progress at u/s side on 06.04.2026
93/100
Instream Storage Structure, Gudvella
Brickwork at control room building is under progress on 05.04.2026
94/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 05.04.2026
95/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 05.04.2026
96/100
Instream Storage Structure, Nandagaon
• Due to heavy wind storm occurred at ISS site on dated 05.04.2026 at 7.30pm, all the machineries such a Excavator doors, welding machines deployed at site became in unworkable position and roof shed and side boundary of the camp have also been damaged. Therefore, all the site activities are stopped till getting repaired of machineries and camp site on 06.04.2026
97/100
Instream Storage Structure, Nandagaon
• Due to heavy wind storm occurred at ISS site on dated 05.04.2026 at 7.30pm, all the machineries such a Excavator doors, welding machines deployed at site became in unworkable position and roof shed and side boundary of the camp have also been damaged. Therefore, all the site activities are stopped till getting repaired of machineries and camp site on 06.04.2026
98/100
Instream Storage Structure, Nandagaon
• Due to heavy wind storm occurred at ISS site on dated 05.04.2026 at 7.30pm, all the machineries such a Excavator doors, welding machines deployed at site became in unworkable position and roof shed and side boundary of the camp have also been damaged. Therefore, all the site activities are stopped till getting repaired of machineries and camp site on 06.04.2026
99/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right divide wall raft for 2nd lift upto RL-230.60m is in progress through concrete pump in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 87mm on 05.04.2026
100/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right divide wall raft for 2nd lift upto RL-230.60m is in progress through concrete pump in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 87mm on 05.04.2026