1/100
Instream Storage Structure, Khalpal
Present flow condition of Rainfall at ISS khalpal site.
2/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
DCAC meeting conducted by supervision of Deputy Collector, keonjhar, S. E & S D. O, Rengali Dam Division, Tahasildar Telkoi, L. A. O, keonjhar, all landlord & R. S. A staff for ISS Santeibhanja.
3/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
DCAC meeting conducted by supervision of Deputy Collector, keonjhar, S. E & S D. O, Rengali Dam Division, Tahasildar Telkoi, L. A. O, keonjhar, all landlord & R. S. A staff for ISS Telkoi.
4/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Watchman building foundation is under progress in presence of Client & PSS Team.
5/100
Instream Storage Structure, Hamirpur
Binding of Reinforcement for Building footing vertical is under progress.
6/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.440m.
7/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 37.04/mm2 for 07 days) of Cross Girder (Bay No-13 & 14) and M25A20 (Strength is 21.48/mm2 for 07 days) of Precast Hand Railing has done in presence of Client & PSS team.
8/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Watchman building foundation is under progress in presence of Client & PSS Team.
9/100
Instream Storage Structure, Hamirpur
Column guide line welding work is in progress.
10/100
Instream Storage Structure, Hamirpur
MS plate marking and cutting for column base plate work is in progress.
11/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 95 mm) of Deck slab (Bay No-14) done in presence of Client & PSS Team.
12/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Deck slab (Bay No-14) is under progress in presence of Client & PSS Team.
13/100
Instream Storage Structure, Jakameripalli
Visit of QA/QC Expert, Mechanical site engineer and support staffs of PMC to the ISS Site for Routine inspection during Defect liability period.
14/100
Instream Storage Structure, Jakameripalli
Visit of QA/QC Expert, Mechanical site engineer and support staffs of PMC to the ISS Site for Routine inspection during Defect liability period.
15/100
Instream Storage Structure, Jakameripalli
02/01/2026 -Visit to ISS Jakmarapalli by PMC team consisting of QA/QC Expert, SDE, HME and Site Engineer Mechanical. The following observations made on Hydro Mechanical Equipment - Yearly Maintenance work.
1. Rope Drum Hoists Worm Reducers Oil change completed.
2. Greasing completed for Rope Drum Hoists gear assembly and other items.
3. Cardium compound applied for all Wire ropes of Hoists and Under Slung Hoist (for Stop log operation)
4. The painting work completed on Hoists Assembly Covers.
5. Greasing completed for Pulley Blocks and Gate Rollers.
16/100
Instream Storage Structure, Jakameripalli
02/01/2026 -Visit to ISS Jakmarapalli by PMC team consisting of QA/QC Expert, SDE, HME and Site Engineer Mechanical. The following observations made on Hydro Mechanical Equipment - Yearly Maintenance work.
1. Rope Drum Hoists Worm Reducers Oil change completed.
2. Greasing completed for Rope Drum Hoists gear assembly and other items.
3. Cardium compound applied for all Wire ropes of Hoists and Under Slung Hoist (for Stop log operation)
4. The painting work completed on Hoists Assembly Covers.
5. Greasing completed for Pulley Blocks and Gate Rollers.
17/100
Instream Storage Structure, Jakameripalli
02/01/2026 -Visit to ISS Jakmarapalli by PMC team consisting of QA/QC Expert, SDE, HME and Site Engineer Mechanical. The following observations made on Hydro Mechanical Equipment - Yearly Maintenance work.
1. Rope Drum Hoists Worm Reducers Oil change completed.
2. Greasing completed for Rope Drum Hoists gear assembly and other items.
3. Cardium compound applied for all Wire ropes of Hoists and Under Slung Hoist (for Stop log operation)
4. The painting work completed on Hoists Assembly Covers.
5. Greasing completed for Pulley Blocks and Gate Rollers.
18/100
Instream Storage Structure, Jakameripalli
02/01/2026 -Visit to ISS Jakmarapalli by PMC team consisting of QA/QC Expert, SDE, HME and Site Engineer Mechanical. The following observations made on Hydro Mechanical Equipment - Yearly Maintenance work.
1. Rope Drum Hoists Worm Reducers Oil change completed.
2. Greasing completed for Rope Drum Hoists gear assembly and other items.
3. Cardium compound applied for all Wire ropes of Hoists and Under Slung Hoist (for Stop log operation)
4. The painting work completed on Hoists Assembly Covers.
5. Greasing completed for Pulley Blocks and Gate Rollers.
19/100
Instream Storage Structure, Jakameripalli
02/01/2026 -Visit to ISS Jakmarapalli by PMC team consisting of QA/QC Expert, SDE, HME and Site Engineer Mechanical. The following observations made on Hydro Mechanical Equipment - Yearly Maintenance work.
1. Rope Drum Hoists Worm Reducers Oil change completed.
2. Greasing completed for Rope Drum Hoists gear assembly and other items.
3. Cardium compound applied for all Wire ropes of Hoists and Under Slung Hoist (for Stop log operation)
4. The painting work completed on Hoists Assembly Covers.
5. Greasing completed for Pulley Blocks and Gate Rollers.
20/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 24.09.2026
21/100
MMIP, Bankatira Barrage Project
Bankatira Barrage site inspection of PSS consultants.
22/100
MMIP, Bankatira Barrage Project
Flood water situation on river Budhabalanga at bankatira Barrage Site.
23/100
MMIP, Bankatira Barrage Project
Budhabalanga Flood water ( Submerged Nuagan - Shankarpur Road ) cutting off the Bankatira Barrage site Access.
24/100
MMIP, Bankatira Barrage Project
Bankatira Barrage site on 1- 07-2026.
25/100
MMIP, Bankatira Barrage Project
Site inspected by Superintending Engineer in the presence of PMC Consultants.
26/100
MMIP, Bankatira Barrage Project
Inspection of sheet pile drawing work by Irrigation Expert PMC S.B. Basin Baripada.
27/100
MMIP, Bankatira Barrage Project
Inspection of sheet pile driving work at site by S.E. & PMC staff.
28/100
Instream Storage Structure, Dhanei
Visit of SD Expert, PMC to RI Laxmana Pali, RI Chirikipada and SDO, Dhanei during the visit to ISS Sanabargam today (24.9.2026). Updated them on the latest status of land acquisition and made discussion on re-demarcation of private land scheduled for 01.10.2026, and the Collector’s letter(letter no:619 dt:1.9.26) to the Tahasildar, Polasara regarding demarcation of Government land by deploying revenue team.
29/100
Instream Storage Structure, Dhanei
Visit of SD Expert, PMC to RI Laxmana Pali, RI Chirikipada and SDO, Dhanei during the visit to ISS Sanabargam today (24.9.2026). Updated them on the latest status of land acquisition and made discussion on re-demarcation of private land scheduled for 01.10.2026, and the Collector’s letter(letter no:619 dt:1.9.26) to the Tahasildar, Polasara regarding demarcation of Government land by deploying revenue team.
30/100
Instream Storage Structure, Dhanei
Visit of SD Expert, PMC to RI Laxmana Pali, RI Chirikipada and SDO, Dhanei during the visit to ISS Sanabargam today (24.9.2026). Updated them on the latest status of land acquisition and made discussion on re-demarcation of private land scheduled for 01.10.2026, and the Collector’s letter(letter no:619 dt:1.9.26) to the Tahasildar, Polasara regarding demarcation of Government land by deploying revenue team.
31/100
Instream Storage Structure, KansariGanda
24.09.26
32/100
Instream Storage Structure, KansariGanda
24.09.26
33/100
Instream Storage Structure, KansariGanda
24.09.26
34/100
Instream Storage Structure, KansariGanda
24.09.26
35/100
Instream Storage Structure, KansariGanda
22.09.26
36/100
Instream Storage Structure, KansariGanda
Mechanical Gate and Trestle fabrication work in progress
37/100
Instream Storage Structure, KansariGanda
11.09.26
38/100
Instream Storage Structure, KansariGanda
Demarcation Update – UDS pur Mauja
Date: 09.09.2026
Demarcation for UDS pur Mauja continued today in the presence of Sarapancha and the villagers. During re-demarcation, it was observed that certain government lands have been converted into private patta land on the ground.
As these latest ground-level changes are not yet reflected in revenue records/maps, such discrepancies surfaced during spot verification, carried out in the presence of the land holders.
As per standard practice, boundary pegs with red flags have been fixed at the demarcation points.
39/100
Instream Storage Structure, KansariGanda
Demarcation Update – UDS pur Mauja
Date: 09.09.2026
Demarcation for UDS pur Mauja continued today in the presence of Sarapancha and the villagers. During re-demarcation, it was observed that certain government lands have been converted into private patta land on the ground.
As these latest ground-level changes are not yet reflected in revenue records/maps, such discrepancies surfaced during spot verification, carried out in the presence of the land holders.
As per standard practice, boundary pegs with red flags have been fixed at the demarcation points.
40/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 23.09.2026
41/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 23.09.2026
42/100
Instream Storage Structure, Nandagaon
• Visited the ISS Nandagaon site with CME, QC exp in presence of site engineers. The work position of project site is as follows.
1.Basement slab & basement flooring PCC of control room building completed. No further work done since last one month.
2. No manpower for mechanical gate balance works.
3. Stone pitching work done for 300mtrs only on u/s right side & no further work is going on.
4. Wearing coat over the bridge slab haven’t taken off till now on 22.09.2026
43/100
Instream Storage Structure, Nandagaon
• Visited the ISS Nandagaon site with CME, QC exp in presence of site engineers. The work position of project site is as follows.
1.Basement slab & basement flooring PCC of control room building completed. No further work done since last one month.
2. No manpower for mechanical gate balance works.
3. Stone pitching work done for 300mtrs only on u/s right side & no further work is going on.
4. Wearing coat over the bridge slab haven’t taken off till now on 22.09.2026
44/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 22.09.2026
45/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 22.09.2026
46/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 21.09.2026
47/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 19.09.2026
48/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 19.09.2026
49/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 18.09.2026
50/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 18.09.2026
51/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 17.09.2026
52/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 17.09.2026
53/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 16.09.2026
54/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 16.09.2026
55/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 15.09.2026
56/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 15.09.2026
57/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 14.09.2026
58/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 14.09.2026
59/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 13.09.2026
60/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 13.09.2026
61/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 11.09.2026
62/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 11.09.2026
63/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.89/mm2 for 28 days) of D/S Flank wall, 7th lift at Block No-5 and M35A20 (Strength is 37.63/mm2 for 07 days) of Deck slab (Bay No-18) has done in presence of Client & PSS team.
64/100
Instream Storage Structure, Hamirpur
Visited by S.E, RID, A.E.E, A.E RID of Client & PSS team along with representative of EPC agency at site.
65/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Slab hand railing at Block No-4 done in presence of Client & PSS Team.
66/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Slab hand railing at Block No-4 is under progress in presence of Client & PSS Team.
67/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.620m.
68/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
69/100
Instream Storage Structure, Khalpal
Inspection by Dy. TL, Site Engineer Of PSS team along with EPC agency at site.
70/100
Instream Storage Structure, Near Village Basantpur across River Daya
CE, MKS, SE, Prachi division with departmental engineers along with PSS team visited the ISS work Site.
71/100
Instream Storage Structure, Kuakhai
CE ,MKS, SE,Prachi division with departmental engineers along with PSS team visited the work Site .
72/100
Instream Storage Structure, Kuakhai
Water level RL 12.9m.
73/100
Instream Storage Structure, Kuakhai
Water level RL 13.6m.
74/100
Instream Storage Structure, Kuakhai
Water level RL 14.25m.
75/100
Instream Storage Structure, Kushabhadra
Brick masonry work is under progress in parapet of O&M building.
76/100
Instream Storage Structure, Kushabhadra
Inspection of gate works & other ancillary mechanical works by Hydro-Mechanical Expert with MKS Team & Agency at the worksite.
77/100
Instream Storage Structure, Kushabhadra
O&M Building parapet wall bricks work is under progress.
78/100
Instream Storage Structure, Kushabhadra
Canal road Clearing & grubbing work progress.
79/100
Instream Storage Structure, Kushabhadra
DTL & Team is Discussing with the Agency regarding completion of .head room, constn. of parapet, septic tank & soak pit etc.
80/100
Instream Storage Structure, Kushabhadra
Inspection of O&M building work by MKS Team along with the Agency at the ISS site.
81/100
Instream Storage Structure, Kushabhadra
Cdu motor and gearbox installation work under progress.
82/100
Instream Storage Structure, Kushabhadra
Mechanical work center drive unit, motor, gearbox, ropeway, installation work is in progress.
83/100
Instream Storage Structure, Kushabhadra
Canal road Clearing & grubbing work progress.
84/100
Instream Storage Structure, Kushabhadra
O&M Building ground floor electrical chasing / chipping work inside the building is under progress.
85/100
Instream Storage Structure, Kushabhadra
Curing work going on.
86/100
Instream Storage Structure, Kushabhadra
O&M Building 1st floor brick work is under progress.
87/100
Instream Storage Structure, Kushabhadra
Canal road cleaning work is under progress.
88/100
Instream Storage Structure, Kushabhadra
Inspection of O&M building construction work by DTL & Team.
89/100
Instream Storage Structure, Kushabhadra
O&M Building 1st floor Lintel beam Beam with sunshade shuttering work is under progress.
90/100
Instream Storage Structure, Kushabhadra
Flood water level RL 12.70m.
91/100
Instream Storage Structure, Kushabhadra
Flood water level RL 13.10m.
92/100
Instream Storage Structure, Kushabhadra
O&M Building 1st floor brick work is under progress.
93/100
UGPL, Left Lower Suktel Canal Division
Tree plantation by CCE, SE, Dam division SE, Canal Division No.-I SE, RR division SE, SDO of DoWR, TLs of (PES & PSS) and MEIL Project manager at Left Command Pump House LSIP.
94/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.610m.
95/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.760m.
96/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of D/S Flank wall, 10th lift at Block No-5 done in presence of Client & PSS Team.
97/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flank wall, 10th lift at Block No-5 is under progress in presence of Client & PSS Team.
98/100
Instream Storage Structure, Hamirpur
Rope drum Hoist bottom block bracket welding work is in progress.
99/100
Instream Storage Structure, Hamirpur
Column Trestle No-25 bracing welding work is in progress.
100/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Deck slab (Bay No-18) done in presence of Client & PSS Team.
❮
❯