Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Integrated Barrage across river Kochila and across river Baitarini
BAITARANI -ISS Wing wall reinforcement is in progress-06.12.2025.
2/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
• CE, QA&QC, ACE,QA- BBSR, SE-QA, CTN, SE-K I Division, OCCL and PMC visited Choudhury gada and Tikhiri ISS project site and discussed with Project Manager of agency-06.12.2025
3/100
Instream Storage Structure, Dhanei
Slump cone test conducted at site in presence of Dept. officials, QA/QC expert and Site engineer PMC.
4/100
Instream Storage Structure, Dhanei
Visit of AEE, AE of Irr. Dept., AEE, AE of QC Dept., QA/QC expert along with site engineer PMC to the ISS Site. Inspected the Overall progress of work and O&M building ground floor roof slab concreting.
5/100
Instream Storage Structure, Dhanei
Visit of AEE, AE of Irr. Dept., AEE, AE of QC Dept., QA/QC expert along with site engineer PMC to the ISS Site. Inspected the Overall progress of work and O&M building ground floor roof slab concreting.
6/100
Instream Storage Structure, Budharaja
Shuttering & Mechanic work is in Progress at RHS Divide Wall, Hoist Gate Portion.
7/100
Instream Storage Structure, Budharaja
2nd Stage Shuttering (Gate Groove) Work is in Progress at Pier No:3.
8/100
Instream Storage Structure, Budharaja
De- Shuttering work is in Progress at Pier No.7 ,Hoist Gate Portion.
9/100
Instream Storage Structure, Budharaja
De-Shuttering work is in Progress at Pier No:6, Hoist Gate Portion.
10/100
Instream Storage Structure, Budharaja
De-Shuttering Work is in Progress at RHS D/S Flared Out Wall, 5th Step.
11/100
Instream Storage Structure, Budharaja
Curing work is in Progress at Pier No: 2, Hoist Gate Portion.
12/100
Instream Storage Structure Across Bheden near village Saida
LHS Abutment to LHS Divide wall between mid portion Deck slab staging de-shuttering work is going on .
13/100
Instream Storage Structure Across Bheden near village Saida
P-5 ,10th lift shuttering work is going on .
14/100
Instream Storage Structure, Kudabega
RHS us wing wall 5th lift casting work in progress
15/100
Instream Storage Structure, Kudabega
Slump 85mm of RHS us wing wall 5th lift
16/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Barrage gate Installation work is in progress at Span no - 21
17/100
Instream Storage Structure, Kudabega
Span 23 gate groove, service gate casting
18/100
Instream Storage Structure, Kudabega
2nd stage concreting. Span -23
19/100
Instream Storage Structure, Kudabega
Span 23 stoplog service gate groove, slump 80mm
20/100
Instream Storage Structure, Kudabega
Slump-85mm (span -16 bottom sill beam )
21/100
Instream Storage Structure, Kudabega
Buttom sill casting of span No-16
22/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Guide Fixing work is in progress at Span no - 14
23/100
Instream Storage Structure, Kudabega
Span 23 deshuttering and shuttering work
24/100
Instream Storage Structure, Kudabega
Span 18 deshuttering and shuttering work
25/100
Instream Storage Structure, Kudabega
Soil unloading work
26/100
Instream Storage Structure, Kudabega
RHS abutment 8th lift and us wing wall 5th lift shuttering
27/100
Instream Storage Structure, Kudabega
2nd stage concreting of pier No-19 L is going on
28/100
Instream Storage Structure, Kudabega
Slump 80mm span 20 of stoplog service gate groove
29/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Trestle's or Column's Installation work is in progress at Span no -20
30/100
Instream Storage Structure, Kopsinga
Pier no -19 Chipping work
31/100
Instream Storage Structure, Kopsinga
Pier 18 chipping work
32/100
Instream Storage Structure, Kopsinga
RHS Wing wall 2nd lift reinforcement cleaning
33/100
UGPL, Right Lower Suktel Canal Division
Jointing work is in progress for fixing of 1Ha outlet at village Charbahali in presence of DoWR Personnel & PMC team.
34/100
Instream Storage Structure across river Sapei near village Kinjirma
Casting completed of LHS pier no-3 6th lift.
35/100
Instream Storage Structure across river Sapei near village Kinjirma
T m 07 90mm
36/100
UGPL, Right Lower Suktel Canal Division
Primer painting work is in progress at Boundary inside wall of Pump House.
37/100
Instream Storage Structure across river Sapei near village Kinjirma
Casting work under progress of pier no-3 6th lift LHS(M25A20) in presence of dept. AEE sir and JE madam .
38/100
Instream Storage Structure across river Sapei near village Kinjirma
80mm,tm-6
39/100
Instream Storage Structure across river Sapei near village Kinjirma
80mm,tm-5
40/100
Instream Storage Structure across river Sapei near village Kinjirma
Casting of pier -3 6th lift
41/100
Instream Storage Structure across river Sapei near village Kinjirma
80mm,tm-4
42/100
Instream Storage Structure across river Sapei near village Kinjirma
90mm,tm-3 pier no-3 6th lift
43/100
Instream Storage Structure across river Sapei near village Kinjirma
Concreting under progress of building staff quarter and control rooms columns (M25A20) .
44/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump-90mm(M25A20), building staff quarter and control rooms column .
45/100
UGPL, Right Lower Suktel Canal Division
Inside slope wall portion plastering work is in progress of internal drain type-4 at Pump House.
46/100
Instream Storage Structure across river Sapei near village Kinjirma
90mm,tm-2
47/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump-90mm,tm-1(M25A20) LHS pier no-3 6th lift .
48/100
Instream Storage Structure, Khirasasan
Slump 80mm
49/100
Instream Storage Structure, Khirasasan
RHS D/S mud cleaning work under progress
50/100
Instream Storage Structure, Khirasasan
Pier 2 hoist portion shuttering work under progress.
51/100
Instream Storage Structure, Khirasasan
Abutment hoist portion shuttering work under progress.
52/100
Instream Storage Structure, Khirasasan
Sir, checked placing supporting bars and alignment of shuttering work in LHS d/s flared out 12th lift RL- 216.500 to 217.100 Now the area is ready for concrete casting M20 A20. So recommended for the purpose. Approved by AEE sir SID Sambalpur in presence of JE
53/100
UGPL, Left Lower Suktel Canal Division
HDPE 125mm Dia pipe jointing work is in progress from J-554 to Lo-40 at village Kusmel ,
54/100
UGPL, Left Lower Suktel Canal Division
Butt fusion jointing work is in progress for 200mm Dia HDPE pipe line from node J-251 to J-371 at Village Sargad.
55/100
UGPL, Left Lower Suktel Canal Division
Earth pit chamber making work is in progress at Pump House.
56/100
MMIP, Bankatira Barrage Project
Chief Engineer, Quality control, Superintending Engineer & PSS consultants inspected Barrage site on 04.12.2025.
57/100
Instream Storage Structure, Gudvella
Casting of wearing coat at cistern area from P7 to P9 with RL 147.85m to 148.00m is under progress through chute in the presence of Dept JE, site engineer of PMC and agency. Slump achieved 71mm on 05.12.2025
58/100
Instream Storage Structure, Gudvella
Casting of wearing coat at cistern area from P7 to P9 with RL 147.85m to 148.00m is under progress through chute in the presence of Dept JE, site engineer of PMC and agency. Slump achieved 71mm on 05.12.2025
59/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at Pier no.12 / mid right divide wall for 9th lift at U/S side and 10th lift at D/S side from RL-243.40m to RL-244.30m is in progress through concrete pump in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 83mm on 05.12.2025
60/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at Pier no.12 / mid right divide wall for 9th lift at U/S side and 10th lift at D/S side from RL-243.40m to RL-244.30m is in progress through concrete pump in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 83mm on 05.12.2025
61/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at U/S right flared out wall from sec.1-1 to sec.2-2 for 7th lift from RL-237.60m to RL-238.20m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 72mm on 05.12.2025
62/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at U/S right flared out wall from sec.1-1 to sec.2-2 for 7th lift from RL-237.60m to RL-238.20m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 72mm on 05.12.2025
63/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for total of 2nos. C.C block of size 6x1.5x0.6m at D/S left flared out wall i.e 1no. at sec.4-4 for 4th lift & 1no. from sec.5-5 to sec.6-6 for 5th lift of 0.6m hight upto RL-238.20m is in progress in presence of SDO JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 75mm on 05.12.2025
64/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for total of 2nos. C.C block of size 6x1.5x0.6m at D/S left flared out wall i.e 1no. at sec.4-4 for 4th lift & 1no. from sec.5-5 to sec.6-6 for 5th lift of 0.6m hight upto RL-238.20m is in progress in presence of SDO JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 75mm on 05.12.2025
65/100
Instream Storage Structure, Nandagaon
Trestle base plate channel drilling of dia 34mm under progress on 05.12.2025
66/100
Instream Storage Structure, Nandagaon
Gate no 5 both stop log gate and barrage bay gate centre guide erection work under progress on 05.12.2025
67/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M25A20 (Value 80 mm) of Middle pier slope portion done in presence of Client & PSS Team.
68/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of Middle pier slope portion is under progress in presence of Client & PSS Team.
69/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Curing of Abutment & Counter fort wall is under progress.
70/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of Divide wall, 4th lift is under progress.
71/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
De-Shuttering of Abutment & Counter fort wall, 2nd lift is under progress.
72/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M20A20 of LHS Gravity floor is under progress in presence of Client & PSS Team.
73/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M20A20 (Value 90 mm) of LHS Gravity floor done in presence of Client & PSS Team.
74/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning of RHS Raft area is under progress.
75/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS D/S Counter fort wall, 1st lift is under progress.
76/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS Divide wall, 2nd lift is under progress.
77/100
Instream Storage Structure, Jharbeda
Cleaning of reinforcement for Pier No-6 is under progress.
78/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for D/S Cut-off wall is under progress.
79/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Pier No-27, Pedestal at Block No-4 done in presence of Client & PSS Team.
80/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-27, Pedestal at Block No-4 is under progress in presence of Client & PSS Team.
81/100
Instream Storage Structure, Hamirpur
Slump testing M15A40 (Value 45 mm) of Flared out wall at Block No-5 done in presence of Client & PSS Team.
82/100
Instream Storage Structure, Hamirpur
Concreting M15A40 of Flared out wall at Block No-5 is under progress in presence of Client & PSS Team.
83/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-9, 4th lift at Block No-2 done in presence of Client & PSS Team.
84/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-9, 4th lift at Block No-2 is under progress in presence of Client & PSS Team.
85/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.54/mm2 for 28 days) of Pier No-31, 2nd lift and (Strength is 30.79/mm2 for 28 days) of Pier No-23, 8th lift and (Strength is 21.33/mm2 for 07 days) of Pier No-31, 6th lift and (Strength is 21.48/mm2 for 07 days) of Pier No-23, 11th lift has done in presence of Client & PSS team.
86/100
Instream Storage Structure, Hamirpur
The stop log groove centre guide erection work at Pier No-34 is currently in progress.
87/100
Instream Storage Structure, Hamirpur
Shuttering of RHS U/S Flared out wall at Block No-5 is under progress.
88/100
Instream Storage Structure, Hamirpur
Curing of Piers is under progress.
89/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-31, 8th lift at Block No-5 is under progress.
90/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-17, 10th lift at Block No-3 is under progress.
91/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-17, 10th lift at Block No-3 is under progress.
92/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-18, 10th lift at Block No-4 is under progress.
93/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-22, 8th lift at Block No-4 is under progress.
94/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-10, 5th lift at Block No-2 is under progress.
95/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-29, 13th lift at Block No-4 is under progress.
96/100
Instream Storage Structure, Khalpal
Samal Lab mix design trial mix conducted at site laboratory of M15A40, 28 days cube (Strength 36.22 N/mm²) in presence of PSS Team.
97/100
Barrage across river Turi & Guntat
Sieve analysis of Fine aggregates conducted at Turi Barrage Site.
98/100
Integrated Barrage across river Kochila and across river Baitarini
BAITARANI -ISS Wing wall distribution binding work in progress
99/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Upstream Bamboo coffer dam sand packing work in progress in Chaudhurygada iss project- 05.12.2025
100/100
Instream Storage Structure, Budharaja
Slump Value: 60mm.