GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Mahulpali
Walk way railing primer paint is in progress. on 12.09.2024
2/100
Instream Storage Structure, Mahulpali
Curing of Control room building ground floor slab is in progress on 12.09.2024
3/100
Instream Storage Structure, Mahulpali
Visit to the site with SD Expert on Cast of control room building ground floor with maintaining of SHE manual procedure on 12.09.2024
4/100
Instream Storage Structure, Mahulpali
U/S gate middle rubber seal fitting is in progress on 12.09.2024
5/100
Instream Storage Structure, Mahulpali
D/S view of ISS ISS Mahulpali Barrage on 12.09.2024
6/100
Instream Storage Structure, Mahulpali
U/S view of ISS ISS Mahulpali Barrage on 12.09.2024
7/100
Instream Storage Structure, Mahulpali
U/S gate side guide Roller Fitting is in progress on 11.09.2024
8/100
Instream Storage Structure, Mahulpali
Bar binding and shuttering for the cast of control room building ground floor slab RCC checked by Ong Dam division SDO ,JE ,AE and PMC site Engineer on 11.09.2024
9/100
Instream Storage Structure, Mahulpali
Cast of concrete of control room building ground floor slab RCC M25,A20 grade, Slump value as tested 74 mm on 11.09.2024
10/100
Instream Storage Structure, Mahulpali
Cast of concrete of control room building ground floor slab RCC M25,A20 grade, Slump value as tested 74 mm on 11.09.2024
11/100
Instream Storage Structure, Mahulpali
D/S view of ISS ISS Mahulpali Barrage on 11.09.2024
12/100
Instream Storage Structure, Mahulpali
U/S view of ISS ISS Mahulpali Barrage on 11.09.2024
13/100
Instream Storage Structure, Mahulpali
U/s gate Side guide Roller Fitting is in progress on 10.09.2024
14/100
Instream Storage Structure, Mahulpali
D/S view of ISS ISS Mahulpali Barrage on 10.09.2024
15/100
Instream Storage Structure, Mahulpali
U/S view of ISS ISS Mahulpali Barrage on 10.09.2024
16/100
Instream Storage Structure, Mahulpali
Service gate Side guide Roller Fitting is in progress on 09.09.2024
17/100
Instream Storage Structure, Mahulpali
D/S view of ISS ISS Mahulpali Barrage on 09.09.2024
18/100
Instream Storage Structure, Mahulpali
U/S view of ISS ISS Mahulpali Barrage on 09.09.2024
19/100
Instream Storage Structure, Dholapita
Watchman shed compound wall plastering work is in progress.
20/100
Instream Storage Structure, Mahulpali
D/S view of ISS ISS Mahulpali Barrage on 08.09.2024
21/100
Instream Storage Structure, Mahulpali
U/S view of ISS ISS Mahulpali Barrage on 08.09.2024
22/100
Instream Storage Structure, Mahulpali
D/S view of ISS ISS Mahulpali Barrage on 07.09.2024
23/100
Instream Storage Structure, Mahulpali
U/S view of ISS ISS Mahulpali Barrage 07.09.2024
24/100
Instream Storage Structure, KansariGanda
CC blocks curing continuing at site.
25/100
Instream Storage Structure, Mahulpali
D/S view of ISS ISS Mahulpali Barrage on 06.09.2024
26/100
Instream Storage Structure, Mahulpali
U/S view of ISS ISS Mahulpali Barrage on 06.09.2024
27/100
Instream Storage Structure, KansariGanda
CC blocks curing continuing at site.
28/100
Instream Storage Structure, Mahulpali
Formwork for the cast of control room building ground floor wall beam and roof slab on 05.09.2024
29/100
Instream Storage Structure, KansariGanda
Cube cast at site in presence of QA/QC Expert & Site Engineer of PMC.
30/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site in presence of QA/QC Expert & Site Engineer of PMC.
31/100
Instream Storage Structure, KansariGanda
Cube cast at site in presence of QA/QC Expert & Site Engineer of PMC.
32/100
Instream Storage Structure, Mahulpali
Service gate Side guide Roller Fitting is in progress 05.09.2024
33/100
Instream Storage Structure, Mahulpali
D/S view of ISS ISS Mahulpali Barrage on 05.09.2024
34/100
Instream Storage Structure, Mahulpali
U/S view of ISS ISS Mahulpali Barrage on 05.09.2024
35/100
Instream Storage Structure, Dholapita
Watchman shed compound wall plastering work is in progress.
36/100
Instream Storage Structure, Jakameripalli
Today Sri Ramesh Mishra, Hydro Mechanical Expert & Sri Manoranjan Biswal Electrical & Automation Expert from PMU, Bhubaneswar visited the ISS Jakhamaripali. Hydro Mechanical Expert has inspected working of gate lifting motors, drum, wire ropes, lifting beam, mono rail, stop log gates etc. Conducted dry test for all 8 no. Of gates. The Electrical & Automation Expert has inspected all electrical installations including DG set and compliance to the observations of electrical inspector. Addl. CE, RB Basin, Berhampur Dy. Team Leader and his team, SE, Mechanical Division, Berhampur, SDO of department with his team present during the inspection. The agency has made all necessary arrangements for the inspection.
37/100
Instream Storage Structure, Jakameripalli
Today Sri Ramesh Mishra, Hydro Mechanical Expert & Sri Manoranjan Biswal Electrical & Automation Expert from PMU, Bhubaneswar visited the ISS Jakhamaripali. Hydro Mechanical Expert has inspected working of gate lifting motors, drum, wire ropes, lifting beam, mono rail, stop log gates etc. Conducted dry test for all 8 no. Of gates. The Electrical & Automation Expert has inspected all electrical installations including DG set and compliance to the observations of electrical inspector. Addl. CE, RB Basin, Berhampur Dy. Team Leader and his team, SE, Mechanical Division, Berhampur, SDO of department with his team present during the inspection. The agency has made all necessary arrangements for the inspection.
38/100
Instream Storage Structure, Jakameripalli
Today Sri Ramesh Mishra, Hydro Mechanical Expert & Sri Manoranjan Biswal Electrical & Automation Expert from PMU, Bhubaneswar visited the ISS Jakhamaripali. Hydro Mechanical Expert has inspected working of gate lifting motors, drum, wire ropes, lifting beam, mono rail, stop log gates etc. Conducted dry test for all 8 no. Of gates. The Electrical & Automation Expert has inspected all electrical installations including DG set and compliance to the observations of electrical inspector. Addl. CE, RB Basin, Berhampur Dy. Team Leader and his team, SE, Mechanical Division, Berhampur, SDO of department with his team present during the inspection. The agency has made all necessary arrangements for the inspection.
39/100
Instream Storage Structure, Jakameripalli
Today Sri Ramesh Mishra, Hydro Mechanical Expert & Sri Manoranjan Biswal Electrical & Automation Expert from PMU, Bhubaneswar visited the ISS Jakhamaripali. Hydro Mechanical Expert has inspected working of gate lifting motors, drum, wire ropes, lifting beam, mono rail, stop log gates etc. Conducted dry test for all 8 no. Of gates. The Electrical & Automation Expert has inspected all electrical installations including DG set and compliance to the observations of electrical inspector. Addl. CE, RB Basin, Berhampur Dy. Team Leader and his team, SE, Mechanical Division, Berhampur, SDO of department with his team present during the inspection. The agency has made all necessary arrangements for the inspection.
40/100
Instream Storage Structure, Jakameripalli
Today Sri Ramesh Mishra, Hydro Mechanical Expert & Sri Manoranjan Biswal Electrical & Automation Expert from PMU, Bhubaneswar visited the ISS Jakhamaripali. Hydro Mechanical Expert has inspected working of gate lifting motors, drum, wire ropes, lifting beam, mono rail, stop log gates etc. Conducted dry test for all 8 no. Of gates. The Electrical & Automation Expert has inspected all electrical installations including DG set and compliance to the observations of electrical inspector. Addl. CE, RB Basin, Berhampur Dy. Team Leader and his team, SE, Mechanical Division, Berhampur, SDO of department with his team present during the inspection. The agency has made all necessary arrangements for the inspection.
41/100
Instream Storage Structure, Jakameripalli
Today Sri Ramesh Mishra, Hydro Mechanical Expert & Sri Manoranjan Biswal Electrical & Automation Expert from PMU, Bhubaneswar visited the ISS Jakhamaripali. Hydro Mechanical Expert has inspected working of gate lifting motors, drum, wire ropes, lifting beam, mono rail, stop log gates etc. Conducted dry test for all 8 no. Of gates. The Electrical & Automation Expert has inspected all electrical installations including DG set and compliance to the observations of electrical inspector. Addl. CE, RB Basin, Berhampur Dy. Team Leader and his team, SE, Mechanical Division, Berhampur, SDO of department with his team present during the inspection. The agency has made all necessary arrangements for the inspection.
42/100
Instream Storage Structure, Dholapita
Watchman shed compound wall plastering work is in progress.
43/100
Instream Storage Structure, KansariGanda
7 days cube strength test for M20A20 grade concrete (CC Blocks) conducted at field laboratory in presence of Irr. Engg. Expert & Site Engineer of PMC. The test results are found satisfactory.
44/100
Instream Storage Structure, KansariGanda
CC blocks curing continuing at site.
45/100
Instream Storage Structure, KansariGanda
Cube cast at site in presence of Irr. Engg. Expert & Site Engineer of PMC.
46/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site in presence of Irr. Engg. Expert & Site Engineer of PMC.
47/100
Instream Storage Structure, KansariGanda
CC blocks casting is in progress in presence of Irr. Engg. Expert & Site Engineer of PMC.
48/100
Instream Storage Structure, Chhatamakhana
Site condition of ISS Chhatamakhana Barrage on 15.09.2024
49/100
Instream Storage Structure, Chhatamakhana
Site condition of ISS Chhatamakhana Barrage on 14.09.2024
50/100
Instream Storage Structure, Chhatamakhana
Site condition of ISS Chhatamakhana Barrage on 13.09.2024
51/100
Instream Storage Structure, Chhatamakhana
Site condition of ISS Chhatamakhana Barrage on 12.09.2024
52/100
Instream Storage Structure, Chhatamakhana
Site condition of ISS Chhatamakhana Barrage on 11.09.2024
53/100
Instream Storage Structure, Chhatamakhana
Site condition of ISS Chhatamakhana Barrage on 10.09.2024
54/100
Instream Storage Structure, Chhatamakhana
Site condition of ISS Chhatamakhana Barrage on 09.09.2024
55/100
Instream Storage Structure, Chhatamakhana
Site condition of ISS Chhatamakhana Barrage on 08.09.2024
56/100
Instream Storage Structure, Chhatamakhana
Site condition of ISS Chhatamakhana Barrage on 07.09.2024
57/100
Instream Storage Structure, Chhatamakhana
Site condition of ISS Chhatamakhana Barrage on 06.09.2024
58/100
Instream Storage Structure, Chhatamakhana
Site condition of ISS Chhatamakhana Barrage on 05.09.2024
59/100
Instream Storage Structure, Julko
U/S view of ISS Julko Barrage on 15.09.2024
60/100
Instream Storage Structure, Julko
D/S view of ISS Julko Barrage on 15.09.2024
61/100
Instream Storage Structure, Julko
U/S view of ISS Julko Barrage on 14.09.2024
62/100
Instream Storage Structure, Julko
D/S view of ISS Julko Barrage on 14.09.2024
63/100
Instream Storage Structure, Julko
U/S view of ISS Julko Barrage on 13.09.2024
64/100
Instream Storage Structure, Julko
D/S view of ISS Julko Barrage on 13.09.2024
65/100
Instream Storage Structure, Julko
fitting Barricade of plants is in progress on 12.09.2024
66/100
Instream Storage Structure, Julko
U/S view of ISS Julko Barrage on 12.09.2024
67/100
Instream Storage Structure, Julko
D/S view of ISS Julko Barrage on 12.09.2024
68/100
Instream Storage Structure, Julko
fitting Barricade of plants is in progress on 11.09.2024
69/100
Instream Storage Structure, Julko
U/S view of ISS Julko Barrage on 11.09.2024
70/100
Instream Storage Structure, Julko
D/S view of ISS Julko Barrage on 11.09.2024
71/100
Instream Storage Structure, Julko
fitting Barricade of plants is in progress on 10.09.2024
72/100
Instream Storage Structure, Julko
U/S view of ISS Julko Barrage on 10.09.2024
73/100
Instream Storage Structure, Julko
D/S view of ISS Julko Barrage on 10.09.2024
74/100
Instream Storage Structure, Julko
U/S view of ISS Julko Barrage on 09.09.2024
75/100
Instream Storage Structure, Julko
D/S view of ISS Julko Barrage on 09.09.2024
76/100
Instream Storage Structure, Julko
U/S view of ISS Julko Barrage on 08.09.2024
77/100
Instream Storage Structure, Julko
D/S view of ISS Julko Barrage on 08.09.2024
78/100
Instream Storage Structure, Julko
U/S view of ISS Julko Barrage on 07.09.2024
79/100
Instream Storage Structure, Julko
D/S view of ISS Julko Barrage on 07.09.2024
80/100
Instream Storage Structure, Julko
U/S view of ISS Julko Barrage on 06.09.2024
81/100
Instream Storage Structure, Julko
D/S view of ISS Julko Barrage on 06.09.2024
82/100
Instream Storage Structure, Julko
U/S view of ISS Julko Barrage on 05.09.2024
83/100
Instream Storage Structure, Julko
D/S view of ISS Julko Barrage on 05.09.2024
84/100
Instream Storage Structure, Khirasasan
Flow of water is straight. Flow can be seen at RL-211.500 Against design crest Level-210.900
85/100
Instream Storage Structure, Khirasasan
No work in site
86/100
Instream Storage Structure, Gochara
Double levelling carry work is going on from KINJIRIMA to Gochhara site
87/100
Instream Storage Structure across river Sapei near village Kinjirma
Double levelling carry work is going on from KINJIRIMA to Gochhara site
88/100
Instream Storage Structure, Gochara
Double levelling carry work is on progress from ISS Kinjirma site to Gochhara site
89/100
Instream Storage Structure, Kopsinga
Casting of LHS d/s wing wall with CF1 to CF5 (RL 225.800 to 225.300) is in under progress with presence of Department, PMC site engineer.
90/100
Instream Storage Structure, Kopsinga
Cube casting
91/100
Instream Storage Structure, Kopsinga
Slump test conducted, value is 75mm
92/100
Instream Storage Structure, Kopsinga
Casting of LHS d/s wing wall with CF1 to CF5 (RL 225.800 to 225.300) is in under progress with presence of Department, PMC site engineer.
93/100
Instream Storage Structure, Kopsinga
Slump test conducted, value is 80MM
94/100
Instream Storage Structure, Kopsinga
Reinforced, Shuttering and spacings checked by presence of Department AEE ISS KOPSINGHA
95/100
Instream Storage Structure, Kopsinga
Reinforced, Shuttering and spacings checked by presence of Department AEE ISS KOPSINGHA
96/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Horizontal girder's platform work is in progress for Sluice barrage gate no - 1
97/100
Instream Storage Structure, Budharaja
No activity at site
98/100
Instream Storage Structure, Kudabega
28days cube testing DS Wing wall 6th lift left side(M25A20) and left side US wing wall 5th lift(M25A20)
99/100
Instream Storage Structure, Kudabega
28days cube testing DS Wing wall 6th lift left side(M25A20) and left side US wing wall 5th lift(M25A20)
100/100
Instream Storage Structure, Kudabega
ISS Kudabaga - N-box work in progress for Sluice service gate no -19

Enter Login Details

Forgot Password ?