1/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Steel cutting, bending & binding works is in progress at Choudhary gada iss project-30.01.2026
2/100
Integrated Barrage across river Kochila and across river Baitarini
D/s divide wall shuttering work in progress-30.01.2026
3/100
Instream Storage Structure across river Sapei near village Kinjirma
L.H.s Pier no02 to double Pier slab staging work of under progress
4/100
Instream Storage Structure across river Sapei near village Kinjirma
L.H.s Pier no02 to double Pier slab staging work of under progress
5/100
Instream Storage Structure, Gochara
QCE, E&A Expert & Geologist of PMC visited ISS Gochhara. Stone pitching in LHS guide bund in progress.
6/100
Instream Storage Structure, Gochara
QCE, E&A Expert & Geologist of PMC visited ISS Gochhara. Stone pitching in LHS guide bund in progress.
7/100
Instream Storage Structure, Gochara
LHS U/S Forest land demarcation work is done in presence of forest department, Revenue Inspector & Department of JE.
8/100
Instream Storage Structure, Gochara
LHS D/S Stone pitching work in progress.
9/100
Instream Storage Structure, Gochara
Staff quarter stair case shuttering work on progress .
10/100
Instream Storage Structure, Gochara
Staff quarter stair case shuttering work on progress .
11/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S of river.
12/100
Instream Storage Structure, Khirasasan
QCE, E&A Expert & Geologist of PMC visited ISS Kirasasan. Advised to excavate foundation of RHS u/s flared out wall up to desired level at the earliest.
13/100
Instream Storage Structure, Khirasasan
RHS C F WING WALL 11 TH LIFT SHUTTERING WORK IS UNDER PROGRESS
14/100
Instream Storage Structure, Khirasasan
RHS d/s abutment hoist portion shuttering work is under progress.
15/100
Instream Storage Structure, Khirasasan
RHS d/s divide wall Hoist portion shuttering work has completed and ready for casting.
16/100
Instream Storage Structure, Khirasasan
RHS d/s Flared out wall 15th lift de shuttering work is under progress.
17/100
Instream Storage Structure, Khirasasan
LHS U/S FLARED OUT WALL 17 TH LIFT SHUTTERING WORK IS UNDER PROGRESS. (RL 219.500 - 220.100)
18/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
19/100
Instream Storage Structure, Khirasasan
Slump 90mm
20/100
Instream Storage Structure, Khirasasan
checked placing supporting bars and alignment of shuttering work in RHS D/S flared out 15th step RL- 219.500 to 220.100 Now the area is ready for concrete casting M20 A20. So recommended for the purpose. Approved by AEE sir SID Sambalpur in presence of JE
21/100
Instream Storage Structure, Khirasasan
RHS D/S FLARED OUT WALL 15 TH LIFT SHUTTERING WORK IS UNDER PROGRESS
22/100
Instream Storage Structure, Khirasasan
LHS U/S FLARED OUT WALL 16 TH LIFT SHUTTERING WORK IS UNDER PROGRESS
23/100
Instream Storage Structure, Khirasasan
RHS divide wall hoist portion shuttering work under progress
24/100
Instream Storage Structure, Khirasasan
RHS C F WING WALL 11 TH LIFT SHUTTERING WORK IS UNDER PROGRESS
25/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
26/100
Instream Storage Structure, Budharaja
Slump Value: 65mm.
27/100
Instream Storage Structure, Budharaja
checked placing and positioning of Supporting bars and alignment of shuttering work in RHS U/S Flared-Out wall, 16th step. RL: 215.300 to 215.900. Now the area is ready for concrete casting M20 A20. So recommend Sired for the purpose. Approved by AEE sir SID Sambalpur in the presence of JE sir.
28/100
Instream Storage Structure, Budharaja
Advised to excavate LHS d/s sluice bay channel early.
29/100
Instream Storage Structure, Budharaja
QCE, E&A Expert and Geologist visited ISS Budharaja. Witnessed erection of service gate in between P6 to P7.
30/100
Instream Storage Structure, Budharaja
QCE, E&A Expert and Geologist visited ISS Budharaja. Witnessed erection of service gate in between P6 to P7.
31/100
Instream Storage Structure, Budharaja
Shuttering Work is in Progress at LHS U/S Flared-Out Wall, 18th Step. RL: 215.900 to 216.500.
32/100
Instream Storage Structure, Budharaja
Shuttering Work is in Progress at RHS U/S Flared-Out Wall, 16th Step. RL: 215.300 to 215.900.
33/100
Instream Storage Structure, Budharaja
De-Shuttering in 18th step & Shuttering Work is in Progress at RHS D/S Flared-Out Wall, 19th Step. RL: 216.500 to 217.100.
34/100
Instream Storage Structure, Kudabega
Slump 85mm of DS flared wall.
35/100
Instream Storage Structure, Kudabega
Slump 80mm of LHS US flared wall
36/100
Instream Storage Structure, Kudabega
Slump 85mm
37/100
Instream Storage Structure, Kudabega
Flared wall LHS U/S section 7/7 15th step M20A20 casting work in progress
38/100
Instream Storage Structure, Kudabega
Barrage bay-3 span no-08 p-08 & p-07 for stoplog & service gate groove 2nd stage 6th lift M30A20 casting work in progress
39/100
Instream Storage Structure, Kudabega
Slump 85mm
40/100
Instream Storage Structure, Kudabega
Barrage bay-3 span no-06 p-06 & p-05 for stoplog & service gate groove 2nd stage 4th lift M30A20 casting work in progress
41/100
Instream Storage Structure, Kudabega
Span no-01hand railing Post deshuttering work in progress
42/100
Instream Storage Structure, Kudabega
Flared wall LHS D/S section 2/2 15th step Deshuttering work in progress
43/100
Instream Storage Structure, Kudabega
Flared wall LHS U/S section 6/6 15th step Deshuttering work in progress
44/100
Instream Storage Structure, Kudabega
Span no-07 gate groove shuttering work in progress
45/100
Instream Storage Structure, Kudabega
Span no-04 gate groove deshuttering & Shuttering work in progress
46/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Under-Sluice gate no - 4 Installation work is in progress
47/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Hoist bridge's 32th platforms assembly work is in progress
48/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Monorail girder's joints work is in progress
49/100
Instream Storage Structure Across Bheden near village Saida
QCE,E&A Expert & Geologist of PMC visited ISS SAIDA .
50/100
Instream Storage Structure Across Bheden near village Saida
Shuttering work progress in LHS d/s Flared out wall step-7
51/100
Instream Storage Structure Across Bheden near village Saida
Shuttering work progress in RHS d/s flank wall 3rd lift
52/100
Instream Storage Structure Across Bheden near village Saida
De-shuttering work progress in bay no-5 deck slab
53/100
Instream Storage Structure Across Bheden near village Saida
RHS D/S Flank wall 5th lift Reinforcement bar binding & shuttering work is going on .
54/100
Instream Storage Structure Across Bheden near village Saida
P-2 ,Hoist portion shuttering work is going on .
55/100
Instream Storage Structure Across Bheden near village Saida
P-4 to P-5 between mid portion Deck slab de-shuttering work is in progress .
56/100
Instream Storage Structure, Kopsinga
Slump 85 mm
57/100
Instream Storage Structure, Kopsinga
RHS U/S divide wall d2 with breast wall 8th lift casting work under progress
58/100
Instream Storage Structure, Kopsinga
RHS D/S 2nd lift casting under progress M20 A20
59/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Trestle's or Column's Installation work is in progress at Span no - 15
60/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Trestle's or Column's work is in progress
61/100
Instream Storage Structure, Kopsinga
Slump-95mm
62/100
Instream Storage Structure, Kopsinga
Slump-95mm Flank wall
63/100
Instream Storage Structure, Kopsinga
Slump-95mm
64/100
Instream Storage Structure, Kopsinga
RHS D/S Wing wall Casting under progress..Dept..AEE sir
65/100
Instream Storage Structure, Kopsinga
Slump-90mm mm
66/100
Instream Storage Structure, Kopsinga
Flared wall casting under progress
67/100
Instream Storage Structure, Kopsinga
Cube test..
68/100
Instream Storage Structure, Kopsinga
Slump-80mm flared wall
69/100
Instream Storage Structure, Gudvella
Cast of concrete 11th lift PCC M20A20 grade at right side D/s flared out wall from sec 1-1 to 4-4 with RL 154.60m to 155.20m is under progress in the presence of Dept JE, site engineers of PMC n agency foreman. The slump test value is 70mm on 29.01.2026
70/100
Instream Storage Structure, Gudvella
Cast of concrete 11th lift PCC M20A20 grade at right side D/s flared out wall from sec 1-1 to 4-4 with RL 154.60m to 155.20m is under progress in the presence of Dept JE, site engineers of PMC n agency foreman. The slump test value is 70mm on 29.01.2026
71/100
Instream Storage Structure, Gudvella
Casting of concrete at A2 u/s flared out wall of grade M20A20 10th lift PCC from RL 154.00 m to 154.60 m(section 2-2 to 4-4) is under progress through chute in the presence of Dept JE, PMC n agency site engineers. The slump test value is 70mm on 29.01.2026
72/100
Instream Storage Structure, Gudvella
Casting of concrete at A2 u/s flared out wall of grade M20A20 10th lift PCC from RL 154.00 m to 154.60 m(section 2-2 to 4-4) is under progress through chute in the presence of Dept JE, PMC n agency site engineers. The slump test value is 70mm on 29.01.2026
73/100
Instream Storage Structure, Gudvella
Cast of concrete 6th lift RCC M25A20 grade at right side d/s flank wall including return wall from RL155.05 m to 156.30m is under progress through pump in the presence of Dept JE, site engineers of PMC n agency. The slump test value is 88mm on 29.01.2026
74/100
Instream Storage Structure, Gudvella
Cast of concrete 6th lift RCC M25A20 grade at right side d/s flank wall including return wall from RL155.05 m to 156.30m is under progress through pump in the presence of Dept JE, site engineers of PMC n agency. The slump test value is 88mm on 29.01.2026
75/100
Instream Storage Structure, Gudvella
Column assembly work under progress on 29.01.2026
76/100
Instream Storage Structure, Gudvella
Roller track and guide installation work at barrage bay no 8 is under progress on 29.01.2026
77/100
Instream Storage Structure, Gudvella
Roller track and guide installation work at barrage bay no 8 is under progress on 29.01.2026
78/100
Instream Storage Structure, Gudvella
• 1. Reinforcement work at right side D/s flank wall for 6th lift RCC is under progress.
2. Shuttering work at right side d/s flared out wall is under progress.
3. Reinforcement work at right side D/s wing wall for 5th lift RCC is under progress on 29.01.2026
79/100
Instream Storage Structure, Gudvella
Erection of pylon at deck slab no -10 in under progress on 29.01.2026
80/100
Instream Storage Structure, Gudvella
• 1. Shuttering work at right side u/s flared out wall is under progress.
2. Reinforcement work at right side u/s flank wall for 8th lift RCC is under progress on 29.01.2026
81/100
Instream Storage Structure, Gudvella
Reinforcement work of plinth beam at building area is under progress on 29.01.2026
82/100
Instream Storage Structure, Gudvella
Reinforcement & shuttering work at Abutment A2 for 8th lift RCC is under progress on 29.01.2026
83/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at right abutment along with CF wall from double CF wall CJ to U/S EJ for 4th lift at U/S floor and 5th lift at D/S portion of under sluice bay area from RL-237.75m to RL-239.05m is in progress through concrete pump in presence of PM, EPC agency,Site Engineers of PMC & Site Engineer of EPC agency. The slump test value is 90mm on 29.01.2026
84/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at right abutment along with CF wall from double CF wall CJ to U/S EJ for 4th lift at U/S floor and 5th lift at D/S portion of under sluice bay area from RL-237.75m to RL-239.05m is in progress through concrete pump in presence of PM, EPC agency,Site Engineers of PMC & Site Engineer of EPC agency. The slump test value is 90mm on 29.01.2026
85/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.5 for 6th lift and pier no.6 for 8th lift of bay no.6 is in progress in presence of PM,EPC agency,Site Engineers of PMC & Site Engineer of EPC agency. The slump test value is 74mm on 29.01.2026
86/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.5 for 6th lift and pier no.6 for 8th lift of bay no.6 is in progress in presence of PM,EPC agency,Site Engineers of PMC & Site Engineer of EPC agency. The slump test value is 74mm on 29.01.2026
87/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of 2nos. C.C blocks at U/S right flared out wall i.e. 1no. at sec.5-5 for 8th lift upto RL-240.60m& 1no. at sec.4-4 for 9th lift upto RL-241.20m is in progress in presence of PM, EPC agency,Site Engineers of PMC & Site Engineer of EPC agency. The slump test value is 73mm on 29.01.2026
88/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of 2nos. C.C blocks at U/S right flared out wall i.e. 1no. at sec.5-5 for 8th lift upto RL-240.60m& 1no. at sec.4-4 for 9th lift upto RL-241.20m is in progress in presence of PM, EPC agency,Site Engineers of PMC & Site Engineer of EPC agency. The slump test value is 73mm on 29.01.2026
89/100
Instream Storage Structure, Nandagaon
• 4.Checked the area of right abutment along with CF walls with following activities in presence of PM, EPC agency, Site Engineers of PMC & Site Engineer of EPC agency:-
(i).Checked the reinforcement in binding, tying n spacing of both vertical main & horiz. dist. bars of right abutment along with CF walls from double CF wall CJ to U/S EJ for 4th lift at U/S floor and 5th lift at D/S portion of stilling basin area from RL-237.75m to RL-239.05m completed.
(ii).Rigid n smooth shuttering with 75mm clear cover using cover blocks of 75mm are done.
(iii).Application of bitumen paint at CJ vertical existing concrete surface of double CF walls are completed.
(iv).Placing of expansion joint material along the EJ between U/S right flank wall & abutment wall is done as per approved drawing n design.
(v).The concrete surface is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with RCC M25A20 grade on 29.01.2026
90/100
Instream Storage Structure, Nandagaon
• 3.Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay No.6 of Pier No. 5 for 6th lift and pier no.6 for 8th lift has been checked and found correct by HM Expert of PMC during his site visit on dt.21.01.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through air water jetting and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 29.01.2026
91/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.5 for 8th lift of bay no.5 is in progress in presence of PM,EPC agency,Site Engineers of PMC & Site Engineer of EPC agency. The slump test value is 77mm on 29.01.2026
92/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.5 for 8th lift of bay no.5 is in progress in presence of PM,EPC agency,Site Engineers of PMC & Site Engineer of EPC agency. The slump test value is 77mm on 29.01.2026
93/100
Instream Storage Structure, Nandagaon
• 2. The casting of CC blocks at following area have been checked in presence of PM, EPC agency, Site Engineers of PMC & EPC Agency:
(i) 2Nos. CC block at U/S right Flared out wall i.e 1no. of size 3.6x1.5x0.6m from at sec.5-5 for 8th lift upto RL-240.60m and 1no. of size 6.0x1.5x0.6m at sec.4-4 for 9th lift upto RL-241.20m is completed.
(ii) Filling of inverted filter materials covering with LDPE paper adjacent to each CC block in earth side are done before placement.
(iii) Application of 2 coat bitumen paint at cj's concrete surface is done.
(iv) Area is ready and passed by SE KID, Bh. Patna to place concrete with PCC M20A20 grade on 29.01.2026
94/100
Instream Storage Structure, Nandagaon
• 1.Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay No.5 of Pier No. 5 for 8th lift has been checked and found correct by HM Expert of PMC during his site visit on dt.21.01.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i) Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii) The area is cleaned properly through air water jetting and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 29.01.2026
95/100
Instream Storage Structure, Nandagaon
Gate no 10 both barrage bay gate and stoplog gate sil beam water level, spirit level and all measurements checked as per approved drawing. Hence ready for concrete on 29.01.2026
96/100
Instream Storage Structure, Nandagaon
Gate no 10 both barrage bay gate and stoplog gate sil beam water level, spirit level and all measurements checked as per approved drawing. Hence ready for concrete on 29.01.2026
97/100
Instream Storage Structure, Nandagaon
Gate no 10 both barrage bay gate and stoplog gate sil beam water level, spirit level and all measurements checked as per approved drawing. Hence ready for concrete on 29.01.2026
98/100
Instream Storage Structure, Nandagaon
Gate no 10 both barrage bay gate and stoplog gate sil beam water level, spirit level and all measurements checked as per approved drawing. Hence ready for concrete on 29.01.2026
99/100
Instream Storage Structure, Nandagaon
Shuttering for CC blocks at U/S right flared out wall, Block-1 is in progress on 29.01.2026
100/100
Instream Storage Structure, Nandagaon
Shuttering for CC blocks at D/S left flared out wall, Block-1 is in progress on 29.01.2026
❮
❯