1/100
Instream Storage Structure, Gudvella
Paint work at walkway railing is under progress at site on 02.08.2026
2/100
Instream Storage Structure, Gudvella
Placement of filler material is under progress at building tiles on 02.08.2026
3/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 02.08.2026
4/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 02.08.2026
5/100
Instream Storage Structure, Gudvella
Placement of building tiles is under progress at site on 01.08.2026
6/100
Instream Storage Structure, Gudvella
Primer painting work is under progress at site on 01.08.2026
7/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 01.08.2026
8/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 01.08.2026
9/100
Instream Storage Structure, Nandagaon
Concrete casting with M20A20 grade of CC block at U/S left flared out wall is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 84mm on 02.08.2026
10/100
Instream Storage Structure, Nandagaon
Concrete casting with M20A20 grade of CC block at U/S left flared out wall is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 84mm on 02.08.2026
11/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 21nos. Precast RCC railing is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 86mm on 02.08.2026
12/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 21nos. Precast RCC railing is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 86mm on 02.08.2026
13/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for precast railing is in progress on 02.08.2026
14/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.94/mm2 for 28 days) of D/S Flank wall, 2nd lift at Block No-5 and (Strength is 31.21/mm2 for 28 days) of Pier No-26, 14th lift and (Strength is 21.63/mm2 for 07 days) of U/S Flank wall, 10th lift at Block No-5 has done in presence of Client & PSS team.
15/100
Instream Storage Structure, Nandagaon
Shuttering for CC block at U/S left flared out wall is under progress on 02.08.2026
16/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 21nos. Precast RCC railing is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency.. The slump test value is 84mm on 01.08.2026
17/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 21nos. Precast RCC railing is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency.. The slump test value is 84mm on 01.08.2026
18/100
Instream Storage Structure, Nandagaon
Trestle base plate welding is under progress on 01.08.2026
19/100
Instream Storage Structure, Nandagaon
Monorail walkway railing work is under progress on 01.08.2026
20/100
Instream Storage Structure, Nandagaon
Fixing of precast railing is in progress at deck slab no. 13 ON 01.08.2026
21/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for Precast railing is in progress on 01.08.2026
22/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.220m.
23/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at Telkoi site.
24/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-52 done in presence of Client & PSS Team.
25/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-52 is under progress in presence of Client & PSS Team.
26/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of D/S (A2) Flank wall, 5th lift at Block No-5 done in presence of Client & PSS Team.
27/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S (A2) Flank wall, 5th lift at Block No-5 is under progress in presence of Client & PSS Team.
28/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
29/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall, 12th lift at Block No-5 is under progress.
30/100
Instream Storage Structure, Hamirpur
C.D.U to R.D.U shaft fixing work is in progress of hoist bridge platform.
31/100
Instream Storage Structure, Hamirpur
Gantry girder's 1st stage embedded plate fixing and welding work is in progress.
32/100
Instream Storage Structure, Hamirpur
Column Trestle welding work is in progress.
33/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.410m.
34/100
Instream Storage Structure, Khalpal
Binding of reinforcement for Girder No-55 is under progress.
35/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 58.53m.
36/100
Instream Storage Structure, KansariGanda
Site condition of ISS Kansariganda on 31.07.26.
37/100
Instream Storage Structure, KansariGanda
Silt content of sand checked and found 2.7% in presence of Irr. Engg. Expert & Site Engineer of PMC.
38/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site in presence of Irr. Engg. Expert & Site Engineer of PMC.
39/100
Instream Storage Structure, KansariGanda
Girder no - 41 concrete pouring started in presence of Irr. Engg. Expert & Site Engineer of PMC.
40/100
Instream Storage Structure, KansariGanda
Sir,
Honrable MLA, Chatrapur along with SE, BeID,Bam with team made a public meeting in villages Raulibandha and Bahalpur regarding Land aquisition for Feeder Channel and Spill channel of the Project ISS KANSARIGANDA.
41/100
Instream Storage Structure, KansariGanda
Sir,
Honrable MLA, Chatrapur along with SE, BeID,Bam with team made a public meeting in villages Raulibandha and Bahalpur regarding Land aquisition for Feeder Channel and Spill channel of the Project ISS KANSARIGANDA.
42/100
Instream Storage Structure, KansariGanda
Sir,
Honrable MLA, Chatrapur along with SE, BeID,Bam with team made a public meeting in villages Raulibandha and Bahalpur regarding Land aquisition for Feeder Channel and Spill channel of the Project ISS KANSARIGANDA.
43/100
Instream Storage Structure, KansariGanda
Sir,
Honrable MLA, Chatrapur along with SE, BeID,Bam with team made a public meeting in villages Raulibandha and Bahalpur regarding Land aquisition for Feeder Channel and Spill channel of the Project ISS KANSARIGANDA.
44/100
Instream Storage Structure, KansariGanda
Site condition of ISS Kansariganda on 02.08.26.
45/100
Instream Storage Structure, KansariGanda
Site condition of ISS Kansariganda on 02.08.26.
46/100
Instream Storage Structure, KansariGanda
Site condition of ISS Kansariganda on 02.08.26.
47/100
Instream Storage Structure, Gudvella
Placement of building tiles is under progress at site on 31.07.2026
48/100
Instream Storage Structure, Gudvella
• 1.Primer painting is under progress at mechanical yard.
2.Grinding and finishing work is underprogress at site on 31.07.2026
49/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 31.07.2026
50/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 31.07.2026
51/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 21nos. Precast RCC railing is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 85mm on 31.07.2026
52/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 21nos. Precast RCC railing is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 85mm on 31.07.2026
53/100
Instream Storage Structure, Nandagaon
Monorail girder alignment work is under progress on 31.07.2026
54/100
Instream Storage Structure, Nandagaon
Monorail walkway railing work is under progress on 31.07.2026
55/100
Instream Storage Structure, Nandagaon
Stone pitching work at U/S right embankment in progress on 31.07.2026
56/100
Instream Storage Structure, Nandagaon
Fixing of precast railing is in progress at deck slab no. 13 on 31.07.2026
57/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of U/S Flank wall, 11th lift at Block No-5 done in presence of Client & PSS Team.
58/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of U/S Flank wall, 11th lift at Block No-5 is under progress in presence of Client & PSS Team.
59/100
Instream Storage Structure, Hamirpur
Observed of moisture content test in presence of Client & PSS team along with EPC agency.
60/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 42.08/mm2 for 28 days) of Gantry Girder No-43 and (Strength is 37.63/mm2 for 07 days) of Gantry Girder No-49 and M15A40 (Strength is 13.18/mm2 for 07 days) of U/S Flared wall, 12th lift at Block No-5 and M25A20 (Strength is 30.87/mm2 for 28 days) of U/S Flank wall, 7th lift at Block No-5 has done in presence of Client & PSS team.
61/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
62/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flank wall, 5th lift at Block No-5 is under progress.
63/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall, 12th lift at Block No-5 is under progress.
64/100
Instream Storage Structure, Hamirpur
R.D.U assembly set No-23 gear box fixing work is in progress.
65/100
Instream Storage Structure, Hamirpur
Trestle No-18 base plate & bracing welding work is in progress.
66/100
Instream Storage Structure, Hamirpur
Column Trestle No- -19 bracing fixing work is in progress.
67/100
UGPL, Right Lower Suktel Canal Division
Reservoir water level at RL 199.701m
68/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.710m.
69/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Present status of river Samakoi at Santeibhanja site.
70/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at Telkoi site.
71/100
Instream Storage Structure, Khalpal
Checking for binding of reinforcement of End Girder No-38 in presence of Client & PSS team.
72/100
Instream Storage Structure, Khalpal
Testing of Compressive M25A20 (Strength is 34.00/mm2 for 28 days) of LHS D/S Divide wall, 3rd lift and (Strength is 34.01/mm2 for 28 days) of LHS Double Pier No-18 (Starter) has done in presence of Client & PSS team.
73/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 58.4m.
74/100
Instream Storage Structure, Gudvella
Primer painting is under progress at staircase at mechanical yard on 30.07.2026
75/100
Instream Storage Structure, Gudvella
Placement of building tiles is under progress at site on 30.07.2026
76/100
Instream Storage Structure, Gudvella
Grinding and finishing work is under progress at site on 30.07.2026
77/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 30.07.2026
78/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 30.07.2026
79/100
Instream Storage Structure, Nandagaon
SDO ISS Nandagaon visit the site with DTL, CME, QC exp, site engineering of PMC & site engineering of EPC agency today flood level of river is 237.0m against bed level 234.0m yesterday flood level of river was 238.80m on 30.07.2026
80/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of precast railing is in progress in presence of DTL, Tel basin Bhawanipatna, CME & QAC Expert of PMC, SDO ISS Nandagaon, PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 80mm on 30.07.2026
81/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of precast railing is in progress in presence of DTL, Tel basin Bhawanipatna, CME & QAC Expert of PMC, SDO ISS Nandagaon, PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 80mm on 30.07.2026
82/100
Instream Storage Structure, Nandagaon
Monorail walkway railing work is under progress on 30.07.2026
83/100
Instream Storage Structure, Nandagaon
1st NOS of monorail girder erection work is under progress on 30.07.2026
84/100
Instream Storage Structure, Nandagaon
Hoist bridge alignment work is under progress over 1st under sluice gate on 30.07.2026
85/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for precast railing is in progress on 30.07.2026
86/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-51 done in presence of Client & PSS Team.
87/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-51 is under progress in presence of Client & PSS Team.
88/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 42.23/mm2 for 28 days) of Gantry Girder No-42 and M15A40 (Strength is 20.50/mm2 for 28 days) of U/S Flared wall, 10th lift at Block No-5 has done in presence of Client & PSS team.
89/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
90/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for D/S Flank wall, 5th lift at Block No-5 is under progress.
91/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for U/S Flank wall, 12th lift at Block No-5 is under progress.
92/100
Instream Storage Structure, Hamirpur
Trestle No-18 bracing welding work is in progress.
93/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 180.060m.
94/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Present status of river Samakoi at Santeibhanja site.
95/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at Telkoi site.
96/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 58m.
97/100
UGPL, Right Lower Suktel Canal Division
Reservoir water level at RL 199.731m
98/100
UGPL, Right Lower Suktel Canal Division
Reservoir water level at RL 201.570m
99/100
Instream Storage Structure, Gudvella
Placement of filler material is under progress before placing of building tiles on 29.07.2026
100/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 29.07.2026
❮
❯