1/100
UGPL, Left Lower Suktel Canal Division
OMS verification work is in progress of OMS LO 11B, LM-1, at village Chhatabahal.
2/100
UGPL, Left Lower Suktel Canal Division
OMS verification work is in progress of OMS LO 12B, LM-1, at village Chhatabahal.
3/100
Instream Storage Structure, Gudvella
• Today the Irrigation Engineer Expert and Quality Control Expert from PMC visited the ISS Gudvella site.
During their visit, the Department JE, PMC Site Engineer and Agency Engineer were present.
1. The experts inspected the overall site conditions and reviewed the progress of the ongoing works. They instructed the agency to complete all remaining works at the earliest. It was also informed that the dry test and load test will be conducted after completion of all pending works on 08.07.2026
4/100
Instream Storage Structure, Gudvella
Transformer fitt-up work is under progress at electrical yard on 08.07.2026
5/100
Instream Storage Structure, Gudvella
Welding and grinding work is under progress at site on 08.07.2026
6/100
Instream Storage Structure, Gudvella
Electrical work is in progress on 08.07.2026
7/100
Instream Storage Structure, Gudvella
Plastering work is under progress at building area on 08.07.2026
8/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 08.07.2026
9/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 08.07.2026
10/100
Instream Storage Structure, Nandagaon
3 numbers of Monorail girder erection work is completed on 08.07.2026
11/100
Instream Storage Structure, Nandagaon
Hoist bridge erection work is under progress on Barrage bay gate no 4 on 08.07.2026
12/100
Instream Storage Structure, Nandagaon
Barrage bay gate no 5 erection work is under progress on 08.07.2026
13/100
Instream Storage Structure, Nandagaon
Monorail walkway erection work is under progress on 08.07.2026
14/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Bracing Support Fixing work at Choudhurygada ISS in Progress.
15/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
6th lift Steel placing and shuttering work of Pier No..9 at Choudhurygada ISS in progress.
16/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Bracing Support fixing and installation work of Barrage Bay Gate at Choudhurygada ISS in progress
17/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Slump Test for RCC work of RHS Undersluice End Pter 3rd lift of Choudhurygada ISS Project in progress.
18/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
RHS Under Sluice end pier 3rd lift RCC work of Choudhurygada ISS project in progress.
19/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
LHS Divide Wall cut off de-shuttering work of Choudhutygada ISS in Progress
20/100
Instream Storage Structure, Khalpal
Testing of Compressive M20A20 (Strength is 29.63/mm2 for 28 days) of Barrage Bay No-2 Gravity floor and M25A20 (Strength is 34.70/mm2 for 28 days) of LHS U/S Divide wall, 3rd lift has done in presence of Client & PSS team.
21/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 55.8 m.
22/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.4m.
23/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-44 done in presence of Client & PSS Team.
24/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-44 is under progress in presence of Client & PSS Team.
25/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-17, 15th lift done in presence of Client & PSS Team.
26/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-17, 15th lift is under progress in presence of Client & PSS Team.
27/100
Instream Storage Structure, Hamirpur
Testing of Compressive M15A40 (Strength is 20.41/mm2 for 28 days) of Flared out wall PCC and M30A20 (Strength is 38.00/mm2 for 28 days) of Groove 2nd stage, 1st , 4th & 10th lift (Bay No-7, 8 & 23) has done in presence of Client & PSS team.
28/100
Instream Storage Structure, Hamirpur
R.D.U fixing work is in progress of hoist bridge platform No-4.
29/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
30/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall at Block No-5 is under progress.
31/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-25, 14th lift at Block No-4 is under progress.
32/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpu site water level RL 180.050 m.
33/100
Instream Storage Structure, Gudvella
• Today the HM Expert and SHE Expert visited ISS Gudvella. During their visit, the Department JE, PMC Site Engineers and Agency Engineers were present.
1. The HM Expert reviewed all mechanical works and instructed the agency to complete all remaining finishing works at the earliest and to complete electricity connection work also earlier on 07.07.2026
34/100
Instream Storage Structure, Gudvella
Electrical work is in progress on 07.07.2026
35/100
Instream Storage Structure, Gudvella
Plastering work is under progress at building area on 07.07.2026
36/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 07.07.2026
37/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 07.07.2026
38/100
Instream Storage Structure, Nandagaon
Stiffener alignment under progress on 07.07.2026
39/100
Instream Storage Structure, Nandagaon
Monorail walkway alignment under progress on 07.07.2026
40/100
Instream Storage Structure, Nandagaon
Shuttering for CC block at D/S right flared out wall is in progress on 07.07.2026
41/100
Instream Storage Structure, Nandagaon
Erection work has been stopped due to heavy rainfall on 07.07.2026
42/100
UGPL, Left Lower Suktel Canal Division
OMS verification work is in progress of OMS LO 6A, LM-1, at village Kushmel.
43/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.01/mm2 for 28 days) of D/S Flank Cut-off wall, 2nd lift at Block No-1 and (Strength is 30.91/mm2 for 28 days) of Pier No-3, 10th lift and M35A20 (Strength is 42.30/mm2 for 28 days) of Gantry Girder No-34 and M30A20 (Strength is 37.63/mm2 for 28 days) of Groove 2nd stage, 3rd lift (Bay No-8) has done in presence of Client & PSS team.
44/100
Instream Storage Structure, Hamirpur
Chequred plate marking and cutting work is in progress for hoist bridge platform.
45/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.875 m.
46/100
Instream Storage Structure, Khalpal
Testing of Compressive M20A20 (Strength is 29.60/mm2 for 28 days) of Barrage Bay No-2 Gravity floor has done in presence of Client & PSS team.
47/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 55.8 m.
48/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.2m.
49/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-18, 16th lift done in presence of Client & PSS Team.
50/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-18, 16th lift is under progress in presence of Client & PSS Team.
51/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.48/mm2 for 07 days) of Flank wall Raft and (Strength is 30.94/mm2 for 28 days) of Abutment (A1), 7th lift and M35A20 (Strength is 37.33/mm2 for 07 days) of Gantry Girder No-41 and M15A40 (Strength is 20.44/mm2 for 28 days) of Staff building foundation PCC and M30A20 (Strength is 37.78/mm2 for 28 days) of Groove 2nd stage (Bay No-8) has done in presence of Client & PSS team.
52/100
Instream Storage Structure, Hamirpur
C.D.U frame drilling work is in progress.
53/100
Instream Storage Structure, Hamirpur
C.D.U frame welding work is in progress.
54/100
Instream Storage Structure, Hamirpur
R.D.U fit-up work is in progress.
55/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Gantry Girder is under progress.
56/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-25, 14th lift is under progress.
57/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-17, 16th lift is under progress.
58/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall, 3rd lift at Block No-5 is under progress.
59/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall, 8th lift at Block No-5 is under progress.
60/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Present status of river Samakoi at Santeibhanja site.
61/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at Telkoi site.
62/100
Instream Storage Structure, Khalpal
Testing of Compressive M20A20 (Strength is 29.75/mm2 for 28 days) of Barrage Bay No-2 Gravity floor has done in presence of Client & PSS team.
63/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 56.15m.
64/100
Instream Storage Structure across river Sapei near village Kinjirma
View showing flow of river from D/S Side (D/S of River) .
* Flow direction is straight flow is seen at RL- 207.250 against crest level RL- 206.250 .
* Water is flowing 1m above the crest level .
65/100
Instream Storage Structure across river Sapei near village Kinjirma
U/S view
No ancillary work today.
66/100
Instream Storage Structure across river Sapei near village Kinjirma
U/S site view
No ancillary work today.
67/100
Instream Storage Structure across river Sapei near village Kinjirma
U/S site view
No ancillary work .
68/100
Instream Storage Structure, Kopsinga
Work is stop due to heavy rain fall ISS Kopsingha site
Water level -215.700 against crest level-215.100
69/100
Instream Storage Structure, Kopsinga
Double storied building slab shuttering work under progress
70/100
Instream Storage Structure, Kopsinga
Double storied building column Reinforcement with shuttering work under progress
71/100
Instream Storage Structure, Kopsinga
Water level -215.600
against crest level-215.100
72/100
Instream Storage Structure, Kopsinga
Double storied building FIRST FLOOR Roof slab shuttering work is under progress
73/100
Instream Storage Structure, Kopsinga
Control building column reinforcement with shuttering work is under progress
74/100
Instream Storage Structure, Kopsinga
Double storied building column reinforcement with shuttering work under progress
75/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Railling fixing work is in progress of Hoist-bridge
76/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Bracket fixing work is in progress of Barrage gates
77/100
Instream Storage Structure, Kopsinga
Double storied building Roof beam with slab shuttering work under progress
78/100
Instream Storage Structure, Kopsinga
Double stored building roof beam with slab shuttering work under progress
79/100
Instream Storage Structure, Kopsinga
Control building brick work under progress
80/100
Instream Storage Structure, Kopsinga
SS Kopsingha - Chakkar plate fixing work is in progress of Hoist-bridge
81/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Bracket fixing work is in progress of Barrage gates
82/100
Instream Storage Structure, Kudabega
View of the river from D/S. Water level R/L -206.980
83/100
Instream Storage Structure, Kudabega
Binding of steel of control room at Belaigarh
84/100
Instream Storage Structure, Kudabega
Tree demarcation of road at Bilaigarh
85/100
Instream Storage Structure, Kudabega
Stone Boulder pitching of us afflux bund
86/100
Instream Storage Structure, Kudabega
Water level 206.830m
87/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Top Guide fixing work is in progress of Barrage gates
88/100
Instream Storage Structure, Kudabega
Rod binding work of control room Building in progress
89/100
Instream Storage Structure, Kudabega
Stone Boulder packing of us afflux bund, left side
90/100
Instream Storage Structure, Kudabega
Stone pitching of left side Afflux bund
91/100
Instream Storage Structure, Kudabega
Steel binding work in progress of controll room Building
92/100
Instream Storage Structure, Kudabega
RHS Site control building slab shuttering & reinforcement work in progress
93/100
Instream Storage Structure, Kudabega
Slump 75mm
94/100
Instream Storage Structure, Kudabega
Slump 80mm
95/100
Instream Storage Structure, Kudabega
barrage bay-01 & 02 D/S & U/S wearing coat casting work in progress
96/100
Instream Storage Structure, Gudvella
Erection of stoplog gate is under progress at site on 06.07.2026
97/100
Instream Storage Structure, Gudvella
Plastering work is under progress at building area on 06.07.2026
98/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 06.07.2026
99/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 06.07.2026
100/100
Instream Storage Structure, Nandagaon
No activity due to rainfall on 06.07.2026
❮
❯