GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door & angle fixing work is in progress OCS No:- 2305090-C02A near village Atasingha in presence of PMC team and L&T staff.
2/100
UGPL, Right Lower Suktel Canal Division
Fire fighting system ground floor 900mm height outside wall plastering work is in progress at Pump House.
3/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for Laying of 125mm Dia HDPE pipe in between node from J-625 to LO- 222,LM-11 at village Kandajhuri in presence of PMC team.
4/100
UGPL, Left Lower Suktel Canal Division
1hecter Outlet extension work is in progress at OMS point LO 318B, Z-7023, LM-16 near village Sargad.
5/100
UGPL, Left Lower Suktel Canal Division
Internal Drainage - 2 wall shuttering bord fixing work is in progress of Pump House visiting by DoWR AEE, JE, PMC team and MEIL staff.
6/100
Instream Storage Structure, Gudvella
Erection of pylon at deck slab no -9 is under progress on 12.01.2026
7/100
Instream Storage Structure, Gudvella
Reinforcement work at right side D/s wing wall for 4th lift RCC on 12.01.2026
8/100
Instream Storage Structure, Gudvella
• 1. Shuttering work work at right side u/s flank wall including return wall for 4th lift RCC 2. Shuttering work at right side u/s wing wall for 7th lift RCC 3. Shuttering work at right side u/s flard out wall for 1st lift PCC on 12.01.2026
9/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade for 6nos. Pedestals at pier no.13 from RL-245.40m to RL-245.70m is in progress in presence of Site Engineers of PMC & Site Engineer of EPC agency.. The slump test value is 86mm on 12.01.2026
10/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade for 6nos. Pedestals at pier no.13 from RL-245.40m to RL-245.70m is in progress in presence of Site Engineers of PMC & Site Engineer of EPC agency.. The slump test value is 86mm on 12.01.2026
11/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade for 6nos. Pedestals at pier no.13 from RL-245.40m to RL-245.70m is in progress in presence of Site Engineers of PMC & Site Engineer of EPC agency.. The slump test value is 86mm on 12.01.2026
12/100
Instream Storage Structure, Nandagaon
• 2. (i) The Area of 6nos. pedestals at Pier No.13 from RL-245.40m to RL-245.70m have been checked in presence of Site Engineers of PMC & Site Engineer of EPC Agency. (ii) Reinforcement binding, tying & placing in proper position of 6nos. pedestals of size 650x500x300mm each with provision of Type-A mesh bars are completed. (iii) Rigid & smooth shuttering of 6nos. Pedestals are completed. (iv) The area is cleaned properly through air water jetting and passed by SE, KID, Bh.Patna for placing with RCC M25A20 grade. (v) Grooves of sizes 320mmx200mmx6mm for fixing of Elastomeric bearing pad may be executed using wooden plates of required dimensions on 12.01.2026
13/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade for 6nos. Pedestals at pier no.12 from RL-245.40m to RL-245.70m is in progress in presence of Site Engineers of PMC & Site Engineer of EPC agency. The slump test value is 84mm on 12.01.2026
14/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade for 6nos. Pedestals at pier no.12 from RL-245.40m to RL-245.70m is in progress in presence of Site Engineers of PMC & Site Engineer of EPC agency. The slump test value is 84mm on 12.01.2026
15/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade for 6nos. Pedestals at pier no.12 from RL-245.40m to RL-245.70m is in progress in presence of Site Engineers of PMC & Site Engineer of EPC agency. The slump test value is 84mm on 12.01.2026
16/100
Instream Storage Structure, Nandagaon
• 1. (i) The Area of 6nos. pedestals at Pier No.12 from RL-245.40m to RL-245.70m have been checked in presence of Site Engineers of PMC & Site Engineer of EPC Agency. (ii) Reinforcement binding, tying & placing in proper position of 6nos. pedestals of size 650x500x300mm each with provision of Type-A mesh bars are completed. (iii) Rigid & smooth shuttering of 6nos. Pedestals are completed. (iv) The area is cleaned properly through air water jetting and passed by SE, KID, Bh.Patna for placing with RCC M25A20 grade. (v) Grooves of sizes 320mmx200mmx6mm for fixing of Elastomeric bearing pad may be executed using wooden plates of required dimensions on 12.01.2026
17/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering at U/S right flank wall Block-2 is in progress on 12.01.2026
18/100
Instream Storage Structure, Nandagaon
Monorail supporting beam welding under progress on 12.01.2026
19/100
Instream Storage Structure, Nandagaon
Monorail walkway fit-up and welding work is in progress on 12.01.2026
20/100
Instream Storage Structure, Nandagaon
Reinforcement binding, Shuttering & curing at right abutment Block-2 is in progress on 12.01.2026
21/100
Instream Storage Structure, Nandagaon
De-Shuttering & Shuttering for 2nd stage concrete at pier no.3,bay-4, Block-1 is in progress on 12.01.2026
22/100
Instream Storage Structure, Kuakhai
Casting of M30A20 at left side counterfort wall from RL 8.65m to 10.05m is in progress.
23/100
Instream Storage Structure, Nandagaon
Reinforcement binding & curing at D/S right flank wall Block-2 is in progress on 12.01.2026
24/100
Instream Storage Structure, Nandagaon
De-watering is in progress at D/S right flared out wall foundation, Block-2 is in progress on 12.01.2026
25/100
Instream Storage Structure, KansariGanda
Curing continuing at site.
26/100
Instream Storage Structure, KansariGanda
Curing continuing at site.
27/100
Instream Storage Structure, KansariGanda
Curing continuing at site.
28/100
Instream Storage Structure, KansariGanda
Curing continuing at site.
29/100
Instream Storage Structure, Kuakhai
Preparation for PCC at left side U/s flank wall raft portion.
30/100
Instream Storage Structure, Kuakhai
Reinforcement binding at pier no.3 in progress.
31/100
Instream Storage Structure, Kuakhai
Ongoing reinforcement binding at pier no.7A.
32/100
Instream Storage Structure, Kuakhai
Pier no.7A first stage embedded parts welding and dowal bar welding in progress.
33/100
Instream Storage Structure, Kushabhadra
Ongoing Shuttering at right D/S flank wall & return wall.
34/100
Instream Storage Structure, Dhanei
Visit of QA/QC Expert along with Site Engineer to the ISS Site. Inspected the overall progress of work and like, 1) O & M building 1st floor brick work. 2) preparation for gate work erection. 3) Dewatering and cleaning at stilling basin.
35/100
Instream Storage Structure, Dhanei
Visit of QA/QC Expert along with Site Engineer to the ISS Site. Inspected the overall progress of work and like, 1) O & M building 1st floor brick work. 2) preparation for gate work erection. 3) Dewatering and cleaning at stilling basin.
36/100
Instream Storage Structure, Dhanei
Visit of QA/QC Expert along with Site Engineer to the ISS Site. Inspected the overall progress of work and like, 1) O & M building 1st floor brick work. 2) preparation for gate work erection. 3) Dewatering and cleaning at stilling basin.
37/100
Instream Storage Structure, Dhanei
Visit of QA/QC Expert along with Site Engineer to the ISS Site. Inspected the overall progress of work and like, 1) O & M building 1st floor brick work. 2) preparation for gate work erection. 3) Dewatering and cleaning at stilling basin.
38/100
Instream Storage Structure, Dhanei
Visit of QA/QC Expert along with Site Engineer to the ISS Site. Inspected the overall progress of work and like, 1) O & M building 1st floor brick work. 2) preparation for gate work erection. 3) Dewatering and cleaning at stilling basin.
39/100
Instream Storage Structure, Kushabhadra
Reinforcement binding of columns for O&M building is in progress.
40/100
Instream Storage Structure, Kushabhadra
Pier no.2 Stoplog gate groove second stage concreting work in progress.
41/100
Instream Storage Structure, Kushabhadra
Casting of CC M20A20 in Left U/S Flared out wall CC Block (sec 2-2 to 4-4) from RL-12.5m to 13.1m in progress.
42/100
Instream Storage Structure, Kushabhadra
28 days cube test for CCM2OA20 done at field laboratory of the ISS.
43/100
Instream Storage Structure, Kushabhadra
Left D/S Flared out wall balance cut-off area excavation work in progress.
44/100
Instream Storage Structure, Kushabhadra
Left U/S flared out wall CC Block area preparation for concreting.
45/100
Instream Storage Structure, Kushabhadra
O&M building column stirrup binding work in progress.
46/100
Instream Storage Structure, Kushabhadra
28 days cube test for CCM25A20 done at field laboratory of the ISS.
47/100
Instream Storage Structure, Kushabhadra
Inspection of left d/s flared out wall cutoff Area by PSS Team.
48/100
Instream Storage Structure, Kushabhadra
Casting of CC M20A20 in Right D/S Flared out wall (sec 3-3 to 4-4) from RL 10.10m to 10.70m in progress.
49/100
Instream Storage Structure, Kushabhadra
Shuttering work at left u/s flared out wall in progress.
50/100
Instream Storage Structure, Kushabhadra
O&M building column shuttering and stirrup binding work in progress.
51/100
Instream Storage Structure, Kushabhadra
Left D/S Flared out wall cutoff reinforcement and shuttering work in progress.
52/100
Instream Storage Structure, Kushabhadra
Soil compaction test conducted at Right U/S counter fort & flank wall area.
53/100
Instream Storage Structure, Kushabhadra
7 days cube testing for CCM20A20 & 28 days cube testing for CCM20A20 done at field laboratory of the ISS.
54/100
Instream Storage Structure, Kushabhadra
General Manager, OCCL visited the ISS site.
55/100
Instream Storage Structure, Kushabhadra
7 days cube testing for CCM20A20 & 28 days cube testing for CCM25A20 done at field laboratory of the ISS.
56/100
Instream Storage Structure, Kushabhadra
Right D/S Flank Wall and return Wall Deshuttering work in progress.
57/100
Instream Storage Structure, Kushabhadra
Right U/S CC Block area Excavation & Mud cleaning for CC Block filter.
58/100
Instream Storage Structure, Kushabhadra
Right U/S Flared out wall CC Block shuttering work in progress.
59/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
As per request of RFI, the area is inspected by SDO QA & QC Jagatsinghpur,JE kdp irr. Dvn and PMC site engineers-12.01.2026
60/100
Instream Storage Structure, KansariGanda
Curing continuing at site.
61/100
Instream Storage Structure, KansariGanda
Curing continuing at site.
62/100
Instream Storage Structure, KansariGanda
Curing continuing at site.
63/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site.
64/100
Integrated Barrage across river Kochila and across river Baitarini
PMC MBBS chandikhol visited Kochila-Baitarani ISS project today. Discussion held with Agency on different issues which impedes the progress of the project-13.01.2026
65/100
Instream Storage Structure, KansariGanda
Visit of CE QA BBSR together with ACE QA South BAM, ACE RB Basin, SE BeID, SE QA BAM & EE Design, AEE, AE of Department, Irigation Eng. Expert, QA/QC Expert along with Site Engineers of PMC as well as Agency's Staffs were present at site. Inspected the overall progress of site and like, 1.Left Side Abutment Counter fort Wall Zone 4 to 6 Concreting with M25A20, 2.CC Block Casting with M20A20, 3.Necessary Arrangement is being made for testing of Test Pile No 1 pertaining to Right Barrage Bay Portion, 4.Diaphragm Walls Cage Reinforcement Binding, 5.Mechanical Fabrication work of various components.
66/100
Instream Storage Structure, KansariGanda
Visit of CE QA BBSR together with ACE QA South BAM, ACE RB Basin, SE BeID, SE QA BAM & EE Design, AEE, AE of Department, Irigation Eng. Expert, QA/QC Expert along with Site Engineers of PMC as well as Agency's Staffs were present at site. Inspected the overall progress of site and like, 1.Left Side Abutment Counter fort Wall Zone 4 to 6 Concreting with M25A20, 2.CC Block Casting with M20A20, 3.Necessary Arrangement is being made for testing of Test Pile No 1 pertaining to Right Barrage Bay Portion, 4.Diaphragm Walls Cage Reinforcement Binding, 5.Mechanical Fabrication work of various components.
67/100
Instream Storage Structure, KansariGanda
Visit of CE QA BBSR together with ACE QA South BAM, ACE RB Basin, SE BeID, SE QA BAM & EE Design, AEE, AE of Department, Irigation Eng. Expert, QA/QC Expert along with Site Engineers of PMC as well as Agency's Staffs were present at site. Inspected the overall progress of site and like, 1.Left Side Abutment Counter fort Wall Zone 4 to 6 Concreting with M25A20, 2.CC Block Casting with M20A20, 3.Necessary Arrangement is being made for testing of Test Pile No 1 pertaining to Right Barrage Bay Portion, 4.Diaphragm Walls Cage Reinforcement Binding, 5.Mechanical Fabrication work of various components.
68/100
Instream Storage Structure, KansariGanda
Visit of CE QA BBSR together with ACE QA South BAM, ACE RB Basin, SE BeID, SE QA BAM & EE Design, AEE, AE of Department, Irigation Eng. Expert, QA/QC Expert along with Site Engineers of PMC as well as Agency's Staffs were present at site. Inspected the overall progress of site and like, 1.Left Side Abutment Counter fort Wall Zone 4 to 6 Concreting with M25A20, 2.CC Block Casting with M20A20, 3.Necessary Arrangement is being made for testing of Test Pile No 1 pertaining to Right Barrage Bay Portion, 4.Diaphragm Walls Cage Reinforcement Binding, 5.Mechanical Fabrication work of various components.
69/100
Integrated Barrage across river Kochila and across river Baitarini
M25 Grade 7days Compressive strength test Conducted for R/s Wing wall and Counter fort wall at Baitarani ISS Site laboratory in presence of PMC and representatives of Agency QC&QA Engineer-12.01.2026
70/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site in presence of AEE, AE of dept., Irrigation Eng. Expert along with Site Engineers PMC. Curing continuing at site.
71/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site in presence of AEE, AE of dept., Irrigation Eng. Expert along with Site Engineers PMC. Curing continuing at site.
72/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of dept., Irrigation Eng. Expert along with Site Engineers PMC to the ISS site. Inspected the overall progress of site and like, 1.Left Side Abutment Counter fort Wall Reinforcement Binding 2.CC Block Casting 3.Dummy Pile for Test Pile No 2 (under sluice location) digging 4.Necessary Arrangement is being made for testing of Test Pile No 1 pertaining to Right Barrage Bay Portion 5.Fish Pass Pier 5th lift Concreting with M25A20 6.Diaphragm Walls Cage Reinforcement Binding 7.Mechanical Fabrication work of various components.
73/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of dept., Irrigation Eng. Expert along with Site Engineers PMC to the ISS site. Inspected the overall progress of site and like, 1.Left Side Abutment Counter fort Wall Reinforcement Binding 2.CC Block Casting 3.Dummy Pile for Test Pile No 2 (under sluice location) digging 4.Necessary Arrangement is being made for testing of Test Pile No 1 pertaining to Right Barrage Bay Portion 5.Fish Pass Pier 5th lift Concreting with M25A20 6.Diaphragm Walls Cage Reinforcement Binding 7.Mechanical Fabrication work of various components.
74/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of dept., Irrigation Eng. Expert along with Site Engineers PMC to the ISS site. Inspected the overall progress of site and like, 1.Left Side Abutment Counter fort Wall Reinforcement Binding 2.CC Block Casting 3.Dummy Pile for Test Pile No 2 (under sluice location) digging 4.Necessary Arrangement is being made for testing of Test Pile No 1 pertaining to Right Barrage Bay Portion 5.Fish Pass Pier 5th lift Concreting with M25A20 6.Diaphragm Walls Cage Reinforcement Binding 7.Mechanical Fabrication work of various components.
75/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of dept., Irrigation Eng. Expert along with Site Engineers PMC to the ISS site. Inspected the overall progress of site and like, 1.Left Side Abutment Counter fort Wall Reinforcement Binding 2.CC Block Casting 3.Dummy Pile for Test Pile No 2 (under sluice location) digging 4.Necessary Arrangement is being made for testing of Test Pile No 1 pertaining to Right Barrage Bay Portion 5.Fish Pass Pier 5th lift Concreting with M25A20 6.Diaphragm Walls Cage Reinforcement Binding 7.Mechanical Fabrication work of various components.
76/100
Instream Storage Structure, KansariGanda
Visit of NABARD team, ACE of RB basin, AEE, AE of dept., Geologist, Irrigation Eng. Expert and QA/QC expert along with Site Engineers PMC to the ISS site. Inspected the barrage works, pile testing site, batching plant and quality control Lab. Reviewed the progress and collected the information on various aspects of the project from the department officials regarding the LA, benefits of the projects, quality testing of works.
77/100
Instream Storage Structure, KansariGanda
Visit of NABARD team, ACE of RB basin, AEE, AE of dept., Geologist, Irrigation Eng. Expert and QA/QC expert along with Site Engineers PMC to the ISS site. Inspected the barrage works, pile testing site, batching plant and quality control Lab. Reviewed the progress and collected the information on various aspects of the project from the department officials regarding the LA, benefits of the projects, quality testing of works.
78/100
Instream Storage Structure, KansariGanda
Visit of NABARD team, ACE of RB basin, AEE, AE of dept., Geologist, Irrigation Eng. Expert and QA/QC expert along with Site Engineers PMC to the ISS site. Inspected the barrage works, pile testing site, batching plant and quality control Lab. Reviewed the progress and collected the information on various aspects of the project from the department officials regarding the LA, benefits of the projects, quality testing of works.
79/100
Instream Storage Structure, KansariGanda
Visit of NABARD team, ACE of RB basin, AEE, AE of dept., Geologist, Irrigation Eng. Expert and QA/QC expert along with Site Engineers PMC to the ISS site. Inspected the barrage works, pile testing site, batching plant and quality control Lab. Reviewed the progress and collected the information on various aspects of the project from the department officials regarding the LA, benefits of the projects, quality testing of works.
80/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of D/S Divide wall, raft is under progress in presence of Client & PSS Team.
81/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for Gravity floor, Top is under progress.
82/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
RHS side earth excavation is under progress.
83/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cube casting & Slump testing M20A20 (Value 80 mm) of D/S Gravity floor PCC done in presence of Client & PSS Team.
84/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for Right hand side Barrage Way, Raft is under progress.
85/100
Instream Storage Structure, Jharbeda
Reinforcement placing of Pier No-6, 5th lift is under Progress.
86/100
Instream Storage Structure, Jharbeda
Cleaning of Pier No-6 to Pier No-8 for D/S Gravity floor is under Progress.
87/100
Instream Storage Structure, Jharbeda
Cleaning of RHS Abutment (A2) work is under Progress.
88/100
Instream Storage Structure, Jharbeda
Reinforcement placing of Pier No-5, 6th lift is under Progress.
89/100
Instream Storage Structure, Jharbeda
Dewatering work is in Progress.
90/100
Instream Storage Structure, Jharbeda
Curing of Pier No-5 is in Progress
91/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-20, 10th lift at Block No-3 done in presence of Client & PSS Team.
92/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-20, 10th lift at Block No-3 is under progress in presence of Client & PSS Team.
93/100
Instream Storage Structure, Hamirpur
U/S Bracket installation work is in progress at Block-5 for slab staging and shuttering works at Bay-28 & Bay-29.
94/100
Instream Storage Structure, Hamirpur
R.D.U & CDU fixing work is in progress on hoist bridge platform No-1.
95/100
Instream Storage Structure, Hamirpur
Column trestle bracing welding work is in progress.
96/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-9, 11th lift is under progress.
97/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-10, 13th lift is under progress.
98/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-11, 9th lift is under progress.
99/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-12, 8th lift is under progress.
100/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-30, 7th lift is under progress.

Enter Login Details

Forgot Password ?