1/100
Instream Storage Structure Across Bheden near village Saida
LHS U/S Flared out wall cleaning work in progress.
2/100
Instream Storage Structure Across Bheden near village Saida
LHS D/S Flank wall final lift de-shuttering work is going on .
3/100
Instream Storage Structure Across Bheden near village Saida
LHS U/S Flared out wall mud cleaning work is going on .
4/100
Instream Storage Structure Across Bheden near village Saida
Shuttering & alignment checking in RHS divide wall Pier portion 10th lift.Rl-222.800 to 224.100 .
5/100
Instream Storage Structure, Gochara
Deck slab cleaning work is going on...
6/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. Flow direction is straight. The direction of flow is seen in middle of the river. Now the flow level is 225.600mt against design crest level 225.500 i.e. flood lift 0.1mt.
7/100
Instream Storage Structure, Gochara
Deck slab cleaning work is going on..
8/100
Instream Storage Structure, Gochara
U/S coffer dam work is going on .
9/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
10/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. Flow direction is straight. The direction of flow is seen in middle of the river. Now the flow level is 225.600mt against design crest level 225.500 i.e. flood lift 0.1mt.
11/100
Instream Storage Structure, Budharaja
De- Shuttering Work is in Progress at LHS Flared Out Wall 7th Lift.
12/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at Pier No: 5, Hoist Gate Portion.
13/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at Pier No: 4, Hoist Gate Portion.
14/100
Instream Storage Structure, Budharaja
De-Shuttering work is in Progress at LHS Divided Wall, Hoist Gate Portion.
15/100
Instream Storage Structure, Budharaja
Curing work is in Progress at Pier No: 2, Hoist Gate Portion.
16/100
Instream Storage Structure, Budharaja
Curing work is in Progress at Pier No: 1, Hoist Gate Portion.
17/100
Instream Storage Structure, Budharaja
Curing work is in Progress at Pier No: 1, Hoist Gate Portion.
18/100
Instream Storage Structure, Budharaja
Curing work is in Progress at Pier No: 2, Hoist Gate Portion.
19/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at Pier No: 6, Hoist Gate Portion.
20/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at Pier No: 5, Hoist Gate Portion.
21/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at Pier No: 4, Hoist Gate Portion.
22/100
Instream Storage Structure, Budharaja
De-Shuttering work is in Progress at LHS Abutment, Hoist Gate Portion.
23/100
Instream Storage Structure, Khirasasan
Slump 80mm
24/100
Instream Storage Structure, Khirasasan
Sir, checked placing and positioning of steel reinforcement, supporting bars and alignment of shuttering work with minimum cover 75mm . Pier No. 6 Hoist Portion . Now the area is ready for concrete M25 A20. So recommended for the purpose. RL: 223.400 to 224.900. Approved by AEE Sir, Sambalpur. In the presence of JE Sir.
25/100
Instream Storage Structure, Khirasasan
Pier no 5 Hoist portion shuttering work completed and ready for concrete casting
26/100
Instream Storage Structure, Khirasasan
Curing work under progress
27/100
Instream Storage Structure, Khirasasan
Pier no. 6 hoist portion shuttering work is in progress
28/100
Instream Storage Structure, Khirasasan
LHS D/S Flared out wall 8th lift shuttering work under progress
29/100
Instream Storage Structure, Khirasasan
LHS D/S Flared out wall 8th lift shuttering work under progress
30/100
Instream Storage Structure, Khirasasan
Pier no. 6 hoist portion shuttering work is in progress
31/100
Instream Storage Structure, Khirasasan
Pier no. 5 hoist portion shuttering work completed and ready for casting.
32/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
33/100
Instream Storage Structure across river Sapei near village Kinjirma
Building staff quarter and control rooms plinth beam shuttering work under progress .
34/100
Instream Storage Structure across river Sapei near village Kinjirma
Building staff quarter plinth beam shuttering work under progress .
35/100
Instream Storage Structure, Kopsinga
LHS D/S Guide bond FDD Check
36/100
Instream Storage Structure, Kopsinga
LHS D/S Flared wall Casting under progress M20 A20
37/100
Instream Storage Structure, Kopsinga
Slump-80mm flared wall
38/100
Instream Storage Structure, Kopsinga
LHS U/S 33 Layer guide bond FDD test
39/100
Instream Storage Structure, Kopsinga
Cube test..
40/100
Instream Storage Structure, Kopsinga
Visit of A.G Audit team & Dept AEE sir to ISS Kopsingha
41/100
Instream Storage Structure, Kopsinga
LHS U/S Guide bond FDD Test
42/100
Instream Storage Structure, Kopsinga
LHS Approach road 22 layer FDD test
43/100
Instream Storage Structure, Kudabega
Casting gate groove of span, 22,23
44/100
Instream Storage Structure, Kudabega
Span 29,stoplog service gate groove 2nd stage 2nd lift
45/100
Instream Storage Structure, Kudabega
Casting of both side kerb, span 14
46/100
Instream Storage Structure, Kudabega
Slump 85mm of U/S kerb casting
47/100
Instream Storage Structure, Kudabega
RHS abutment 5th lift reinforcement binding work in progress
48/100
Instream Storage Structure, Kudabega
Span22 gate grooving deshutterig and shuttering work
49/100
Instream Storage Structure, Kudabega
US side road making work
50/100
Instream Storage Structure, Kudabega
Span 14 us side shuttering work
51/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Seal -beam fixing work is in progress of Span no - 16 & 15
52/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Roller - tracker fixing work is in progress of Stop-log gate at Span no - 18
53/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Trestle or Column's work is in progress
54/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Cross -Beam work is in progress
55/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Hoist bridge's 25th platform assembly work is in progress
56/100
Instream Storage Structure, Kudabega
85mm
Tm-5
57/100
Instream Storage Structure, Kudabega
80mm
Tm-3
58/100
Instream Storage Structure, Kudabega
80mm
Tm-1
59/100
Instream Storage Structure, Kudabega
RHS u/s divide wall with breast wall 8th top lift M25A20 (Rl-215.550 to Rl-217.790) casting work in progress.
60/100
Instream Storage Structure, Kudabega
Curing work
61/100
Instream Storage Structure, Kudabega
Span no-14 kerb shuttering work in progress.
62/100
Instream Storage Structure, Kudabega
Pier no-28, gate groove second stage deshuttering work in progress.
63/100
Instream Storage Structure, Kudabega
Span no-05,04 raft gate groove bottom seal cleaning work in progress.
64/100
Instream Storage Structure, Kudabega
Pier no-21,22, gate groove second stage deshuttering & shuttering work is in progress.
65/100
Instream Storage Structure, Kudabega
Pier no-25, gate groove second stage deshuttering work in progress.
66/100
Instream Storage Structure, Kudabega
RHS d/s wing wall 5th lift Deshuttering work in progress.
67/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Work on laying primer on columns and trestles is underway.
68/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Trestle or Column's work is in progress
69/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Cross -beam work is in progress
70/100
Instream Storage Structure, Gudvella
Curing work at P9 under progress on 20.11.2025
71/100
Instream Storage Structure, Gudvella
Steel cutting & bending at steel yard under progress on 20.11.2025
72/100
Instream Storage Structure, Gudvella
Clearance of A2 Abutment on 20.11.2025
73/100
Instream Storage Structure, Nandagaon
A meeting is held in the office chamber of SE, KID, Bhawanipatna among the DTL, Tel Basin, Bhawanipatna,SDO, ISS Nandagaon, Experts and Sr. Site Engineer of PMC. Discussion held for preparation realistic work programme to the balance quantities and deployment of adequate men and machineries at ISS, Nandagaon for timely completion within 2nd EoT i.e 31.03.2026.The Agency has been instructed for preparation and early submission of
Design, drawing of Afflux Bund immediately on 20.11.2025
74/100
Instream Storage Structure, Nandagaon
Base plate drilling for trestle under progress on 20.11.2025
75/100
Instream Storage Structure, Nandagaon
Columns fit up and bracing welding under progress on 20.11.2025
76/100
Instream Storage Structure, Nandagaon
SS plate welding on sil beam under progress on 20.11.2025
77/100
Instream Storage Structure, Nandagaon
Reinforcement binding is in progress at pier no.12, Block-2 on 20.11.2025
78/100
Instream Storage Structure, Nandagaon
Monorail fit up and welding work under progress on 20.11.2025
79/100
Instream Storage Structure, Nandagaon
Curing at D/S left flared out wall is in progress on 20.11.2025
80/100
Instream Storage Structure, Nandagaon
Hoist bridge MIG welding under progress on 20.11.2025
81/100
Instream Storage Structure, Nandagaon
Gate no 5 barrage bay gate erection work under progress on 20.11.2025
82/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress of Dia 75mm HDPE pipe line of LO-330A OMS line (Z-5866), near village Singhanimunda.
83/100
UGPL, Right Lower Suktel Canal Division
OCS fittings Installation work is in progress for OCS -0201205-C11B at village Bhandhaghur in presence of PMC team, L&T and Bermad staff.
84/100
UGPL, Left Lower Suktel Canal Division
Joint verification is in progress for HDPE pipe line OMS point and outlet points of RO-214B (RM-11) at village Banjipali in presence of PMC team.
85/100
Integrated Barrage across river Kochila and across river Baitarini
The team including SE, AEE of Quality Assurance Division Chandikhol, AE of Akhuapada irrigation Division visited the site in presence of PMC team and representatives of Agency on dated 20.11.2025
86/100
UGPL, Left Lower Suktel Canal Division
20mm Dia galvanized steel Conduit pipe laying is in progress for Pump House inner lighting work.
87/100
UGPL, Left Lower Suktel Canal Division
450mm Dia DI pipeline Gap closing work is in progress from node J-254 to J-38, RM-15 at village Birkel.
88/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of Abutment wall is under progress.
89/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Curing of RHS Divide wall is under progress.
90/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for Divide wall, 2nd lift is under progress.
91/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning of D/S Double pier debris is under progress.
92/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning & Vertical straightening of reinforcement for Middle pier is under progress.
93/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS D/S Divide wall, 1st lift is under progress.
94/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-5 is under progress.
95/100
Instream Storage Structure, Jharbeda
Dewatering work is under progress.
96/100
Instream Storage Structure, Jharbeda
Cleaning of Pier No-3 to Pier No-4 is under progress.
97/100
Instream Storage Structure, Jharbeda
Cleaning of Pier No-4 to Pier No-6 is under progress.
98/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-18, 6th lift at Block No-3 done in presence of Client & PSS Team.
99/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-18, 6th lift at Block No-3 is under progress in presence of Client & PSS Team.
100/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-29, 10th lift at Block No-4 done in presence of Client & PSS Team.
❮
❯