GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
UGPL, Right Lower Suktel Canal Division
1Ha subchak excavation work is in progress for 75mm Dia HDPE pipe of OCS No. 0213087-C11B at village Lakhapali In presence of DoWR Staff and PMC team.
2/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS-0213080-C04A at village Bramhinpali in presence of DoWR Staff and PMC team.
3/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door & angle fixing work is in progress OCS No:-0213103-C07B at village Umuria in presence of CME (PSS) along with PMC team.
4/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS-0213060-C11B at village Bramhinpali in presence of CME (PSS) and PMC team.
5/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for Laying of 75mm Dia HDPE Pipes from OMS RO237B( Z-4285) RM-13 for Gap closing work near village Taliudar in presence of PMC team.
6/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI to HDPE pipeline TEE connection at J-518 RM-13 near village Taliudar in presence of PMC team.
7/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE pipe TEE connection at LO-377, LM-4 near village Amamunda in presence of PMC team.
8/100
UGPL, Left Lower Suktel Canal Division
HDPE Tee (125X 75 X 75)mm connection work is in progress at RO-67, RM-4, near village Khaliapali in presence of PMC team.
9/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for RHS Double pier, 5th lift & Divide wall, Final lift and Shuttering of D/S Wing wall is under progress.
10/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of RHS Mid-pier, 2nd lift is under progress.
11/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M20A20 (Value 70 mm) of RHS D/S Gravity floor, 2nd lift done in presence of Client & PSS Team.
12/100
Instream Storage Structure, Jharbeda
Slump testing M20A20 (Value 75 mm) of Pier No-8 to RHS (D2) U/S Gravity floor done in presence of Client & PSS Team.
13/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of Pier No-8 to RHS (D2) U/S Gravity floor is under progress in presence of Client & PSS Team.
14/100
Instream Storage Structure, Jharbeda
Cleaning work is under progress.
15/100
Instream Storage Structure, Jharbeda
Shuttering & Binding of reinforcement for RHS Divide wall pier portion Footing is under progress.
16/100
Instream Storage Structure, Jharbeda
Shuttering & Binding of reinforcement for Pier No-8 is under progress.
17/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-6 is under progress.
18/100
Instream Storage Structure, Jharbeda
De-Shuttering of Pier No-5 is under progress.
19/100
Instream Storage Structure, Jharbeda
Shuttering of RHS D/S Flank wall, 1st Layer is under progress.
20/100
UGPL, Left Lower Suktel Canal Division
140mm Dia HDPE pipe jointing work is in progress at LO-327, LM-17 near village Birkel in presence of DOWR AE and PMC team.
21/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
22/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.94/mm2 for 28 days) of D/S Flared out Cut-off wall, 14th lift and M35A20 (Strength is 42.23/mm2 for 28 days) of Gantry Girder No-1 and M25A20 (Strength is 21.63/mm2 for 07 days) of Pier No-21, 11th lift has done in presence of Client & PSS team.
23/100
UGPL, Left Lower Suktel Canal Division
DI to HDPE pipeline connection work is in progress at J-391, Lm-4 near village Amamunda in presence of PMC team.
24/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE pipe TEE connection (160*125*125) at J-184, near village Semelia.
25/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform No-3 girder's web and flange plate fixing work is in progress.
26/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-2 fit up work is in progress.
27/100
Instream Storage Structure, Hamirpur
Barrage bay groove 2nd stage embedded parts roller track and guide erection work is in progress at Bay No-9.
28/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Abutment (A1), 8th lift at Block No-1 is under progress.
29/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall is under progress.
30/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-1, 5th lift is under progress.
31/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-2, 5th lift is under progress.
32/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-3, 6th lift is under progress.
33/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4, 5th lift is under progress
34/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-15, 13th lift is under progress.
35/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall raft at Block no-5 is under progress.
36/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Gantry Girder is under progress
37/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier no-21, 13th lift is under progress.
38/100
Instream Storage Structure, Khalpal
Joint inspection at ISS site by Dy.TL, PSS in presence of A.E.E & A.E, AID, QAE of PSS team along with Staffs of EPC agency.
39/100
Instream Storage Structure, Khalpal
Curing of Piers is under progress.
40/100
Instream Storage Structure, Jharbeda
Concreting M25A20 of Pier No-8 to RHS (D2) End sill, 2nd Layer is under progress in presence of Client & PSS Team.
41/100
Instream Storage Structure, Khalpal
Curing of Pier is under progress.
42/100
Instream Storage Structure, Khalpal
Curing of Wing wall is under progress.
43/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M20A20 (Value 70 mm) of RHS D/S Gravity floor, 2nd lift done in presence of Client & PSS Team.
44/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irr. Eng. Exp. and QA/QC Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site, 4TH lift U/S left devide wall casting, LHS barrage bay girder no- 6 reinforcement & shuttering check and Pile no -101 casting.
45/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irr. Eng. Exp. and QA/QC Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site, 4TH lift U/S left devide wall casting, LHS barrage bay girder no- 6 reinforcement & shuttering check and Pile no -101 casting.
46/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irr. Eng. Exp. and QA/QC Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site, 4TH lift U/S left devide wall casting, LHS barrage bay girder no- 6 rainforcement & shuttering check and Pile no -101 casting.
47/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irr. Eng. Exp. and QA/QC Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site, 4TH lift U/S left devide wall casting, LHS barrage bay girder no- 6 rainforcement & shuttering check and Pile no -101 casting.
48/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irr. Eng. Exp. and QA/QC Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site, 4TH lift U/S left devide wall casting, LHS barrage bay girder no- 6 rainforcement & shuttering check and Pile no -101 casting.
49/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irr. Eng. Exp. and QA/QC Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site, Right side Barrage bay pile no-98 casting and Right side U/S divide wall panel no-80 casting. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
50/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irr. Eng. Exp. and QA/QC Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site, Right side Barrage bay pile no-98 casting and Right side U/S divide wall panel no-80 casting. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
51/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irr. Eng. Exp. and QA/QC Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site, Right side Barrage bay pile no-98 casting and Right side U/S divide wall panel no-80 casting. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
52/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irr. Eng. Exp. and QA/QC Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site, Right side Barrage bay pile no-98 casting and Right side U/S divide wall panel no-80 casting. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
53/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irr. Eng. Exp. and QA/QC Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site, Right side Barrage bay pile no-98 casting and Right side U/S divide wall panel no-80 casting. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
54/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irr. Eng. Exp. and QA/QC Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site, Right side Barrage bay pile no-98 casting and Right side U/S divide wall panel no-80 casting. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
55/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-21, 12th lift done in presence of Client & PSS Team.
56/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-21, 12th lift is under progress in presence of Client & PSS Team.
57/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Abutment wall (A1), 7th lift at Block No-1 done in presence of Client & PSS Team.
58/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Abutment wall (A1), 7th lift at Block No-1 is under progress in presence of Client & PSS Team.
59/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-1, 4th lift done in presence of Client & PSS Team.
60/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-1, 4th lift is under progress in presence of Client & PSS Team.
61/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-16 done in presence of Client & PSS Team.
62/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-16 is under progress in presence of Client & PSS Team.
63/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.92/mm2 for 28 days) of Pier No-16, 8th lift and (Strength is 30.89/mm2 for 28 days) of Pier No-15, 6th lift and (Strength is 21.63/mm2 for 07 days) of U/S Flank wall at block No-1 has done in presence of Client & PSS team.
64/100
Instream Storage Structure, Hamirpur
Stop-log groove 2nd stage embedded parts guide erection work is in progress at Bay No-9.
65/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform No-3 girder's fit-up work is in progress.
66/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-1 welding work is in progress.
67/100
Instream Storage Structure, Hamirpur
MS plate marking and cutting for hoist platform girder's flange work is in progress.
68/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4 is under progress.
69/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-3, 6th lift is under progress.
70/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Flank wall at Block No-1 is under progress.
71/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall at Block No-1 is under progress.
72/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-1, 3rd lift is under progress.
73/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-15, 13th lift is under progress.
74/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall at Block no-5 is under progress.
75/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Gantry Girder is under progress.
76/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Pier no-2, 5th lift is under progress.
77/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of RHS Mid-pier Cap is under progress.
78/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for RHS Double pier, 5th lift is under progress.
79/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering & binding of reinforcement for RHS Counterfort with Wing wall, 2nd lift is under progress.
80/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 85 mm) of LHS D/S Divide wall, 5th lift done in presence of Client & PSS Team.
81/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS D/S Divide wall, 5th lift is under progress in presence of Client & PSS Team.
82/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 50 mm) of RHS (A2) Footing, 2nd Layer done in presence of Client & PSS Team.
83/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of RHS (A2) Footing, 2nd Layer is under progress in presence of Client & PSS Team.
84/100
Instream Storage Structure, Hamirpur
Cleaning of Pier No-8 to RHS (D2) U/S Gravity floor is under progress.
85/100
Instream Storage Structure, Hamirpur
Cutting & bending for reinforcement is under progress.
86/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-8, 4th lift is under progress.
87/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for RHS (D2) D/S Footing, 2nd Layer is under progress.
88/100
Instream Storage Structure, Hamirpur
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
89/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 80 mm) of Barrage Bay No-2 Mid Cut-off, 2nd lift done in presence of Client & PSS Team.
90/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Barrage Bay No-2 Mid Cut-off, 2nd lift is under progress in presence of Client & PSS Team.
91/100
Instream Storage Structure, Khalpal
Curing of Piers is under progress.
92/100
Instream Storage Structure across river Sapei near village Kinjirma
85mm Tm-17
93/100
Instream Storage Structure across river Sapei near village Kinjirma
RHS U/S divide wall raft M25A20 casting work in progress
94/100
Instream Storage Structure across river Sapei near village Kinjirma
80mm Tm-15
95/100
Instream Storage Structure across river Sapei near village Kinjirma
85mm Tm-14
96/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 80mm,tm-13
97/100
Instream Storage Structure across river Sapei near village Kinjirma
80mm Tm-12
98/100
Instream Storage Structure across river Sapei near village Kinjirma
80mm Tm-11
99/100
Instream Storage Structure across river Sapei near village Kinjirma
RHS U/S divide wall raft M25A20 casting work in progress
100/100
Instream Storage Structure across river Sapei near village Kinjirma
Tm-10 85mm

Enter Login Details

Forgot Password ?