1/100
UGPL, Right Lower Suktel Canal Division
External drain brick masonry work is in progress at Pump House in presence of DoWR JE and PMC team.
2/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No- 0213087- C16A near village Puintala in presence of PMC team.
3/100
UGPL, Left Lower Suktel Canal Division
Butt fusion jointing work is in progress for 250mm Dia HDPE pipe of J-203 to J-383, LM-7 Near village Uparudar in presence of PMC team.
4/100
UGPL, Left Lower Suktel Canal Division
HDD machine road pushing work is in progress of 75mm Dia HDPE pipe (Road crossing) at LO-141B (Z-7134, Z-6743, Z-7112, Z-7172) LM-7 near village Uparudar in presence of PMC team.
5/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-32 done in presence of Client & PSS Team.
6/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-32 is under progress in presence of Client & PSS Team.
7/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of D/S Flared out wall, Raft at Block No-5 (Bank side) done in presence of Client & PSS Team.
8/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flared out wall, Raft at Block No-5 (Bank side) is under progress in presence of Client & PSS Team.
9/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Pier No-2, 6th lift done in presence of Client & PSS Team.
10/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-2, 6th lift is under progress in presence of Client & PSS Team.
11/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.06/mm2 for 28 days) of Pier No-3, 5th lift and (Strength is 30.87/mm2 for 28 days) of Pier No-16, 13th lift and (Strength is 31.09/mm2 for 28 days) of Pier No-2, 4th lift and M35A20 (Strength is 42.15/mm2 for 28 days) of Gantry Girder No-14 has done in presence of Client & PSS team.
12/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-3 welding work is in progress.
13/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-5 girder's stiffener welding work is in progress.
14/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform girder's web plate butt welding work is in progress.
15/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-2, 6th lift is under progress.
16/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Flank wall Cut-off at Block No-1 is under progress.
17/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall at Block No-5 is under progress.
18/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flank wall, Raft at Block No-5 is under progress.
19/100
Instream Storage Structure, Hamirpur
Shuttering of Abutment (A1), 5th lift at Block No-1 is under progress.
20/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
21/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for LHS side Raft is under progress.
22/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M20A20 (Value 65 mm) of RHS Gravity floor, Final lift done in presence of Client & PSS Team.
23/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 80 mm) of RHS Double pier, 1st lift done in presence of Client & PSS Team.
24/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of RHS Double pier, 1st lift is under progress in presence of Client & PSS Team
25/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Testing of Compressive M20A20 (Strength is 24.20/mm2 for 28 days) of RHS Gravity floor has done in presence of Client & PSS team.
26/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) in presence of Client & PSS team along with EPC agency.
27/100
Instream Storage Structure, Jharbeda
Slump testing M25A20 (Value 80 mm) of RHS (A2) wall, 1st lift done in presence of Client & PSS Team.
28/100
Instream Storage Structure, Jharbeda
Concreting M25A20 of RHS (A2) wall, 1st lift is under progress in presence of Client & PSS Team.
29/100
Instream Storage Structure, Jharbeda
Slump testing M20A20 (Value 40 mm) of RHS D/S Flank wall Footing, Final Layer done in presence of Client & PSS Team.
30/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of RHS D/S Flank wall Footing, Final Layer is under progress in presence of Client & PSS Team.
31/100
Instream Storage Structure, Jharbeda
Cleaning of (A2), Footing Top is under progress.
32/100
Instream Storage Structure, Jharbeda
Shuttering of RHS D/S Flank wall Footing, Final lift is under progress.
33/100
Instream Storage Structure, Jharbeda
De-Shuttering of RHS D/S Training wall, Footing is under progress.
34/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-7 is under progress.
35/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
36/100
Instream Storage Structure, Jharbeda
Dewatering work is under progress.
37/100
Instream Storage Structure, Khalpal
Curing of under sluice End sill is in progress.
38/100
Instream Storage Structure, Khalpal
Testing of Compressive M25A20 (Strength is 33.68/mm2 for 28 days) of Pier No-19 Crest portion and (Strength is 33.67/mm2 for 28 days) of Mid Cut-off, 1st lift at Barrage Bay No-2 has done in presence of Client & PSS team.
39/100
Instream Storage Structure, Khalpal
Binding of reinforcement for Barrage Bay No-2, Raft is under progress.
40/100
Instream Storage Structure, Khalpal
Shuttering of pier No-21, 2nd lift is under progress.
41/100
Instream Storage Structure, Khalpal
Shuttering of Double pier No-25 is under progress.
42/100
Instream Storage Structure, Khalpal
Curing of Piers is in progress.
43/100
Instream Storage Structure, Gudvella
Cast of posts of U/s side of span -6 and span – 1 on 06.05.2026
44/100
Instream Storage Structure, Gudvella
Reinforcement work of building columns at the staircase area is under progress at site on 06.05.2026
45/100
Instream Storage Structure, Gudvella
Shuttering work of posts deck slab on 06.05.2026
46/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 06.05.2026
47/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 06.05.2026
48/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no. 9,10,11&12 is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 83mm on 06.05.2026
49/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no. 9,10,11&12 is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 83mm on 06.05.2026
50/100
Instream Storage Structure, Nandagaon
Conducted slump test for casting with PCC M15A40 grade at D/S curtain wall for 1st lift upto RL-233.50m in presence of PM EPC agency, Site Engineer of PMC & EPC agency and found value is 86mm at placing site. The slump test value is 86mm on 06.05.2026
51/100
Instream Storage Structure, Nandagaon
Conducted slump test for casting with PCC M15A40 grade at D/S curtain wall for 1st lift upto RL-233.50m in presence of PM EPC agency, Site Engineer of PMC & EPC agency and found value is 86mm at placing site. The slump test value is 86mm on 06.05.2026
52/100
Instream Storage Structure, Nandagaon
• 4.The area of placing concrete at U/S right divide wall has been checked before placement in presence of PM of EPC Agency, Site Engineer of PMC & EPC Agency as follows:
(i).The reinforcement in binding, tying n spacing of both vertical main & horiz. dist. bar and tie bars for casting of U/S right divide wall for 9th lift from RL-242.40m to RL-243.80m are found completed.
(ii).Rigid & smooth shuttering and maintained clear cover of 75mm from main bar to shutter plates are done.
(iii).The area is cleaned properly through air water jetting and passed by SE, KID, Bhawanipatna for placing with RCC M25A20 grade on 06.05.2026
53/100
Instream Storage Structure, Nandagaon
• 3.Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay No.-10&11 of Pier No.9,10 &11 have been checked and found correct by HM Expert of PMC during his site visit on dt.05.05.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 06.05.2026
54/100
Instream Storage Structure, Nandagaon
• 2.(i) Checked the area before placement of concrete at D/S curtain wall with following activities in presence of PM of EPC Agency,Site Engineers of PMC & EPC Agency:
(ii) Rigid and smooth shuttering for curtain wall with PCC M15A40 grade for 1st. lift of 1.00 mt. ht. and 1.0m width from RL-232.50m to RL-233.50m are found completed.
(iii)The concrete surface is cleaned properly through air water jetting and passed by SE, KID Bhawanipatna for placing concrete with PCC M15A40 grade on 06.05.2026
55/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no.11 upto RL-246.30m is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 84mm on 06.05.2026
56/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no.11 upto RL-246.30m is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 84mm on 06.05.2026
57/100
Instream Storage Structure, Nandagaon
• 1(i).Fixing & fittings and alignment of All trestle and columns foundation bolts measurements has been checked at pier no.-11,12&13for Blockout area of 6.8m length and found correct by HM Expert of PMC during his site visit on dt.06.05.2026 in presence of mechanical Site Engineers of PMC and EPC Agency.
(ii) Rigid and smooth shuttering for Blockout area with M35A20 grade at pier no.-7 upto RL-247.00m and pier no.9 from RL-245.40m to RL-246.30m are found completed.
(iii).The area is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with M35A20 grade on 06.05.2026
58/100
Instream Storage Structure, Nandagaon
Placing of CC blocks is in progress at D/S side on 06.05.2026
59/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering is in progress at U/S right divide wall on 06.05.2026
60/100
Instream Storage Structure, Nandagaon
Hoist bridge painting work under progress on 06.05.2026
61/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for gap closing of 300mm Dia DI pipeline between J-470 to J-443, RM-3 near village Jamutia in presence of PMC team.
62/100
Instream Storage Structure, Budharaja
Staff Quarter 1st floor plastering work is in Progress.
63/100
Instream Storage Structure, Budharaja
Shuttering and Cleaning work is in progress at LHS D/S Flared-out Wall Portion.
64/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S of river.
65/100
Instream Storage Structure, Budharaja
Staff Quarter 1st floor plastering work is in Progress.
66/100
Instream Storage Structure, Budharaja
Shuttering and Cleaning work is in progress at LHS D/S Flared-out Wall Portion.
67/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S of river.
68/100
Instream Storage Structure, Budharaja
Staff Quarter 1st floor plastering work is in Progress.
69/100
Instream Storage Structure, Budharaja
Shuttering work is in progress at LHS D/S Flared-out Wall Portion.
70/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S of river.
71/100
Instream Storage Structure, Budharaja
Staff Quarter 1st floor plastering work is in Progress.
72/100
Instream Storage Structure, Budharaja
Shuttering and Cleaning work is in progress at LHS D/S Flared-out Wall Portion.
73/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S of river.
74/100
Instream Storage Structure, Budharaja
Today no working activities at site due to Labour day.
75/100
Instream Storage Structure Across Bheden near village Saida
RHS D/S Flared out of step -12th de-shuttering work is going on .
76/100
Instream Storage Structure Across Bheden near village Saida
Staff quarters plinth beam Reinforcement bar binding work is in progress .
77/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from U/S to D/S of river.
78/100
Instream Storage Structure Across Bheden near village Saida
Staff quarters plinth beam Reinforcement bar binding work is going on .
79/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from U/S to D/S of river.
80/100
Instream Storage Structure Across Bheden near village Saida
LHS divide wall to p-1 hoist column gate erection work in progress.
81/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from U/S to D/S of river.
82/100
Instream Storage Structure Across Bheden near village Saida
RHS U/S Flared out wall step - 16th de-shuttering work is going on .
83/100
Instream Storage Structure Across Bheden near village Saida
LHS Undersluice hoist column erection work in progress.
84/100
Instream Storage Structure Across Bheden near village Saida
P-5 hoist portion shuttering work is going on .
85/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from U/S to D/S of river.
86/100
Instream Storage Structure Across Bheden near village Saida
Today no work at site due Labours day
87/100
UGPL, Right Lower Suktel Canal Division
HDPE Tee (140 x 110 x140)mm connection work is in progress at J-5338 near village Jarajirang in presence of PMC team.
88/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for fixing of 1HA outlet of OCS -02305095-C06A at village Jarajaring in presence of PMC team.
89/100
UGPL, Right Lower Suktel Canal Division
OCS chamber above GL finishing work is in progress of OCS No:- 0213136-CO5B at village Timapali in presence of PMC team.
90/100
UGPL, Right Lower Suktel Canal Division
External drain brick masonry work is in progress at Pump House.
91/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No- 0213112-C04A near village Kadalipalli in presence of PMC team.
92/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door and angle fixing work is in progress OCS No:-0201297- C02A at village Rinabachan in presence of PMC team.
93/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 250mm Dia HDPE pipeline gap closing between J-203 to J-383, LM-7 near Uparudar.
94/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No- 0201345- C11B near village Balangir in presence of DoWR SDO, AE, JE and PMC team.
95/100
UGPL, Left Lower Suktel Canal Division
DI to HDPE connection work is in progress at Lm-10 J-515 village Kadajuri in presence of PMC team.
96/100
Instream Storage Structure, Gudvella
Curing at slab is under progress on 05.05.2026
97/100
Instream Storage Structure, Gudvella
Shuttering work of posts deck slab on 05.05.2026
98/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 05.05.2026
99/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 05.05.2026
100/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right divide wall for 9th lift upto RL-243.80m is in progress through concrete pump in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 88mm on 05.05.2026
❮
❯