1/100
Instream Storage Structure, Gudvella
Clearance at A2 work under progress on 23.11.2025
2/100
Instream Storage Structure, Gudvella
Reinforcement and cleaning simultaneously at A2 is in progress on 22.11.2025
3/100
UGPL, Right Lower Suktel Canal Division
1Ha. chamber fixing work is in progress of LO-329B, Z-6148 ( LM-16) near village Birkel.
4/100
Instream Storage Structure, Gudvella
Visited ISS Gudvella site . Dept JE ,Site engineers of PMC n agency were present.
1. Casting of concrete RCC M25A20 grade at deck slab no -6 in between P5 and P6 is in progress.
2. Slump checked at site and slump value is 81mm.
3. Casting of cubes done at site
4. Conducted test for 28 days compressive strength of concrete cube PCC M15A40 grade at field laboratory and result found 22.51N/mm2
5. Conducted gradation of 10mm at field laboratory and result found satisfactory
6. Conducted gradation of 20mm at field laboratory and result found satisfactory on 21.11.2025
5/100
Instream Storage Structure, Gudvella
Visited ISS Gudvella site . Dept JE ,Site engineers of PMC n agency were present.
1. Casting of concrete RCC M25A20 grade at deck slab no -6 in between P5 and P6 is in progress.
2. Slump checked at site and slump value is 81mm.
3. Casting of cubes done at site
4. Conducted test for 28 days compressive strength of concrete cube PCC M15A40 grade at field laboratory and result found 22.51N/mm2
5. Conducted gradation of 10mm at field laboratory and result found satisfactory
6. Conducted gradation of 20mm at field laboratory and result found satisfactory on 21.11.2025
6/100
Instream Storage Structure, Gudvella
Casting of concrete at deck slab number-06 in between P5 and P6 of grade M25A20 from RL 159.50 m to 160.30 m is under progress through pump in the presence of Dept JE, PMC & agency site engineers at site. Slump achieved 81mm on 21.11.2025
7/100
Instream Storage Structure, Gudvella
Casting of concrete at deck slab number-06 in between P5 and P6 of grade M25A20 from RL 159.50 m to 160.30 m is under progress through pump in the presence of Dept JE, PMC & agency site engineers at site. Slump achieved 81mm on 21.11.2025
8/100
Instream Storage Structure, Nandagaon
Cleaning at right abutment, Block-2 is in progress on 23.11.2025
9/100
Instream Storage Structure, Nandagaon
Curing at U/S left flared out wall is in progress on 22.11.2025
10/100
Instream Storage Structure, Nandagaon
Hoist bridge MIG welding under progress on 21.11.2025
11/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering at pier no. 12, Block-2 is in progress on 21.11.2025
12/100
UGPL, Right Lower Suktel Canal Division
Primary filtration unit area turfing work is in progress at Pump House.
13/100
UGPL, Right Lower Suktel Canal Division
Internal Approach RCC road concrete pouring work is in progress at Pump House.
14/100
UGPL, Right Lower Suktel Canal Division
Slump test is in progress for internal RCC road concreting of Pump House.
15/100
UGPL, Right Lower Suktel Canal Division
OCS fittings Installation work is in progress for OCS -0213060-C01A, at village Brahaminpali in presence of L&T, Bermad team and PMC team.
16/100
UGPL, Left Lower Suktel Canal Division
Joint verification is in progress for HDPE pipe line OMS point and outlet points of LO-329B(LM-17) at village Singhanimunda in presence of PMC team.
17/100
UGPL, Left Lower Suktel Canal Division
Air valve verification work is in progress between J-472 to J-490, LM-1, at village Kushmel in presence of DoWR JE and PMC team.
18/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Upstream coffer dam sand filling work in progress-24.11.2025
19/100
Integrated Barrage across river Kochila and across river Baitarini
Coffer dam is in progress at Baitarani ISS Project-24.11.2025
20/100
Instream Storage Structure, Kuakhai
CE, SE of QA QC with team visited the site & inspecting the ongoing works .
21/100
Instream Storage Structure, Kuakhai
Pier no. 8 reinforcement bars arrangement has been completed from RL 20.993m to 22.286m, including the pier cap and pedestal bars.
22/100
Instream Storage Structure, Kuakhai
Rust removal using Sand blasting is under progress at left side barrage bay pier.
23/100
Instream Storage Structure, Kuakhai
Curing on casted girders in progress.
24/100
Instream Storage Structure, Kuakhai
Arrangement of pedestal reinforcement bars at pier no. 8.
25/100
Instream Storage Structure, Kuakhai
Curing on casted girders in progress.
26/100
Instream Storage Structure, Kuakhai
Left side downstream excavation work is in progress.
27/100
Instream Storage Structure, Kuakhai
Curing on casted girders in progress.
28/100
Instream Storage Structure, Kuakhai
Rust removal using sand blasting in progress at left side barrage bay pier.
29/100
Instream Storage Structure, Kuakhai
Ongoing Earthwork excavation at right side under sluice downstream area.
30/100
Instream Storage Structure, Kuakhai
Rust cleaning work is under progress at pier no.10.
31/100
Instream Storage Structure, Kuakhai
Reinforcement bar arrangement is under progress in pier no. 8.
32/100
Instream Storage Structure, Kuakhai
Casting of RCC M35A20 in pre-cast main girder (No.22) for the bridge is completed.
33/100
Instream Storage Structure, Kuakhai
Curing on casted girders in progress.
34/100
Instream Storage Structure, Kuakhai
Removal of rust from reinforcement bars.
35/100
Instream Storage Structure, Kuakhai
Casting of precast girder is in progress.
36/100
Instream Storage Structure, Kuakhai
Casting of RCC M35A20 in pre-cast main girder (No.22) for the bridge is started.
37/100
Instream Storage Structure, Kuakhai
Curing on casted girders in progress.
38/100
Instream Storage Structure, Kuakhai
Pier cap reinforcement bar arrangement is under progress at pier no-8.
39/100
Instream Storage Structure, Kuakhai
Rust removal from reinforcement using sand blasting.
40/100
Instream Storage Structure, Kuakhai
Curing on casted girders in progress.
41/100
Instream Storage Structure, Kuakhai
PSS Team observing the ongoing sand blasting and silt cleaning at left side barrage bay.
42/100
Instream Storage Structure, Kuakhai
Ongoing cleaning of rust from reinforcement bars, by using wire brush.
43/100
Instream Storage Structure, Kuakhai
Arrangement of pier cap reinforcement bars at pier no.8.
44/100
Instream Storage Structure, Kuakhai
Casting of precast girder is in progress.
45/100
Instream Storage Structure, Kuakhai
Dewatering is under progress in left D/S area.
46/100
Instream Storage Structure, Kuakhai
Ongoing Earthwork excavation at Left D/S divide wall portion.
47/100
Instream Storage Structure, Kuakhai
Casting of RCC M35A20 in pre-cast main girder (No.21) for the bridge is under progress.
48/100
UGPL, Left Lower Suktel Canal Division
20mm Dia galvanized steel Conduit pipe laying is in progress for Pump House inner lighting work.
49/100
UGPL, Left Lower Suktel Canal Division
900mm DI Pipeline Gap closing work is in progress Dy-2, J-536 to J-31 at village Tentulikhunti
50/100
Instream Storage Structure, Hamirpur
Curing of Piers is under progress.
51/100
Instream Storage Structure, Hamirpur
Curing of Flank walls is under progress.
52/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-29, 11th lift at Block No-4 is under progress.
53/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-17, 7th lift at Block No-3 is under progress.
54/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-23, 11th lift at Block No-4 is under progress.
55/100
Instream Storage Structure, Khalpal
Slump testing M20A40 (Value 60 mm) C.C Blocks done in presence of Client & PSS Team.
56/100
Instream Storage Structure, Khalpal
Casting of C.C Block (M20A40) is under progress in presence of Client & PSS Team.
57/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 170 mm) of Left sluice cross cut-off Panel No-30 done in presence of Client & PSS Team.
58/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Left sluice cross cut-off Panel No-30 done in presence of Client & PSS Team.
59/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M25A20 (Value 80mm) of Abutment & Counterfort, 1st lift is under progress done in presence of Client & PSS Team.
60/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of Abutment & Counterfort, 1st lift is under progress in presence of Client & PSS Team.
61/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Curing of RHS Divide wall is under progress.
62/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning of Raft area is under progress.
63/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS U/S Divide wall, 1st lift is under progress.
64/100
Instream Storage Structure, Jharbeda
Dewatering work is under progress.
65/100
Instream Storage Structure, Jharbeda
Cleaning of Floor area is under progress.
66/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-6, 3rd lift is under progress.
67/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Flank wall, 6th lift at Block No-5 done in presence of Client & PSS Team.
68/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Flank wall, 6th lift at Block No-5 is under progress in presence of Client & PSS Team.
69/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-18, 7th lift at Block No-3 done in presence of Client & PSS Team.
70/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-18, 7th lift at Block No-3 is under progress in presence of Client & PSS Team.
71/100
Instream Storage Structure, Hamirpur
Curing of Piers is under progress.
72/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-17, 7th lift at Block No-3 is under progress.
73/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-27, 13th lift at Block No-4 is under progress.
74/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-29, 11th lift at Block No-4 is under progress.
75/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-24, 13th lift at Block No-4 is under progress.
76/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 170 mm) of Left sluice cross cut-off Panel No-32 done in presence of Client & PSS Team.
77/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Left sluice cross cut-off Panel No-32 done in presence of Client & PSS Team.
78/100
Instream Storage Structure, Khalpal
Diaphragm wall cage placing for Left sluice cross cut-off Panel No-32 in presence of Client & PSS Team.
79/100
Instream Storage Structure, Khalpal
Excavation of Diaphragm wall Left sluice cross cut-off Panel No-32 is under progress in presence of Client & PSS Team.
80/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site in presence of QA/QC Expert and Site Engineer PMC. Cube cast at site.
81/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site in presence of QA/QC Expert and Site Engineer PMC. Cube cast at site.
82/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Exp. along with Site engineer of PMC to the ISS site. Inspected the progress of work and Intermediate Pier no 3 concreting.
83/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Exp. along with Site engineer of PMC to the ISS site. Inspected the progress of work and Intermediate Pier no 3 concreting.
84/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Exp. along with Site engineer of PMC to the ISS site. Inspected the progress of work and Intermediate Pier no 3 concreting.
85/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Exp. along with Site engineer of PMC to the ISS site. Inspected the progress of work and Intermediate Pier no 3 concreting.
86/100
UGPL, Right Lower Suktel Canal Division
Back filling and levelling work is in progress at primary filtration unit area of Pump House .
87/100
Integrated Barrage across river Kochila and across river Baitarini
Divide wall cleaning work in progress at Baitarani ISS Project-23.11.2025
88/100
Integrated Barrage across river Kochila and across river Baitarini
BAITARANI -ISS RHS abutment clean work is in progress.
89/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of Abutment wall is under progress.
90/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Curing of RHS Divide wall is under progress.
91/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for Divide wall, 2nd lift is under progress.
92/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 80mm) of LHS D/S Divide wall, 1st lift is under progress done in presence of Client & PSS Team.
93/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS D/S Divide wall, 1st lift is under progress in presence of Client & PSS Team.
94/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning & Vertical straightening of reinforcement for LHS D/S Abutment wall is under progress.
95/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS D/S Divide wall, 1st lift is under progress.
96/100
Instream Storage Structure, Jharbeda
Dewatering work is under progress.
97/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-5, 3rd lift is under progress.
98/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-6, 3rd lift is under progress.
99/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.33/mm2 for 07 days) of Pier No-31, 3rd lift and M25A20(Strength is 21.04/mm2 for 07 days) of Pier No-17, 6th lift and M25A20(Strength is 21.48/mm2 for 07 days) of Pier No-23, 9th lift and M35A20(Strength is 41.85/mm2 for 28 days) of Girder No-87 has done in presence of Client & PSS team.
100/100
Instream Storage Structure, Hamirpur
Seal beam erection work is in progress of bay No-15.
❮
❯