1/100
Instream Storage Structure, Gudvella
Fixing of precast railing with posts is in progress on 17.04.2026
2/100
Instream Storage Structure, Gudvella
• Today DTL and HM Expert Sir visited the ISS Gudvella site. During the visit, the Department JE, PMC Site engineers and agency site engineer were present.
1. The mechanical work checked by HM Expert.
2. The agency was directed to submit the design and drawings for the afflux bund and approach road without further delay.
3. DTL Sir has instructed the agency to procure stone for stone pitching and ensure its completion before the monsoon without fail.
4. Conducted 28 days CS of cubes M30A20 & M20A40 grade at field laboratory and results found 40.88 N/mm2 & 22.88 N/mm2 respectively.
5. Checked the parapet wall with posting and building and found it as per the approved design drawing.
6. Regular monitoring should be carried out to ensure quality and timely completion of the balance works.
7. Design, drawing for the road and sluice gate on afflux bund may be submitted for further approval on 17.04.2026
3/100
Instream Storage Structure, Gudvella
• Today DTL and HM Expert Sir visited the ISS Gudvella site. During the visit, the Department JE, PMC Site engineers and agency site engineer were present.
1. The mechanical work checked by HM Expert.
2. The agency was directed to submit the design and drawings for the afflux bund and approach road without further delay.
3. DTL Sir has instructed the agency to procure stone for stone pitching and ensure its completion before the monsoon without fail.
4. Conducted 28 days CS of cubes M30A20 & M20A40 grade at field laboratory and results found 40.88 N/mm2 & 22.88 N/mm2 respectively.
5. Checked the parapet wall with posting and building and found it as per the approved design drawing.
6. Regular monitoring should be carried out to ensure quality and timely completion of the balance works.
7. Design, drawing for the road and sluice gate on afflux bund may be submitted for further approval on 17.04.2026
4/100
Instream Storage Structure, Gudvella
• 1)Hoist structure erection work under progress in between P2 to P9. Alignment work under progress.
2) Remaining columns and Trestles installation work under progress.
3) 7 Gates were installed in 7 vent portions. Supporting elements work under progress.
4) Walk way and Monorail girders installation work under progress on 17.04.2026
5/100
Instream Storage Structure, Gudvella
• 1)Hoist structure erection work under progress in between P2 to P9. Alignment work under progress.
2) Remaining columns and Trestles installation work under progress.
3) 7 Gates were installed in 7 vent portions. Supporting elements work under progress.
4) Walk way and Monorail girders installation work under progress on 17.04.2026
6/100
Instream Storage Structure, Gudvella
Paint work is under progress on 17.04.2026
7/100
Instream Storage Structure, Gudvella
Manorail girder installation work under progress at P3 to P4 on 17.04.2026
8/100
Instream Storage Structure, Gudvella
Shuttering work is under progress for parapet wall post's on 17.04.2026
9/100
Instream Storage Structure, Gudvella
Brick work at 1st floor of building is under progress at site on 17.04.2026
10/100
Instream Storage Structure, Gudvella
Casting of precast parapet railing is under progress on 16.04.2026
11/100
Instream Storage Structure, Gudvella
• Visited ISS Gudvella site along with IE expert .Dept JE, Site engineers of PMC n agency were present.
1. Cast of concrete RCC M25A20 grade of Posting at D/s side of deck slab no-3 in between P2 and P3 is in progress
2. Slump checked at site and slump value is 70mm
3. Brick work of building is in progress
4. Conducted test for 7 days compressive strength of concrete cube PCC M20 A40 grade at field laboratory and result found 17.77 N/mm2
5. Test for 28 days compressive strength of concrete cube RCC M30 A20 grade conducted and result found 41.56 N/mm2 on 16.04.2026
12/100
Instream Storage Structure, Gudvella
• Visited to ISS at Gudvela all the site engineers and deptt je were present. It was observed that the construction of the downstream (d/s) parapet wall has been initiated and is in progress. The work is expected to be completed within the current month. Then wiring coat to the slab will be started.
All other concrete works related to the structure have been completed.
However, it is noted that the required stone materials have not yet been collected at the site, which may affect the progress of the remaining associated works.
Suggestion:- 1. The concerned agency should ensure immediate procurement and stacking of the required stone materials at the site without further delay.
2. The parapet construction work should be expedited to meet the targeted completion timeline.
3. Proper planning and coordination should be maintained to avoid any hindrance in subsequent works due to material shortage.
4. Regular monitoring should be carried out to ensure quality and timely completion of the balance works.
5. Design, drawing for the road and sluice gate on afflux bund may be submitted for further approval on 16.04.2026
13/100
Instream Storage Structure, Gudvella
Conducted slump test of posting at D/s side of span -3 in between P2 to P3 in the presence of Dept JE, site engineers of PMC n agency at site where result found 70mm on 16.07.2026
14/100
Instream Storage Structure, Gudvella
Paint work is under progress on 16.04.2026
15/100
Instream Storage Structure, Gudvella
Hoist bridge and CDU Rope drum installation work under progress at P8 to P9 on 16.04.2026
16/100
Instream Storage Structure, Gudvella
Fixing of precast railing with posts at the downstream side of span 3 is in progress on 16.04.2026
17/100
Instream Storage Structure, Gudvella
Brick work at 1st floor of building is under progress at site on 16.04.2026
18/100
UGPL, Right Lower Suktel Canal Division
Inspected of BFV and BFV Chamber is in progress for 180mm DIa HDPE pipe from J-3027 to J-3230 (p-3202) at village Kharjhura.
19/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of CC block at D/S right flared out wall upto RL-239.40m is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 80mm on 17.04.2026
20/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of CC block at D/S right flared out wall upto RL-239.40m is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 80mm on 17.04.2026
21/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade for 2nd stage at pier no.7&8 for 6th lift of bay-8 is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 84mm on 17.04.2026
22/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade for 2nd stage at pier no.7&8 for 6th lift of bay-8 is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 84mm on 17.04.2026
23/100
Instream Storage Structure, Nandagaon
• 2.The casting of CC block at following area has been checked in presence of PM,EPC agency, Site Engineers of PMC & EPC Agency:
(i) Shuttering for CC block at D/S right Flared out wall i.e size 25.8x1.5x0.6m & 5.6x1.8x0.6m upto RL-239.40m is completed.
(ii). Filling of inverted filter materials covering with LDPE paper at adjacent to each CC block in earth side are done before placement.
(iii) Application of 2 coat bitumen paint at cj's concrete surface is done.
(iv). Area is ready and passed by SE KID, Bh. Patna to place concrete with PCC M20A20 grade on 17.04.2026
24/100
Instream Storage Structure, Nandagaon
• 1. Fixing & fittings and alignment of 2nd. stage embedded parts and fixing of number of dowel bars as per drawing at roller tracks of both stoplog & service gate grooves at bay No.-9;&11 of Pier No. 8&9 for 5th lift and pier no. 10&11 for 2nd lift have been checked and found correct by HM Expert of PMC during his site visit on dt.13.04.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 17.04.2026
25/100
Instream Storage Structure, Nandagaon
De-Shuttering & Shuttering for 2nd stage concrete is in progress at pier no.8 on 17.04.2026
26/100
Instream Storage Structure, Nandagaon
Shuttering for CC block is in progress at D/S right flared out wall on 17.04.2026
27/100
Instream Storage Structure, Nandagaon
Reinforcement binding is in progress at U/S right divide wall on 17.04.2026
28/100
Instream Storage Structure, Nandagaon
Reinforcement binding of kerb at deck slab is in progress on 17.04.2026
29/100
Instream Storage Structure, Nandagaon
M25 A20 grade casting on dated 09/04/26 at U/S right divide wall raft for 3rd lift and tested on dated 16/04/26(7 day) in presence of above technical person the ave. cube strength is 24.29N/mm2 on 16.04.2026
30/100
Instream Storage Structure, Nandagaon
M35 A20 grade casting on dated 19/03/26 at 2nd stage at pier no.1 & left abutment for 4th lift of under sluice bay-1 tested on dated 16/4/26(28 day) in presence of DTL, QC exp. site engineering of PMC & site engineering of EPC agency the ave. Cube strength is 47.70N/mm2 against design strength 44..07N/mm2 on 16.04.2026
31/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade at U/S right divide wall for 2nd/final lift from RL-232.90m to RL-234.00m is in progress in presence of PM EPC agency,Site Engineer of PMC & EPC agency. The slump test value is 84mm on 16.04.2026
32/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade at U/S right divide wall for 2nd/final lift from RL-232.90m to RL-234.00m is in progress in presence of PM EPC agency,Site Engineer of PMC & EPC agency. The slump test value is 84mm on 16.04.2026
33/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade at U/S right divide wall for 2nd/final lift from RL-232.90m to RL-234.00m is in progress in presence of PM EPC agency,Site Engineer of PMC & EPC agency. The slump test value is 84mm on 16.04.2026
34/100
Instream Storage Structure, Nandagaon
• 2.Checked the area before placement of concrete at U/S right divide wall Raft top PCC with following activities in presence of PM,EPC agency,Site Engineer of PMC & Site Engineer of EPC Agency, ISS, Nandagaon:
(i).Shuttering of U/S right divide wall raft top PCC with M20A20 grade for 2nd/final lift from RL-232.90m to RL-234.00m is completed.
(ii).The concrete surface is cleaned properly through air water jetting and passed by SE, KID Bhawanipatna for placing concrete with PCC M20A20 grade on 16.04.2026
35/100
Instream Storage Structure, Nandagaon
• 1. The area of placing concrete at U/S right divide wall has been checked before placement in presence of PM of EPC Agency, Site Engineer of PMC & EPC Agency as follows:
(i).The reinforcement in binding, tying n spacing of both vertical main & horiz. dist. bar and tie bars for casting of U/S right divide wall for 2nd lift from RL-232.90m to RL-234.00m are found completed.
(ii).Rigid & smooth shuttering and maintained clear cover of 75mm from main bar to shutter plates are done.
(iii).The area is cleaned properly through air water jetting and passed by SE, KID, Bhawanipatna for placing with RCC on 16.04.2026
36/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No-0213082- C06A near village Gandabahal.
37/100
Instream Storage Structure, Nandagaon
2nd stage embedded parts Roller track and Guide erection work under progress in Under Sluice gate No-04 on 16.04.2026
38/100
Instream Storage Structure, Nandagaon
Shuttering for CC block is in progress at D/S right flared out wall on 16.04.2026
39/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress at left abutment on 16.04.2026
40/100
UGPL, Right Lower Suktel Canal Division
Valve Chamber Pre-cast slab de shuttering work is in progress of Pump House.
41/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door & angle fixing work is in progress OCS No:-0213084-C02B at village KhairaPali in presence of PMC team.
42/100
Barrage across river Turi & Guntat
Meeting with land loosers of TGIP in presence of MLA, Nabarangpur, Collector & Dist. Magistrate, Nabarangpur, CE & BM, I.K.Basin, S.E., N.I.D., D.T..L, PMC and other officials.
43/100
UGPL, Left Lower Suktel Canal Division
Butt Fusion jointing work is in progress for 75mm and 125mm Dia HDPE pipe at RO 109, RM-6 near village Sakma.
44/100
UGPL, Left Lower Suktel Canal Division
HDPE Tee (140 X 75X 75)mm connection work is in progress at LO-324, LM-17, near village Birkel in presence of PMC team.
45/100
UGPL, Left Lower Suktel Canal Division
HDD machine road pushing work is in progress of 140mm Dia HDPE pipe main line at Lo-180(Lm-9) near village Bhadra in presence of PMC team.
46/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI to HDPE pipeline connection at J-287, LM-15 near village Buromunda in presence of DoWR AE and PMC team.
47/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
PMC team- Chandikhole visited ISS- Chaudhurygada today. PMC Site engineers including agency representatives were also present at site.
48/100
Integrated Barrage across river Kochila and across river Baitarini
LHS Wing wall & Counterfort wall Shuttering work is in progress at Baitarani ISS.
49/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-20 done in presence of Client & PSS Team.
50/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-20 is under progress in presence of Client & PSS Team.
51/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-1, 5th lift done in presence of Client & PSS Team.
52/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-1, 5th lift is under progress in presence of Client & PSS Team.
53/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.04/mm2 for 28 days) of Pier No-13, 12th lift and (Strength is 30.99/mm2 for 28 days) of Abutment (A1), 5th lift at Block No-1 and (Strength is 21.63/mm2 for 07 days) of Pier No-21, 12th lift and M35A20 (Strength is 42.37/mm2 for 28 days) of Gantry Girder No-3 has done in presence of Client & PSS team.
54/100
Instream Storage Structure, Hamirpur
Excavation of D/S at Block No-1 is under progress.
55/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Abutment (A1), 4th lift at Block No-1 is under progress.
56/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4, 5th is under progress.
57/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-15, 14th is under progress.
58/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
59/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall Raft at Block No-5 is under progress.
60/100
Instream Storage Structure, Jharbeda
Slump testing M25A20 (Value 80 mm) of Pier No-8, 4th lift done in presence of Client & PSS Team.
61/100
Instream Storage Structure, Jharbeda
Concreting M25A20 of Pier No-8, 4th lift is under progress in presence of Client & PSS Team.
62/100
Instream Storage Structure, Jharbeda
Mud cleaning work is under progress.
63/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for RHS (D2) pier portion Footing is under progress.
64/100
Instream Storage Structure, Jharbeda
De-Shuttering of Pier No-6 is under progress.
65/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-6 to Pier No-7 slope portion Wearing coat is under progress.
66/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for End sill, Top Layer is under progress.
67/100
Instream Storage Structure, Jharbeda
Curing of RHS Flank wall, 1st Layer is under progress.
68/100
Instream Storage Structure, Jharbeda
Curing of (A2) Footing is under progress.
69/100
Instream Storage Structure, Khalpal
Inspection by Addl. C.E Angul with S.E, AID, I.E.E of PSS team along with EPC Agency at site and Checked the level of filter media of gravity floor for (Barrage Bay No-3) & Shuttering of piers.
70/100
Instream Storage Structure, Khalpal
Curing of Piers, Cut-off & Barrage Bay (Raft) work is in progress.
71/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for LHS side Raft under sluice portion is under progress.
72/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 80 mm) of LHS D/S Counterfort & Wing wall, 3rd lift done in presence of Client & PSS Team.
73/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS D/S Counterfort & Wing wall, 3rd lift is under progress in presence of Client & PSS Team.
74/100
MMIP, Bankatira Barrage Project
Sheet Pile work in progress at site.
75/100
Instream Storage Structure, Gudvella
Casting of precast parapet railing under progress on 15.04.2026
76/100
Instream Storage Structure, Gudvella
Paint work is under progress on 15.04.2026
77/100
Instream Storage Structure, Gudvella
Hoist bridge and CDU Rope drum installation work under progress at P7 to P8 on 15.04.2026
78/100
Instream Storage Structure, Gudvella
Shuttering of Railing and posting of parapet wall of deck slab on 15.04.2026
79/100
Instream Storage Structure, Gudvella
Brick work at 1st floor of building is under progress at site on 15.04.2026
80/100
Instream Storage Structure, Gudvella
Fixing of precast railing with posts at the downstream side of span 2 is in progress on 14.04.2026
81/100
Instream Storage Structure, Gudvella
Casting of precast railing over parapet wall on the deck slab is in progress with dimensions 1.424 m × 0.13 m × 0.17 m on 14.04.2026
82/100
Instream Storage Structure, Gudvella
Paint work under progress on 14.04.2026
83/100
Instream Storage Structure, Gudvella
Hoist bridge and CDU Rope drum installation work under progress at P6 to P7 on 14.04.2026
84/100
Instream Storage Structure, Gudvella
Shuttering of Railing and posting of parapet wall of deck slab on 14.04.2026
85/100
Instream Storage Structure, Gudvella
Brick work at 1st floor of building is underprogress at site on 14.04.2026
86/100
Instream Storage Structure, Gudvella
Casting of precast railing over parapet wall on the deck slab has been commenced with dimensions 1.424 m × 0.13 m × 0.17 m on 13.04.2026
87/100
Instream Storage Structure, Gudvella
CDU ROPE drum installation work under progress at P3 to P5 on 13.04.2026
88/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No-0213125-C08A near village Jamgaon.
89/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for laying of 110mm Dia HDPE pipe from J-5335 to 2305099-C03 at Village Bhadrapali .
90/100
Instream Storage Structure, Gudvella
Brick work at building area is under progress at site on 13.04.2026
91/100
Instream Storage Structure, Gudvella
Shuttering of Railing and posting of parapet wall of deck slab on 13.04.2026
92/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of CC block at D/S right flared out wall is completed in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 78mm on 15.04.2026
93/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of CC block at D/S right flared out wall is completed in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 78mm on 15.04.2026
94/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.8,9,10&11 is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 85mm on 15.04.2026
95/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.8,9,10&11 is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 85mm on 15.04.2026
96/100
Instream Storage Structure, Nandagaon
• 2.The casting of CC block at following area has been checked in presence of PM,EPC agency, Site Engineers of PMC & EPC Agency:
(i)1no. CC block at D/S right Flared out wall i.e 1no. of size 18.8x1.5x0.6m upto RL-238.80m is completed.
(ii). Filling of inverted filter materials covering with LDPE paper at adjacent to each CC block in earth side are done before placement.
(iii) Application of 2 coat bitumen paint at cj's concrete surface is done.
(iv). Area is ready and passed by SE KID, Bh. Patna to place concrete with PCC M20A20 grade on 15.04.2026
97/100
Instream Storage Structure, Nandagaon
• 1. Fixing & fittings and alignment of 2nd. stage embedded parts and numbers of dowel bars as per drawing at roller tracks of both stoplog & service gate grooves at bay No.-9;&11 of Pier No. 8&9 for 5th lift and pier no. 10&11 for 2nd lift have been checked and found correct by HM Expert of PMC during his site visit on dt.13.04.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 15.04.2026
98/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no.11 on 15.04.2026
99/100
Instream Storage Structure, Nandagaon
Shuttering for CC blocks is in progress at D/S right flared out wall on 15.04.2026
100/100
Instream Storage Structure, Nandagaon
Shuttering is in progress at U/S right divide wall on 15.04.2026
❮
❯