1/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of D/S Flank Cut-off wall, 3rd lift at Block No-1 done in presence of Client & PSS Team.
2/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flank Cut-off wall, 3rd lift at Block No-1 is under progress in presence of Client & PSS Team.
3/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-35 done in presence of Client & PSS Team.
4/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-35 is under progress in presence of Client & PSS Team.
5/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.26/mm2 for 28 days) of Pier No-3, 7th lift and (Strength is 21.63/mm2 for 07 days) of U/S Flank wall, 2nd lift at Block No-1 and M35A20 (Strength is 38.07/mm2 for 07 days) of Flank wall Cut-off, 1st lift at Block No-1 and (Strength is 20.89/mm2 for 07 days) of Pier No-1, 10th lift has done in presence of Client & PSS team.
6/100
Instream Storage Structure, Hamirpur
Site inspected by S.E, RID in presence A.E.E, A.E RID, IEE & Site Engineer of PSS team along with EPC Agency and discussed with EPC Agency about the Progress of work.
7/100
Instream Storage Structure, Hamirpur
Barrage bay groove 2nd stage embedded parts side guide erection work is in progress at Bay No-13.
8/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall Cut-off at Block No-1 is under progress.
9/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
10/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4, 7th lift is under progress.
11/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-1, 10th lift is under progress.
12/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Pier No-2, 9th lift is under progress.
13/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Abutment (A1), 8th lift at Block No-1 is under progress.
14/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Flank wall Block No-1 is under progress.
15/100
Instream Storage Structure, Gudvella
Brickwork of the parapet wall of the building is in progress. Inside plastering is also in progress and outside plastering will start shortly on 11.06.2026
16/100
Instream Storage Structure, Gudvella
Stone packing under progress at u/s side on 11..06.2026
17/100
Instream Storage Structure, Gudvella
Stone packing work is under progress at d/s side on 11.06.2026
18/100
Instream Storage Structure, Gudvella
Mechanical work under progress at site on 11.06.2026
19/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 80 mm) of Pier No-8, 6th lift done in presence of Client & PSS Team.
20/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 11.06.2026
21/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-8, 6th lift is under progress in presence of Client & PSS Team.
22/100
Instream Storage Structure, Khalpal
Site inspected by S.E, RID in presence A.E.E, A.E RID, IEE & Site Engineer of PSS team along with EPC Agency and discussed with EPC Agency about the Progress of work.
23/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 11.06.2026
24/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 85 mm) of Pier No-20, 2nd lift done in presence of Client & PSS Team.
25/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-20, 2nd lift is under progress in presence of Client & PSS Team.
26/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 85 mm) of Barrage Bay No-2 Gravity floor done in presence of Client & PSS Team.
27/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Barrage Bay No-2 Gravity floor is under progress in presence of Client & PSS Team.
28/100
Instream Storage Structure, Khalpal
Shuttering & Binding of reinforcement for RHS Double pier No-25, 2nd lift is in progress.
29/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
30/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at right abutment upto RL-246.30m is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 84mm on 11.06.2026
31/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at right abutment upto RL-246.30m is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 84mm on 11.06.2026
32/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at right abutment is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 87mm on 11.06.2026
33/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at right abutment is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 87mm on 11.06.2026
34/100
Instream Storage Structure, Nandagaon
• 1(i).Fixing & fittings and alignment of All trestle and columns foundation bolts measurements has been checked at right abutment for Blockout area of 6.8m length and found correct by HM Expert of PMC during his site visit on dt.01.06.2026 in presence of mechanical Site Engineers of PMC and EPC Agency.
(ii) Rigid and smooth shuttering for Blockout area with M35A20 grade at right abutment from RL-245.40m to RL-246.30m are found completed.
(iii).The area is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with M35A20 grade on 11.06.2026
35/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no.12&13 on 11.06.2026
36/100
Instream Storage Structure, Nandagaon
Shuttering for D/S curtain wall under sluice bay area is in progress on 11.06.2026
37/100
Instream Storage Structure, Nandagaon
Shuttering for plinth beam of office building is in progress on 11.06.2026
38/100
UGPL, Right Lower Suktel Canal Division
Joint verification work is in progress of outlet OCS No. 0213105-CO4A at village Kandapali in the presence of SDO along with DOWR officials, PMC team and L&T Team.
39/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE Tee (75 X 125 ×75)mm connection at RO-104 ,RM-6, near village Kuturapali in presence of PMC team.
40/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE to HDPE line connection Rm-6, Ro-104 at village Kuturapali.
41/100
UGPL, Left Lower Suktel Canal Division
MS line Land Levelling work is in progress J-108 to J-416 at village Kushmel in presence of PMC team.
42/100
Barrage across river Turi & Guntat
Today Chief Engineer, I & K Basin, Bariniput, Jaypur met with Hon'ble M. L. A., Nabarangapur at District Planning Board Office.
43/100
Barrage across river Turi & Guntat
Today Chief Engineer, I &K Basin, Bariniput, Jaypur met with Collector & D. M., Nabarangapur.
44/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door and angle fixing work is in progress OCS No-: 0213131-C08B at village Kulthipali in presence of PMC team.
45/100
UGPL, Left Lower Suktel Canal Division
A video conference meeting was held under the chairmanship of PMU TL in the office chamber of the CCE regarding the progress and balance work of Pump House, Pipe laying, all valves fitting of pipe line network, OMS instrumentation installation, chamber erection, outlet fixing, kilometre marking, Scada system and formation of Pani panchayat in presence of CCE, SE, SDO and other departmental of DoWR, TL (PES & PSS), RE of PSS, PMC team along with representative of Agency.
46/100
UGPL, Right Lower Suktel Canal Division
A video conference meeting was held under the chairmanship of PMU TL in the office chamber of the CCE regarding the progress and balance work of Pump House, Pipe laying, all valves fitting of pipe line network, OCS instrumentation installation, chamber erection, outlet fixing, kilometre marking, Scada system and formation of Pani panchayat in presence of SE, SDO and other departmental of DoWR, TL (PES & PSS), RE of PSS, PMC team along with representative of Agency.
47/100
Instream Storage Structure, Gudvella
• Visited SE to ISS Gudvella. During his visit the Department JE, PMC site engineers and agency engineers were present.
1. Inspected the overall site conditions and instructed the agency to expedite and complete the remaining works at the earliest.
2. Checked the mechanical works and observed the operation of one gate, which was found to be functioning satisfactorily on 10.06.2026
48/100
Instream Storage Structure, Gudvella
• Visited SE to ISS Gudvella. During his visit the Department JE, PMC site engineers and agency engineers were present.
1. Inspected the overall site conditions and instructed the agency to expedite and complete the remaining works at the earliest.
2. Checked the mechanical works and observed the operation of one gate, which was found to be functioning satisfactorily on 10.06.2026
49/100
Instream Storage Structure, Gudvella
Today the Vice President of Zilla Parishad, Balangir visited ISS Gudvella on 10.06.2026
50/100
Instream Storage Structure, Gudvella
Today the Vice President of Zilla Parishad, Balangir visited ISS Gudvella on 10.06.2026
51/100
Instream Storage Structure, Gudvella
Stone packing work is under progress at d/s side on 10.06.2026
52/100
Instream Storage Structure, Gudvella
Mechanical work under progress at site on 10.06.2026
53/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 10.06.2026
54/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 10.06.2026
55/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A40 grade at D/S curtain wall of undersluice bay area is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 85mm on 10.06.2026
56/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A40 grade at D/S curtain wall of undersluice bay area is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 85mm on 10.06.2026
57/100
Instream Storage Structure, Nandagaon
• 2.(i) Checked the area before placement of concrete at D/S curtain wall stared from right divide wall with PCC M15A40 grade of 2.0m width & 0.50m thickness with following activities in presence of PM of EPC Agency,Site Engineers of PMC & EPC Agency:
(ii) The area has been excavated upto the design depth and foundation bottom is well watered compacted by mechanical means.
(iii)The area is ready and passed by SE, KID Bhawanipatna for placing concrete with PCC M15A40 grade on 10.06.2026
58/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no. 12,13& right abutment is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 84mm on 10.06.2026
59/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no. 12,13& right abutment is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 84mm on 10.06.2026
60/100
UGPL, Right Lower Suktel Canal Division
OCS pre-cast chamber installation work is in progress of OCS no-0213122-C06A near village Bhursipali in presence of PMC team.
61/100
Instream Storage Structure, Nandagaon
• 1.Fixing & fittings and alignment of 2nd. stage embedded parts and numbers of dowel bars provided as per approved drawing at roller tracks of both stoplog & service gate grooves at bay no.13 of pier no.12 for 10th lift & 8th lift and pier no.13 for 10th lift & 9th lift and bay no.14 of pier no. 13&right abutment for 2nd &3rd lift have been checked and found correct by HM Expert of PMC during his site visit on dt.01.06.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for M35A20 grade on 10.06.2026
62/100
Instream Storage Structure, Nandagaon
Pier no 3 barrage bay gate groove cleaning process under progress on 10.06.2026
63/100
Instream Storage Structure, Nandagaon
Shuttering for Block out portion is in progress at right abutment on 10.06.2026
64/100
Instream Storage Structure, Nandagaon
Shuttering for plinth beam of office building is in progress on 10.06.2026
65/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for fixing of branch Tee (110 X 75×75)mm connection from J-0213119- C20 to J-02013119- C20B, at village Bileisarda in presence of PMC team.
66/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.86/mm2 for 28 days) of U/S Flared out Cut-off wall at Block No-1 and (Strength is 30.87/mm2 for 28 days) of Pier No-15, 14th lift and (Strength is 21.18/mm2 for 07 days) of Flank wall Cut-off, 1st lift at Block No-1 and (Strength is 20.89/mm2 for 07 days) of Pier No-1, 10th lift has done in presence of Client & PSS team.
67/100
Instream Storage Structure, Hamirpur
Pier No-16 & 17 Girder is being lifted for fixing in (Bay 14) work is in progress.
68/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-7 bracket plate welding work is in progress.
69/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
70/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-4, 5th lift is under progress.
71/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Pier No-1, 10th lift is under progress.
72/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Pier No-2, 9th lift is under progress.
73/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Abutment (A1), 8th lift at Block No-1 is under progress.
74/100
UGPL, Left Lower Suktel Canal Division
OMS manifold installation work is in progress at RO-242A, RM-13, near village Kusang in presence of PMC team.
75/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE to HDPE connection at Lm-5 j- 270, near village sujia in presence of PMC team.
76/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI to HDPE connection at Lm-5 j-356, near village sujia in presence of PMC team visited by DoWR SDO.
77/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall Cut-off at Block No-1 is under progress.
78/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE Tee (75 X 140 ×75)mm connection at LO-193, LM-10, near village Kandajuri in presence of DoWR AE and PMC team.
79/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for OMS manifold installation at RO-242A, RM-13 near village Kusanga in presence of PMC team.
80/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M20A20 (Value 85 mm) of Gravity floor done in presence of Client & PSS Team.
81/100
Instream Storage Structure, Jharbeda
Cleaning of Pier No-9 area work is in progress.
82/100
Instream Storage Structure, Jharbeda
Shuttering & Binding of reinforcement for U/S Pier No-7 to Pier No-8 wearing coat is under progress.
83/100
Instream Storage Structure, Jharbeda
Shuttering of RHS U/S Flank wall is under progress.
84/100
Instream Storage Structure, Jharbeda
De-Shuttering of RHS D/S Training wall is under progress.
85/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 85 mm) of Barrage Bay No-2 Gravity floor done in presence of Client & PSS Team.
86/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Barrage Bay No-2 Gravity floor is under progress in presence of Client & PSS Team.
87/100
Instream Storage Structure, Khalpal
Binding of reinforcement for RHS Double pier No-25, 2nd lift is in progress.
88/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
89/100
Instream Storage Structure, Gudvella
The DCAC meeting for the Right Side Land Acquisition was successfully held under the chairmanship of the Collector Sir Sir. The meeting was attended by the ADM Revenue, LAO Balangir, Tahsildar Tusura, Horticulture Officer, Forest Officers, SE, SDO, AE and JE of the Irrigation Department. All concerned officials participated in the discussion regarding the land acquisition process on 09.06.2026
90/100
Instream Storage Structure, Gudvella
Plastering work is under progress at control room building on 09.06.2026
91/100
Instream Storage Structure, Gudvella
Stone packing under progress at d/s side on 09.06.2026
92/100
Instream Storage Structure, Gudvella
Mechanical work under progress at site on 09.06.2026
93/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 09.06.2026
94/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 09.06.2026
95/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no. 11, 12 & 13 on 09.06.2026
96/100
Instream Storage Structure, Nandagaon
Shuttering for plinth beam of office building is in progress on 09.06.2026
97/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-34 done in presence of Client & PSS Team.
98/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-34 is under progress in presence of Client & PSS Team.
99/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of D/S Flank Cut-off wall, 2nd lift (River side) at Block No-1 done in presence of Client & PSS Team.
100/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flank Cut-off wall, 2nd lift (River side) at Block No-1 is under progress in presence of Client & PSS Team.
❮
❯