1/100
Instream Storage Structure, Gudvella
Paint work under progress.(trestle, column) on 18.03.2026
2/100
Instream Storage Structure, Gudvella
Roller track and guide installation work under progress at A1 & P1 on 18.03.2026
3/100
Instream Storage Structure, Gudvella
Curing at building area is under progress at site on 18.03.2026
4/100
Instream Storage Structure, Gudvella
Placement of CC block is under progress at u/s side of site on 18.03.2026
5/100
Instream Storage Structure, Gudvella
Shuttering work at block out area on 18.03.2026
6/100
Instream Storage Structure, Gudvella
Shuttering work of CC BLOCK is under progress at site on 18.03.2026
7/100
Instream Storage Structure, Gudvella
Cast of concrete 1st lift RCC M30A20 grade at block out area from P2 to P8 with RL 159.50m to 160.40m is under progress in the presence of Dept JE, site engineer of PMC and agency at site. The slump test value is 75mm on 17.03.2026
8/100
Instream Storage Structure, Gudvella
Cast of concrete 1st lift RCC M30A20 grade at block out area from P2 to P8 with RL 159.50m to 160.40m is under progress in the presence of Dept JE, site engineer of PMC and agency at site. The slump test value is 75mm on 17.03.2026
9/100
Instream Storage Structure, Gudvella
• Foundation bolts have been fixed as per the approved design and drawing and were checked by the PMC Mechanical Expert, PMC Mechanical Site Engineer, Agency Mechanical Engineer, department staffs and pmc staffs.
After successful inspection the shuttering, centring and reinforcement works were found to be completed properly. The surface was cleaned using an air water jet to remove dust and debris(P2 to P8).
Hence the area is allowed for concreting with M30A20 grade concrete. RL 159.50 m to 160.40 m on 17.03.2026
10/100
Instream Storage Structure, Gudvella
Roller track and guide installation work under progress at A1 & P1 on 17.03.2026
11/100
Instream Storage Structure, Gudvella
Paint work is under progress on 17.03.2026
12/100
Instream Storage Structure, Gudvella
Brick work at building area on 17.03.2026
13/100
Instream Storage Structure, Gudvella
Shuttering work is under progress at blockout area on 17.03.2026
14/100
Instream Storage Structure, Gudvella
Shuttering work of CC BLOCK is under progress at site on 17.03.2026
15/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 2nos. Cross girders at middle double pier is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency.. The slump test value is 85mm on 18.03.2026
16/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 2nos. Cross girders at middle double pier is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency.. The slump test value is 85mm on 18.03.2026
17/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of 2nos. CC blocks at D/S right Flared out wall i.e 1no. of size 6.0x1.8x0.6m from sec. 5-5 to sec. 6-6 for 4th lift & 1no. of size 6.0x1.5x0.6m from sec.4-4 to sec.5-5 for 3rd lift upto RL-238.20m is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 83mm on 18.03.2026
18/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of 2nos. CC blocks at D/S right Flared out wall i.e 1no. of size 6.0x1.8x0.6m from sec. 5-5 to sec. 6-6 for 4th lift & 1no. of size 6.0x1.5x0.6m from sec.4-4 to sec.5-5 for 3rd lift upto RL-238.20m is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 83mm on 18.03.2026
19/100
Instream Storage Structure, Nandagaon
• 2. Reinforcement works including shuttering for casting of 2nos. cross girders with RCC M35A20 grade at middle double pier is completed and checked in presence of PM,EPC agency, Site Engineers of PMC and Site Engineer of EPC Agency as follows:
(i) Laying & placing in proper position of 2 layers 16mm dia bottom main bars @ 3nos. at 1st.layer & 2nos. at 2nd layer tied with 10mm dia 2-Legged stirrups @150mm C/C including binding 10mm dia dist. bars on both sides of vertical faces of girders are completed.
(ii) Rigid and smooth shuttering with 40mm clear cover at bottom and both vertical faces are completed.
(iii) Fixing & placing of 8mm dia B-type mesh bars @ 2 layers at both end points of girder is completed. iv)The area is ready and passed by SE KID Bhawanipatna for placing with RCC M35A20 grade on 18.03.2026
20/100
Instream Storage Structure, Nandagaon
• 1. The casting of CC blocks at following area has been checked in presence of PM,EPC agency, Site Engineers of PMC & EPC Agency:
(i)2Nos. CC blocks at D/S right Flared out wall i.e 1no. of size 6.0x1.8x0.6m from sec. 5-5 to sec. 6-6 for 4th lift & 1no. of size 6.0x1.5x0.6m from sec.4-4 to sec.5-5 for 3rd lift upto RL-238.20m is completed.
(ii). Filling of inverted filter materials covering with LDPE paper at adjacent to each CC block in earth side are done before placement.
(iii) Application of 2 coat bitumen paint at cj's concrete surface is done.
(iv). Area is ready and passed by SE KID, Bh. Patna to place concrete with PCC M20A20 grade on 18.03.2026
21/100
Instream Storage Structure, Nandagaon
All trestle and columns foundation bolts all measurements checked as per drawings from pier 1 to pier 7. Hence ready for concrete on 18.03.2026
22/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no-1&2 for 8th lift of undersluice bay-2 is in progress in presence of PM EPC agency Site Engineers of PMC & EPC agency. The slump test value is 86mm on 18.03.2026
23/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no-1&2 for 8th lift of undersluice bay-2 is in progress in presence of PM EPC agency Site Engineers of PMC & EPC agency. The slump test value is 86mm on 18.03.2026
24/100
Instream Storage Structure, Nandagaon
Monorail walkway MIG welding under progress on 18.03.2026
25/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no-2 on 18.03.2026
26/100
Instream Storage Structure, Nandagaon
Foundation excavation is in progress at U/S right divide wall on 18.03.2026
27/100
Instream Storage Structure, Nandagaon
Shuttering is in progress at D/S right flared out wall Block-2 on 18.03.2026
28/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for cross girder is in progress at middle double pier on 18.03.2026
29/100
Instream Storage Structure, Nandagaon
Curing is in progress at RCC deck slab on 18.03.2026
30/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A40 grade at D/S curtain wall of 1.0m ht. and 1.0m width from RL-232.50m to RL-233.50m is in progress in presence of PM EPC agency Site Engineers of PMC & EPC agency. The slump test value is 76mm on 17.03.2026
31/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A40 grade at D/S curtain wall of 1.0m ht. and 1.0m width from RL-232.50m to RL-233.50m is in progress in presence of PM EPC agency Site Engineers of PMC & EPC agency. The slump test value is 76mm on 17.03.2026
32/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at right abutment from double CF wall CJ to D/S EJ for 9th lift upto RL-244.50m is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 86mm on 17.03.2026
33/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at right abutment from double CF wall CJ to D/S EJ for 9th lift upto RL-244.50m is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 86mm on 17.03.2026
34/100
Instream Storage Structure, Nandagaon
• 3.Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at under sluice bay No.2 of Pier No. 1&2 for 8th lift has been checked and found correct by HM Expert of PMC during his site visit on dt.11.03.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 17.03.2026
35/100
Instream Storage Structure, Nandagaon
• 2.(i) Checked the area before placement of concrete at D/S curtain wall with following activities in presence of PM of EPC Agency,Site Engineers of PMC & EPC Agency:
(ii) Rigid and smooth shuttering for curtain wall with PCC M15A40 grade for 1st. lift of 1.00 mt. ht. and 1.0m width from RL-232.50m to RL-233.50m are found completed.
(iii)The concrete surface is cleaned properly through air water jetting and passed by SE, KID Bhawanipatna for placing concrete with PCC M15A40 grade on 17.03.2026
36/100
Instream Storage Structure, Nandagaon
• 1.Checked the area of right abutment along with CF walls with following activities in presence of PM, EPC agency, Site Engineers of PMC & Site Engineer of EPC agency:-
(i).Checked the reinforcement in binding, tying n spacing of both vertical main & horiz. dist. bars of right abutment along with CF walls from double CF wall CJ to D/S EJ for 9th lift of stilling basin area from RL-243.10m to RL-244.50m completed.
(ii).Rigid n smooth shuttering with 75mm clear cover using cover blocks of 75mm are done.
(iii).Placing of expansion joint material along the EJ between D/S right flank wall & abutment wall is done as per approved drawing n design.
(iv).The concrete surface is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with RCC M25A20 grade on 17.03.2026
37/100
Instream Storage Structure, Nandagaon
Monorail walkway MIG welding under progress on 17.03.2026
38/100
Instream Storage Structure, Nandagaon
Foundation bolts, anchor bolts installation work with proper measurements under progress in Pier No. 04 &-06 on 17.03.2026
39/100
Instream Storage Structure, Nandagaon
Foundation bolts, anchor bolts installation work with proper measurements under progress in Pier No. 04 &-06 on 17.03.2026
40/100
Instream Storage Structure, Nandagaon
Foundation excavation is in progress at U/S right divide wall on 17.03.2026
41/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-15, 7th lift done in presence of Client & PSS Team.
42/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-15, 7th lift is under progress in presence of Client & PSS Team.
43/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no.1 on 17.03.2026
44/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Gantry Girder No-2 done in presence of Client & PSS Team.
45/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-2 is under progress in presence of Client & PSS Team.
46/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering is in progress at right abutment, Block-2 on 17.03.2026
47/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.04/mm2 for 28 days) of Pier No-6, 6th lift and (Strength is 30.91/mm2 for 28 days) of Pier No-14, 11th lift and (Strength is 21.48/mm2 for 07 days) of D/S Flared out cut-off wall, 3rd lift and M35A20 (Strength is 37.78/mm2 for 07 days) of Cross Girder (Bay No-25) has done in presence of Client & PSS team.
48/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for cross girder is in progress at middle double pier on 17.03.2026
49/100
Instream Storage Structure, Hamirpur
Barrage service gate single pier hoist bridge No-17 assembly work in under progress.
50/100
Instream Storage Structure, Hamirpur
Barrage service gate single pier hoist bridge No-17 lifting plate drilling work in under progress.
51/100
Instream Storage Structure, Nandagaon
Reinforcement binding at pier no. 4 is in progress on 17.03.2026
52/100
Instream Storage Structure, Hamirpur
Binding of reinforcement of Pier No-3, 3th lift is under progress.
53/100
Instream Storage Structure, Hamirpur
Binding of reinforcement of Deck slab (Bay No-22 & 23) is under progress.
54/100
Instream Storage Structure, Nandagaon
Shuttering at D/S right flared out wall, Block-2 is in progress on 17.03.2026
55/100
Instream Storage Structure, Hamirpur
Binding of reinforcement of Pier No-4, 3th lift is under progress.
56/100
Instream Storage Structure, Hamirpur
Binding of reinforcement of Pier No-13, 12th lift is under progress.
57/100
Instream Storage Structure, Hamirpur
Binding of reinforcement of D/S Abutment (A1), 5th lift is under progress.
58/100
Instream Storage Structure, Hamirpur
Binding of reinforcement of Pier No-16, 9th lift is under progress.
59/100
Instream Storage Structure, Hamirpur
Binding of reinforcement of Girder is under progress.
60/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-21, 8th lift is under progress.
61/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 85 mm) of LHS Double pier, 8th lift done in presence of Client & PSS Team.
62/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS Double pier, 8th lift is under progress in presence of Client & PSS Team.
63/100
Instream Storage Structure, Jharbeda
Slump testing M20A20 (Value 50 mm) of D/S Pier No-8 to (D2) Gravity floor, 3rd lift done in presence of Client & PSS Team.
64/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of D/S Pier No-8 to (D2) Gravity floor, 3rd lift is under progress in presence of Client & PSS Team.
65/100
Instream Storage Structure, Jharbeda
Slump testing M20A20 (Value 50 mm) of D/S Pier No-2 to Pier No-8 Curtain wall, 1st lift done in presence of Client & PSS Team.
66/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of D/S Pier No-2 to Pier No-8 Curtain wall, 1st lift is under progress in presence of Client & PSS Team.
67/100
Instream Storage Structure, Jharbeda
Testing of Compressive M20A20 (Strength is 29.99/mm2 for 28 days) has done in presence of Client & PSS team.
68/100
Instream Storage Structure, Jharbeda
Shuttering of D/S Pier No-7 to Pier No-8 End sill, 1st lift is under progress.
69/100
Instream Storage Structure, Jharbeda
Shuttering of D/S Gravity floor Pier No-8 to RHS Divide wall (D2), 3rd lift is under progress.
70/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
71/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 90 mm) of Barrage Bay No-3 (Raft) at Block No-4 done in presence of Client & PSS Team.
72/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Barrage Bay No-3 (Raft) at Block No-4 is under progress in presence of Client & PSS Team.
73/100
UGPL, Left Lower Suktel Canal Division
Stem pipe Encasing work is in progress at J-244 RM-1 Near village Ranipali In Presence of PMC team.
74/100
UGPL, Left Lower Suktel Canal Division
Air Vacuum valve (surge valve) installation work is in progress at LM-7 LO-124A near village Lankabahal .
75/100
UGPL, Right Lower Suktel Canal Division
Inspected of BFV and BFV Chamber is in progress for 280mm DIa HDPE pipe from J-8011 to J-8024 (p-8029) at village Charbahali.
76/100
UGPL, Right Lower Suktel Canal Division
OCS chamber piping work is in progress of OCS No-0213026-C12B at village Jharbalangir in presence of DOWR Staff PMC team and L&T personnel.
77/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door fixing work is in progress OCS No:-0201214 - CO5A at village Dhubaudar presence of PMC team and L&T staff.
78/100
UGPL, Left Lower Suktel Canal Division
HDPE pipeline connection work is in progress at LO-32B near village Chhatabahal.
79/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
LHS under sluice cut-off deshuttering work is in progress at choudhary gada iss project- 19.03.2026
80/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay raft reinforcement fixing work in progress at baitarani iss project- 19.03.2026
81/100
Instream Storage Structure, Budharaja
Curing Work is in Progress.
82/100
Instream Storage Structure, Budharaja
De-Shuttering work is in Progress at LHS U/S Flared-out Wall, 22nd Step. RL: 218.300 to 218.900.
83/100
Instream Storage Structure, Budharaja
De-Shuttering work is in Progress at LHS U/S Flared-out Wall, 22nd Step. RL: 218.300 to 218.900.
84/100
Instream Storage Structure, Budharaja
Curing Work is in Progress.
85/100
Instream Storage Structure, Budharaja
Curing work is in progress.
86/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at LHS U/S Flared-out Wall, 22nd Step. RL: 218.300 to 218.900.
87/100
Instream Storage Structure, Budharaja
Slump Value: 80mm
88/100
Instream Storage Structure, Budharaja
Slump Value: 80mm
89/100
Instream Storage Structure, Budharaja
No-1 STOPLOG GATE Erection work under progress
7 Nos of Hoist bridge installation completed out of 11
90/100
Instream Storage Structure, Budharaja
Sir, checked placing and positioning of steel reinforcement, supporting bars and alignment of shuttering work with minimum cover 25mm for Slab & 40mm for Beam. Staff Quarter, 1st Floor Slab. Now the area is ready for concrete M25 A20. So recommended for the purpose. RL:226.600 to 226.725. Approved by SE SID Sambalpur, In presence of Department JE.
91/100
Instream Storage Structure, Budharaja
SE SID Sambalpur inspected ISS Budharaja.PMC team Sambalpur & other Departmental officers were present. Instructed to complete the Balance work within targeted time line.
92/100
Instream Storage Structure, Budharaja
Sample collection of sand
93/100
Instream Storage Structure, Budharaja
Hoist bridge 5 Nos. installation work done out of 11 in Bay No-5
94/100
Instream Storage Structure, Budharaja
Angel joint both hoist column in pier No-4
95/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at LHS U/S Flared-out Wall, 21nd Step. RL: 217.700 to 218.300.
96/100
Instream Storage Structure, Budharaja
No-3 Hoist bridge erection work in progress
97/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at LHS U/S Flared-out Wall, 21nd Step. RL: 217.700 to 218.300.
98/100
Instream Storage Structure Across Bheden near village Saida
ISS SAIDA Undersluice Bay no-2 both Barrage Bay Gate & StopLog gate Sill beam all measurements checked as per approved drawings, Spirit level & water level checked.
99/100
Instream Storage Structure Across Bheden near village Saida
ISS SAIDA Undersluice Bay no-2 both Barrage Bay Gate & StopLog gate Sill beam all measurements checked as per approved drawings, Spirit level & water level checked.
100/100
Instream Storage Structure Across Bheden near village Saida
RHS D/S Flank wall 5th lift de-shuttering work & 6th lift shuttering work is going on .
❮
❯