PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Gudvella
Plastering work is in progress on 19.06.2026
2/100
Instream Storage Structure, Gudvella
The DG trial has started now on 19.06.2026
3/100
Instream Storage Structure, Gudvella
Brick work of parapet wall is under progress at site on 19.06.2026
4/100
Instream Storage Structure, Gudvella
Laying of WBM is under progress for approach road construction on 19.06.2026
5/100
Instream Storage Structure, Gudvella
Mechanical work is under progress at site on 19.06.2026
6/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 19.06.2026
7/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 19.06.2026
8/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no. 13&A2 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 87mm on 19.06.2026
9/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no. 13&A2 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 87mm on 19.06.2026
10/100
Instream Storage Structure, Nandagaon
• 2.Fixing & fittings and alignment of 2nd. stage embedded parts and numbers of dowel bars provided as per approved drawing at roller tracks of both stoplog & service gate grooves at bay no.14 of pier no.13 & right abutment 9th lift have been checked and found correct by HM Expert of PMC during his site visit on dt.01.06.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs. (i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows: (ii) Chipping of old vertical concrete surface is done. (iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for M35A20 grade on 19.06.2026
11/100
Instream Storage Structure, Nandagaon
Concrete casting with M20A20 grade of CC block at D/S right flared out wall is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 85mm on 19.06.2026
12/100
Instream Storage Structure, Nandagaon
Concrete casting with M20A20 grade of CC block at D/S right flared out wall is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 85mm on 19.06.2026
13/100
Instream Storage Structure, Nandagaon
• 1.The casting of the CC block at the following area has been checked in the presence of PM, EPC agency, Site Engineers of PMC & EPC Agency: (i) Shuttering for CC block at D/S right Flared out wall of 37.50m length & 0.6m ht. from RL-240.60m to RL-241.20m is completed. (ii). Filling of inverted filter materials covering with LDPE paper at adjacent to each CC block in earth side are done before placement. (iii) Application of 2 coat bitumen paint at cj's concrete surface is done. (iv). Area is ready and passed by SE KID, Bh. Patna to place concrete with PCC M20A20 grade on 19.06.2026
14/100
Instream Storage Structure, Nandagaon
Trestle and columns alignment work under progress on 19.06.2026
15/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no.13& A2 on 19.06.2026
16/100
Instream Storage Structure, Nandagaon
Shuttering for basement slab of office building is in progress on 19.06.2026
17/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Pier No-3,11th lift done in presence of Client & PSS Team.
18/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-3,11th lift is under progress in presence of Client & PSS Team.
19/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-39 done in presence of Client & PSS Team.
20/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-39 is under progress in presence of Client & PSS Team.
21/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Deck slab (Bay No-10 & 11) done in presence of Client & PSS Team.
22/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Deck slab (Bay No-10 & 11) is under progress in presence of Client & PSS Team.
23/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-5,4th lift done in presence of Client & PSS Team.
24/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-5,4th lift is under progress in presence of Client & PSS Team.
25/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.15/mm2 for 28 days) of U/S Flared out wall Raft at Block No-1 and (M35A20) (Strength is 42.07/mm2 for 28 days) of Gantry Girder No-35 and M25A20 (Strength is31.02/mm2 for 28 days) of Pier No-16, 15th lift has done in presence of Client & PSS team.
26/100
Instream Storage Structure, Hamirpur
Gantry Girder fixing is in progress in Pier No-19 & 20.
27/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Pier No-2, 10th lift is under progress.
28/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for D/S Flank wall Cut-off at Block No-1 is under progress.
29/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for U/S Flank wall at Block No-1 is under progress.
30/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-1, 11th lift is under progress.
31/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 85 mm) of LHS Barrage Bay No-3 Deck slab done in presence of Client & PSS Team.
32/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS Barrage Bay No-3 Deck slab is under progress in presence of Client & PSS Team.
33/100
Instream Storage Structure, Khalpal
Testing of Compressive M25A20 (Strength is 34.45/mm2 for 28 days) of Barrage Bay No-2 Raft (RCC) and (Strength is 34.22/mm2 for 28 days) of LHS U/S Divide wall, 1st lift has done in presence of Client & PSS team.
34/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 90 mm) of Pier No-11 (Starter) done in presence of Client & PSS Team.
35/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-11 (Starter) is under progress in presence of Client & PSS Team.
36/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 85 mm) of Barrage Bay No-2 Gravity floor done in presence of Client & PSS Team.
37/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Barrage Bay No-2 Gravity floor is under progress in presence of Client & PSS Team.
38/100
Instream Storage Structure, Khalpal
Shuttering of Pier No-11 (Starter) is under progress.
39/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
40/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-4,4th lift done in presence of Client & PSS Team.
41/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-4,4th lift is under progress in presence of Client & PSS Team.
42/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.33/mm2 for 07 days) of D/S Flank Cut-off wall, 3rd lift at Block No-1 and (M15A40 (Strength is 13.18/mm2 for 07 days) of U/S Flared out wall at Block No-1 (PCC) and M35A20 (Strength is 37.33/mm2 for 07 days) of Gantry Girder No-35 and (Strength is 37.04/mm2 for 07 days) of Cross Girder (Bay No-9) has done in presence of Client & PSS team.
43/100
Instream Storage Structure, Hamirpur
Visited by S.E, Q.A, Sundargarh in presence of A.E.E QC, J.E QC, A.E.E RID, A.E RID, IEE and Site Engineer of PSS team along with representative of EPC agency at site.
44/100
Instream Storage Structure, Hamirpur
Observed of Sieve analysis of Coarse aggregate in presence of S.E, Q.A, Sundargarh in presence of A.E.E QC, J.E QC, A.E.E RID, A.E RID, IEE and Site Engineer of PSS team.
45/100
Instream Storage Structure, Hamirpur
Gantry Girder fixing is in progress in Pier No-14 & 15.
46/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Deck slab (Bay No-10) is under progress.
47/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-2, 10th lift is under progress.
48/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall Cut-off at Block No-1 is under progress.
49/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Abutment (A1), 11th lift at Block No-1 is under progress.
50/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-2, 10th lift is under progress.
51/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Checking of Reinforcement for Raft in presence of Client & PSS team.
52/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of LHS D/S Abutment Counterfort, 1st lift is under progress.
53/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering & Binding of reinforcement for LHS D/S Divide wall is under progress.
54/100
Instream Storage Structure, Jharbeda
Slump testing M25A20 (Value 85 mm) of RHS (D2) U/S Footing, 2nd lift done in presence of Client & PSS Team.
55/100
Instream Storage Structure, Jharbeda
Concreting M25A20 of RHS (D2) U/S Footing, 2nd lift is under progress in presence of Client & PSS Team.
56/100
Instream Storage Structure, Jharbeda
Visited by S.E, Q.A, Sundargarh in presence of A.E.E QC, J.E QC, A.E.E RID, A.E RID and Site Engineer of PSS team along with representative of EPC agency at site.
57/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of RHS Double Pier No-25, 2nd lift done in presence of Client & PSS Team.
58/100
Instream Storage Structure, Khalpal
Concreting M25A20 of RHS Double Pier No-25, 2nd lift is under progress in presence of Client & PSS Team.
59/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
60/100
Instream Storage Structure, Gudvella
• Today SDO and AE visited ISS Gudvella. During the visit, the Department JE, PMC Site Engineer and Agency Engineers were present. 1. The overall site conditions were inspected and the agency was instructed to expedite the erection of the stoplog gate and complete the work at the earliest. 2. The agency was also instructed to complete the remaining building finishing works and approach road works immediately without any further delay on 18.06.2026
61/100
Instream Storage Structure, Gudvella
Installation work of staircase at mechanical site is under progress at site on 18.06.2026
62/100
Instream Storage Structure, Gudvella
Compaction work of the GSB layer for the road is currently in progress on 18.06.2026
63/100
Instream Storage Structure, Gudvella
Brick work of building parapet wall is under progress at site on 18.06.2026
64/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 18.06.2026
65/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 18.06.2026
66/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage at pier no.13&A2 is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 84mm on 18.06.2026
67/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage at pier no.13&A2 is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 84mm on 18.06.2026
68/100
Instream Storage Structure, Nandagaon
• 1.Fixing & fittings and alignment of 2nd. stage embedded parts and numbers of dowel bars provided as per approved drawing at roller tracks of both stoplog & service gate grooves at bay no.14 of pier no.13 & right abutment 8th lift have been checked and found correct by HM Expert of PMC during his site visit on dt.01.06.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs. (i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows: (ii) Chipping of old vertical concrete surface is done. (iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for M35A20 grade on 18.06.2026
69/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no.13&right abutment on 18.06.2026
70/100
Instream Storage Structure, Nandagaon
Trestle and columns alignment under progress on 18.06.2026
71/100
Instream Storage Structure, Nandagaon
Trestle and columns alignment under progress on 18.06.2026
72/100
Instream Storage Structure, Nandagaon
Painting work has been stopped due to labour issue on 18.06.2026
73/100
Instream Storage Structure, Nandagaon
Shuttering work for CC block at D/S right flared out wall is in progress on 18.06.2026
74/100
Instream Storage Structure, Nandagaon
Shuttering for basement slab of office building is in progress on 18.06.2026
75/100
UGPL, Right Lower Suktel Canal Division
1HA Outlet Pipe extension work is in progress of OCS no- 0201211-C02A at village Sindurbahal visited by DoWR SE & SDO, PMC team along with L&T personnel.
76/100
UGPL, Right Lower Suktel Canal Division
OCS erection work is in progress of 0213094 C06A at village Randa.
77/100
UGPL, Right Lower Suktel Canal Division
Joint verification is in progress of OCS No. 0201219-CO6A 4000 HA at village Kutumbtola village is in progress in presence of DOWR JE, PMC team and EPC staff.
78/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE pipe line Tee (75 X 125 ×75)mm connection at LO 199, LM -10, near village Jharmunda in presence of PMC team.
79/100
Instream Storage Structure, Gudvella
Floor tiles fitting under progress at control room building on 17.06.2026
80/100
Instream Storage Structure, Gudvella
Placement of GSB for approach road is under progress at site on 17.06.2026
81/100
Instream Storage Structure, Gudvella
Outside plastering is under progress at control room building on 17.06.2026
82/100
Instream Storage Structure, Gudvella
Stone pitching work at u/s side is under progress at site on 17.06.2026
83/100
Instream Storage Structure, Gudvella
Mechanical work is under progress at site on 17.06.2026
84/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 17.06.2026
85/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 17.06.2026
86/100
Instream Storage Structure, KansariGanda
Slump cone test conducted in progress.
87/100
Instream Storage Structure, KansariGanda
The first Girder placement IN PROGRESS
88/100
Instream Storage Structure, KansariGanda
The first Girder placement IN PROGRESS
89/100
Instream Storage Structure, Gudvella
Approach road construction is under progress at site on 16.06.2026
90/100
Instream Storage Structure, Gudvella
Placement of GSB for approach road is under progress at site on 16.06.2026
91/100
Instream Storage Structure, Gudvella
Outside plastering is under progress at control room building on 16.06.2026
92/100
Instream Storage Structure, Gudvella
Stone pitching work at u/s side is under progress at site on 16.06.2026
93/100
Instream Storage Structure, Gudvella
Mechanical work is under progress at site on 16.06.2026
94/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 16.06.2026
95/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 16.06.2026
96/100
Instream Storage Structure, Nandagaon
Witnessed the material testing of IS 2062 material. Tensile test, Bend test and Material composition tests were conducted at NABL Laboratory Balanagar Hyderabad on 17.06.2026
97/100
Instream Storage Structure, Nandagaon
Witnessed the material testing of IS 2062 material. Tensile test, Bend test and Material composition tests were conducted at NABL Laboratory Balanagar Hyderabad on 17.06.2026
98/100
Instream Storage Structure, Nandagaon
Witnessed the material testing of IS 2062 material. Tensile test, Bend test and Material composition tests were conducted at NABL Laboratory Balanagar Hyderabad on 17.06.2026
99/100
Instream Storage Structure, Nandagaon
De-Shuttering & Shuttering for 2nd stage concrete is in progress at pier no. 13&A2 on 17.06.2026
100/100
Instream Storage Structure, Nandagaon
There is no erection and painting work in progress at the site today due to labour issues on 17.06.2026