GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Gudvella
Placement of filler material is under progress before placing of building tiles on 04.08.2026
2/100
Instream Storage Structure, Gudvella
Adjustment of rubber seal of mechanical gate is under progress at site on 04.08.2026
3/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 04.08.2026
4/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 04.08.2026
5/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 32nos. Precast RCC railing is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 83mm on 04.08.2026
6/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 32nos. Precast RCC railing is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 83mm on 04.08.2026
7/100
Instream Storage Structure, Nandagaon
Monorail walkway railing work is under progress on 04.08.2026
8/100
Instream Storage Structure, Nandagaon
Trestle and columns base plate welding under progress on 04.08.2026
9/100
Instream Storage Structure, Nandagaon
Stone pitching work at U/S right embankment is in progress on 04.08.2026
10/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for precast railing is in progress on 04.08.2026
11/100
Instream Storage Structure, Khalpal
Curing of Girder No-55 is under progress.
12/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 58.05m.
13/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at D/S Telkoi site.
14/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Gantry Girder No-54 done in presence of Client & PSS Team.
15/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-54 is under progress in presence of Client & PSS Team.
16/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall, 12th lift at Block No-5 is under progress.
17/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
18/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for D/S Flank wall, 6th lift at Block No-5 is under progress.
19/100
Instream Storage Structure, Hamirpur
Trestle No-20 bracing fixing work is in progress.
20/100
Instream Storage Structure, Hamirpur
Trestle No-19 bracing welding work is in progress.
21/100
Instream Storage Structure, Hamirpur
Chequred plate marking & cutting for hoist bridge platform work is in progress.
22/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.330m.
23/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS Project water level 5.2m
24/100
UGPL, Right Lower Suktel Canal Division
Reservoir water level at RL 200.272m
25/100
Instream Storage Structure, Gudvella
Primer painting is under progress at mechanical yard on 03.08.2026
26/100
Instream Storage Structure, Gudvella
Placement of building tiles is under progress on 03.08.2026
27/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 03.08.2026
28/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 03.08.2026
29/100
Instream Storage Structure, Nandagaon
Monorail walkway railing work is under progress on 03.08.2026
30/100
Instream Storage Structure, Nandagaon
Monorail walkway alignment work is under progress on 03.08.2026
31/100
Instream Storage Structure, Nandagaon
Stone pitching work at U/S right embankment is in progress on 03.08.2026
32/100
Instream Storage Structure, Nandagaon
De-Shuttering is in progress at U/S left flared out wall on 03.08.2026
33/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 37.93/mm2 for 07 days) of Ganrty Girder No-50 and M25A20 (Strength is 31.21/mm2 for 28 days) of Pier No-18, 16th lift and (Strength is 13.33/mm2 for 07 days) of U/S Flared out wall, 12th lift at Block No-5 has done in presence of Client & PSS team.
34/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-53 done in presence of Client & PSS Team.
35/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-53 is under progress in presence of Client & PSS Team.
36/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
37/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for D/S Flank wall, 6th lift at Block No-5 is under progress.
38/100
Instream Storage Structure, Hamirpur
Hoist bridge platform assembly No-4 Chequered plate welding work is in progress.
39/100
Instream Storage Structure, Hamirpur
Column Trestle No-19 base plate welding work is in progress.
40/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.220m.
41/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Present status of river Samakoi at Santeibhanja site.
42/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at Telkoi site.
43/100
Instream Storage Structure, Khalpal
Slump testing M35A20 (Value 90 mm) of Girder No-55 done in presence of Client & PSS Team.
44/100
Instream Storage Structure, Khalpal
Concreting M35A20 of Girder No-55 is under progress in presence of Client & PSS Team.
45/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 58.12m.
46/100
Instream Storage Structure, Gudvella
Paint work at walkway railing is under progress at site on 02.08.2026
47/100
Instream Storage Structure, Gudvella
Placement of filler material is under progress at building tiles on 02.08.2026
48/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 02.08.2026
49/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 02.08.2026
50/100
Instream Storage Structure, Gudvella
Placement of building tiles is under progress at site on 01.08.2026
51/100
Instream Storage Structure, Gudvella
Primer painting work is under progress at site on 01.08.2026
52/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 01.08.2026
53/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 01.08.2026
54/100
Instream Storage Structure, Nandagaon
Concrete casting with M20A20 grade of CC block at U/S left flared out wall is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 84mm on 02.08.2026
55/100
Instream Storage Structure, Nandagaon
Concrete casting with M20A20 grade of CC block at U/S left flared out wall is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 84mm on 02.08.2026
56/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 21nos. Precast RCC railing is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 86mm on 02.08.2026
57/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 21nos. Precast RCC railing is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 86mm on 02.08.2026
58/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for precast railing is in progress on 02.08.2026
59/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.94/mm2 for 28 days) of D/S Flank wall, 2nd lift at Block No-5 and (Strength is 31.21/mm2 for 28 days) of Pier No-26, 14th lift and (Strength is 21.63/mm2 for 07 days) of U/S Flank wall, 10th lift at Block No-5 has done in presence of Client & PSS team.
60/100
Instream Storage Structure, Nandagaon
Shuttering for CC block at U/S left flared out wall is under progress on 02.08.2026
61/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 21nos. Precast RCC railing is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency.. The slump test value is 84mm on 01.08.2026
62/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 21nos. Precast RCC railing is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency.. The slump test value is 84mm on 01.08.2026
63/100
Instream Storage Structure, Nandagaon
Trestle base plate welding is under progress on 01.08.2026
64/100
Instream Storage Structure, Nandagaon
Monorail walkway railing work is under progress on 01.08.2026
65/100
Instream Storage Structure, Nandagaon
Fixing of precast railing is in progress at deck slab no. 13 ON 01.08.2026
66/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for Precast railing is in progress on 01.08.2026
67/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.220m.
68/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at Telkoi site.
69/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-52 done in presence of Client & PSS Team.
70/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-52 is under progress in presence of Client & PSS Team.
71/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of D/S (A2) Flank wall, 5th lift at Block No-5 done in presence of Client & PSS Team.
72/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S (A2) Flank wall, 5th lift at Block No-5 is under progress in presence of Client & PSS Team.
73/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
74/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall, 12th lift at Block No-5 is under progress.
75/100
Instream Storage Structure, Hamirpur
C.D.U to R.D.U shaft fixing work is in progress of hoist bridge platform.
76/100
Instream Storage Structure, Hamirpur
Gantry girder's 1st stage embedded plate fixing and welding work is in progress.
77/100
Instream Storage Structure, Hamirpur
Column Trestle welding work is in progress.
78/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.410m.
79/100
Instream Storage Structure, Khalpal
Binding of reinforcement for Girder No-55 is under progress.
80/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 58.53m.
81/100
Instream Storage Structure, KansariGanda
Site condition of ISS Kansariganda on 31.07.26.
82/100
Instream Storage Structure, KansariGanda
Silt content of sand checked and found 2.7% in presence of Irr. Engg. Expert & Site Engineer of PMC.
83/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site in presence of Irr. Engg. Expert & Site Engineer of PMC.
84/100
Instream Storage Structure, KansariGanda
Girder no - 41 concrete pouring started in presence of Irr. Engg. Expert & Site Engineer of PMC.
85/100
Instream Storage Structure, KansariGanda
Sir, Honrable MLA, Chatrapur along with SE, BeID,Bam with team made a public meeting in villages Raulibandha and Bahalpur regarding Land aquisition for Feeder Channel and Spill channel of the Project ISS KANSARIGANDA.
86/100
Instream Storage Structure, KansariGanda
Sir, Honrable MLA, Chatrapur along with SE, BeID,Bam with team made a public meeting in villages Raulibandha and Bahalpur regarding Land aquisition for Feeder Channel and Spill channel of the Project ISS KANSARIGANDA.
87/100
Instream Storage Structure, KansariGanda
Sir, Honrable MLA, Chatrapur along with SE, BeID,Bam with team made a public meeting in villages Raulibandha and Bahalpur regarding Land aquisition for Feeder Channel and Spill channel of the Project ISS KANSARIGANDA.
88/100
Instream Storage Structure, KansariGanda
Sir, Honrable MLA, Chatrapur along with SE, BeID,Bam with team made a public meeting in villages Raulibandha and Bahalpur regarding Land aquisition for Feeder Channel and Spill channel of the Project ISS KANSARIGANDA.
89/100
Instream Storage Structure, KansariGanda
Site condition of ISS Kansariganda on 02.08.26.
90/100
Instream Storage Structure, KansariGanda
Site condition of ISS Kansariganda on 02.08.26.
91/100
Instream Storage Structure, KansariGanda
Site condition of ISS Kansariganda on 02.08.26.
92/100
Instream Storage Structure, Gudvella
Placement of building tiles is under progress at site on 31.07.2026
93/100
Instream Storage Structure, Gudvella
• 1.Primer painting is under progress at mechanical yard. 2.Grinding and finishing work is underprogress at site on 31.07.2026
94/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 31.07.2026
95/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 31.07.2026
96/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 21nos. Precast RCC railing is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 85mm on 31.07.2026
97/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 21nos. Precast RCC railing is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 85mm on 31.07.2026
98/100
Instream Storage Structure, Nandagaon
Monorail girder alignment work is under progress on 31.07.2026
99/100
Instream Storage Structure, Nandagaon
Monorail walkway railing work is under progress on 31.07.2026
100/100
Instream Storage Structure, Nandagaon
Stone pitching work at U/S right embankment in progress on 31.07.2026

Enter Login Details

Forgot Password ?