1/100
Barrage across river Turi & Guntat
Site inspection of Chief Engineer along with department SE, AEE, JE, PMC Site engineers, Agency staff to Turi & Guntat site.
2/100
Barrage across river Turi & Guntat
Site inspection of Chief Engineer along with department SE, AEE, JE, PMC Site engineers, Agency staff to Turi & Guntat site.
3/100
Barrage across river Turi & Guntat
Slump Test conducted at Location GUNTAT site. RCC of U/S Flank wall and Return wall Barrage Portion.
Grade:- M25 A20
Slump:- 90mm
It is in admissible limit.
4/100
Barrage across river Turi & Guntat
RCC concreting of U/S flank wall and Return wall L/S & R/S going on at Guntat site of grade M25 A20 from RL - 556.20m to 557.35m
5/100
Barrage across river Turi & Guntat
Slump Test conducted at Location TURI site. RCC of Counterfort wall underway Barrage Portion
Grade:- M25 A20
Slump:- 85mm.
6/100
Barrage across river Turi & Guntat
RCC concreting of Counterfort wall underway at Turi site of grade M25 A20 on dt-16.10.2025
7/100
UGPL, Left Lower Suktel Canal Division
1800mm Dia MS pipe Outer welding work is in progress from J-380 to J-450 at Kushmel.
8/100
UGPL, Right Lower Suktel Canal Division
Pump House internal RCC road Shoulder portion soil filling work is in progress.
9/100
UGPL, Right Lower Suktel Canal Division
28 Days M30 concrete cube testing is in progress for Fire fighting Building slab concrete at Pump House compressive strength 37.76 N/mm2.
10/100
UGPL, Right Lower Suktel Canal Division
Pump House plinth protection soil preparation work is in progress.
11/100
UGPL, Right Lower Suktel Canal Division
HT Motor no-5 on load (wet run) is in progress at Pump House.
12/100
UGPL, Right Lower Suktel Canal Division
Pump House internal drain brick masonry work is in progress In the presence of PMC staff.
13/100
UGPL, Left Lower Suktel Canal Division
Fitting of Sluice Valve is in progress from J-380 to J-450 near village Kushmel.
14/100
Integrated Barrage across river Kochila and across river Baitarini
BAITARANI -ISS C.C Block casting work in site camp at kochila baitarani Iss-17.10.2025
15/100
UGPL, Left Lower Suktel Canal Division
1000KW motor no 1 wet run is in progress in presence of ABB Services Engineer at Pump House, Zone 1- .
16/100
UGPL, Left Lower Suktel Canal Division
PLC panel programming work and instrumentation cable re checking work is in progress by PLC Engineer at Pump House.
17/100
UGPL, Left Lower Suktel Canal Division
1800mm Dia MS pipe laying work is in progress from J-380 to J-450 at village Kushmel in presence of DoWR AE and PMC team.
18/100
Instream Storage Structure, Kushabhadra
CE MKS, CE Design, Addl. CE, CIC & SE, Prachi visited the ISS site in presence of OCCL staff, PSS-MKS team & the Agency.
19/100
Instream Storage Structure, Kushabhadra
Pier no.1 hoist blockout and monorail blockout shuttering work completed & the area is ready to receive concrete.
20/100
Instream Storage Structure, Kushabhadra
Inspection of O & M building foundation work by PSS Team.
21/100
Instream Storage Structure, Kushabhadra
28 days cube test for CCM15A40 done at field laboratory of the ISS in presence of PSS Team.
22/100
Instream Storage Structure, Kushabhadra
7 days cube test for CCM25A20 done at field laboratory of the ISS.
23/100
Instream Storage Structure, Kushabhadra
SDO with AE, Balianta discussing the foundation concrete progress of O&M building with site engineer of the Agency.
24/100
Instream Storage Structure, Kushabhadra
Laying of CC M15A40 PCC in column foundation.
25/100
Instream Storage Structure, Kushabhadra
7 days cube test for CC M15A40 done at field laboratory.
26/100
Instream Storage Structure, Kushabhadra
Ongoing Shuttering work for laying of footing PCC in column no-2 & 8.
27/100
Instream Storage Structure, Kushabhadra
Casting of PCC in foundation is in progress.
28/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-29, 6th lift at Block No-4 done in presence of Client & PSS Team.
29/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-29, 6th lift at Block No-4 is under progress in presence of Client & PSS Team.
30/100
Instream Storage Structure, Hamirpur
Column base plate welding work is in progress.
31/100
Instream Storage Structure, Hamirpur
Hoist bridge's single girder's welding work is in progress.
32/100
Instream Storage Structure, Hamirpur
Cleaning of reinforcement of Pier No-23 at Block No-4 is under progress by Sand blasting method.
33/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-27, 8th lift at Block No-4 is under progress.
34/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-28, 8th lift at Block No-4 is under progress.
35/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Flank wall at Block No-5 is under progress.
36/100
Instream Storage Structure, Khalpal
Slump testing M20A40 (Value 60 mm) C.C Blocks done in presence of Client & PSS Team.
37/100
Instream Storage Structure, Khalpal
Casting of C.C Block (M20A40) is under progress in presence of Client & PSS Team.
38/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
39/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. Flow direction is straight. The direction of flow is seen in middle of the river. Now the flow level is 225.600mt against design crest level 225.500 i.e. flood lift 0.1mt.
40/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-215.100 mtr against design crest level RL- 215.000 mtr .i.e 0.1 mtr flood lift .
41/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from U/S to D/S (From U/S of river)
42/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S of river.
The flow level is 206.980 m against the design RL: 206.700, i.e., 0.280 m flood lift.
43/100
Instream Storage Structure, Budharaja
View Showing Flow of river From U/S to D/S ( From U/S of river)
44/100
Instream Storage Structure, Khirasasan
View showing flow of river from D/S of river .
45/100
Instream Storage Structure, Khirasasan
The flow level is 211.200 m against the design
RL: 210.900, i.e., 0.3M flood lift.
46/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
47/100
Instream Storage Structure across river Sapei near village Kinjirma
Flow direction is straight flow is seen at RL-207.00 against crest level RL-206.250 . * ?Water is flowing 0.75m above the crest level .
48/100
Instream Storage Structure, Kudabega
Slump 85mm of pier NO21 of Expansion joint casting work M-35 A20
49/100
Instream Storage Structure, Kudabega
Span 19 raft gate groove bottom seal cleaning work in progress
50/100
Instream Storage Structure, Kudabega
Span 16 deck slab de shuttering work in progress
51/100
Instream Storage Structure, Kudabega
Pier NO 14LHS Gate Groove chipping work
52/100
Instream Storage Structure, Kudabega
Calibration of Batching plant in presence of Deptt, site Engg PMC and Agency
53/100
Instream Storage Structure, Kudabega
Calibration of Batching plant in presence of Deptt, site Engg PMC and Agency
54/100
Instream Storage Structure, Kudabega
US Flow(us of river)
Flow seen at RL 206.800m against crest level 206.00m(.800m Ht of water level)
55/100
Instream Storage Structure, Kudabega
Flow of DS side(DS of river)
56/100
Instream Storage Structure, Kopsinga
Batching plant calibration in presence of Dept ..QAC
57/100
Instream Storage Structure, Kopsinga
Batching plant calibration in presence of Dept ..QAC
58/100
Instream Storage Structure, Kopsinga
Cube test ISS Kopsingha
59/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Hoist bridge's single girder's work is in progress
60/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Hoist bridge's 15th platform assembly work is in progress
61/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - 'Walk -Way' number - 8 & 9 work is in progress
62/100
UGPL, Right Lower Suktel Canal Division
Pump House internal drain excavation work is in progress.
63/100
UGPL, Right Lower Suktel Canal Division
Right Pump House plinth protection concrete pouring work is in progress.
64/100
UGPL, Right Lower Suktel Canal Division
28 Days M25 concrete cube testing is in progress for Pump House Internal approach road RCC compressive strength 31.53 N/mm2.
65/100
UGPL, Right Lower Suktel Canal Division
HT Motor no-5 on load (wet run) is in progress at Pump House.
66/100
UGPL, Right Lower Suktel Canal Division
Pump House Internal drain wall bricks masonry work is in progress.
67/100
UGPL, Right Lower Suktel Canal Division
Soil levelling work is in progress for Pump House PLC room plinth protection at Pump House.
68/100
Integrated Barrage across river Kochila and across river Baitarini
BAITARANI -ISS C.C Block casting work in site camp at kochila baitarani Iss-16.10.2025
69/100
UGPL, Left Lower Suktel Canal Division
HT panel internal control wiring connection checking work is in progress by ABB Services Engineer at Pump House.
70/100
UGPL, Left Lower Suktel Canal Division
PLC panel programming work is in progress by PLC Engineer at Pump House.
71/100
UGPL, Left Lower Suktel Canal Division
Boundary wall inner side plastering work is in progress at Pump House.
72/100
UGPL, Left Lower Suktel Canal Division
1800mm Dia Ms pipe laying is in progress node from J-380 to J-450 Near village Kushmel.
73/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
No activities at site and present status of river & Structure.
74/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.200m.
75/100
Instream Storage Structure, Hamirpur
Survey & counting of structure on RSP land to be acquired carried out by the agency as per the suggestion of joint verification team comprising of R.I, RSP and R.I of Tahasil office Rourkela.
76/100
Instream Storage Structure, Hamirpur
U.T test conducted today of hoist bridge platform assembly No-12 & 13 inpresnce of A.E R.I.D and PSS team.
77/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-28, 8th lift is under progress.
78/100
Instream Storage Structure, Hamirpur
Inspection by A.E, RID with PSS team for shuttering of Pier No-27, 8th lift at Block No-4.
79/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-28, 8th lift at Block No-4 is under progress.
80/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-29, 6th lift at Block No-4 is under progress.
81/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Flank wall at Block No-5 is under progress.
82/100
Instream Storage Structure, Sirigida
Present status in river.
83/100
Instream Storage Structure, Khalpal
Slump testing M20A40 (Value 70 mm) C.C Blocks done in presence of Client & PSS Team.
84/100
Instream Storage Structure, Khalpal
Casting of C.C Block (M20A40) is under progress in presence of Client & PSS Team.
85/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
86/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. Flow direction is straight. The direction of flow is seen in middle of the river. Now the flow level is 225.600mt against design crest level 225.500 i.e. flood lift 0.1mt.
87/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S of river.
The flow level is 207.150 m against the design RL: 206.700, i.e., 0.450 m flood lift.
88/100
Instream Storage Structure, Budharaja
View Showing Flow of river From U/S to D/S ( From U/S of river)
89/100
Instream Storage Structure, Khirasasan
The flow level is 211.100 m against the design
RL: 210.900, i.e., 0.2 M flood lift.
90/100
Instream Storage Structure, Khirasasan
View showing flow of river from D/S of river .
91/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
92/100
Instream Storage Structure across river Sapei near village Kinjirma
Flow direction is straight flow is seen at RL-207.100 against crest level RL-206.250 . * ?Water is flowing 0.85m above the crest level .
93/100
Instream Storage Structure across river Sapei near village Kinjirma
Curing of building staff quarter & control room Tie beam
94/100
Instream Storage Structure, Kopsinga
Slump-80mm kerb
95/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Inspection of Mechanical site by 'IEE' sir & 'QCE' sir
96/100
Instream Storage Structure, Kudabega
P-14 gate groove chipping work in progress
97/100
Instream Storage Structure, Kudabega
Fixing of strip sill in expansion joint on pier no-21 is in Progress in presence of IEE QCE and PMC site engg & DPM of agency
98/100
Instream Storage Structure, Kudabega
Casting of Deck slab- no 13 of barrage bay -2 is in Progress.
99/100
Instream Storage Structure, Kudabega
Casting of Deck slab- no 13 of barrage bay -2 is in Progress.
100/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Hoist bridge's single girder's work is in progress
❮
❯