1/100
Instream Storage Structure across river Sapei near village Kinjirma
Building staff quarter and Control room plinth beam reinforcement and shuttering work under progress .
2/100
Instream Storage Structure Across Bheden near village Saida
Slump value-80MM
3/100
Instream Storage Structure Across Bheden near village Saida
Shuttering & alignment checking in RHS divide wall Pier portion 10th lift.Rl-222.800 to 224.100
4/100
Instream Storage Structure Across Bheden near village Saida
Curing work progress in Deck slab
5/100
Instream Storage Structure, Budharaja
Slump Value: 60mm.
6/100
Instream Storage Structure, Budharaja
Slump Value: 55mm.
7/100
Instream Storage Structure, Budharaja
Curing work is in Progress at Pier No: 2, Hoist Gate Portion.
8/100
Instream Storage Structure, Budharaja
Curing work is in Progress at Pier No: 2, Hoist Gate Portion.
9/100
Instream Storage Structure, Budharaja
Curing work is in Progress at LHS Abutment, Hoist Gate Portion.
10/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at Pier No: 5, Hoist Gate Portion.
11/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at Pier No: 4, Hoist Gate Portion.
12/100
Instream Storage Structure, Khirasasan
LHS D/S FLARED OUT WALL 7TH LIFT concrete casting complete
13/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
14/100
Instream Storage Structure, Khirasasan
Pier no. 6 hoist portion shuttering work is in progress
15/100
Instream Storage Structure, Khirasasan
Pier no. 5 hoist portion shuttering work completed and ready for casting.
16/100
Instream Storage Structure, Khirasasan
View showing flow of river from D/S of river
17/100
Instream Storage Structure, KansariGanda
Season's 1st concreting started for ISS Kansariganda. Observed Slump is 80mm. All in concerned officials CE & BM, RBVN, BASIN, ACE, QAD.Bam, SE, BeID, SE, QAD, Bam SE, QA&QC Expert of PMU, BBSR has checked area before concreting of Pier No1.
18/100
Instream Storage Structure, KansariGanda
Concreting is in progress.
19/100
Instream Storage Structure, KansariGanda
Concreting is in progress.
20/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert of PMU, BBSR, CE & BM RBVN basin, ACE, QA, Berhampur , SE BeID, SE QA Divn.,AE and AEE of Dept., PMC team comprising Dy TL, Irrigation Engg expert and QA&QC expert along with Site engineers to the ISS Site. Agency has kept ready area for concreting of Pier No1. Cleaning of old concreting surface, de-rusting of MS reinforcement were also done. Scaffolding arrangements were made for inspection of the concrete was also made. He has also visited the construction materials dump yard near batching plant and materials were found satisfactory. Gradation of CA aggregate was done during the visit. Vivid discussion on different issues on quality aspects and executional aspects was done. Some pics of the are posted below.
21/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert of PMU, BBSR, CE & BM RBVN basin, ACE, QA, Berhampur , SE BeID, SE QA Divn.,AE and AEE of Dept., PMC team comprising Dy TL, Irrigation Engg expert and QA&QC expert along with Site engineers to the ISS Site. Agency has kept ready area for concreting of Pier No1. Cleaning of old concreting surface, de-rusting of MS reinforcement were also done. Scaffolding arrangements were made for inspection of the concrete was also made. He has also visited the construction materials dump yard near batching plant and materials were found satisfactory. Gradation of CA aggregate was done during the visit. Vivid discussion on different issues on quality aspects and executional aspects was done. Some pics of the are posted below.
22/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert of PMU, BBSR, CE & BM RBVN basin, ACE, QA, Berhampur , SE BeID, SE QA Divn.,AE and AEE of Dept., PMC team comprising Dy TL, Irrigation Engg expert and QA&QC expert along with Site engineers to the ISS Site. Agency has kept ready area for concreting of Pier No1. Cleaning of old concreting surface, de-rusting of MS reinforcement were also done. Scaffolding arrangements were made for inspection of the concrete was also made. He has also visited the construction materials dump yard near batching plant and materials were found satisfactory. Gradation of CA aggregate was done during the visit. Vivid discussion on different issues on quality aspects and executional aspects was done. Some pics of the are posted below.
23/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert of PMU, BBSR, CE & BM RBVN basin, ACE, QA, Berhampur , SE BeID, SE QA Divn.,AE and AEE of Dept., PMC team comprising Dy TL, Irrigation Engg expert and QA&QC expert along with Site engineers to the ISS Site. Agency has kept ready area for concreting of Pier No1. Cleaning of old concreting surface, de-rusting of MS reinforcement were also done. Scaffolding arrangements were made for inspection of the concrete was also made. He has also visited the construction materials dump yard near batching plant and materials were found satisfactory. Gradation of CA aggregate was done during the visit. Vivid discussion on different issues on quality aspects and executional aspects was done. Some pics of the are posted below.
24/100
Instream Storage Structure, KansariGanda
Visit of CE RBVN Basin, Addl CE, SE QA Divn, Berhampur including SE BeID with his team, PMC team comprising Dy TL, Irrigation Engg expert and QA&QC expert along with Site Engineers to the ISS site. He has reviewed preparatory arrangements at ISS site after post monsoon. Agency has kept ready area for concreting of Peir No1. Cleaning of old concreting surface, de-rusting of MS reinforcement were in progress. CE has also inspected the construction materials near batching plant.
25/100
Instream Storage Structure, KansariGanda
Visit of CE RBVN Basin, Addl CE, SE QA Divn, Berhampur including SE BeID with his team, PMC team comprising Dy TL, Irrigation Engg expert and QA&QC expert along with Site Engineers to the ISS site. He has reviewed preparatory arrangements at ISS site after post monsoon. Agency has kept ready area for concreting of Peir No1. Cleaning of old concreting surface, de-rusting of MS reinforcement were in progress. CE has also inspected the construction materials near batching plant.
26/100
Instream Storage Structure, KansariGanda
Visit of CE RBVN Basin, Addl CE, SE QA Divn, Berhampur including SE BeID with his team, PMC team comprising Dy TL, Irrigation Engg expert and QA&QC expert along with Site Engineers to the ISS site. He has reviewed preparatory arrangements at ISS site after post monsoon. Agency has kept ready area for concreting of Peir No1. Cleaning of old concreting surface, de-rusting of MS reinforcement were in progress. CE has also inspected the construction materials near batching plant.
27/100
Instream Storage Structure, KansariGanda
Visit of CE RBVN Basin, Addl CE, SE QA Divn, Berhampur including SE BeID with his team, PMC team comprising Dy TL, Irrigation Engg expert and QA&QC expert along with Site Engineers to the ISS site. He has reviewed preparatory arrangements at ISS site after post monsoon. Agency has kept ready area for concreting of Peir No1. Cleaning of old concreting surface, de-rusting of MS reinforcement were in progress. CE has also inspected the construction materials near batching plant.
28/100
UGPL, Left Lower Suktel Canal Division
Trench Excavation work is in progress for Laying of Dia 350mm DI pipe line node from J-99 to J-193 at village Singhanimunda.
29/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 18.11.2025
30/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 18.11.2025
31/100
Instream Storage Structure, Kudabega
Slump 80mm
Tm-4
32/100
Instream Storage Structure, Gudvella
1. Erection of pylon at deck slab no -8 in between P7 and P8 is under progress.
2. Shuttering work at right side middle portion of divide wall for 9th lift RCC is under progress on 18.11.2025
33/100
Instream Storage Structure, Kudabega
Slump 85mm
Tm-3
34/100
Instream Storage Structure, Gudvella
• Visited by: SE Sir, Balangir Irrigation Division
Location: ISS Gudvella Site
Present: Department JE, PMC Site Engineers, and Agency Representatives Observations and Instructions
1. The agency was instructed to deploy additional manpower to expedite the ongoing construction works.
2. The agency was advised to immediately commence the second stage of mechanical works.
3. The agency was directed to submit the Afflux Survey Report and the approach road data of the site at the earliest.
4. The agency was instructed to start the building works without any further delay.
Remarks / Conclusion
The overall progress of the work was reviewed during the visit. The agency was advised to enhance the pace of execution and ensure timely submission of all required data and reports. The quality of work must be maintained strictly as per specifications under the close supervision of PMC and departmental officials on 17.11.2025
35/100
Instream Storage Structure, Gudvella
• Visited by: SE Sir, Balangir Irrigation Division
Location: ISS Gudvella Site
Present: Department JE, PMC Site Engineers, and Agency Representatives Observations and Instructions
1. The agency was instructed to deploy additional manpower to expedite the ongoing construction works.
2. The agency was advised to immediately commence the second stage of mechanical works.
3. The agency was directed to submit the Afflux Survey Report and the approach road data of the site at the earliest.
4. The agency was instructed to start the building works without any further delay.
Remarks / Conclusion
The overall progress of the work was reviewed during the visit. The agency was advised to enhance the pace of execution and ensure timely submission of all required data and reports. The quality of work must be maintained strictly as per specifications under the close supervision of PMC and departmental officials on 17.11.2025
36/100
Instream Storage Structure, Kudabega
Slump 80mm
Tm-2
37/100
Instream Storage Structure, Kudabega
Slump 80mm
Tm-1
38/100
Instream Storage Structure, Gudvella
1. Erection of pylon at deck slab no -8 in between P7 and P8 is under progress at site
2. Shuttering work is under progress at right side middle portion of divide wall for 9th lift RCC on 17.11.2025
39/100
Instream Storage Structure, Kudabega
Right side d/s wing wall 5th lift M25A20 (Rl-209.500 to Rl-210.850) casting work in progress
40/100
Instream Storage Structure, Kudabega
Slump 85mm
41/100
Instream Storage Structure, Kudabega
Slump 80mm
42/100
Instream Storage Structure, Nandagaon
5th gate both stoplog gate and barrage bay gate 2nd stage embedded parts erection work under progress on 18.11.2025
43/100
Instream Storage Structure, Kudabega
Barrage bay-1 span no- 25 p-25 & p-24 for stoplog & service gate groove 2nd stage 8th lift M30A20 casting work in progress
44/100
Instream Storage Structure, Nandagaon
SS plate ( 8mm ) welding on embedded parts under progress on 18.11.2025
45/100
Instream Storage Structure, Kudabega
Slump 80mm
Tm-8
46/100
Instream Storage Structure, Nandagaon
Monorail fit up and welding work under progress on 18.11.2025
47/100
Instream Storage Structure, Kudabega
Slump 85mm
Tm-7
48/100
Instream Storage Structure, Kudabega
Slump 80mm
Tm-6
49/100
Instream Storage Structure, Nandagaon
Columns fit up work and welding under progress on 18.11.2025
50/100
Instream Storage Structure, Nandagaon
Curing at U/S left flared out wall is in progress on 18.11.2025
51/100
Instream Storage Structure, Kudabega
Slump 80mm
Tm-5
52/100
Instream Storage Structure, Nandagaon
Hoist bridge MIG welding under progress on 18.11.2025
53/100
Instream Storage Structure, Kudabega
Casting of concrete M25A20 for RHS Abutment 4th lift RL-209.050 to 210.450 work under progress
54/100
Instream Storage Structure, Kudabega
Casting of concrete M25A20 for RHS Abutment 4th lift RL-209.050 to 210.450 work under progress
55/100
Instream Storage Structure, Nandagaon
Reinforcement binding at pier no.12, Block-2 is in progress on 18.11.2025
56/100
Instream Storage Structure, Kudabega
Slump 80mm
Tm-4
57/100
Instream Storage Structure, Kudabega
Slump 85mm
Tm-3
58/100
Instream Storage Structure, Nandagaon
3.River water flow is diverted through under sluice bays at block-2 by the arrangements of making cross bund at U/S across the river on 17.11.2025
59/100
Instream Storage Structure, Kudabega
Slump85mm
Tm-2
60/100
Instream Storage Structure, Kudabega
Slump 80mm
Tm-1
61/100
Instream Storage Structure, Nandagaon
2. Inspected the Mechanical works going at barrage bays. Erection of vertical roller tracks at barrage bays at block -1 is in progress. Vertical and horizontal alignment are checked in presence of HME, Sr. Mechanical Engineer of PMC, PM of EPC Agency and mechanical Site Engineers of PMC on 17.11.2025
62/100
Instream Storage Structure, Kudabega
Right under sluice bay RHS abutment 4th lift and counter fort 4th lift M25A20 (Rl-209.50 to Rl-210.450) casting work in progress
63/100
Instream Storage Structure, Nandagaon
• Site visit of ISS, Nandagaon today on dt. 17.11.2025 by DTL, Tel Basin, Bhawanipatna along with QAC Expert, SHEE, HME and Sr. Site Engineer of PMC.
1. During site visit the following activities are seen at site:
(i). Rigid and smooth shuttering is completed for 6th lift of Pier No. 12(right divide wall) up to RL-241.60m.
(ii) Reinforcement main & distribution bars, tie bars are completed. Seen existing exposed bars since last rainy season. The PM of EPC Agency is directed to clean out corrosion from the rods properly using gunny bags by manual means.
(iii) Kindly be done proper staggering arrangements before area is ready for placing concrete. Maintain the proper alignment and profile using TS machine on 17.11.2025
64/100
Instream Storage Structure, Kudabega
Right under sluice bay RHS abutment 4th lift and counter fort 4th lift M25A20 (Rl-209.50 to Rl-210.450) casting work in progress
65/100
Instream Storage Structure, Kudabega
Pier no-25, gate groove second stage deshuttering work in progress.
66/100
Instream Storage Structure, Nandagaon
M20 A20 grade concrete casting on date 10.11.25 & date of testing on 17.11.25 in presence of DTL, QC Exp. Sr site engineering, site engineering with PM of agency, ave. Value of cube strength is 20N/mm2 (casting at d/s left side flared out wall 1st lift at sec.4-4 to sec.5-5 & sec.5-5 to sec.6-6) on 17.11.2025
67/100
Instream Storage Structure, Kudabega
Pier no-29, gate groove second stage deshuttering work in progress.
68/100
Instream Storage Structure, Kudabega
RHS abutment 4th lift shuttering work in progress
69/100
Instream Storage Structure, Nandagaon
Monorail girders fit up work under progress. Measured the dimensions as per approved drawings on 17.11.2025
70/100
Instream Storage Structure, Nandagaon
Monorail girders fit up work under progress. Measured the dimensions as per approved drawings on 17.11.2025
71/100
Instream Storage Structure, Kudabega
RHS d/s wing wall 5th lift cleaning work in progress
72/100
Instream Storage Structure, Kudabega
ISS Kudabaga - 'Walk-Way' work is in progress
73/100
Instream Storage Structure, Nandagaon
Columns fit up and welding work under progress. Inspected the welding rods as per specification and approved drawings on 17.11.2025
74/100
Instream Storage Structure, Nandagaon
Columns fit up and welding work under progress. Inspected the welding rods as per specification and approved drawings on 17.11.2025
75/100
Instream Storage Structure, Nandagaon
Curing at U/S left flared out wall is in progress on 17.11.2025
76/100
Instream Storage Structure, Nandagaon
Hoist bridge ribs MIG welding under progress on 17.11.2025
77/100
Instream Storage Structure, Nandagaon
Barrage bay gate no 2, 2nd stage embedded parts erection work under progress on 17.11.2025
78/100
Instream Storage Structure, Nandagaon
Barrage bay gate no 2, 2nd stage embedded parts erection work under progress on 17.11.2025
79/100
Instream Storage Structure, Gochara
Deck slab cleaning work is going on..
80/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
81/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. Flow direction is straight. The direction of flow is seen in middle of the river. Now the flow level is 225.600mt against design crest level 225.500 i.e. flood lift 0.1mt.
82/100
Instream Storage Structure, Kopsinga
LHS U/S 24th layer FDD Check
83/100
Instream Storage Structure, Kopsinga
LHS D/S Flared wall 30th layer FDD Check
84/100
Instream Storage Structure, Kopsinga
LHS Approach 20th layer FDD Check
85/100
Instream Storage Structure, Kopsinga
LHS U/S Guided bond 23th layer FDD Check in presence of Dept. AEE Sir & QC
86/100
Instream Storage Structure, Kopsinga
LHS U/S Guided bond 23th layer FDD Check in presence of Dept. AEE Sir & QC
87/100
Instream Storage Structure, Kopsinga
7 days Cube test
Flared wall 5th lift U/S (M20 A20)
88/100
Instream Storage Structure, Kopsinga
Slump-90mm Tm2 P3 D/S wall
89/100
Instream Storage Structure, Kopsinga
LHS D/S 28 th layer Guide bond FDD Check
90/100
Instream Storage Structure, Kopsinga
LHS Approach road 18th layer FDD Check
91/100
Instream Storage Structure, Kopsinga
Slump-90mm Pier 3 LHS D/S Final lift
92/100
UGPL, Right Lower Suktel Canal Division
OCS fittings Installation work is in progress of OCS -0213064-08A at village Bhaler in presence of L&T personnel, Bermad team and PMC team.
93/100
UGPL, Right Lower Suktel Canal Division
Internal drain plastering work is in progress of Pump House.
94/100
UGPL, Left Lower Suktel Canal Division
Outlet extension work is in progress from RO-286B, Z-5607, RM-15 at village Jharmunda In presence of DoWR SDO, AE and PMC team.
95/100
UGPL, Left Lower Suktel Canal Division
Boundary wall outer side plastering work is in progress at Pump House.
96/100
Instream Storage Structure, Khalpal
Hirakud Government Lab mix design trial mix conducted at site laboratory of M15A40, 07 days cube (Strength 19.82 N/mm²) and M25A20, 14 days cube (Strength 39.02 N/mm²) in presence of A.E.E, AID and PSS Team of Angul.
97/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of RHS Divide wall is under progress.
98/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cleaning & binding of reinforcement for Middle pier is under progress.
99/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning & Vertical straightening of reinforcement for Divide wall is under progress.
100/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning of silt at RHS Raft area is under progress.
❮
❯