GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Gudvella
• Today SDO and AE visited ISS Gudvella. During the visit, the Department JE, PMC Site Engineer and Agency Engineers were present. 1. The overall site conditions were inspected and the agency was instructed to expedite the erection of the stoplog gate and check the rubber seal properly. 2. The agency was also instructed to complete the remaining building finishing works and approach road works immediately on 18.07.2026
2/100
Instream Storage Structure, Gudvella
• Today the Hydro Mechanical Expert from PMC visited ISS Gudvella. During his visit, the Department JE, PMC Site Engineers and Agency Engineers were present. 1. The HM Expert reviewed all mechanical works and instructed the agency to complete all remaining finishing works at the earliest and to complete electric inspection work also earlier on 18.07.2026
3/100
Instream Storage Structure, Gudvella
Grinding and finishing work is under progress at stoplog gate at site on 18.07.2026
4/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 18.07.2026
5/100
Instream Storage Structure, Gudvella
Grinding work at stoplog groove is under progress at site on 17.07.2026
6/100
Instream Storage Structure, Gudvella
• Due to continuous rainfall, the water level of the Roul River near ISS Gudvella has gradually increased and at present approximately 1.4 m of water is flowing above the crest level. Due to continuous rainfall, all construction activities at the site have been temporarily suspended on 17.07.2026
7/100
Instream Storage Structure, Gudvella
• Due to continuous rainfall, the water level of the Roul River near ISS Gudvella has gradually increased and at present approximately 1.4 m of water is flowing above the crest level. Due to continuous rainfall, all construction activities at the site have been temporarily suspended on 17.07.2026
8/100
Instream Storage Structure, Nandagaon
Monorail girder erection work under progress on 18.07.2026
9/100
Instream Storage Structure, Nandagaon
Hoist bridge, trestle and stiffener erection work under progress on gate no 11 on 18.07.2026
10/100
Instream Storage Structure, Nandagaon
Stone pitching work at U/S right embankment is in progress on 18.07.2026
11/100
Instream Storage Structure, Nandagaon
River flood water passing through total 9 bays of ISS on 18.07.2026
12/100
Instream Storage Structure, Nandagaon
Erection work has been stopped due crane issue on 17.07.2026
13/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for precast railing is in progress on 17.07.2026
14/100
Instream Storage Structure, Nandagaon
River flood water passing through total 14nos. bays of ISS on 17.07.2026
15/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 of D/S Flank wall, 4th lift at Block No-5 (95mm) done in presence of Client & PSS Team.
16/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flank wall, 4th lift at Block No-5 is under progress in presence of Client & PSS Team.
17/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.6m.
18/100
Instream Storage Structure, Khalpal
Testing of Compressive M25A20 (Strength is 33.74/mm2 for 28 days) of Pier No-16 (Starter) has done in presence of Client & PSS team.
19/100
Instream Storage Structure, Khalpal
Shuttering & Binding of reinforcement for LHS Abutment Counterfort wall, 4th lift is under progress.
20/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 55.5 m.
21/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 42.67/mm2 for 28 days) of Gantry Girder No-40 and M25A20 (Strength is 21.48/mm2 for 07 days) of Pier No-25, 13th lift has done in presence of Client & PSS team.
22/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flank wall, 4th lift at Block No-5 is under progress.
23/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 of U/S Flank wall, 10th lift at Block No-5 (80mm) done in presence of Client & PSS Team.
24/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of U/S Flank wall, 10th lift at Block No-5 is under progress in presence of Client & PSS Team.
25/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
26/100
Instream Storage Structure, Hamirpur
RDU assembly fit-up work is in progress.
27/100
Instream Storage Structure, Hamirpur
Column box welding work is in progress.
28/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Present status of river Samakoi at Santeibhanja site.
29/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at Telkoi site.
30/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-49 done in presence of Client & PSS Team.
31/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-49 is under progress in presence of Client & PSS Team.
32/100
Instream Storage Structure, Hamirpur
Slump testing M15A40 of U/S Flared out wall, 12th lift at Block No-5 done in presence of Client & PSS Team.
33/100
Instream Storage Structure, Hamirpur
Concreting M15A40 of U/S Flared out wall, 12th lift at Block No-5 is under progress in presence of Client & PSS Team.
34/100
Instream Storage Structure, Hamirpur
1st stage embedded plate fixing work is in progress for gantry girder's.
35/100
Instream Storage Structure, Hamirpur
Column/ Trestle No-17 bracing fixing work is in progress.
36/100
Instream Storage Structure, Khalpal
Testing of Compressive M20A20 (Strength is 29.87/mm2 for 28 days) of Barrage Bay No-2 Gravity floor has done in presence of Client & PSS team.
37/100
Instream Storage Structure, Khalpal
Curing of LHS Abutment Counterfort wall, 3rd lift is under progress.
38/100
Instream Storage Structure, Khalpal
Shuttering & Binding of reinforcement for LHS Abutment Counterfort wall, 4th lift is under progress.
39/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.4m
40/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at Telkoi site.
41/100
Instream Storage Structure, Khalpal
Testing of Compressive M20A20 (Strength is 29.62/mm2 for 28 days) of Barrage Bay No-2 Gravity floor and M25A20 (Strength is 34.42/mm2 for 28 days) of Pier No-15 (Starter) has done in presence of Client & PSS team.
42/100
Instream Storage Structure, Khalpal
DCAC meeting conducted for village Khalpal & Kulei for acquisition of Private land under the Chairmanship of ADM (REV), Dhenkanal at Block Office, conference hall, Parjang.
43/100
Instream Storage Structure, Khalpal
Curing of LHS Abutment Counterfort wall, 3rd lift is under progress.
44/100
Instream Storage Structure, Khalpal
Shuttering & Binding of reinforcement for LHS Abutment Counterfort wall, 4th lift is under progress.
45/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 56.3 m.
46/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.8m.
47/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 181.100m.
48/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.09/mm2 for 28 days) of Pier No-1, 13th lift and (Strength is 21.18/mm2 for 07 days) of D/S Flank wall, 3rd lift at Block No-5 and M15A40 (Strength is 20.59/mm2 for 28 days) of D/S Flank wall Raft PCC at Block No-1 and M35A20 (Strength is 37.93/mm2 for 07 days) of Gantry Girder No-48 has done in presence of Client & PSS team.
49/100
Instream Storage Structure, Hamirpur
MS plate marking & cutting for column box and gantry 1st stage embedded plate work is in progress.
50/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Present status of river Samakoi at Santeibhanja site.
51/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at Telkoi site.
52/100
Barrage across river Turi & Guntat
Ststus of Guntat barrage.
53/100
Barrage across river Turi & Guntat
Status of Turi Barrage.
54/100
Barrage across river Turi & Guntat
Status of Turi Barrage.
55/100
Instream Storage Structure, Khalpal
Binding of reinforcement for LHS Abutment Counterfort wall, 4th lift is under progress.
56/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 56.5 m.
57/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.78/mm2 for 07 days) of U/S Flank wall, 9th lift at Block No-5 has done in presence of Client & PSS team.
58/100
Instream Storage Structure, Hamirpur
Inspection by A.E.E & A.E RID along with PSS Team and EPC agency at ISS Hamirpur site.
59/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall, 10th lift at Block No-5 is under progress.
60/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 181.300m.
61/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Present status of river Samakoi at Telkoi site.
62/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at Telkoi site.
63/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.8m.
64/100
UGPL, Right Lower Suktel Canal Division
Pump House Boundary wall outside back filling work is in progress.
65/100
UGPL, Right Lower Suktel Canal Division
Back filling work is in progress at MSDSS Boundary wall outside.
66/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 85 mm) of LHS D/S Divide wall, 7th lift done in presence of Client & PSS Team.
67/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS D/S Divide wall, 7th lift is under progress in presence of Client & PSS Team.
68/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.705m.
69/100
Instream Storage Structure, Khalpal
Inspection of Director IWAI along with Addl. C.E, S.E, A.E.E & A.E, AID and Dy. TL, CME, QAE, S.D.E of PSS team & Representative of Agency at ISS Khalpal site.
70/100
Instream Storage Structure, Khalpal
Testing of Compressive M25A20 (Strength is 30.75/mm2 for 28 days) of Pier No-14 (Starter) has done in presence of Client & PSS team.
71/100
Instream Storage Structure, Khalpal
Curing of LHS Abutment Counterfort wall, 3rd lift is under progress.
72/100
Instream Storage Structure, Khalpal
Binding of reinforcement for LHS Abutment Counterfort wall, 4th lift is under progress.
73/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 55.40 m.
74/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.94/mm2 for 28 days) of Pier No-1, 12th lift and (Strength is 21.48/mm2 for 07 days) of Pier No-23, 15th lift and (Strength is 30.84/mm2 for 28 days) of Flank cut-off wall, 2nd lift (Bank side) & Flank cut-off wall, 6th lift (River side) and M35A20 (Strength is 37.63/mm2 for 07 days) of Gantry Girder No-47 and M15A40 (Strength is 13.18/mm2 for 07 days) of U/S Flared out wall, 11th lift at Block No-5 and (Strength is 13.48/mm2 for 07 days) of D/S Flared out wall, 2nd lift at Block No-5 has done in presence of Client & PSS team.
75/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
76/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall, 10th lift at Block No-5 is under progress.
77/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for D/S Flank wall, 4th lift at Block No-5 is under progress.
78/100
Instream Storage Structure, Hamirpur
Shuttering of Railing beam (Bay No-18 to 29) is under progress.
79/100
Instream Storage Structure, Hamirpur
Shuttering of Flared wall is under progress.
80/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 180.02m.
81/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
De-shuttering of CC Blocks is under progress.
82/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Present status of river Samakoi at Santeibhanja site.
83/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering & Binding of reinforcement for RHS Double pier, 5th lift is under progress.
84/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering & Binding of reinforcement for LHS D/S Divide wall, 7th lift is under progress.
85/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.2m.
86/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of LHS Abutment Counterfort wall, 3rd lift done in presence of Client & PSS Team.
87/100
Instream Storage Structure, Khalpal
Concreting M25A20 of LHS Abutment Counterfort wall, 3rd lift is under progress in presence of Client & PSS Team.
88/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 55.30 m.
89/100
UGPL, Left Lower Suktel Canal Division
OMS verification work is in progress of OMS (RO-08A) in presence of PMC team near Gerdi
90/100
UGPL, Left Lower Suktel Canal Division
Out side boundary wall stone pitching work is in progress of Pump House.
91/100
UGPL, Right Lower Suktel Canal Division
Pump House Boundary wall outside back filling work is in progress.
92/100
UGPL, Right Lower Suktel Canal Division
Joint verification is conducted of OCS No-0213055-C01B for relocation to highest points of one hectare outlet near Timapali.
93/100
Instream Storage Structure, Khalpal
Testing of Compressive M20A20 (Strength is 29.41/mm2 for 28 days) of Barrage Bay No-2 Gravity floor and M25A20 (Strength is 34.38/mm2 for 28 days) of Pier No-13 (Starter) has done in presence of Client & PSS team.
94/100
Instream Storage Structure, Khalpal
Shuttering & Binding of reinforcement for LHS Abutment Counterfort wall, 2nd lift is under progress.
95/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 56.15 m.
96/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flank wall, 4th lift at Block No-5 is under progress.
97/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall, 9th lift at Block No-5 is under progress.
98/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
99/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 180.300m.
100/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.96/mm2 for 28 days) of Pier No-2, 10th lift and M35A20 (Strength is 37.63/mm2 for 07 days) of Gantry Girder No-46 and M30A20 (Strength is 28.59/mm2 for 07 days) of Groove 2nd stage, 5th lift (Bay No-27) has done in presence of Client & PSS team.