1/100
Instream Storage Structure, KansariGanda
Today SDO of department & Irr expert of PMC visited and checked shuttering & steel of Pier 4 3rd lift. Pouring of concrete started. Before concreting spread cement mortar. Slump Cone test and cube cast at site in presence of AEE, AE department Irr. Eng. Expert & site engineer PMC. Curing work progress at site. Chaining and rolling of coffer dam is in progress. Excavation of foundation for Guard wall of diaphragm wall of left flank wall is in progress. Levelling of d/s of left under sluice area for marking of d/s divide wall.
2/100
Instream Storage Structure, KansariGanda
Today SDO of department & Irr expert of PMC visited and checked shuttering & steel of Pier 4 3rd lift. Pouring of concrete started. Before concreting spread cement mortar. Slump Cone test and cube cast at site in presence of AEE, AE department Irr. Eng. Expert & site engineer PMC. Curing work progress at site. Chaining and rolling of coffer dam is in progress. Excavation of foundation for Guard wall of diaphragm wall of left flank wall is in progress. Levelling of d/s of left under sluice area for marking of d/s divide wall.
3/100
Instream Storage Structure, KansariGanda
Today SDO of department & Irr expert of PMC visited and checked shuttering & steel of Pier 4 3rd lift. Pouring of concrete started. Before concreting spread cement mortar. Slump Cone test and cube cast at site in presence of AEE, AE department Irr. Eng. Expert & site engineer PMC. Curing work progress at site. Chaining and rolling of coffer dam is in progress. Excavation of foundation for Guard wall of diaphragm wall of left flank wall is in progress. Levelling of d/s of left under sluice area for marking of d/s divide wall.
4/100
Instream Storage Structure, KansariGanda
Today SDO of department & Irr expert of PMC visited and checked shuttering & steel of Pier 4 3rd lift. Pouring of concrete started. Before concreting spread cement mortar. Slump Cone test and cube cast at site in presence of AEE, AE department Irr. Eng. Expert & site engineer PMC. Curing work progress at site. Chaining and rolling of coffer dam is in progress. Excavation of foundation for Guard wall of diaphragm wall of left flank wall is in progress. Levelling of d/s of left under sluice area for marking of d/s divide wall.
5/100
Instream Storage Structure, KansariGanda
Today SDO of department & Irr expert of PMC visited and checked shuttering & steel of Pier 4 3rd lift. Pouring of concrete started. Before concreting spread cement mortar. Slump Cone test and cube cast at site in presence of AEE, AE department Irr. Eng. Expert & site engineer PMC. Curing work progress at site. Chaining and rolling of coffer dam is in progress. Excavation of foundation for Guard wall of diaphragm wall of left flank wall is in progress. Levelling of d/s of left under sluice area for marking of d/s divide wall.
6/100
Instream Storage Structure, KansariGanda
Today SDO of department & Irr expert of PMC visited and checked shuttering & steel of Pier 4 3rd lift. Pouring of concrete started. Before concreting spread cement mortar. Slump Cone test and cube cast at site in presence of AEE, AE department Irr. Eng. Expert & site engineer PMC. Curing work progress at site. Chaining and rolling of coffer dam is in progress. Excavation of foundation for Guard wall of diaphragm wall of left flank wall is in progress. Levelling of d/s of left under sluice area for marking of d/s divide wall.
7/100
Instream Storage Structure, KansariGanda
Today SDO of department & Irr expert of PMC visited and checked shuttering & steel of Pier 4 3rd lift. Pouring of concrete started. Before concreting spread cement mortar. Slump Cone test and cube cast at site in presence of AEE, AE department Irr. Eng. Expert & site engineer PMC. Curing work progress at site. Chaining and rolling of coffer dam is in progress. Excavation of foundation for Guard wall of diaphragm wall of left flank wall is in progress. Levelling of d/s of left under sluice area for marking of d/s divide wall.
8/100
UGPL, Left Lower Suktel Canal Division
75mm Dia HDPE pipe laying work is in progress of node from LO-330 to LO-330B near village Birkel.
9/100
UGPL, Left Lower Suktel Canal Division
DI pipe (300×125×300)mm Tee fitting work is in progress at j-170(LM-6) near village Badipali.
10/100
Instream Storage Structure, Gudvella
Visited SE , IE expert at ISS Gudvella site today. Dept JE , site engineer of PMC and agency were present.
1. Checked the reinforcement work of right side abutment (A2)
2. Instructed to agency increase the manpower for speed up work on 02.12.2025
11/100
Instream Storage Structure, Gudvella
Reinforcement at right side under sluice bay in between P9 and A2 for final lift pocket filling work is under progress on 02.12.2025
12/100
UGPL, Left Lower Suktel Canal Division
Excavation work in progress for connection of DI to HDPE line of node from J-170 to LO-115 (LM-6) near village Badipali.
13/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at Pier no.9 for 7th lift at U/S side & 8th lift at D/S side from RL-241.10m to RL-242.45m is in progress through concrete pump in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 85mm on 02.12.2025
14/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at Pier no.9 for 7th lift at U/S side & 8th lift at D/S side from RL-241.10m to RL-242.45m is in progress through concrete pump in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 85mm on 02.12.2025
15/100
Instream Storage Structure, Nandagaon
Columns fit up and base plate welding under progress on 02.12.2025
16/100
Instream Storage Structure, Nandagaon
Shuttering at D/S left flared out wall, Block-1 is in progress on 02.12.2025
17/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering at pier no-12,Block-2 is in progress on 02.12.2025
18/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress at double crop area for laying of DN 75 HDPE Pipe of 1Ha. sub-chak from Junction - J-0775 to J-1084 at village Gaintala In presence of PMC team.
19/100
UGPL, Right Lower Suktel Canal Division
Inside slope wall portion plastering work is in progress of internal drainage at Pump House.
20/100
UGPL, Right Lower Suktel Canal Division
Fire fighting system water tank outside primer painting work is in progress at Pump House.
21/100
UGPL, Left Lower Suktel Canal Division
HDPE pipe (140×75×75)mm Tee connection work is in progress of RO-158(RM-8) At village Bhainsa.
22/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 75mm Dia HDPE pipe line from LO-307 to LO-307B(LM16) near village Singhanimunda .
23/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of Counter fort, 1st lift is under progress in presence of Client & PSS Team.
24/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Excavation of D/S Counter fort wing wall is under progress.
25/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for Divide wall, 3rd lift is under progress.
26/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
De-shuttering of LHS D/S Counter fort is under progress.
27/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
De-shuttering of LHS D/S Divide wall, 1st lift is under progress.
28/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS U/S Divide wall, 2nd lift is under progress.
29/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cube casting & Slump testing M20A20 (Value 85 mm) of LHS Gravity floor PCC done in presence of Client & PSS Team.
30/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M20A20 of LHS Gravity floor PCC is under progress in presence of Client & PSS Team.
31/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-7, 2nd lift is under progress.
32/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-6, 3rd lift is under progress.
33/100
Instream Storage Structure, Jharbeda
Shuttering of D/S Cut-off wall is under progress.
34/100
Instream Storage Structure, Jharbeda
Dewatering work is under progress.
35/100
Instream Storage Structure, Hamirpur
Concreting M30A20 of Sill beam (Bay No-12) is under progress in presence of Client & PSS Team.
36/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-10, 5th lift done in presence of Client & PSS Team.
37/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-10, 5th lift is under progress in presence of Client & PSS Team.
38/100
Instream Storage Structure, Hamirpur
2nd stage embedded parts, seal beam installation work is in progress at Bay No-10.
39/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 29.88/mm2 for 28 days) of Pier No-27, 10th lift and (Strength is 21.48/mm2 for 07 days) of Pier No-28, 15th lift and (Strength is 21.48/mm2 for 07 days) of Pier No-29, 11th lift has done in presence of Client & PSS team.
40/100
Instream Storage Structure, Hamirpur
Curing of Pier No-17, 8th lift is under progress.
41/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Pier No-18, 9th lift is under progress.
42/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Pier No-23, 12th lift is under progress.
43/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Pier No-29, 13th lift is under progress.
44/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-31, 7th lift is under progress.
45/100
Instream Storage Structure, Khalpal
Review meeting conducted by S.E, AID at his office in presence of A.E.E, AID, Dy. TL & SDE of PSS team along with representative of EPC agency and discussion held on future work plan as well as to expedite the Land acquisition & land alienation process.
46/100
Instream Storage Structure, Khalpal
Visited by S.E, AID in presence of A.E.E, AID, CME & IEE of PSS team along with representative of EPC agency at ISS Site for inspection of Shuttering & Binding of reinforcement of Girder and other construction work activities at site.
47/100
Instream Storage Structure, Khalpal
Hirakud Government Lab mix design trial mix conducted at site laboratory of M25A20, 28 days cube (Strength 46.49 N/mm²) in presence of PSS Team.
48/100
Instream Storage Structure, KansariGanda
Intermediate Pier No- 4 Shuttering & reinforcement binding is in progress.
49/100
Instream Storage Structure, KansariGanda
Intermediate Pier No- 4 Shuttering & reinforcement binding is in progress.
50/100
UGPL, Left Lower Suktel Canal Division
225mm Dia HDPE Pipe laying work is in progress node from J-166 to J-188 at village Ramsingha.
51/100
Integrated Barrage across river Kochila and across river Baitarini
M20 Grade 28days Compressive strength test Conducted for C.C Block at Baitarani ISS Site laboratory in presence of Quality Control AEE of Quality Assurance Division Chandikhol. Superintending Engineer,AEE and AE of Akhuapada irrigation Division,PMCand representatives of Agency-02.12.2025
52/100
Integrated Barrage across river Kochila and across river Baitarini
SE, Akhuapada along with AEE & AE & AEE, QA Divn., Chandikhol and PMC inspecting work progress at Baitarani ISS Project-02.12.2025
53/100
Instream Storage Structure, Gudvella
Cast of concrete 3rd lift pocket filling M20A20 grade at right side under sluice bay in between P9 and A2 from RL 146.15 m to 147.10m in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 83mm on 01.12.2025
54/100
Instream Storage Structure, Gudvella
Cast of concrete 3rd lift pocket filling M20A20 grade at right side under sluice bay in between P9 and A2 from RL 146.15 m to 147.10m in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 83mm on 01.12.2025
55/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for total of 1no. of CC block at U/S right flared out wall from sec.4-4 to sec.5-5 for 2nd lift of hight 0.6m upto RL-237.00m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 75mm on 01.12.2025
56/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for total of 1no. of CC block at U/S right flared out wall from sec.4-4 to sec.5-5 for 2nd lift of hight 0.6m upto RL-237.00m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 75mm on 01.12.2025
57/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for total 2nos. CC blocks at D/S left flared out wall i.e 1no. of size 6.0x1.5x0.6m from sec.5-5 to sec.6-6 for 4th lift & 1no. from sec.4-4 to sec.5-5bfpr 3rd lift of 0.6m hight upto RL-237.60m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 72mm on 01.12.2025
58/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for total 2nos. CC blocks at D/S left flared out wall i.e 1no. of size 6.0x1.5x0.6m from sec.5-5 to sec.6-6 for 4th lift & 1no. from sec.4-4 to sec.5-5bfpr 3rd lift of 0.6m hight upto RL-237.60m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 72mm on 01.12.2025
59/100
Instream Storage Structure, Nandagaon
Columns fit up and base plate welding under progress on 01.12.2025
60/100
Instream Storage Structure, Nandagaon
Reinforcement binding & shuttering at pier no-12, Block-2 is in progress on 01.12.2025
61/100
UGPL, Left Lower Suktel Canal Division
Internal drainage wall concreting work is in progress near boundary wall of Pump House.
62/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress at double crop area for laying of DN 225 HDPE Pipe of from Junction - J-0775 to J-1084 at village Gaintala In presence of DoWR SDO & PMC team.
63/100
UGPL, Left Lower Suktel Canal Division
1Ha. chamber fixing work is in progress of OMS RO-271B ,Z-4766 near village Jharmunda In presence of PMC team and EPC staff.
64/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 90mm Dia HDPE pipe line from LO-309 to LO-309A(LM-16 )near village Sargad.
65/100
UGPL, Left Lower Suktel Canal Division
Excavation work in progress for connection of DI to HDPE line of node from J-135 to LO-206 (LM-11) near village Tentulikhunti In presence of PMC team and Meil personnel.
66/100
UGPL, Left Lower Suktel Canal Division
Wall shuttering bord fixing work is in progress of Internal drainage near boundary wall of Pump House.
67/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of Abutment & Counter fort is under progress.
68/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cube casting & Slump testing M25A20 (Value 85 mm) of D/S Abutment & Counter fort wall done in presence of Client & PSS Team.
69/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of D/S Abutment & Counter fort wall is under progress in presence of Client & PSS Team.
70/100
Instream Storage Structure, Jharbeda
Dewatering work is under progress.
71/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 88 mm) of Pier No-24, 13th lift done in presence of Client & PSS Team.
72/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-24, 13th lift is under progress in presence of Client & PSS Team.
73/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-17, 8th lift done in presence of Client & PSS Team.
74/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-17, 8th lift is under progress in presence of Client & PSS Team.
75/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.32/mm2 for 28 days) of Pier No-28, 11th lift and (Strength is 30.16/mm2 for 28 days) of Pier No-31, 1st lift and (Strength is 21.33/mm2 for 07 days) of Pier No-31, 5th lift has done in presence of Client & PSS team.
76/100
Instream Storage Structure, Hamirpur
2nd stage embedded parts, seal beam erection work is in progress at (Bay No-11).
77/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-18, 9th lift is under progress.
78/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-10, 5th lift is under progress.
79/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 155 mm) of U/S Barrage bay Panel No-21 done in presence of Client & PSS Team.
80/100
Instream Storage Structure, Khalpal
Concreting M25A20 of U/S Barrage bay Panel No-21 done in presence of Client & PSS Team.
81/100
Instream Storage Structure, Khalpal
End stopper fixing for U/S Barrage bay Panel No-21 in presence of Client & PSS Team.
82/100
UGPL, Left Lower Suktel Canal Division
Outlet point fixing work is in progress at LM-6,LO114A(z-7170) near village Badipali.
83/100
Instream Storage Structure, Khalpal
Diaphragm wall cage placing for U/S Barrage bay Panel No-21 in presence of Client & PSS Team.
84/100
Instream Storage Structure, Khalpal
Excavation of Diaphragm wall U/S Barrage bay Panel No-21 is under progress in presence of Client & PSS Team.
85/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cube casting & Slump testing M25A20 (Value 85 mm) of RHS Divide wall, 3rd lift done in presence of Client & PSS Team.
86/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of RHS Divide wall, 3rd lift is under progress in presence of Client & PSS Team.
87/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M15A40 of D/S Divide wall raft PCC is under progress in presence of Client & PSS Team.
88/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of D/S Abutment wall is under progress.
89/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cube casting & Slump testing M25A20 (Value 85 mm) of LHS D/S Slope Divide wall done in presence of Client & PSS Team.
90/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS D/S Slope Divide wall is under progress in presence of Client & PSS Team.
91/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Testing of Compressive M25A20 (Strength is 19.43/mm2 for 07 days) of D/S Divide wall has done in presence of Client & PSS team.
92/100
Instream Storage Structure, Hamirpur
Cleaning of reinforcement for Pier No-11 is under progress by Sand blasting method.
93/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Pier No-9, 4th lift is under progress.
94/100
Instream Storage Structure, Hamirpur
Curing of Pier No-29, 12th lift is under progress.
95/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Pier No-10, 5th lift is under progress.
96/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-23, 12th lift is under progress.
97/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-24, 13th lift is under progress.
98/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-31, 7th lift is under progress.
99/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-29, 13th lift is under progress.
100/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of Divide wall, 3rd lift is under progress.
❮
❯