GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Integrated Barrage across river Kochila and across river Baitarini
LHS Barrage bay wing wall shear key wall casting work in progress-14.02.2026
2/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
First stage embedded parts fixing work is going on at Choudhary gada iss project-14.02.2026
3/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of Divide wall, 6th lift is under Progress.
4/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering & binding of reinforcement for D/S Wing wall is under Progress.
5/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for Double pier, 2nd lift & Middle pier, 8th lift is under Progress.
6/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cube casting & Slump testing M25A20 (Value 87 mm) of LHS side Cut-off done in presence of Client & PSS Team.
7/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cube casting & Slump testing M25A20 (Value 80 mm) of LHS Counterfort & Abutment wall, 7th lift done in presence of Client & PSS Team.
8/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS Counterfort & Abutment wall, 7th lift is under progress in presence of Client & PSS Team.
9/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for RHS D/S Counterfort & Abutment wall, 1st lift is under Progress.
10/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of RHS Barrage bay Sill beam and U/S & D/S Slope portion is under Progress.
11/100
Instream Storage Structure, Jharbeda
Curing of End sill is under Progress.
12/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-7, 5th lift is under Progress.
13/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-6, 7th lift is under Progress.
14/100
Instream Storage Structure, Jharbeda
Cleaning of RHS (D2) area is under Progress.
15/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-8 Footing, 2nd lift is under Progress.
16/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
17/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 80 mm) of Cross Girder (Bay No-26) at Block No-5 done in presence of Client & PSS Team.
18/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Cross Girder (Bay No-26) at Block No-5 is under progress in presence of Client & PSS Team.
19/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-8, 15th lift at Block No-2 done in presence of Client & PSS Team.
20/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-8, 15th lift at Block No-2 is under progress in presence of Client & PSS Team.
21/100
Instream Storage Structure, Hamirpur
Slump testing M15A40 (Value 45 mm) of U/S Flared wall, 7th lift at Block No-5 done in presence of Client & PSS Team.
22/100
Instream Storage Structure, Hamirpur
Concreting M15A40 of U/S Flared wall, 7th lift at Block No-5 is under progress in presence of Client & PSS Team.
23/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.92/mm2 for 28 days) of Pier No-19, 9th lift and M15A40 (Strength is 20.82/mm2 for 28 days) of RHS (A2) Core wall, 3rd lift at Block No-5 and M30A20 (Strength is 28.59/mm2 for 07 days) of Groove 2nd stage, 3rd & 5th lift (Bay No-23 & 24) and M35A20 (Strength is 36.59/mm2 for 07 days) of Cross Girder (Bay No-27) has done in presence of Client & PSS team.
24/100
Instream Storage Structure, Hamirpur
R.D.U assembly No-2 fixing work is in progress.
25/100
Instream Storage Structure, Hamirpur
Double pier hoist platform assembly 4 welding work is in progress.
26/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Deck slab (Bay No-27) is under progress.
27/100
Instream Storage Structure, Hamirpur
Shuttering of Flared wall, 7th lift is under progress.
28/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-30, 8th lift is under progress.
29/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-16, 5th lift is under progress.
30/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-13, 9th lift is under progress.
31/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-12, 14th lift is under progress.
32/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-11, 14th is under progress.
33/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-7, 9th lift is under progress.
34/100
Instream Storage Structure, Khalpal
S.E, inspected the tree enumeration exercise conducted for the joint verification and valuation of trees for the acquisition of private land.
35/100
Instream Storage Structure, Khalpal
Inspection by S.E, AID along with A.E.E & J.E, AID with Dy. TL, QAE & IEE of PSS team regarding Curing, Shuttering & binding of reinforcement for Barrage bay & Concreting of Girder and other ongoing activities at site.
36/100
Instream Storage Structure, Khalpal
Slump testing M35A20 (Value 85 mm) of Girder No-46 done in presence of Client & PSS Team.
37/100
Instream Storage Structure, Khalpal
Concreting M35A20 of Girder No-46 is under progress in presence of Client & PSS Team.
38/100
Instream Storage Structure, Khalpal
Slump testing M35A20 (Value 90 mm) of Girder No-45 done in presence of Client & PSS Team.
39/100
Instream Storage Structure, Khalpal
Concreting M35A20 of Girder No-45 is under progress in presence of Client & PSS Team.
40/100
Instream Storage Structure, Budharaja
Curing work is in Progress.
41/100
Instream Storage Structure, Budharaja
Shuttering Work is in Progress at Staff Quarter 1st Floor Slab.
42/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at RHS D/S Flared-out Wall, 22nd Step. RL: 218.300 to 218.900.
43/100
Instream Storage Structure, Budharaja
ISS-Budharaja 'Walk way' installation work is in progress top of the Pier
44/100
Instream Storage Structure, Budharaja
ISS -Budharaja monorail column installation work is in progress Pier No-3
45/100
Instream Storage Structure, Budharaja
Shuttering Work is in Progress at Staff Quarter 1st Floor Slab.
46/100
Instream Storage Structure, Budharaja
De-Shuttering in 21st Step & Shuttering work is in Progress at RHS D/S Flared-out Wall, 22nd Step. RL: 218.300 to 218.900.
47/100
Instream Storage Structure, Gochara
Discussed with site engineer (Mech)& Mech Engineer of Ageny.Instructed to furnish a realistic work programme immediately.
48/100
Instream Storage Structure, Gochara
Inspected Staff Qr & QC building. Advised to complete the Balance ancillary work immediately.
49/100
Instream Storage Structure, Gochara
IEE of PMC Sambalpur visited ISS Gochhra.
50/100
Instream Storage Structure, Gochara
Inspected LHS Afflux Bund. Advised to demarcate the land & give lay out profile immediately.
51/100
Instream Storage Structure, Gochara
Visited ISS Gochhra. Inspected RHS Approach road.Advised to expedite the progress of work so as to complete the Balance ancillary work latest by 15 th of March 2026.
52/100
Instream Storage Structure, Gochara
Trestle or column's nut tightening work is in progress.
53/100
Instream Storage Structure, Gochara
Cross beam nut and bolt fixing work is in progress of Barrage Bay no-3.
54/100
Instream Storage Structure, Gochara
Staff quarter roof reinforcement work in progress.
55/100
Instream Storage Structure, Gochara
Stone pitching in RHS U/S guide bund in progress.
56/100
Instream Storage Structure, Gochara
Trestle or column's nut tightening work is in progress.
57/100
Instream Storage Structure, Gochara
ISS GOCHHARA Cross beam nut and bolt fixing work is in progress of RHS Site Undersluice Bay.
58/100
Instream Storage Structure, Gochara
Staff quarter roof reinforcement work on progress
59/100
Instream Storage Structure, Gochara
Stone pitching in RHS U/S guide bund in progress.
60/100
Instream Storage Structure, Khirasasan
Slump 80mm
61/100
Instream Storage Structure, Khirasasan
LHS U/S FLARED OUT WALL 21TH STEP DESHUTTERING WORK IS UNDER PROGRESS
62/100
Instream Storage Structure, Khirasasan
RHS U/S FLANK WALL PROFILE 3RD LIFT SHUTTERING WORK IS UNDER PROGRESS.
63/100
Instream Storage Structure, Khirasasan
RHS ABUTMENT HOIST PORTION SHUTTERING WORK UNDER PROGRESS
64/100
Instream Storage Structure, Khirasasan
checked placing supporting bars and alignment of shuttering work in RHS D/S FLANK WALL 10th lift RL- 221.600 to 222.900 Now the area is ready for concrete casting M20 A20. So recommended for the purpose. Approved by AEE sir SID Sambalpur in presence of JE
65/100
Instream Storage Structure, Khirasasan
Slump 80mm
66/100
Instream Storage Structure, Khirasasan
checked placing supporting bars and alignment of shuttering work in RHS D/S flared out 19th step RL- 220.700 to 221.300 Now the area is ready for concrete casting M20 A20. So recommended for the purpose. Approved by AEE sir SID Sambalpur in presence of JE
67/100
Instream Storage Structure, Khirasasan
RHS ABUTMENT HOIST PORTION SHUTTERING WORK UNDER PROGRESS
68/100
Instream Storage Structure, Khirasasan
RHS D/S FLANK WALL PROFILE 10TH SHUTTERING WORK UNDER PROGRESS
69/100
Instream Storage Structure, Khirasasan
RHS U/S FLANK WALL PROFILE 3RD LIFT SHUTTERING WORK IS UNDER PROGRESS.
70/100
Instream Storage Structure, Khirasasan
RHS D/S FLARED OUT WALL 19TH STEP SHUTTERING WORK IS UNDER PROGRESS.
71/100
Instream Storage Structure, Khirasasan
LHS U/S FLARED OUT WALL 20TH STEP DESHUTTERING WORK IS UNDER PROGRESS
72/100
Instream Storage Structure Across Bheden near village Saida
Hoist Concreting in Peir no 1 , 2 & 3 completed.Instructed to complete Bal 6nos Joist by end of February.
73/100
Instream Storage Structure Across Bheden near village Saida
Visited ISS Saida. Instructed PM of Agency to expedite progress of work in order to complete the Balance ancillary work in targeted timeline.
74/100
Instream Storage Structure Across Bheden near village Saida
Shuttering work progress in LHS d/s flared out wall step-9
75/100
Instream Storage Structure Across Bheden near village Saida
Shuttering work progress in RHS u/s flared out wall step-3
76/100
Instream Storage Structure Across Bheden near village Saida
P-3 , Hoist portion curing work is going on .
77/100
Instream Storage Structure Across Bheden near village Saida
RHS U/S Flared out wall step -2 shuttering work is going on.
78/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump-180mm,tm-2
79/100
Instream Storage Structure across river Sapei near village Kinjirma
Concrete work under progress of diaphragm wall panel no 75 (M25A20) tremie concrete in presence of dept. AEE sir & AE sir .
80/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump-185mm,tm-1 D-Wall panel no 75 in presence of dept. AE sir (M25A20) tremie concrete
81/100
Instream Storage Structure across river Sapei near village Kinjirma
Core(soft rock) recovered from panel no 75 at RL- 198.3
82/100
Instream Storage Structure across river Sapei near village Kinjirma
Excavation work under progress of panel no 75 in presence of IEE, geologist and QCE of PMC Sambalpur.
83/100
Instream Storage Structure across river Sapei near village Kinjirma
Excavation work under progress of panel no 75 in presence of IEE, geologist and QCE of PMC Sambalpur.
84/100
Instream Storage Structure, Kopsinga
Double storied building footing raft 2no casting work is under progress presence of dept JE
85/100
Instream Storage Structure, Kopsinga
Cc block casting work is under progress presence of dept JE
86/100
Instream Storage Structure, Kopsinga
Double storied building footing raft =2no shuttering & reinforcement with cover checking completed now the area ready for casting M30/A20 presence of dept JE
87/100
Instream Storage Structure, Kopsinga
Cc block casting work is under progress
88/100
Instream Storage Structure, Kopsinga
RSH D/S flared Wall 10th lift casting work is under progress presence of dept JE & SDO
89/100
Instream Storage Structure, Kopsinga
Slump-75mm
90/100
Instream Storage Structure, Kopsinga
LHS D/S Flared wall casting work in progress
91/100
Instream Storage Structure, Kopsinga
Slump-85mm Flared wall
92/100
Instream Storage Structure, Kopsinga
Cube test
93/100
Instream Storage Structure, Kopsinga
RHS D/S Flared wall shuttering work
94/100
Instream Storage Structure, Kopsinga
Double storage building column steel work
95/100
Instream Storage Structure, Kudabega
LHS US flared wall casting in progress
96/100
Instream Storage Structure, Kudabega
Slump 80mm of stoplog , service gate groove, span 04
97/100
Instream Storage Structure, Kudabega
Slump 80mm of LHS us flared wall
98/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Cross-beam work is in progress
99/100
Instream Storage Structure, Kudabega
Slump 85mm
100/100
Instream Storage Structure, Kudabega
Right under sluice bay span no-03 p-3R & p-02 M30A20 for stoplog & service gate groove 2nd stage 1st lift casting work in progress

Enter Login Details