PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Gudvella
Casting of precast parapet railing under progress on 15.04.2026
2/100
Instream Storage Structure, Gudvella
Paint work is under progress on 15.04.2026
3/100
Instream Storage Structure, Gudvella
Hoist bridge and CDU Rope drum installation work under progress at P7 to P8 on 15.04.2026
4/100
Instream Storage Structure, Gudvella
Shuttering of Railing and posting of parapet wall of deck slab on 15.04.2026
5/100
Instream Storage Structure, Gudvella
Brick work at 1st floor of building is under progress at site on 15.04.2026
6/100
Instream Storage Structure, Gudvella
Fixing of precast railing with posts at the downstream side of span 2 is in progress on 14.04.2026
7/100
Instream Storage Structure, Gudvella
Casting of precast railing over parapet wall on the deck slab is in progress with dimensions 1.424 m × 0.13 m × 0.17 m on 14.04.2026
8/100
Instream Storage Structure, Gudvella
Paint work under progress on 14.04.2026
9/100
Instream Storage Structure, Gudvella
Hoist bridge and CDU Rope drum installation work under progress at P6 to P7 on 14.04.2026
10/100
Instream Storage Structure, Gudvella
Shuttering of Railing and posting of parapet wall of deck slab on 14.04.2026
11/100
Instream Storage Structure, Gudvella
Brick work at 1st floor of building is underprogress at site on 14.04.2026
12/100
Instream Storage Structure, Gudvella
Casting of precast railing over parapet wall on the deck slab has been commenced with dimensions 1.424 m × 0.13 m × 0.17 m on 13.04.2026
13/100
Instream Storage Structure, Gudvella
CDU ROPE drum installation work under progress at P3 to P5 on 13.04.2026
14/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No-0213125-C08A near village Jamgaon.
15/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for laying of 110mm Dia HDPE pipe from J-5335 to 2305099-C03 at Village Bhadrapali .
16/100
Instream Storage Structure, Gudvella
Brick work at building area is under progress at site on 13.04.2026
17/100
Instream Storage Structure, Gudvella
Shuttering of Railing and posting of parapet wall of deck slab on 13.04.2026
18/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of CC block at D/S right flared out wall is completed in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 78mm on 15.04.2026
19/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of CC block at D/S right flared out wall is completed in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 78mm on 15.04.2026
20/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.8,9,10&11 is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 85mm on 15.04.2026
21/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.8,9,10&11 is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 85mm on 15.04.2026
22/100
Instream Storage Structure, Nandagaon
• 2.The casting of CC block at following area has been checked in presence of PM,EPC agency, Site Engineers of PMC & EPC Agency: (i)1no. CC block at D/S right Flared out wall i.e 1no. of size 18.8x1.5x0.6m upto RL-238.80m is completed. (ii). Filling of inverted filter materials covering with LDPE paper at adjacent to each CC block in earth side are done before placement. (iii) Application of 2 coat bitumen paint at cj's concrete surface is done. (iv). Area is ready and passed by SE KID, Bh. Patna to place concrete with PCC M20A20 grade on 15.04.2026
23/100
Instream Storage Structure, Nandagaon
• 1. Fixing & fittings and alignment of 2nd. stage embedded parts and numbers of dowel bars as per drawing at roller tracks of both stoplog & service gate grooves at bay No.-9;&11 of Pier No. 8&9 for 5th lift and pier no. 10&11 for 2nd lift have been checked and found correct by HM Expert of PMC during his site visit on dt.13.04.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs. (i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows: (ii) Chipping of old vertical concrete surface is done. (iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 15.04.2026
24/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no.11 on 15.04.2026
25/100
Instream Storage Structure, Nandagaon
Shuttering for CC blocks is in progress at D/S right flared out wall on 15.04.2026
26/100
Instream Storage Structure, Nandagaon
Shuttering is in progress at U/S right divide wall on 15.04.2026
27/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right divide wall for 1st lift upto RL-232.90m is in progress through concrete pump in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 86mm on 14.04.2026
28/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right divide wall for 1st lift upto RL-232.90m is in progress through concrete pump in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 86mm on 14.04.2026
29/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.9&10 for 4th lift of bay.-10 is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 88mm on 14.04.2026
30/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.9&10 for 4th lift of bay.-10 is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 88mm on 14.04.2026
31/100
Instream Storage Structure, Nandagaon
Concrete Casting with M35A20 grade of Blockout portion at left abutment upto RL-246.30m is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency.The slump test value is 86mm on 14.04.2026
32/100
Instream Storage Structure, Nandagaon
Concrete Casting with M35A20 grade of Blockout portion at left abutment upto RL-246.30m is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency.The slump test value is 86mm on 14.04.2026
33/100
UGPL, Right Lower Suktel Canal Division
Valve chamber pre-cast cover slab concrete pouring work is in progress near Pump House.
34/100
Instream Storage Structure, Nandagaon
• 3.Checked the area of U/S right divide wall with following activities in presence of PM, EPC agency, Site Engineers of PMC & Site Engineer of EPC agency:- (i).Checked the reinforcement in binding, tying n spacing of both vertical main & horiz. dist. bars of U/S divide wall for 1st lift from RL-231.90m to RL-232.90m completed. (ii).Rigid n smooth shuttering with 75mm clear cover using cover blocks of 75mm are done. (iii).The concrete surface is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with RCC M25A20 grade on 14.04.2026
35/100
Instream Storage Structure, Nandagaon
• 2.Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay No.-10 of Pier No. 9&10 for 4th lift have been checked and found correct by HM Expert of PMC during his site visit on dt.13.04.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs. (i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows: (ii) Chipping of old vertical concrete surface is done. (iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 14.04.2026
36/100
Instream Storage Structure, Nandagaon
• 1(i).Fixing & fittings and alignment of All trestle and columns foundation bolts measurements has been checked at left abutment for Blockout area of 6.8m length and found correct by HM Expert of PMC during his site visit on dt.13.04.2026 in presence of mechanical Site Engineers of PMC and EPC Agency. (ii) Rigid and smooth shuttering for Blockout area with M35A20 grade at left abutment from RL-245.40m to RL-246.30m are found completed. (iii).The area is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with M35A20 grade on 14.04.2026
37/100
Instream Storage Structure, Nandagaon
De-Shuttering & Shuttering for 2nd stage concrete is in progress at pier no.10 on 14.04.2026
38/100
Instream Storage Structure, Nandagaon
De-Shuttering & Shuttering for CC blocks is in progress at D/S right flared out wall on 14.04.2026
39/100
Instream Storage Structure, Nandagaon
• U/S right divide wall following with activities:- i)Reinforcement binding is in progress. ii) De- Shuttering & Shuttering is in progress. iii) Curing is in progress on 14.04.2026
40/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of 2nos. CC blocks at D/S right Flared out wall i.e 1no. of size 4.0x1.8x0.6m at sec. 6-6 for 4th lift & 1no. of size 6.0x1.5x0.6m from sec.4-4 to sec.5-5 for 3rd lift upto RL-238.20m is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 84mm on 13.04.2026
41/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of 2nos. CC blocks at D/S right Flared out wall i.e 1no. of size 4.0x1.8x0.6m at sec. 6-6 for 4th lift & 1no. of size 6.0x1.5x0.6m from sec.4-4 to sec.5-5 for 3rd lift upto RL-238.20m is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 84mm on 13.04.2026
42/100
UGPL, Left Lower Suktel Canal Division
HDPE to 10ha tee connection work is in progress at RM-3 RO-42 Village Kusmel in presence of PMC team.
43/100
Instream Storage Structure, Nandagaon
Visited the Mechanical workshop area. Sand blasting n painting is in progress on 13.04.2026
44/100
Instream Storage Structure, Nandagaon
Visited the right embankment area. Layout and profile of U/S right Afflux Bond is given. Filling with excavated earth at bottom layer is in progress after preparation of bed by base stepping. Found the filling earth is not in suitable for compaction and was not in OMC condition before spreading. @ PM of EPC Agency is suggested for arrangement to heap watering system for each n every unloaded n dumping earth upto OMC condition before spreading of approved layer on 13.04.2026
45/100
Instream Storage Structure, Nandagaon
Casting of PCC with M20A20 grade on existing RCC raft for 1at. lift at U/S right Divide wall is in progress. Due to frequent choke of concrete pump today concrete work is going hampered. The PM of EPC Agency is suggested to do the needful for continuity of placement without break during placing concrete on 13.04.2026
46/100
Instream Storage Structure, Nandagaon
Sand blasting and painting work under progress on 13.04.2026
47/100
Instream Storage Structure, Nandagaon
Sand blasting and painting work under progress on 13.04.2026
48/100
UGPL, Left Lower Suktel Canal Division
HDPE Tee (75X 125 X 75)mm connection work is in progress at RO -127, RM-7, near village Sakma in presence of DoWR JE and PMC team.
49/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no.1,7&8 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 87mm on 13.04.2026
50/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no.1,7&8 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 87mm on 13.04.2026
51/100
Instream Storage Structure, Nandagaon
• Site visit of ISS Nandagaon, by HME, SHEE, Sr. Site Engineer and SDO, ISS Nandagaon in presence of PM of EPC Agency, Site Engineers of PMC & EPC Agency. Observations are made during visit as follows :- 1 (i).Fixing & fittings of trestles and columns foundation bolts including the alignment have been checked at Pier No.-7&8 of Blockout area of 6.8m length and found correct by HM Expert of PMC during his site visit on dt.13.04.2026 in presence of mechanical Site Engineers of PMC and EPC Agency. (ii) Rigid and smooth shuttering for Blockout area with M35A20 grade at pier upto RL-247.00m are found completed. (iii).The area is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with M35A20 grade on 13.04.2026
52/100
Instream Storage Structure, Nandagaon
Intermediate Concrete casting with PCC M20A40 grade at U/S right divide wall for 1st lift from RL-231.90m to RL-232.90m is in progress through concrete pump in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 87mm on 13.04.2026
53/100
Instream Storage Structure, Nandagaon
Intermediate Concrete casting with PCC M20A40 grade at U/S right divide wall for 1st lift from RL-231.90m to RL-232.90m is in progress through concrete pump in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 87mm on 13.04.2026
54/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage is in progress at pier no.10 on 13.04.2026
55/100
Instream Storage Structure, Nandagaon
Shuttering is in progress at U/S right divide wall on 13.04.2026
56/100
Instream Storage Structure, Nandagaon
Shuttering for CC blocks is in progress at D/S right flared out wall, Block-2 on 13.04.2026
57/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress at left abutment on 13.04.2026
58/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 125mm Dia HDPE pipe from J- 57 to RO -65, RM- 4 at village Fatabahal in presence of PMC team.
59/100
MMIP, Bankatira Barrage Project
The Agency has started Sheet Pile driving on 17.04.2026.
60/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for LHS side Raft under sluice portion is under progress.
61/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for Abutment with Counterfort, 9th lift is under progress.
62/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Testing of Compressive M25A20 (Strength is 21.84/mm2 for 07 days) of U/S Divide wall Footing Raft and (Strength is 30.70/mm2 for 28 days) of LHS Double pier, 8th lift has done in presence of Client & PSS team.
63/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 80 mm) of LHS D/S Counterfort & Wing wall, 3rd lift done in presence of Client & PSS Team.
64/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS D/S Counterfort & Wing wall, 3rd lift is under progress in presence of Client & PSS Team.
65/100
Instream Storage Structure, Jharbeda
Shuttering of (A2) Footing, 2nd lift is under progress.
66/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-5 is under progress.
67/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for pier No-5 to Pier No-6 U/S Wearing coat is under progress.
68/100
Instream Storage Structure, Jharbeda
Curing of Gravity floor is under progress.
69/100
Instream Storage Structure, Jharbeda
Curing of (A2) Footing is under progress.
70/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Gantry Girder No-19 done in presence of Client & PSS Team.
71/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-19 is under progress in presence of Client & PSS Team.
72/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Cross Girder (Bay No-15) at Block No-3 done in presence of Client & PSS Team.
73/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Cross Girder (Bay No-15) at Block No-3 is under progress in presence of Client & PSS Team.
74/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Pier No-3, 6th lift at Block No-1 done in presence of Client & PSS Team.
75/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-3, 6th lift at Block No-1 is under progress in presence of Client & PSS Team.
76/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of U/S Flank wall, 1st lift at Block No-1 done in presence of Client & PSS Team.
77/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of U/S Flank wall, 1st lift at Block No-1 is under progress in presence of Client & PSS Team.
78/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of D/S Flared out Cut-off wall, Raft at Block No-5 done in presence of Client & PSS Team.
79/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flared out wall, Raft at Block No-5 is under progress in presence of Client & PSS Team.
80/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.11/mm2 for 28 days) of Pier No-4, 1st lift and (Strength is 30.91/mm2 for 28 days) of Pier No-27, 14th lift and (Strength is 31.31/mm2 for 28 days) of Fish pass Raft at Block No-1 and M35A20 (Strength is 42.05/mm2 for 28 days) of Deck slab (Bay No-22 & 23) has done in presence of Client & PSS team.
81/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-1, 5th lift is under progress.
82/100
Instream Storage Structure, Hamirpur
Barrage bay groove 2nd stage embedded parts roller track and guide erection work is in progress at bay No-6.
83/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-3, 6th lift is under progress.
84/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-2, 5th lift is under progress.
85/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Abutment (A1), 8th lift is under progress.
86/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4, 5th is under progress.
87/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
88/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier no-16, 14th lift is under progress.
89/100
Instream Storage Structure, Khalpal
Inspection by Dy.TL, Q.A.E & I.E.E of PSS team along with EPC Agency at site and Checked the level of filter media of gravity floor for (Barrage Bay No-3).
90/100
Instream Storage Structure, Khalpal
Curing of Piers, Cut-off & Barrage Bay (Raft) work is in progress.
91/100
UGPL, Left Lower Suktel Canal Division
HDD machine road pushing work is in progress of 75mm Dia HDPE pipe line at RO- 242A(Z-3461) RM-13 near village Kusang in presence of DoWR JE and PMC team.
92/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI to HDPE pipeline connection at J-514, LM-15 near village Buromunda in presence of PMC team.
93/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 450mm Dia DI pipe line Laying and Gap closing LM-18, from J-459 to J-206 at village Birkel in presence of PMC team.
94/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 12.04.2026
95/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 12.04.2026
96/100
Instream Storage Structure, Gudvella
Curing of railing is under progress at site on 12.04.2026
97/100
Instream Storage Structure, Gudvella
• 1. Curing work at building. 2. Brick work at building is under progress on 12.04.2026
98/100
Instream Storage Structure, Gudvella
Casting of precast railing over the parapet wall is in progress with dimensions 1.424 m × 0.13 m × 0.17 m on 11.04.2026
99/100
Instream Storage Structure, Gudvella
Paint work is under progress on 11.04.2026
100/100
Instream Storage Structure, Gudvella
Hoist bridge installation work is under progress at P4 to P5 on 11.04.2026