GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
UGPL, Right Lower Suktel Canal Division
2nd coat painting work is in progress at primary filtration unit of Pump House.
2/100
UGPL, Right Lower Suktel Canal Division
Fire fighting system 150mm thickness final slab reinforcement binding work is in progress of Pump House.
3/100
UGPL, Left Lower Suktel Canal Division
Boundary wall plastering work is in progress of Pump House.
4/100
UGPL, Left Lower Suktel Canal Division
Boundary wall bricks work is in progress of Pump House.
5/100
Instream Storage Structure, Gudvella
Reinforcement & shuttering at middle portion of P9 for 7th lift RCC is under progress on 14.09.2025
6/100
Instream Storage Structure, Gudvella
Reinforcement & shuttering at middle portion of P9 for 7th lift RCC is under progress on 13.09.2025
7/100
Instream Storage Structure, Gudvella
Cast of concrete M25A20 grade at kerb of span - 01 to span - 04 is under progress through chute in the presence of Dept JE, site engineers of PMC n agency at site. Slump achieved 75mm on 12.09.2025
8/100
Instream Storage Structure, Gudvella
Cast of concrete M25A20 grade at kerb of span - 01 to span - 04 is under progress through chute in the presence of Dept JE, site engineers of PMC n agency at site. Slump achieved 75mm on 12.09.2025
9/100
Instream Storage Structure, Nandagaon
Curing of RCC deck slab, Block-1 is in progress on 14.09.2025
10/100
Instream Storage Structure, Nandagaon
• Site visit of ISS, Nandagaon by SE, KID, Bhawanipatna along with the SDO, ISS Nandagaon & Sr. Site Engineer of PMC on dt. 13.09.2025 in presence of PM, EPC Agency and Site Engineers PMC & EPC Agency,ISS Nandagaon. The following activites are being done during his visit: 1. Foundation Layout plan of office/ Control room building is given as per the apprved design n drawings in presnce of SE, KID, Bhawanipatna, SDO & JE ISS Nandagaon, Sr. Site Engineer of PMC and Site Engineers of PMC n EPC agency on 13.09.2025
11/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for RCC deck slab at Span -7 of barrage bay-5, Block-1 is in progress on 13.09.2025
12/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for RCC deck slab at Span -7 of barrage bay-5, Block-1 is in progress on 12.09.2025
13/100
Instream Storage Structure, Mahulpali
D/S view of ISS Mahulpali on 14.09.2025
14/100
Instream Storage Structure, Mahulpali
U/S view of ISS Mahulpali on 14.09.2025
15/100
Instream Storage Structure, Mahulpali
D/S view of ISS Mahulpali on 13.09.2025
16/100
Instream Storage Structure, Mahulpali
U/S view of ISS Mahulpali on 13.09.2025
17/100
Instream Storage Structure, Mahulpali
D/S view of ISS Mahulpali on 12.09.2025
18/100
Instream Storage Structure, Mahulpali
U/S view of ISS Mahulpali on 12.09.2025
19/100
Instream Storage Structure, KansariGanda
Slump cone test and Cube test conducted at site in presence of QA&QC expert along with Site engineer PMC.
20/100
Instream Storage Structure, KansariGanda
Slump cone test and Cube test conducted at site in presence of QA&QC expert along with Site engineer PMC.
21/100
Instream Storage Structure, KansariGanda
Pier-3, 6th lift casting is in progress in presence of AEE, AE department and QA&QC Expert along with Site Engineers of PMC.
22/100
Instream Storage Structure, KansariGanda
Pier-3, 6th lift casting is in progress in presence of AEE, AE department and QA&QC Expert along with Site Engineers of PMC.
23/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.600m.
24/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 180.225m.
25/100
Instream Storage Structure, Hamirpur
Curing of Girders is under progress.
26/100
Instream Storage Structure, Hamirpur
Curing of Abutment wall (A2) at Block -5 is under progress.
27/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Abutment wall (A2), 15th lift with Dirt wall at Block -5 is under progress.
28/100
Instream Storage Structure, Hamirpur
Binding of Reinforcement for Girder No-83 is under progress.
29/100
Instream Storage Structure, Khalpal
Slump testing M20A40 (Value 60 mm) C.C Blocks done in presence of Client & PSS Team.
30/100
Instream Storage Structure, Khalpal
Casting of C.C Block (M20A40) is under progress in presence of Client & PSS Team.
31/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.800m.
32/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Girder No-82 done in presence of Client & PSS Team.
33/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Girder No-82 is under progress in presence of Client & PSS Team.
34/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 36.15/mm2 for 07 days) of Girder No-77 and (Strength is 35.71/mm2 for 07 days) of Girder No-78 has done in presence of Client & PSS team.
35/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 180.450m.
36/100
Instream Storage Structure, Hamirpur
Curing of Girders is under progress.
37/100
Instream Storage Structure, Hamirpur
Curing of Abutment wall (A2) at Block -5 is under progress.
38/100
Instream Storage Structure, Hamirpur
Binding of Reinforcement & Shuttering of U/S Abutment wall (A2), 15th lift with Dirt wall at Block -5 is under progress.
39/100
Instream Storage Structure, Hamirpur
Shuttering of Girder No-82 is under progress.
40/100
Instream Storage Structure, Khalpal
Testing of Compressive M20A40 (Strength is 27.96/mm2 for 07 days) of CC Block has done in presence of Client & PSS team.
41/100
Instream Storage Structure, Khalpal
Slump testing M20A40 (Value 60 mm) C.C Blocks done in presence of Client & PSS Team.
42/100
Instream Storage Structure, Khalpal
Casting of C.C Block (M20A40) is under progress in presence of Client & PSS Team.
43/100
Integrated Barrage across river Kochila and across river Baitarini
CC block casting is in progress-14.09.2025
44/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
No activities at site and present status of river & Structure.
45/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
No activities at site and present status of river & Structure.
46/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.900m.
47/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Girder No-81 done in presence of Client & PSS Team.
48/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Girder No-81 is under progress in presence of Client & PSS Team.
49/100
Instream Storage Structure, Hamirpur
Demarcation of land for approach road in presence of R.I., Amin along with PSS team and EPC agency.
50/100
Instream Storage Structure, Hamirpur
D.P Test going on the hoist bridge platform assembly work is in progress.
51/100
Instream Storage Structure, Hamirpur
Curing of Girders is under progress.
52/100
Instream Storage Structure, Hamirpur
Curing of Abutment wall (A2) at Block -5 is under progress.
53/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Abutment wall (A2), 15th lift with Dirt wall at Block -5 is under progress.
54/100
Instream Storage Structure, Hamirpur
Binding of Reinforcement for Girder No-82 is under progress.
55/100
Instream Storage Structure, Hamirpur
Shuttering of Girder No-81 is under progress.
56/100
Instream Storage Structure, Sirigida
Present status in river.
57/100
Instream Storage Structure, Khalpal
Slump testing M20A40 (Value 65 mm) C.C Blocks done in presence of Client & PSS Team.
58/100
Instream Storage Structure, Khalpal
Casting of C.C Block (M20A40) is under progress in presence of Client & PSS Team.
59/100
Instream Storage Structure across river Sapei near village Kinjirma
D/S ( R. H. S )* Flow direction is straight flow is seen at RL-207.450 against crest level RL-206.250 . * ?Water is flowing 1.2m above the crest level .
60/100
Instream Storage Structure across river Sapei near village Kinjirma
Curing of column 1st footing in Building staff quarter /control room .
61/100
Instream Storage Structure across river Sapei near village Kinjirma
D/S ( R. H. S )* Flow direction is straight flow is seen at RL-207.450 against crest level RL-206.250 . * ?Water is flowing 1.2m above the crest level .
62/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
63/100
Instream Storage Structure, Khirasasan
The flow level is 212.400 m against the design RL: 210.900, i.e.,1.5 M flood lift.
64/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
65/100
Instream Storage Structure, Khirasasan
The flow level is 211.600 m against the design RL: 210.900, i.e.,0.7M flood lift.
66/100
Instream Storage Structure, Budharaja
Precast Reeling Beam casting in progress.
67/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S of river. The flow level is 208.700 m against the design RL: 206.700, i.e., 2.0m flood lift.
68/100
Instream Storage Structure, Budharaja
View Showing Flow of river From U/S to D/S ( From U/S of river)
69/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S of river. The flow level is 208.350 m against the design RL: 206.700, i.e., 1.65 m flood lift.
70/100
Instream Storage Structure, Budharaja
View Showing Flow of river From U/S to D/S ( From U/S of river)
71/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river)
72/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. Flow direction is straight. The direction of flow is seen in middle of the river. Now the flow level is 226.100mt against design crest level 225.500 i.e. flood lift 0.6mt.
73/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
74/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. Flow direction is straight. The direction of flow is seen in middle of the river. Now the flow level is 226.100mt against design crest level 225.500 i.e. flood lift 0.6mt.
75/100
Instream Storage Structure, Kudabega
Slump 80mmspan15 Barrage 2 Both side kerb
76/100
Instream Storage Structure, Kudabega
Casting of span Nzo 17 Barrage 2 Hand rail Both side slump 80mmM35A20
77/100
Instream Storage Structure, Kudabega
Flow seen At us side US of river Flow of river seen at 207.100m against crest RL 206.00m(1.100m Ht of water) Water level 207.100m
78/100
Instream Storage Structure, Kudabega
Flow seen at DS side(DS of river)
79/100
Instream Storage Structure, Kudabega
Span no-18 hand railing fixing & Hand Railing Post Shuttering work in progress
80/100
Instream Storage Structure, Kudabega
Span no-15 Kerb Shuttering work in progress
81/100
Instream Storage Structure, Kudabega
P-15 gate groove chipping work in progress
82/100
Instream Storage Structure, Kudabega
View showing flow of river from D/S Side (D/S of River) . River water level: 206 .900 m.
83/100
Instream Storage Structure, Kudabega
View showing flow of river from U/S side (U/S of river) .
84/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Trestle's base plate work is in progress
85/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Hoist bridge's 19th platform assembly work is in progress
86/100
Instream Storage Structure, Kopsinga
P 8 Hoist casting under progress
87/100
Instream Storage Structure, Kopsinga
Slump-85mm pier no 8 Hoist
88/100
Instream Storage Structure, Kopsinga
P-8 Hoist casting under progress
89/100
Instream Storage Structure, Kopsinga
Slump-85mm
90/100
Instream Storage Structure, Kopsinga
Slump-95mm Tm1 Hoist -9
91/100
Instream Storage Structure, Kopsinga
Pier no -9 Hoist Reinforcement ,Shuttering with cover check in presence of Dept..JE madam now the area ready for casting M25 A20 ISS Kopsingha.
92/100
UGPL, Right Lower Suktel Canal Division
RCC road reinforcement binding work is in progress of Pump House In the presence of SDO, JE (DoWR) and PMC team.
93/100
UGPL, Right Lower Suktel Canal Division
Fire fighting system final roof slab Shuttering work is in progress of Right Pump House.
94/100
UGPL, Left Lower Suktel Canal Division
25x6mm GI earth flat laying and fixing work is in progress for 35/5 ton EOT crane at left Pump House.
95/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress of HDPE pipeline Dia 280mm at Village Kushmel from J-532 to J-596 (LM-7 Gap closing area).
96/100
UGPL, Left Lower Suktel Canal Division
25x6mm GI earth flat laying and fixing work is in progress at Left Pump House.
97/100
UGPL, Left Lower Suktel Canal Division
Boundary wall outer side plastering work is in progress of Pump House.
98/100
UGPL, Left Lower Suktel Canal Division
Boundary Wall column reinforcement rod binding work is in progress of Pump House.
99/100
UGPL, Left Lower Suktel Canal Division
Boundary wall bricks masonry work is in progress of Pump House.
100/100
Instream Storage Structure, Dhanei
U/S left side flank wall and return counter fort wall casting is in progress in presence of Irr. Eng. Expert along with Site Engineer of PMC.