1/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.610m.
2/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.760m.
3/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of D/S Flank wall, 10th lift at Block No-5 done in presence of Client & PSS Team.
4/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flank wall, 10th lift at Block No-5 is under progress in presence of Client & PSS Team.
5/100
Instream Storage Structure, Hamirpur
Rope drum Hoist bottom block bracket welding work is in progress.
6/100
Instream Storage Structure, Hamirpur
Column Trestle No-25 bracing welding work is in progress.
7/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Deck slab (Bay No-18) done in presence of Client & PSS Team.
8/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Deck slab (Bay No-18) is under progress in presence of Client & PSS Team.
9/100
Instream Storage Structure, Hamirpur
Cleaning of reinforcement for Deck slab (Bay No-18) is under progress by Sand blasting method.
10/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.11/mm2 for 28 days) of Hand Rail Beam Bay No-26,27,28 & 29 at Block No-5 and M35A20 (Strength is 42.44/mm2 for 28 days) of Gantry Girder No-59,60,61 & 62 and (Strength is 37.48/mm2 for 07 days) of Gantry Cross Girder has done in presence of Client & PSS team.
11/100
Instream Storage Structure, Hamirpur
Mud cleaning from Watchman Quater footing Area is under progress.
12/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.870m.
13/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
14/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site level RL 56.9m.
15/100
Instream Storage Structure, Khalpal
Slump testing M35A20 (Value 80 mm) of Girder No-63 done in presence of Client & PSS Team.
16/100
Instream Storage Structure, Khalpal
Concreting M35A20 of Girder No-63 is under progress in presence of Client & PSS Team.
17/100
Instream Storage Structure, Khalpal
Shuttering of Girder No-63 is under progress.
18/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
19/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site level RL 56.62m.
20/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
21/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.93/mm2 for 07 days) of Handling No-27 to 29 and M25A20 (Strength is 21.18/mm2 for 07 days) of Railing beam at Block No-5 has done in presence of Client & PSS team.
22/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flank wall, 10th lift at Block No-5 is under progress.
23/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.800m.
24/100
Instream Storage Structure, Khalpal
Slump testing M35A20 (Value 90 mm) of Girder No-62 done in presence of Client & PSS Team.
25/100
Instream Storage Structure, Khalpal
Concreting M35A20 of Girder No-62 is under progress in presence of Client & PSS Team.
26/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
27/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site level RL 56.82m.
28/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 7.40m.
29/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 6.10m.
30/100
Integrated Barrage across river Kochila and across river Baitarini
C.E.,Designs,CE MBBS,Chandikhole,S.E.,AEE,AE of Akhuapada Irrigation Division,PMC team visited Baitarani ISS.
31/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 6.10m
32/100
Integrated Barrage across river Kochila and across river Baitarini
CC Block casting work at Baitarani ISS is in progress.
33/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 6.30m.
34/100
Integrated Barrage across river Kochila and across river Baitarini
CC Block casting work at Baitarani ISS is in progress.
35/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 6.10m.
36/100
Integrated Barrage across river Kochila and across river Baitarini
Girder casting work of Baitarani ISS is in progress.
37/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 6.40m.
38/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 6.40m.
39/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 8.50m.
40/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 10.30m.
41/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 10.30m.
42/100
Integrated Barrage across river Kochila and across river Baitarini
Checking of Reinforcement and shuttering work for pre cast Bridge Girder of Baitarani ISS before its concreting by S.S. & AEE,QAD,Chandikhole AEE Dhamnagar Irr Sub Division and PMC Team
43/100
Integrated Barrage across river Kochila and across river Baitarini
Checking of Reinforcement and shuttering work for pre cast Bridge Girder of Baitarani ISS before its concreting by S.S. & AEE,QAD,Chandikhole AEE Dhamnagar Irr Sub Division and PMC Team
44/100
Integrated Barrage across river Kochila and across river Baitarini
Girder Casting work at Baitarani ISS is in progress.
45/100
Integrated Barrage across river Kochila and across river Baitarini
Girder Shuttering work at Baitarani ISS is in progress.
46/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 10.10m
47/100
Integrated Barrage across river Kochila and across river Baitarini
C.C. Block casting work at Baitarani ISS is in progress.
48/100
Instream Storage Structure, Gudvella
• Visited employee and labours of TATA power at ISS Gudvella site
To energized / charging of transformer is under progress at site on 09.09.2026
49/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
50/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site level RL 56.82m.
51/100
Instream Storage Structure, Hamirpur
Slump testing M15A40 (Value 45 mm) of U/S (A2) Flared out wall, 14th lift at Block No-5 done in presence of Client & PSS Team.
52/100
Instream Storage Structure, Hamirpur
Concreting M15A40 of U/S (A2) Flared out wall, 14th lift at Block No-5 is under progress in presence of Client & PSS Team.
53/100
Instream Storage Structure, Hamirpur
Column guide line fixing and welding work is in progress.
54/100
Instream Storage Structure, Hamirpur
Bottom block rope pulley bracket welding work is in progress.
55/100
Instream Storage Structure, Hamirpur
Reinforcement binding for Deck slab (Bay No-18) is under progress.
56/100
Instream Storage Structure, Hamirpur
Mud cleaning from Watchman Quater footing Area is under progress.
57/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flank wall, 10th lift at Block No-5 is under progress.
58/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.600m.
59/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 08.09.2026
60/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 08.09.2026
61/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
62/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site level RL 56.747m.
63/100
Instream Storage Structure, Khalpal
Testing of Compressive M35A20 (Strength is 41.64/mm2 for 28 days) of Girder No-57 has done in presence of Client & PSS team.
64/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
65/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site level RL 56.73m.
66/100
Instream Storage Structure, Nandagaon
Curing is in progress at approach slab on 08.09.2026
67/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 42.07/mm2 for 28 days) of Gantry Girder No-58 and M35A20 (Strength is 42.44/mm2 for 28 days) of Fish pass slab at Block No-5 and M15A40 (Strength is 13.33/mm2 for 07 days) of U/S Flared out wall, 13th lift at Block No-5 has done in presence of Client & PSS team.
68/100
Instream Storage Structure, Hamirpur
Rope drum hoist lifting arrangements bottom block rope pulley bracket welding work is in progress.
69/100
Instream Storage Structure, Hamirpur
Mud cleaning from Watchman Quater footing Area is under progress.
70/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall, 10th lift at Block No-5 is under progress.
71/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.650m.
72/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 42.30/mm2 for 28 days) of Gantry Girder No-57 has done in presence of Client & PSS team.
73/100
Instream Storage Structure, Hamirpur
MS plate marking and cutting for single pier column guide line stiffener work is in progress.
74/100
Instream Storage Structure, Hamirpur
Single pier column guide line fixing work is in progress.
75/100
Instream Storage Structure, Hamirpur
Rope drum hoist lifting arrangements bottom block rope pulley bracket work is in progress.
76/100
Instream Storage Structure, Hamirpur
Dewatering from Watchman Quater footing Area is under progress.
77/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall, 10th lift at Block No-5 is under progress.
78/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.780m.
79/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.980m.
80/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 07.09.2026
81/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 07.09.2026
82/100
Instream Storage Structure, Nandagaon
Curing is in progress at approach slab on 07.09.2026
83/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water Level 9.20m
84/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water Level 8.30m
85/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water Level 8.30m
86/100
Integrated Barrage across river Kochila and across river Baitarini
C.C. Block shuttering and Curing work at Baitarani ISS is in progress
87/100
Integrated Barrage across river Kochila and across river Baitarini
CC block casting work at Baitarani ISS is in progress
88/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 7.60m
89/100
Integrated Barrage across river Kochila and across river Baitarini
C.C. Block casting work at Baitarani ISS is in progress.
90/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level 10.60m
91/100
Integrated Barrage across river Kochila and across river Baitarini
ISMB placing for precast Girder Platform.
92/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water Level 7.10m
93/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water Level 7.90m
94/100
Instream Storage Structure, KansariGanda
Team (AEE, Site Engineer & team, Amin, PMC-SD expert, Sarpanch-led land losers) carried out joint re-demarcation of 19 private + 28 govt. plots over 1.5 km stretch under UDS Pur.
A . Bond width fixed at 18m, considering cultivable private land
B .Boundary pegs with red flags fixed in presence of villagers
C .Cremation ground exempted from acquisition; bond width maintained as per alignment
Demarcation done with mutual consent of stakeholders.
95/100
Instream Storage Structure, KansariGanda
Team (AEE, Site Engineer & team, Amin, PMC-SD expert, Sarpanch-led land losers) carried out joint re-demarcation of 19 private + 28 govt. plots over 1.5 km stretch under UDS Pur.
A . Bond width fixed at 18m, considering cultivable private land
B .Boundary pegs with red flags fixed in presence of villagers
C .Cremation ground exempted from acquisition; bond width maintained as per alignment
Demarcation done with mutual consent of stakeholders.
96/100
Instream Storage Structure, KansariGanda
Team (AEE, Site Engineer & team, Amin, PMC-SD expert, Sarpanch-led land losers) carried out joint re-demarcation of 19 private + 28 govt. plots over 1.5 km stretch under UDS Pur.
A . Bond width fixed at 18m, considering cultivable private land
B .Boundary pegs with red flags fixed in presence of villagers
C .Cremation ground exempted from acquisition; bond width maintained as per alignment
Demarcation done with mutual consent of stakeholders.
97/100
Instream Storage Structure, KansariGanda
Team (AEE, Site Engineer & team, Amin, PMC-SD expert, Sarpanch-led land losers) carried out joint re-demarcation of 19 private + 28 govt. plots over 1.5 km stretch under UDS Pur.
A . Bond width fixed at 18m, considering cultivable private land
B .Boundary pegs with red flags fixed in presence of villagers
C .Cremation ground exempted from acquisition; bond width maintained as per alignment
Demarcation done with mutual consent of stakeholders.
98/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level 7.70m
99/100
Instream Storage Structure, KansariGanda
Visit of SD Expert of PMC and RI, Malada, and the Sarpanch of UDS Pur along with the Agency team. During the discussion, it was mutually decided to commence the re-demarcation work.
The Sarapancha assured that all land losers are well informed.The Agency team will arrange the required materials, including pegs, crowbars, and hammers, for marking and fixing the demarcated area. The RI Malada will oversee and coordinate the overall re-demarcation work.
100/100
Instream Storage Structure, KansariGanda
Visit of SD Expert of PMC and RI, Malada, and the Sarpanch of UDS Pur along with the Agency team. During the discussion, it was mutually decided to commence the re-demarcation work.
The Sarapancha assured that all land losers are well informed.The Agency team will arrange the required materials, including pegs, crowbars, and hammers, for marking and fixing the demarcated area. The RI Malada will oversee and coordinate the overall re-demarcation work.
❮
❯