Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Gudvella
• Today CE & BM, Tel Basin, Bhawanipatna, SE, SDO and AE, Balangir Irrigation Division, Balangir visited ISS Gudvella. During their visit, the Department JE, PMC Site Engineer and Agency representative were present. 1. The officials inspected the overall site conditions and reviewed the progress of the ongoing works. They instructed the agency to expedite and complete all remaining works without any further delay on 29.06.2026
2/100
Instream Storage Structure, Gudvella
• Today CE & BM, Tel Basin, Bhawanipatna, SE, SDO and AE, Balangir Irrigation Division, Balangir visited ISS Gudvella. During their visit, the Department JE, PMC Site Engineer and Agency representative were present. 1. The officials inspected the overall site conditions and reviewed the progress of the ongoing works. They instructed the agency to expedite and complete all remaining works without any further delay on 29.06.2026
3/100
Instream Storage Structure, Gudvella
Coverage work of roller drum is under progress at mechanical yard on 29.06.2026
4/100
Instream Storage Structure, Gudvella
Brick work is under progress at parapet wall of building on 29.06.2026
5/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 29.06.2026
6/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 29.06.2026
7/100
Instream Storage Structure, Nandagaon
Concrete casting with M20A20 grade of CC block at D/S right flared out wall is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency and found slump test value is 84mm at placing site on 29.06.2026
8/100
Instream Storage Structure, Nandagaon
Concrete casting with M20A20 grade of CC block at D/S right flared out wall is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency and found slump test value is 84mm at placing site on 29.06.2026
9/100
Instream Storage Structure, Nandagaon
• 1.The casting of the CC block at the following area has been checked in the presence of PM, EPC agency, Site Engineers of PMC & EPC Agency: (i) Shuttering for CC block at D/S right Flared out wall of 37.50m length & 0.6m ht. from RL-242.40m to RL-243.00m is completed. (ii). Filling of inverted filter materials covering with LDPE paper at adjacent to each CC block in earth side are done before placement. (iii) Application of 2 coat bitumen paint at cj's concrete surface is done. (iv). Area is ready and passed by SE KID, Bh. Patna to place concrete with PCC M20A20 grade on 29.06.2026
10/100
Instream Storage Structure, Nandagaon
The erection work and painting work has been stopped at the site today due to labour issues on 29.06.2026
11/100
UGPL, Right Lower Suktel Canal Division
OCS chamber above GL work is in progress of OCS No:- 0213094-C06A at village Mehermunda in presence of PMC team and L&T personnel.
12/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door and angle fixing work is in progress OCS No-: 0213127-C09B at village Raksimunda in presence of DoWR AE, PMC team and L&T official.
13/100
UGPL, Right Lower Suktel Canal Division
Approach channel 2nd slope and 3rd berm joint portion concreting work is in progress at Pump House.
14/100
UGPL, Left Lower Suktel Canal Division
Butt Fusion jointing work is in progress for 160mm Dia HDPE pipeline from J-301 to J - 582, RM-6 near village Baghapali in presence of PMC team..
15/100
UGPL, Left Lower Suktel Canal Division
Excavation work in progress for 160mm Dia HDPE pipe laying node from J-301 to J-582, RM-6 near village Baghapali in presence of PMC team.
16/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Gantry Girder No-41 done in presence of Client & PSS Team.
17/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-41 is under progress in presence of Client & PSS Team.
18/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-2, 11th lift done in presence of Client & PSS Team.
19/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-2, 11th lift is under progress in presence of Client & PSS Team.
20/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.17/mm2 for 28 days) of Pier No-1, 9th lift and (Strength is 21.78/mm2 for 07 days) of Pier No-1, 12th lift and M15A40 (Strength is 20.44/mm2 for 28 days) of Flared out wall PCC and M30A20 (Strength is 38.15/mm2 for 28 days) of Groove 2nd stage (Bay No-26, 27 & 28) has done in presence of Client & PSS team.
21/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Gantry Girder is under progress.
22/100
Instream Storage Structure, Hamirpur
Gantry girder's 1st stage embedded plate welding work is in progress.
23/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall Raft at Block No-1 is under progress.
24/100
Instream Storage Structure, Hamirpur
Shuttering of Abutment (A1), 12th lift at Block No-1 is under progress.
25/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for RHS D/S Counerfort & Abutment wall, 4th lift is under progress.
26/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for RHS D/S Counerfort & Wing wall, 3rd lift is under progress.
27/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of Pier No-17 (Starter) done in presence of Client & PSS Team.
28/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-17 (Starter) is under progress in presence of Client & PSS Team.
29/100
Instream Storage Structure, Khalpal
Site inspection by QC&QA Expert, PMU in presence of A.E.E & A.E, AID, Dy. TL, QAE, IEE of PSS team along with EPC agency and observed inside the gravity floor of Barrage Bay-2.
30/100
Instream Storage Structure, Khalpal
Shuttering of RHS Double Pier No-25, 3rd lift is under progress.
31/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
32/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for laying of 75mm Dia HDPE pipe of OCS No- 0201214-C05B for sub chak No-9 At village Buxiudar in presence of PMC team.
33/100
Instream Storage Structure, Gudvella
Brick work at headroom area of building is under progress at site on 28.06.2026
34/100
Instream Storage Structure, Gudvella
Minor mechanical grinding works are currently in progress on 28.06.2026
35/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 28.06.2026
36/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 28.06.2026
37/100
Instream Storage Structure, Gudvella
Today officials from the Gudvella Forest Section visited the ISS Gudvella site to inspect the sal trees located along the proposed approach road. The inspection was conducted to assess the tree and submit a report to their higher authorities for further necessary action on 27.06.2026
38/100
Instream Storage Structure, Gudvella
Brick work at the head room of building area is under progress at site on 27.06.2026
39/100
Instream Storage Structure, Gudvella
Staircase work at mechanical yard is under progress at site on 27.06.2026
40/100
Instream Storage Structure, Gudvella
Fittup work electrical pole is under progress at site on 27.06.2026
41/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 27.06.2026
42/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 27.06.2026
43/100
Instream Storage Structure, Gudvella
Staircase work is under progress at mechanical yard on 26.06.2026
44/100
Instream Storage Structure, Gudvella
Plastering work at building area is under progress at site on 26.06.2026
45/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 26.06.2026
46/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 26.06.2026
47/100
Instream Storage Structure, Nandagaon
Shuttering for CC block is in progress at D/S right flared out wall on 28.06.2026
48/100
Instream Storage Structure, Nandagaon
Shuttering for CC block at D/S right flared out wall is in progress on 27.06.2026
49/100
Instream Storage Structure, Nandagaon
The erection work has been stopped at the site today due to labour issues on 26.06.2026
50/100
Instream Storage Structure, Nandagaon
Curing is in progress at right abutment on 26.06.2026
51/100
Instream Storage Structure, Nandagaon
Shuttering for CC block at D/S right flared out wall is in progress on 26.06.2026
52/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of LHS D/S Divide wall, 2nd lift done in presence of Client & PSS Team.
53/100
Instream Storage Structure, Khalpal
Concreting M25A20 of LHS D/S Divide wall, 2nd lift is under progress in presence of Client & PSS Team.
54/100
Instream Storage Structure, Khalpal
Shuttering of RHS Double Pier No-25, 3rd lift is under progress.
55/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
56/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 85 mm) of RHS D/S Divide wall, 4th lift done in presence of Client & PSS Team.
57/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of RHS D/S Divide wall, 4th lift is under progress in presence of Client & PSS Team.
58/100
Instream Storage Structure, Hamirpur
Testing of Compressive M15A40 (Strength is 20.23/mm2 for 28 days) of Flared out wall Raft PCC and (Strength is 20.89/mm2 for 28 days) of Flank wall Cut-off PCC has done in presence of Client & PSS team.
59/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-40 done in presence of Client & PSS Team.
60/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-40 is under progress in presence of Client & PSS Team.
61/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.04/mm2 for 07 days) of Pier No-3, 11th lift and (Strength is 21.63/mm2 for 07 days) of Pier No-5, 4th lift and M35A20 (Strength is 37.63/mm2 for 07 days) of Deck slab (Bay No-10 &11) and M30A20 (Strength is 37.78/mm2 for 28 days) of Groove 2nd stage, 9th and 1st lift (Bay No-26 & 28) has done in presence of Client & PSS team.
62/100
Instream Storage Structure, Hamirpur
Barrage bay Gate No-25 lifting trial operation work is in progress.
63/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
64/100
Instream Storage Structure, Hamirpur
Gantry girder's 1st stage embedded plate fixing and welding work is in progress.
65/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall Raft at Block No-1 is under progress.
66/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-4 & 5, 5th lift is under progress.
67/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-1, 14th lift is under progress.
68/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-3, 13th lift is under progress.
69/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Abutment (A1), 12th lift at Block No-1 is under progress.
70/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Flank wall, 4th lift at Block No-1 is under progress.
71/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M25A20 (Value 85 mm) of LHS Divide wall, 1st lift done in presence of Client & PSS Team.
72/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of LHS Divide wall, 1st lift is under progress in presence of Client & PSS Team.
73/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 90 mm) of Pier No-16 (Starter) done in presence of Client & PSS Team.
74/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-16 (Starter) is under progress in presence of Client & PSS Team.
75/100
Instream Storage Structure, Khalpal
Shuttering of RHS Double Pier No-25, 3rd lift is under progress.
76/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
77/100
UGPL, Right Lower Suktel Canal Division
OCS chamber above GL work is in progress of OCS No:- 0213055-C11A at village Bubel in presence of CME (PSS) PMC along with team and L&T offical.
78/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for RHS D/S Counerfort & Abutment wall, 4th lift is under progress.
79/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-3, 12th lift done in presence of Client & PSS Team.
80/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-3, 12th lift is under progress in presence of Client & PSS Team.
81/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.04/mm2 for 07 days) of Pier No-3, 11th lift and (Strength is 21.63/mm2 for 07 days) of Pier No-5, 4th lift and M35A20 (Strength is 37.63/mm2 for 07 days) of Deck slab (Bay No-10 &11) and M30A20 (Strength is 37.78/mm2 for 28 days) of Groove 2nd stage, 9th and 1st lift (Bay No-26 & 28) has done in presence of Client & PSS team.
82/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-4 & 5, 6th lift is under progress.
83/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-1, 13th lift is under progress.
84/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-3, 12th lift is under progress.
85/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for D/S Abutment (A1), 9th lift at Block No-1 is under progress.
86/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for U/S Flank wall, 4th lift at Block No-1 is under progress.
87/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 85 mm) of Barrage Bay No-2 Gravity floor done in presence of Client & PSS Team.
88/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Barrage Bay No-2 Gravity floor is under progress in presence of Client & PSS Team.
89/100
Instream Storage Structure, Khalpal
Shuttering of RHS Double Pier No-25, 3rd lift is under progress.
90/100
Instream Storage Structure, Khalpal
Shuttering of LHS D/S Divide wall, 2nd lift is under progress.
91/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
92/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-1, 13th lift done in presence of Client & PSS Team.
93/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-1, 13th lift is under progress in presence of Client & PSS Team.
94/100
Instream Storage Structure, Hamirpur
Barrage Bay Gate installation and hoist Bridge platform installation work in presence of Client & PSS team.
95/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.78/mm2 for 07 days) of Pier No-4, 4th lift and (Strength is 31.04/mm2 for 28 days) of U/S Flared out wall Raft at Block No-1 and (Strength is 21.48/mm2 for 07 days) of U/S Abutment (A1) and M30A20 (Strength is 37.93/mm2 for 28 days) of Groove 2nd stage, 5th lift (Bay No-9) has done in presence of Client & PSS team.
96/100
Instream Storage Structure, Hamirpur
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
97/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-3, 12th lift is under progress.
98/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
99/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-2, 13th lift is under progress.
100/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Abutment (A1), 11th lift at Block No-1 is under progress.