PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.89/mm2 for 28 days) of D/S Flank wall, 7th lift at Block No-5 and M35A20 (Strength is 37.63/mm2 for 07 days) of Deck slab (Bay No-18) has done in presence of Client & PSS team.
2/100
Instream Storage Structure, Hamirpur
Visited by S.E, RID, A.E.E, A.E RID of Client & PSS team along with representative of EPC agency at site.
3/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Slab hand railing at Block No-4 done in presence of Client & PSS Team.
4/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Slab hand railing at Block No-4 is under progress in presence of Client & PSS Team.
5/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.620m.
6/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
7/100
Instream Storage Structure, Khalpal
Inspection by Dy. TL, Site Engineer Of PSS team along with EPC agency at site.
8/100
Instream Storage Structure, Near Village Basantpur across River Daya
CE, MKS, SE, Prachi division with departmental engineers along with PSS team visited the ISS work Site.
9/100
Instream Storage Structure, Kuakhai
CE ,MKS, SE,Prachi division with departmental engineers along with PSS team visited the work Site .
10/100
Instream Storage Structure, Kuakhai
Water level RL 12.9m.
11/100
Instream Storage Structure, Kuakhai
Water level RL 13.6m.
12/100
Instream Storage Structure, Kuakhai
Water level RL 14.25m.
13/100
Instream Storage Structure, Kushabhadra
Brick masonry work is under progress in parapet of O&M building.
14/100
Instream Storage Structure, Kushabhadra
Inspection of gate works & other ancillary mechanical works by Hydro-Mechanical Expert with MKS Team & Agency at the worksite.
15/100
Instream Storage Structure, Kushabhadra
O&M Building parapet wall bricks work is under progress.
16/100
Instream Storage Structure, Kushabhadra
Canal road Clearing & grubbing work progress.
17/100
Instream Storage Structure, Kushabhadra
DTL & Team is Discussing with the Agency regarding completion of .head room, constn. of parapet, septic tank & soak pit etc.
18/100
Instream Storage Structure, Kushabhadra
Inspection of O&M building work by MKS Team along with the Agency at the ISS site.
19/100
Instream Storage Structure, Kushabhadra
Cdu motor and gearbox installation work under progress.
20/100
Instream Storage Structure, Kushabhadra
Mechanical work center drive unit, motor, gearbox, ropeway, installation work is in progress.
21/100
Instream Storage Structure, Kushabhadra
Canal road Clearing & grubbing work progress.
22/100
Instream Storage Structure, Kushabhadra
O&M Building ground floor electrical chasing / chipping work inside the building is under progress.
23/100
Instream Storage Structure, Kushabhadra
Curing work going on.
24/100
Instream Storage Structure, Kushabhadra
O&M Building 1st floor brick work is under progress.
25/100
Instream Storage Structure, Kushabhadra
Canal road cleaning work is under progress.
26/100
Instream Storage Structure, Kushabhadra
Inspection of O&M building construction work by DTL & Team.
27/100
Instream Storage Structure, Kushabhadra
O&M Building 1st floor Lintel beam Beam with sunshade shuttering work is under progress.
28/100
Instream Storage Structure, Kushabhadra
Flood water level RL 12.70m.
29/100
Instream Storage Structure, Kushabhadra
Flood water level RL 13.10m.
30/100
Instream Storage Structure, Kushabhadra
O&M Building 1st floor brick work is under progress.
31/100
UGPL, Left Lower Suktel Canal Division
Tree plantation by CCE, SE, Dam division SE, Canal Division No.-I SE, RR division SE, SDO of DoWR, TLs of (PES & PSS) and MEIL Project manager at Left Command Pump House LSIP.
32/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.610m.
33/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.760m.
34/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of D/S Flank wall, 10th lift at Block No-5 done in presence of Client & PSS Team.
35/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flank wall, 10th lift at Block No-5 is under progress in presence of Client & PSS Team.
36/100
Instream Storage Structure, Hamirpur
Rope drum Hoist bottom block bracket welding work is in progress.
37/100
Instream Storage Structure, Hamirpur
Column Trestle No-25 bracing welding work is in progress.
38/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Deck slab (Bay No-18) done in presence of Client & PSS Team.
39/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Deck slab (Bay No-18) is under progress in presence of Client & PSS Team.
40/100
Instream Storage Structure, Hamirpur
Cleaning of reinforcement for Deck slab (Bay No-18) is under progress by Sand blasting method.
41/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.11/mm2 for 28 days) of Hand Rail Beam Bay No-26,27,28 & 29 at Block No-5 and M35A20 (Strength is 42.44/mm2 for 28 days) of Gantry Girder No-59,60,61 & 62 and (Strength is 37.48/mm2 for 07 days) of Gantry Cross Girder has done in presence of Client & PSS team.
42/100
Instream Storage Structure, Hamirpur
Mud cleaning from Watchman Quater footing Area is under progress.
43/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.870m.
44/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
45/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site level RL 56.9m.
46/100
Instream Storage Structure, Khalpal
Slump testing M35A20 (Value 80 mm) of Girder No-63 done in presence of Client & PSS Team.
47/100
Instream Storage Structure, Khalpal
Concreting M35A20 of Girder No-63 is under progress in presence of Client & PSS Team.
48/100
Instream Storage Structure, Khalpal
Shuttering of Girder No-63 is under progress.
49/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
50/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site level RL 56.62m.
51/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
52/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.93/mm2 for 07 days) of Handling No-27 to 29 and M25A20 (Strength is 21.18/mm2 for 07 days) of Railing beam at Block No-5 has done in presence of Client & PSS team.
53/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flank wall, 10th lift at Block No-5 is under progress.
54/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.800m.
55/100
Instream Storage Structure, Khalpal
Slump testing M35A20 (Value 90 mm) of Girder No-62 done in presence of Client & PSS Team.
56/100
Instream Storage Structure, Khalpal
Concreting M35A20 of Girder No-62 is under progress in presence of Client & PSS Team.
57/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
58/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site level RL 56.82m.
59/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 7.40m.
60/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 6.10m.
61/100
Integrated Barrage across river Kochila and across river Baitarini
C.E.,Designs,CE MBBS,Chandikhole,S.E.,AEE,AE of Akhuapada Irrigation Division,PMC team visited Baitarani ISS.
62/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 6.10m
63/100
Integrated Barrage across river Kochila and across river Baitarini
CC Block casting work at Baitarani ISS is in progress.
64/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 6.30m.
65/100
Integrated Barrage across river Kochila and across river Baitarini
CC Block casting work at Baitarani ISS is in progress.
66/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 6.10m.
67/100
Integrated Barrage across river Kochila and across river Baitarini
Girder casting work of Baitarani ISS is in progress.
68/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 6.40m.
69/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 6.40m.
70/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 8.50m.
71/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 10.30m.
72/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 10.30m.
73/100
Integrated Barrage across river Kochila and across river Baitarini
Checking of Reinforcement and shuttering work for pre cast Bridge Girder of Baitarani ISS before its concreting by S.S. & AEE,QAD,Chandikhole AEE Dhamnagar Irr Sub Division and PMC Team
74/100
Integrated Barrage across river Kochila and across river Baitarini
Checking of Reinforcement and shuttering work for pre cast Bridge Girder of Baitarani ISS before its concreting by S.S. & AEE,QAD,Chandikhole AEE Dhamnagar Irr Sub Division and PMC Team
75/100
Integrated Barrage across river Kochila and across river Baitarini
Girder Casting work at Baitarani ISS is in progress.
76/100
Integrated Barrage across river Kochila and across river Baitarini
Girder Shuttering work at Baitarani ISS is in progress.
77/100
Integrated Barrage across river Kochila and across river Baitarini
Baitarani ISS water level is 10.10m
78/100
Integrated Barrage across river Kochila and across river Baitarini
C.C. Block casting work at Baitarani ISS is in progress.
79/100
Instream Storage Structure, Gudvella
• Visited employee and labours of TATA power at ISS Gudvella site To energized / charging of transformer is under progress at site on 09.09.2026
80/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
81/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site level RL 56.82m.
82/100
Instream Storage Structure, Hamirpur
Slump testing M15A40 (Value 45 mm) of U/S (A2) Flared out wall, 14th lift at Block No-5 done in presence of Client & PSS Team.
83/100
Instream Storage Structure, Hamirpur
Concreting M15A40 of U/S (A2) Flared out wall, 14th lift at Block No-5 is under progress in presence of Client & PSS Team.
84/100
Instream Storage Structure, Hamirpur
Column guide line fixing and welding work is in progress.
85/100
Instream Storage Structure, Hamirpur
Bottom block rope pulley bracket welding work is in progress.
86/100
Instream Storage Structure, Hamirpur
Reinforcement binding for Deck slab (Bay No-18) is under progress.
87/100
Instream Storage Structure, Hamirpur
Mud cleaning from Watchman Quater footing Area is under progress.
88/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flank wall, 10th lift at Block No-5 is under progress.
89/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.600m.
90/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 08.09.2026
91/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 08.09.2026
92/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
93/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site level RL 56.747m.
94/100
Instream Storage Structure, Khalpal
Testing of Compressive M35A20 (Strength is 41.64/mm2 for 28 days) of Girder No-57 has done in presence of Client & PSS team.
95/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
96/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site level RL 56.73m.
97/100
Instream Storage Structure, Nandagaon
Curing is in progress at approach slab on 08.09.2026
98/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 42.07/mm2 for 28 days) of Gantry Girder No-58 and M35A20 (Strength is 42.44/mm2 for 28 days) of Fish pass slab at Block No-5 and M15A40 (Strength is 13.33/mm2 for 07 days) of U/S Flared out wall, 13th lift at Block No-5 has done in presence of Client & PSS team.
99/100
Instream Storage Structure, Hamirpur
Rope drum hoist lifting arrangements bottom block rope pulley bracket welding work is in progress.
100/100
Instream Storage Structure, Hamirpur
Mud cleaning from Watchman Quater footing Area is under progress.