GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Gudvella
Color paint work is under progress at front side of building area on 10.08.2026
2/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 10.08.2026
3/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 10.08.2026
4/100
Instream Storage Structure, Gudvella
Putty work at the building area is under progress at site on 09.08.2026
5/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 09.08.2026
6/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 09.08.2026
7/100
Instream Storage Structure, Gudvella
Primer painting is under progress at mechanical yard on 08.08.2026
8/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 08.08.2026
9/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 08.08.2026
10/100
Instream Storage Structure, Nandagaon
Mechanical erection work has been stopped today due to labour issues on 10.08.2026
11/100
Instream Storage Structure, Nandagaon
Fixing of precast railing is in progress at deck slab no. 10 on 10.08.2026
12/100
Instream Storage Structure, Nandagaon
Stone pitching work at U/S right embankment is in progress on 10.08.2026
13/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 19nos. precast railing is in progress in presence of Site Engineer's of PMC & Site Engineer of EPC agency. The slump test value is 86mm on 09.08.2026
14/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 19nos. precast railing is in progress in presence of Site Engineer's of PMC & Site Engineer of EPC agency. The slump test value is 86mm on 09.08.2026
15/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for precast railing is in progress on 09.08.2026
16/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 16nos. post at deck slab no.11 is in progress in presence of Site Engineer's of PMC & Site Engineer of EPC agency. The slump test value is 84mm on 08.08.2026
17/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 16nos. post at deck slab no.11 is in progress in presence of Site Engineer's of PMC & Site Engineer of EPC agency. The slump test value is 84mm on 08.08.2026
18/100
Instream Storage Structure, Nandagaon
Stone pitching work at U/S right embankment in progress on 08.08.2026
19/100
Instream Storage Structure, Nandagaon
Fixing of precast railing is in progress at deck slab no. 11 on 08.08.2026
20/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Present status of river Samakoi at Santeibhanja site.
21/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at Telkoi site.
22/100
Instream Storage Structure, Hamirpur
Column Trestle No-21 bracing welding work is in progress.
23/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 42.15/mm2 for 28 days) of Gantry Girder No-47 and (Strength is 37.93/mm2 for 07 days) of Gantry Girder No-53 and M25A20 (Strength is 31.16/mm2 for 28 days) of Pier No-23, 15th lift and M15A40 (Strength is 20.35/mm2 for 28 days) of Flared out wall, 11th lift has done in presence of Client & PSS team.
24/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Gantry Girder No-57 done in presence of Client & PSS Team.
25/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-57 is under progress in presence of Client & PSS Team.
26/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Flank wall, 13th lift at Block No-5 is under progress.
27/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
28/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall, 7th lift at Block No-5 is under progress.
29/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 180.200m.
30/100
Instream Storage Structure, Khalpal
Slump testing M35A20 (Value 85 mm) of Girder No-57 done in presence of Client & PSS Team.
31/100
Instream Storage Structure, Khalpal
Concreting M35A20 of Girder No-57 is under progress in presence of Client & PSS Team.
32/100
Instream Storage Structure, Khalpal
Testing of Compressive M35A20 (Strength is 29.81/mm2 for 07 days) of Girder No-55 has done in presence of Client & PSS team.
33/100
Instream Storage Structure, Khalpal
Shuttering of Girder No-57 is under progress.
34/100
Instream Storage Structure, Khalpal
Curing of Girder No-55 & 56 is under progress.
35/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 58.238m.
36/100
Instream Storage Structure, Gudvella
Putty work at the building area is under progress at site on 07.08.2026
37/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 07.08.2026
38/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 07.08.2026
39/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 16nos. Precast RCC railing is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 86mm on 07.08.2026
40/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 16nos. Precast RCC railing is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 86mm on 07.08.2026
41/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for precast railing is in progress on 07.08.2026
42/100
Barrage across river Turi & Guntat
Control room slab casting at Turi barrage site is in progress.
43/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of D/S Flank wall, 6th lift at Block No-5 done in presence of Client & PSS Team.
44/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flank wall, 6th lift at Block No-5 is under progress in presence of Client & PSS Team.
45/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 180.900m.
46/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
47/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 58.698m.
48/100
Instream Storage Structure, Khalpal
Curing of Girder No-55 is under progress.
49/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 58.05m.
50/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of U/S Flank wall, 12th lift at Block No-5 done in presence of Client & PSS Team.
51/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of U/S Flank wall, 12th lift at Block No-5 is under progress in presence of Client & PSS Team.
52/100
Instream Storage Structure, Hamirpur
Column Trestle bracing fixing work is in progress.
53/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 41.93/mm2 for 28 days) of Gantry Girder No-46 and (Strength is 37.93/mm2 for 07 days) of Gantry Girder No-52 and M25A20 (Strength is 21.78/mm2 for 28 days) of Flank wall, 5th lift and M30A20 (Strength is 30.07/mm2 for 28 days) of Groove 2nd stage, 5th lift (Bay No-27) has done in presence of Client & PSS team.
54/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-56 done in presence of Client & PSS Team.
55/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-56 is under progress in presence of Client & PSS Team.
56/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
57/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flank wall, 6th lift at Block No-5 is under progress.
58/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 180.440m.
59/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.33/mm2 for 28 days) of Pier No-24, 16th lift and (Strength is 21.48/mm2 for 07 days) of U/S Flank wall, 11th lift at Block No-5 and M15A40 (Strength is 20.39/mm2 for 28 days) of U/S Flared out wall Block No-5 and (Strength is 20.30/mm2 for 28 days) of U/S Flank wall, 11th lift at Block No-5 has done in presence of Client & PSS team.
60/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 179.610m.
61/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
62/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 57.55m.
63/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at D/S Telkoi site.
64/100
Instream Storage Structure across river Sapei near village Kinjirma
Concrete work is in progress of building staff quarter & control room columns above ground floor(M25A20) (c3,c4,c9,c10,c21,c22,c15,c16)
65/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump-85mm(M25A20) building staff quarter & control room columns above ground floor (c3,c4,c9,c10,c21,c22,c15,c16)
66/100
Instream Storage Structure across river Sapei near village Kinjirma
7days cube testing of lintel beam( building staff quarter & control room )
67/100
Instream Storage Structure across river Sapei near village Kinjirma
Concrete work is in progress of building staff quarter & control room columns Above ground floor (c1,c2,c7,c8,c13,c14,c19,c20) (M25A20) .
68/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump-80mm(M25A20), building staff quarter & control room columns(C1,C2,C7,C8,C13,C14,C19,C20) Above ground floor.
69/100
Instream Storage Structure across river Sapei near village Kinjirma
* Flow direction is straight flow is seen at RL- 206.65 against crest level RL- 206.25 . * Water is flowing 0.4m above the crest level .(D/S)
70/100
Instream Storage Structure across river Sapei near village Kinjirma
PMC team visited ISS Kinjirma.Shuttering of Column above lintel beam of QC room cum Staff Qrs is going on.PM of agency is advised to complete GF slab casting by end of this month.
71/100
Instream Storage Structure across river Sapei near village Kinjirma
PMC team visited ISS Kinjirma.Shuttering of Column above lintel beam of QC room cum Staff Qrs is going on.PM of agency is advised to complete GF slab casting by end of this month.
72/100
Instream Storage Structure across river Sapei near village Kinjirma
Flow direction is straight flow is seen at RL- 207.00 against crest level RL- 206.25 . . Water is flowing 0.75m above the crest level .(D/S)
73/100
Instream Storage Structure across river Sapei near village Kinjirma
Flow direction is straight flow is seen at RL- 207.00 against crest level RL- 206.25 . . Water is flowing 0.75m above the crest level .
74/100
Instream Storage Structure across river Sapei near village Kinjirma
* Flow direction is straight flow is seen at RL- 206.65 against crest level RL- 206.25 . * Water is flowing 0.4m above the crest level .(D/S)
75/100
Instream Storage Structure Across Bheden near village Saida
Slump value-65 MM
76/100
Instream Storage Structure Across Bheden near village Saida
checked placing and positioning of steel reinforcement, supporting bars and alignment of shuttering work with minimum cover 25mm . Staff quarter ground floor slab.Now the area is ready for concrete M25 A20. Approved by SE in presence of JE
77/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from U/S of river . Flow direction is straight & flow can seen at RL-216.300 mtr against design crest level RL- 215.000 mtr .i.e 1.3 mtr flood lift .
78/100
Instream Storage Structure Across Bheden near village Saida
Reinforcement work progress in Staff quarter ground floor slab
79/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-215.500 mtr against design crest level RL- 215.000 mtr .i.e 0.5 mtr flood lift .
80/100
Instream Storage Structure Across Bheden near village Saida
Reinforcement work progress in Staff quarter ground floor slab
81/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-215.600 mtr against design crest level RL- 215.000 mtr .i.e 0.6 mtr flood lift .
82/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from U/S of river . Flow direction is straight & flow can seen at RL-215.400 mtr against design crest level RL- 215.000 mtr .i.e 0.4 mtr flood lift .
83/100
Instream Storage Structure Across Bheden near village Saida
Out of the total 8 no's of gates, all 8 no's of gates have been opened.
84/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-215.300 mtr against design crest level RL- 215.000 mtr .i.e 0.3 mtr flood lift .
85/100
Instream Storage Structure Across Bheden near village Saida
Plate marking work is in progress for fixing of lifting bracket stiffener of Stop Log Gates.
86/100
Instream Storage Structure Across Bheden near village Saida
Top Guide stiffener wedding work is in progress.
87/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-215.700 mtr against design crest level RL- 215.000 mtr .i.e 0.7 mtr flood lift .
88/100
Instream Storage Structure, Khirasasan
Staff Quarter Parapet wall brick work is under progress.
89/100
Instream Storage Structure, Khirasasan
Flow direction is straight flow is seen at RL- 212.300 against crest level RL- 210.900 Water is flowing 1.4 m above the crest level
90/100
Instream Storage Structure, Khirasasan
View showing flow of river from u/s to d/s of river.
91/100
Instream Storage Structure, Khirasasan
Staff Quarter Parapet wall brick work is under progress.
92/100
Instream Storage Structure, Khirasasan
Flow direction is straight flow is seen at RL- 211.500 against crest level RL- 210.900. Water is flowing 0.6 m above the crest level
93/100
Instream Storage Structure, Khirasasan
View showing flow of river from u/s to d/s of river.
94/100
Instream Storage Structure, Khirasasan
View showing flow of river from u/s to d/s of river.
95/100
Instream Storage Structure, Khirasasan
Flow direction is straight flow is seen at RL- 212.000 against crest level RL- 210.900 Water is flowing 1.1m above the crest level
96/100
Instream Storage Structure, Khirasasan
View showing flow of river d/s of river.
97/100
Instream Storage Structure, Khirasasan
Flow direction is straight flow is seen at RL- 211.300 against crest level RL- 210.900 Water is flowing 0.4m above the crest level .
98/100
Instream Storage Structure, Khirasasan
View showing flow of river from u/s to d/s of river.
99/100
Instream Storage Structure, Khirasasan
View showing flow of river from u/s to d/s of river.
100/100
Instream Storage Structure, Khirasasan
All gate are opened