1/100
Instream Storage Structure, Hamirpur
Curing of Flank wall at Block No-1 is under progress.
2/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.08/mm2 for 28 days) of Pier No-6, 14th lift and (Strength is 30.87/mm2 for 28 days) of Pier No-26, 13th lift and M35A20 (Strength is 37.63/mm2 for 07 days) of Gantry Girder No-38 has done in presence of Client & PSS team.
3/100
Instream Storage Structure, Hamirpur
Column base plate with stiffener welding work is in progress at (Bay No-25).
4/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-3, 12th lift is under progress.
5/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-1, 14th lift is under progress.
6/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-2, 12th lift is under progress.
7/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for D/S Abutment (A1), 11th lift at Block No-1 is under progress.
8/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4, 5th lift is under progress.
9/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 80 mm) of RHS Double pier, 3rd lift done in presence of Client & PSS Team.
10/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of RHS Double pier, 3rd lift is under progress in presence of Client & PSS Team.
11/100
Instream Storage Structure, Jharbeda
Testing of Compressive M25A20 (Strength is 21.92/mm2 for 07 days) of Pier No-7, Pier Cap has done in presence of Client & PSS team.
12/100
Instream Storage Structure, Khalpal
Joint verification for tree enumeration & valuation conducted by Forest Department, Revenue Department, and Horticulture Department as well as DoWR Department.
13/100
Instream Storage Structure, Khalpal
Testing of Compressive M25A20 (Strength is 34.14/mm2 for 28 days) of Barrage Bay No-2 Raft and (Strength is 33.83/mm2 for 28 days) of LHS U/S Divide wall, 2nd lift has done in presence of Client & PSS team.
14/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
15/100
Barrage across river Turi & Guntat
Construction of Control room at Turi site is in progress.
16/100
Barrage across river Turi & Guntat
Mechanical works in progress at Turi guntat Barrage.
17/100
Instream Storage Structure, Gudvella
The launching of one part of the Stoplog Gate is currently in progress on 24.06.2026
18/100
Instream Storage Structure, Gudvella
Plastering work is in progress at 1st floor building on 24.06.2026
19/100
Instream Storage Structure, Gudvella
Covering work of roller drum is under progress at mechanical site on 24.06.2026
20/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 24.06.2026
21/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 24.06.2026
22/100
Instream Storage Structure, Nandagaon
River flood water reached at site, U/S view on 24.06.2026
23/100
Instream Storage Structure, Nandagaon
River flood water reached at site, U/S view on 24.06.2026
24/100
Instream Storage Structure, Nandagaon
The erection work and painting work has been stopped at the site today due to labour issues on 24.06.2026
25/100
Instream Storage Structure, Nandagaon
The erection work and painting work has been stopped at the site today due to labour issues on 24.06.2026
26/100
Instream Storage Structure, Nandagaon
Reinforcement binding & shuttering is in progress at D/S right flank wall on 24.06.2026
27/100
UGPL, Right Lower Suktel Canal Division
OCS chamber Below NGL installation work is in progress of OCS No. 0213119-C19A at village RakshiMunda in presence of DoWR SE, SDO, JE and PMC team.
28/100
UGPL, Right Lower Suktel Canal Division
Approach channel bed level cleaning work is in progress at Pump House in presence of PMC team.
29/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door and angle fixing work is in progress OCS No-: 2305216- C01B at village Adakata in presence of PMC team.
30/100
UGPL, Right Lower Suktel Canal Division
Internal drain bottom portion grading work is in progress at Pump House in presence of PMC team.
31/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress of Dia 160mm HDPE pipeline between J-338 to LO-131, LM-6 near village Bianrpali in presence of PMC team.
32/100
UGPL, Left Lower Suktel Canal Division
DI to HDPE connection work is in progress at Rm-4 J-358, near village Khaliapali.
33/100
Instream Storage Structure, KansariGanda
Visit of Irrigation eng. expert along with Site engineer PMC to the ISS site. Inspected the Wearing Coat to Zone No 6 to 3 of Barrage Bay No 3 with PCC and Cube test conducted at site.
34/100
Instream Storage Structure, KansariGanda
Visit of Irrigation eng. expert along with Site engineer PMC to the ISS site. Inspected the Wearing Coat to Zone No 6 to 3 of Barrage Bay No 3 with PCC and Cube test conducted at site.
35/100
Instream Storage Structure, KansariGanda
Visit of Irrigation eng. expert along with Site engineer PMC to the ISS site. Inspected the Wearing Coat to Zone No 6 to 3 of Barrage Bay No 3 with PCC and Cube test conducted at site.
36/100
UGPL, Right Lower Suktel Canal Division
Joint verification work is in progress of OCS no-0201219-C-05A at village Kutumdola in presence of DoWR SE, SDO, JE, PMC team and EPC officials.
37/100
Instream Storage Structure, Jharbeda
Slump testing M25A20 (Value 85 mm) of RHS (D2) Middle pier portion, 2nd lift done in presence of Client & PSS Team.
38/100
Instream Storage Structure, Jharbeda
Concreting M25A20 of RHS (D2) Middle pier portion, 2nd lift is under progress in presence of Client & PSS Team.
39/100
Instream Storage Structure, Jharbeda
Shuttering of RHS U/S Training wall, 2nd lift is under progress.
40/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-7, pier Cap is under progress.
41/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.48/mm2 for 07 days) of Abutment (A1), 10th lift and (Strength is 21.63/mm2 for 07 days) of Pier No-1, 11th lift and M15A40 (Strength is 13.33/mm2 for 07 days) of D/S Flank Cut-off wall at Block No-1 (PCC) has done in presence of Client & PSS team.
42/100
Instream Storage Structure, Gudvella
Installation of dial indicator is under progress at mechanical site on 23.06.2026
43/100
Instream Storage Structure, Hamirpur
Wire ropes fixing work is in progress of hoist bridge platform.
44/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-3, 11th lift is under progress.
45/100
Instream Storage Structure, Gudvella
Installation work of door at 1st floor building is under progress at site on 23.06.2026
46/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-2, 11th lift is under progress.
47/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Abutment (A1), 11th lift at Block No-1 is under progress.
48/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-1, 12th lift is under progress.
49/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 23.06.2026
50/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of Pier No-14 (Starter) done in presence of Client & PSS Team.
51/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-14 (Starter) is under progress in presence of Client & PSS Team.
52/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
53/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 23.06.2026
54/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at right abutment for 11th lift is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 85mm on 23.06.2026
55/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at right abutment for 11th lift is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 85mm on 23.06.2026
56/100
Instream Storage Structure, Nandagaon
Reinforcement binding for basement slab of office building is in progress on 23.06.2026
57/100
Instream Storage Structure, KansariGanda
Curing continuing at site.
58/100
Instream Storage Structure, KansariGanda
Curing continuing at site.
59/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering is in progress at D/S right flank wall on 23.06.2026
60/100
Instream Storage Structure, Nandagaon
• 1. Fixing & fittings and alignment of 2nd. stage embedded parts and numbers of dowel bars provided as per approved drawing at roller tracks of both stop log & service gate grooves at bay no.14 of right abutment for 11th lift have been checked and found correct by HM Expert of PMC during his site visit on dt.01.06.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i) Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for M35A20 grade on 23.06.2026
61/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site.
62/100
Instream Storage Structure, Nandagaon
De-Shuttering & Shuttering for 2nd stage concrete is in progress at right abutment on 23.06.2026
63/100
Instream Storage Structure, KansariGanda
Visit of QA/QC Expert PMU, DyTL, QA/QC expert, Irr. Eng. expert along with Site engineer PMC and Dept. officials to the ISS site. Inspected the overal progress of site.
64/100
Instream Storage Structure, KansariGanda
Visit of QA/QC Expert PMU, DyTL, QA/QC expert, Irr. Eng. expert along with Site engineer PMC and Dept. officials to the ISS site. Inspected the overal progress of site.
65/100
Instream Storage Structure, KansariGanda
Visit of QA/QC Expert PMU, DyTL, QA/QC expert, Irr. Eng. expert along with Site engineer PMC and Dept. officials to the ISS site. Inspected the overal progress of site.
66/100
Instream Storage Structure, KansariGanda
Visit of QA/QC Expert PMU, DyTL, QA/QC expert, Irr. Eng. expert along with Site engineer PMC and Dept. officials to the ISS site. Inspected the overal progress of site.
67/100
Instream Storage Structure, KansariGanda
Slump check done at site in presence of Irrigation expert along with Site engineer PMC.
68/100
Instream Storage Structure, KansariGanda
Pile no-AB 199 Depth checked
69/100
Instream Storage Structure, KansariGanda
Right Side Zone 4 & 5 Gravity Floor in between Barrage Bay No 8 & 9 Concreting
70/100
Instream Storage Structure, KansariGanda
Slump cone test conducted in progress.
71/100
Instream Storage Structure, KansariGanda
Curing continue
72/100
Instream Storage Structure, KansariGanda
Right side pier no-8 concrete casting
73/100
Instream Storage Structure, KansariGanda
cage lowering in progress
74/100
Instream Storage Structure, KansariGanda
Curing continue
75/100
Instream Storage Structure, KansariGanda
Curing continue
76/100
Instream Storage Structure, KansariGanda
LHS Sluice first beam placement in progress
77/100
Instream Storage Structure, KansariGanda
Fw pile no 233 pile concrete complete
78/100
Instream Storage Structure, KansariGanda
Cube test done at site
79/100
Instream Storage Structure, KansariGanda
Slump cone test conducted in progress.
80/100
Instream Storage Structure, KansariGanda
LHS barrage bay 2 1st girder lifting
81/100
UGPL, Right Lower Suktel Canal Division
Excavation for 1HA outlet subchak installation work is in progress of OCS no-0201228-C04A at village Sialbahali ,in presence of DoWR SDO, JE, PMC team and L&T official.
82/100
UGPL, Right Lower Suktel Canal Division
OCS chamber above GL work is in progress of OCS No:- 0213119-C22A at village Belisarda in presence of DoWR SDO, AE, PMC team and L&T offical.
83/100
UGPL, Right Lower Suktel Canal Division
Joint verification is conducted of OCS no-0213134-C07A at village Sikabhenga in presence of DoWR SDO, PMC team and EPC officials.
84/100
UGPL, Right Lower Suktel Canal Division
Joint reverification is conducted of OCS No-0201219-C01A & relocation to highest points of one hectare outlet near Kutumdola.
85/100
UGPL, Right Lower Suktel Canal Division
Approach channel bed level cleaning work is in progress near silt trap at Pump House.
86/100
UGPL, Right Lower Suktel Canal Division
OCS chamber above GL work is in progress of OCS No:- 2305095 - C07A at village Tilesara in presence of PMC team.
87/100
UGPL, Right Lower Suktel Canal Division
Joint reverification is conducted of OCS No-0201219-C03B of one hectare outlet near village Kutumdola in presence of DoWR SDO, PMC team and EPC staff.
88/100
UGPL, Right Lower Suktel Canal Division
PLC room roof water proofing treatment hunch portion plastering work is in progress at Pump House.
89/100
UGPL, Left Lower Suktel Canal Division
Excavation for laying of 140mm dia HDPE pipe is in progress from J-279 to LO-183 near Khairpali in presence of PMC team.
90/100
UGPL, Left Lower Suktel Canal Division
Butt fusion jointing work is in progress for 140mm dia HDPE pipe from J-279 to LO-183 near Khairpali in presence of PMC team.
91/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE to HDPE pipe connection at J-166, RM-3 near Ramsingha in presence of PMC team.
92/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI to DI pipe (800mm to 450mm Dia) connection at J-253 near Birkel in presence of PMC team.
93/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE Tee (225x160x140)mm connection at J-166 near Ramsingha in presence of PMC team.
94/100
Instream Storage Structure, Gudvella
• Today the HM Expert and SH Expert visited ISS Gudvella. During their visit the Department JE, PMC Site Engineers and Agency Engineers were present.
1. The HM Expert reviewed all mechanical works and instructed the agency to start the erection of the Stoplog Gate at the earliest without any delay & to complete all remaining finishing works promptly.
2. It was observed that the dry test can only be conducted after completion of all erection works and after providing electrical connectivity through the DG Set & Transformer. Until then the dry test cannot be carried out on 22.06.2026
95/100
Instream Storage Structure, Gudvella
• Today the HM Expert and SH Expert visited ISS Gudvella. During their visit the Department JE, PMC Site Engineers and Agency Engineers were present.
1. The HM Expert reviewed all mechanical works and instructed the agency to start the erection of the Stoplog Gate at the earliest without any delay & to complete all remaining finishing works promptly.
2. It was observed that the dry test can only be conducted after completion of all erection works and after providing electrical connectivity through the DG Set & Transformer. Until then the dry test cannot be carried out on 22.06.2026
96/100
Instream Storage Structure, Gudvella
Installation of dial indicator is under progress at mechanical site on 22.06.2026
97/100
Instream Storage Structure, Gudvella
Plastering work at building area is under progress at site on 22.06.2026
98/100
Instream Storage Structure, Gudvella
Mechanical work is under progress at site on 22.06.2026
99/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 22.06.2026
100/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 22.06.2026
❮
❯