GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
UGPL, Right Lower Suktel Canal Division
A video conference meeting was held under the chairmanship of PMU TL in the office chamber of the CCE regarding the progress and balance work of Pump House, Pipe laying, all valves fitting of pipe line network, OCS instrumentation installation, chamber erection, outlet fixing, kilometre marking, Scada system and formation of Pani panchayat in presence of SE, SDO and other departmental of DoWR, TL (PES & PSS), ARE of PSS, PMC team along with representative of Agency.
2/100
UGPL, Left Lower Suktel Canal Division
A video conference meeting was held under the chairmanship of PMU TL in the office chamber of the CCE regarding the progress and balance work of Pump House, Pipe laying, all valves fitting of pipe line network, OMS instrumentation installation, chamber erection, outlet fixing, kilometre marking, Scada system and formation of Pani panchayat in presence of SE, SDO and other departmental of DoWR,TL (PES & PSS), ARE of PSS, PMC team along with representative of Agency.
3/100
Instream Storage Structure, Gudvella
Joint verification for a new electrical connection at ISS Gudvella was conducted with the Electrical JE , Electrical SDO, EE (Management), Network Planning Engineer and the Connection Management Group of the Electrical Department, Tata Power, Balangir. The agency representative and the PMC site engineer were also present during the verification on 26.05.2026
4/100
Instream Storage Structure, Gudvella
Joint verification for a new electrical connection at ISS Gudvella was conducted with the Electrical JE , Electrical SDO, EE (Management), Network Planning Engineer and the Connection Management Group of the Electrical Department, Tata Power, Balangir. The agency representative and the PMC site engineer were also present during the verification on 26.05.2026
5/100
Instream Storage Structure, Gudvella
Stone packing under progress at d/s side of ISS Gudvella on 26.05.2026
6/100
Instream Storage Structure, Gudvella
Mechanical work is under progress at site on 26.05.2026
7/100
Instream Storage Structure, Gudvella
Rolling work for the approach road is in progress on the left side on 26.05.2026
8/100
Instream Storage Structure, Gudvella
Piping work for building electrification is in progress on 26.05.2026
9/100
Instream Storage Structure, Nandagaon
2. Brick work in CM 1:6 using well burnt CB Bricks for construction of walls in superstructure at Office Building of ISS, Nandagaon is in progress . The water used in mortar is found cleaned and free from silt, visible materials and within the permissible temperatures during mixing manually at sire. The area may be passed by SE, KID, Bhawnipatna on 26.05.2026
10/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.10,11&12 is completed in presence of PM EPC agency, Site Engineer of PMC & EPC agency on 26.05.2026
11/100
Instream Storage Structure, Nandagaon
• 1.Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay No.- of Pier No.10,11&12have been checked and found correct by HM Expert of PMC during his site visit on dt.20.05.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs. (i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows: (ii) Chipping of old vertical concrete surface is done. (iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 26.05.2026
12/100
Instream Storage Structure, Nandagaon
Hoist bridge sand blasting under progress on 26.05.2026
13/100
Instream Storage Structure, Nandagaon
Placing of CC blocks is in progress at U/S side on 26.05.2026
14/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress at pier no.14 on 26.05.2026
15/100
Instream Storage Structure, Nandagaon
Curing work is in progress on 26.05.2026
16/100
Instream Storage Structure, Nandagaon
Sand blasting of hoist bridge under progress on 26.05.2026
17/100
Instream Storage Structure, Nandagaon
Undersluice and barrage bay gate roller and guide shoe fixing and fitting under progress on 26.05.2026
18/100
Instream Storage Structure, Nandagaon
Latching arrangement on hoist bridge under progress on 26.05.2026
19/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for laying of 450mm Dia DI pipe line from node J-366 to J-212, LM-17 near village Birkel in presence of PMC team.
20/100
UGPL, Right Lower Suktel Canal Division
500mm Dia DI pipe AMS 223 installation work is in progress from J-2510 to J-2512 at village Dhubaudar in presence of DOWR AE, JE and PMC team.
21/100
UGPL, Right Lower Suktel Canal Division
External drain stone pitching work is in progress at Pump House.
22/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for laying of DN 75 mm Dia HDPE pipe of OCS No. 0213080-C19A for 1 Ha Sub-Chak at village Gaintala in presence of PMC team.
23/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI to HDPE pipe connection at J-127, RM-3 near village Kushmel in presence of PMC team.
24/100
UGPL, Left Lower Suktel Canal Division
HDD machine road pushing work is in progress (road crossing) of 125mm Dia HDPE pipe between J-436 to LO-236 LM-12 near village Pandarani in presence of PMC team.
25/100
UGPL, Left Lower Suktel Canal Division
125mm Dia HDPE pipe butt fusion jointing work is in progress of node from J-436 to LO-236, LM-12 at village Pandarani in presence of PMC team.
26/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for laying of DN 75 mm Dia HDPE pipe for 1 Ha Sub-Chak of OCS No. 0213126-C01A at village Junapadar in presence of DoWR JE and PMC team.
27/100
UGPL, Right Lower Suktel Canal Division
75mm Dia HDPE Pipe jointing work is in Progress of OCS no-0213119-C01B at village Bileisarda in presence of PMC team.
28/100
Instream Storage Structure, Gudvella
Stone packing work on river bed is in progress at d/s side on 25.05.2026
29/100
Instream Storage Structure, Gudvella
Fixing of posts at walk way is under progress at site on 25.05.2026
30/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 25.05.2026
31/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 25.05.2026
32/100
Instream Storage Structure, Gudvella
Stone dumping is currently in progress at the downstream site on 24.05.2026
33/100
Instream Storage Structure, Gudvella
Mechanical work is under progress at site on 24.05.2026
34/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 24.05.2026
35/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 24.05.2026
36/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no.12 upto RL-247.0m is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 85mm on 25.05.2026
37/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no.12 upto RL-247.0m is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 85mm on 25.05.2026
38/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade of 8nos. Columns of building is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 82mm on 25.05.2026
39/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade of 8nos. Columns of building is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 82mm on 25.05.2026
40/100
Instream Storage Structure, Nandagaon
• 2(i).Fixing & fittings and alignment of All trestle and columns foundation bolts measurements has been checked at pier no.12 for Blockout area of 6.8m length and found correct by HM Expert of PMC during his site visit on dt.20.05.2026 in presence of mechanical Site Engineers of PMC and EPC Agency. (ii) Rigid and smooth shuttering for Blockout area with M35A20 grade at pier no.12 from RL-246.30m to RL-247.00m are found completed. (iii).The area is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with M35A20 grade on 25.05.2026
41/100
Instream Storage Structure, Nandagaon
• 1.The area of placing concrete of 8nos. column of Office building have been checked before placement in presence of PM of EPC Agency, Site Engineers of PMC & EPC Agency as follows: (i).The reinforcement in binding,placing and tying with 4-legged stirrups of 8nos. column,i.e. No.1,2,5,9,13,14,15 & 16 are found completed (ii).Rigid & smooth shuttering and maintained clear cover of 40mm from main bar to shutter plates for column are done. (iii).The area is cleaned and passed by SE, KID, Bhawanipatna for placing with RCC M25A20 grade on 25.05.2026
42/100
Instream Storage Structure, Nandagaon
Hoist bridge plate painting work under progress on 25.05.2026
43/100
Instream Storage Structure, Nandagaon
Monorail walkway and monorail girder painting work under progress on 25.05.2026
44/100
Instream Storage Structure, Nandagaon
Pier 1 to pier 8 all trestle and columns proper alignment and erection work completed on 25.05.2026
45/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.9,10 & 11 is completed on 24.05.2026
46/100
Instream Storage Structure, Gudvella
Stone pitching work is under progress at d/s side of ISS Gudvella on 23.05.2026
47/100
Instream Storage Structure, Gudvella
Mechanical work is under progress at site on 23.05.2026
48/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 23.05.2026
49/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 23.05.2026
50/100
Instream Storage Structure, Gudvella
• Electrical conduits for building electrification have arrived at the site. Plumbing materials will arrive in the first half of tomorrow on 22.05.2026
51/100
Instream Storage Structure, Gudvella
• Electrical conduits for building electrification have arrived at the site. Plumbing materials will arrive in the first half of tomorrow on 22.05.2026
52/100
Instream Storage Structure, Gudvella
Only primer work has been started for doors, grills etc on 22.05.2026
53/100
Instream Storage Structure, Gudvella
Mechanical work is under progress at site on 22.05.2026
54/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 22.05.2026
55/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 22.05.2026
56/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.11 & 12 is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency on 23.05.2026
57/100
Instream Storage Structure, Nandagaon
Conducted slump test for casting with M35A20 grade of 2nd stage concrete at pier no.11 & 12 in presence of PM EPC agency Site Engineer of PMC & EPC agency and found value is 86mm at placing site on 23.05.2026
58/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no. 9,10,11&12 of bay-10 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency on 22.05.2026
59/100
Instream Storage Structure, Nandagaon
• Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay No.- of Pier No.9,10,11&12have been checked and found correct by HM Expert of PMC during his site visit on dt.20.05.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs. (i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows: (ii) Chipping of old vertical concrete surface is done. (iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 22.05.2026
60/100
Instream Storage Structure, Nandagaon
Hoist bridge sand blasting work under progress on 22.05.2026
61/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 42.25/mm2 for 28 days) of Deck Slab (Bay No-16), M35A20 (Strength is 41.93/mm2 for 28 days) Gantry Girder No-27, M15A40 (Strength is 13.48/mm2 for 07 days) of Flared out Wall Raft PCC and M30A20 (Strength is 28.59/mm2 for 7 days) of Groove 2nd stage, 4th & 2nd lift (Bay No-26 & 9) has done in presence of Client & PSS team.
62/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of U/S Flared out wall Raft (Bank Side) at Block No-1 done in presence of Client & PSS Team.
63/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of U/S Flared out wall Raft (Bank Side) at Block No-1 is under progress in presence of Client & PSS Team.
64/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
65/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Abutment wall (A1), 6th lift at Block No-1 is under progress.
66/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4, 4th lift is under progress.
67/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of Double Pier No-25, 3rd lift done in presence of Client & PSS Team.
68/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Double Pier No-25, 3rd lift is under progress in presence of Client & PSS Team.
69/100
Instream Storage Structure, Khalpal
Shuttering & Binding reinforcement for LHS U/S Divide wall, 2nd lift is under progress.
70/100
Instream Storage Structure, Khalpal
Binding of reinforcement for Pier No-23, 2nd lift is under progress.
71/100
Instream Storage Structure, Khalpal
Curing of Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
72/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of RHS U/S Divide wall D2, levelling coarse is under progress in presence of Client & PSS Team.
73/100
Instream Storage Structure, Jharbeda
Drilling work for anchoring at RHS U/S Divide wall is under progress.
74/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-7, 8th lift is under progress
75/100
Instream Storage Structure, Jharbeda
Curing of RHS D/S Training wall is under progress.
76/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering & Binding of reinforcement for RHS D/S Divide wall, 2nd lift is under progress.
77/100
UGPL, Right Lower Suktel Canal Division
OCS chamber Below NGL footing levelling work is in progress of OCS No. 0213119-C08A at village Belisarda in presence of DoWR AE, JE and PMC team.
78/100
UGPL, Right Lower Suktel Canal Division
Valve Chamber Pre-cast cover slab reinforcement binding work is in progress of Pump House in presence of PMC team.
79/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door and angle fixing work is in progress OCS No-: 0213055-C17A at village Bubel in presence of DoWR SDO, AE & JE and PMC team.
80/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for connection of Air valve Tee of 180mm Dia HDPE pipe at Village Gaintala in between junction J-3172 to J-3196 in presence of AE DoWR, PMC team and L&T Offical,
81/100
UGPL, Left Lower Suktel Canal Division
HDD machine road pushing work is in progress (road crossing) of 125mm Dia HDPE pipe between J-436 to LO-236 LM-12 near village Pandarani in presence of PMC team.
82/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for sluice valve installation at 450mm Dia DI pipeline between J-254 to J-459, LM-18 near village Birkel in presence of PMC team.
83/100
Instream Storage Structure, Jharbeda
Slump testing M25A20 (Value 85 mm) of RHS Abutment wall A2, 2nd lift done in presence of Client & PSS Team.
84/100
Instream Storage Structure, Jharbeda
Concreting M25A20 of RHS Abutment wall A2, 2nd lift is under progress in presence of Client & PSS Team.
85/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-7, 8th lift is under progress.
86/100
Instream Storage Structure, Jharbeda
Shuttering of RHS D/S training wall, 2nd lift is under progress.
87/100
Instream Storage Structure, Jharbeda
Cleaning of U/S RHS Divide wall D2 is under progress.
88/100
Instream Storage Structure, Khalpal
Shuttering & Binding reinforcement for Pier No-23, 2nd lift is under progress.
89/100
Instream Storage Structure, Khalpal
Curing of Piers is in progress.
90/100
Instream Storage Structure, Khalpal
Curing of Raft is in progress.
91/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.84/mm2 for 28 days) of Flared out wall Raft, M35A20 (Strength is 37.63/mm2 for 7 days) Deck Slab Bay No-19 M30A20 (Strength is 28.89/mm2 for 7 days) of Groove 2nd stage (Bay No-26) has done in presence of Client & PSS team.
92/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-3, 8th lift done in presence of Client & PSS Team.
93/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-3, 8th lift is under progress in presence of Client & PSS Team
94/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flared out Raft at Block No-1 is under progress.
95/100
Instream Storage Structure, Hamirpur
Shuttering of Abutment Wall A1, 9th lift at Block No-1 is under progress.
96/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-4, 8th lift at Block No-1 is under progress.
97/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 80 mm) of RHS D/S Counterfort & Wing wall Raft done in presence of Client & PSS Team.
98/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of RHS D/S Counterfort & Wing wall Raft is under progress in presence of Client & PSS Team.
99/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.84/mm2 for 28 days) of Pier No-1, 6th lift has done in presence of Client & PSS team.
100/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-1, 8th lift done in presence of Client & PSS Team.

Enter Login Details

Forgot Password ?