Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 04.09.2026
2/100
Instream Storage Structure, Gudvella
• Today Irrigation Engineer Expert visited the site. Site in-charge of the agency and site engineer, PMC are present.
Observations:-
The rubber seal installation works are yet to be completed in 2 Nos. out of the total 10 Nos. Further, the power transformer has not yet been charged/energized. It is charged from DG set.
The agency shall accord priority to completion of the balance rubber seal installation works and charging/energization of the transformer from TATA Power ,so as to facilitate commencement of the wet test at the earliest and avoid further delay in the testing on 03.09.2026
3/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 03.09.2026
4/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 03.09.2026
5/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 02.09.2026
6/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 02.09.2026
7/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade at left side approach slab is in progress in presence of PM EPC agency,Site Engineers of PMC. The slump test value is 85mm on 04.09.2026
8/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade at left side approach slab is in progress in presence of PM EPC agency,Site Engineers of PMC. The slump test value is 85mm on 04.09.2026
9/100
Instream Storage Structure, Nandagaon
Laying & placing and binding & tying of bottom main & distribution bars of left side approach slab is in progress on 04.09.2026
10/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of 8nos. post at right side approach slab is in progress in presence of PM EPC agency, Site Engineers of PMC. The slump test value is 84mm on 03.09.2026
11/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of 8nos. post at right side approach slab is in progress in presence of PM EPC agency, Site Engineers of PMC. The slump test value is 84mm on 03.09.2026
12/100
Instream Storage Structure, Nandagaon
Fixing of precast railing is in progress at right side approach slab on 03.09.2026
13/100
Instream Storage Structure, Nandagaon
Curing is in progress at office building on 03.09.2026
14/100
Instream Storage Structure, Nandagaon
Right approach M35 A20 grand concrete work of deck slab completed only left approach bridge slab balance and control room building complete up to basement slab on 02.09.2026
15/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of kerb at right side approach slab is in progress in presence of PM EPC agency, Site Engineers of PMC. The slump test value is 83mm on 02.09.2026
16/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of kerb at right side approach slab is in progress in presence of PM EPC agency, Site Engineers of PMC. The slump test value is 83mm on 02.09.2026
17/100
Instream Storage Structure, Nandagaon
Shuttering for kerb at right side approach slab is in progress on 02.09.2026
18/100
Instream Storage Structure, Nandagaon
Curing is in progress at office building on 02.09.2026
19/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Gantry Cross Girder (Bay No-26 & 27) done in presence of Client & PSS Team.
20/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Cross Girder (Bay No-26 & 27) is under progress in presence of Client & PSS Team.
21/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flank wall, 8th lift at Block No-5 is under progress.
22/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 180.520m.
23/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Slab railing beam at Block No-4 done in presence of Client & PSS Team.
24/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Slab railing beam at Block No-4 is under progress in presence of Client & PSS Team.
25/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of hand railing done in presence of Client & PSS Team.
26/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of hand railing is under progress in presence of Client & PSS Team.
27/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for D/S Flank wall, 8th lift at Block No-5 is under progress.
28/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 180.700m.
29/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-25, 15th lift done in presence of Client & PSS Team.
30/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-25, 15th lift is under progress in presence of Client & PSS Team.
31/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Cross Girder (Bay No-28 & 29) done in presence of Client & PSS Team.
32/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Cross Girder (Bay No-28 & 29) is under progress in presence of Client & PSS Team.
33/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 80 mm) of Slab hand railing at Block No-5 done in presence of Client & PSS Team.
34/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Slab hand railing at Block No-5 is under progress in presence of Client & PSS Team.
35/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Cross Girder (Bay No-18) is under progress in presence of Client & PSS Team.
36/100
Instream Storage Structure, Hamirpur
Testing of Compressive M15A40 (Strength is 13.18/mm2 for 07 days) of Flared out wall, 13th lift has done in presence of Client & PSS team.
37/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for D/S Flank wall, 8th lift at Block No-5 is under progress.
38/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 180.940m.
39/100
Instream Storage Structure, Hamirpur
Slump testing M15A40 (Value 45 mm) of U/S Flared out wall, 13th lift at Block No-5 done in presence of Client & PSS Team.
40/100
Instream Storage Structure, Hamirpur
Concreting M15A40 of U/S Flared out wall, 13th lift at Block No-5 is under progress in presence of Client & PSS Team.
41/100
Instream Storage Structure, Hamirpur
Rope drum hoist lifting arrangements bottom block rope pulley bracket work is in progress.
42/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 42.15/mm2 for 28 days) of Gantry Girder No-54 has done in presence of Client & PSS team.
43/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for D/S Flank wall, 8th lift at Block No-5 is under progress.
44/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 181.760m.
45/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
46/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site level RL 59.235m.
47/100
Instream Storage Structure, Khalpal
Binding of reinforcement for Girder No-63 is under progress.
48/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
49/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site level RL 59.28m.
50/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
51/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site level RL 59.26m.
52/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Present status of river Samakoi at Santeibhanja site.
53/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at Telkoi site.
54/100
UGPL, Left Lower Suktel Canal Division
Visit of SDO & JE of DoWR along with PMC team at Pump House.
55/100
Instream Storage Structure, Kopsinga
* Flow direction is straight flow is seen at RL- 217.000 against crest level RL- 215.00
* Water is flowing 2 m above the crest level .(D/S)
56/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Cross-beam Installation work is in progress at Span no - 24
57/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Chequered plate fixing work is in progress of Hoist-bridge at Span no - 24
58/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Chequered plate cutting work is in progress for Hoist-bridge as per drawing
59/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Bottom block fixing work is in progress of Barrage gates at Span no - 16
60/100
Instream Storage Structure, Kopsinga
* Flow direction is straight flow is seen at RL- 217.000 against crest level RL- 215.00
* Water is flowing 2 m above the crest level .(D/S)
61/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - CDU Installation work is in progress of Hoist-bridge at Span no - 21
62/100
Instream Storage Structure, Kopsinga
Control Building Roof slab reinforcement work is under progress
63/100
Instream Storage Structure, Kopsinga
* Flow direction is straight flow is seen at RL- 217.000 against crest level RL- 215.00
* Water is flowing 2 m above the crest level .(D/S)
64/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Shaft fixing work is in progress 'CDU to 'RDU' at Span no - 24
65/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Railing fixing work is in progress of Hoist-bridge at Span no - 20
66/100
Instream Storage Structure, Kopsinga
Control Building Roof slab shuttering work is under progress
67/100
Instream Storage Structure, Kopsinga
* Flow direction is straight flow is seen at RL- 216.800 against crest level RL- 215.00
* Water is flowing 1.800m above the crest level .(D/S)
68/100
Instream Storage Structure, Kopsinga
* Flow direction is straight flow is seen at RL- 216.800 against crest level RL- 215.00
* Water is flowing 1.800m above the crest level .(D/S)
69/100
Instream Storage Structure, Kudabega
Water level D/S-206.85m
70/100
Instream Storage Structure, Kudabega
Water level u/p-207.34m
71/100
Instream Storage Structure, Kudabega
Railing vertical post fixing work in progress
72/100
Instream Storage Structure, Kudabega
Ds water level 207.050m
73/100
Instream Storage Structure, Kudabega
Us water level 207.600m
74/100
Instream Storage Structure, Kudabega
Water level R/L 207/600 metre U/S
75/100
Instream Storage Structure, Kudabega
Water level R/L 207.05 metre
76/100
Instream Storage Structure, Kudabega
Double stored building & control building ground floor slab DeShuttering work in progress
77/100
Instream Storage Structure, Kudabega
US water level 207.640m
78/100
Instream Storage Structure, Kudabega
Ds water level 207.140m
79/100
Instream Storage Structure across river Sapei near village Kinjirma
Reinforcement work of control room cum staff quarter is in progress .
80/100
Instream Storage Structure across river Sapei near village Kinjirma
Wall beam reinforcement work of control room and staff quarter is in progress .
81/100
Instream Storage Structure across river Sapei near village Kinjirma
Flow direction is straight flow is seen at RL- 207.00 against crest level RL- 206.25 .
. Water is flowing 0.75m above the crest level .(D/S)
82/100
Instream Storage Structure across river Sapei near village Kinjirma
* Flow direction is straight flow is seen at RL- 206.75 against crest level RL- 206.25 .
* Water is flowing 0.5m above the crest level .(D/S)
83/100
Instream Storage Structure Across Bheden near village Saida
Staff quarter ground floor out side brick work in progress
84/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-215.900 mtr against design crest level RL- 215.000 mtr .i.e 0.9 mtr flood lift .
85/100
Instream Storage Structure Across Bheden near village Saida
Site visit by sub-collector & SE & SDO SID Sambalpur . instructed to complete the remaining work till November.
86/100
Instream Storage Structure Across Bheden near village Saida
Staff quarter ground floor out side brick wall work is going on .
87/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-216.300 mtr against design crest level RL- 215.000 mtr .i.e 1.300mtr flood lift .
88/100
Instream Storage Structure Across Bheden near village Saida
Staff quarter ground floor out side brick wall work is going on .
89/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-216.600 mtr against design crest level RL- 215.000 mtr .i.e 1.600mtr flood lift .
90/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-215.500 mtr against design crest level RL- 215.000 mtr .i.e 0.5 mtr flood lift .
91/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-215.600 mtr against design crest level RL- 215.000 mtr .i.e 0.6 mtr flood lift .
92/100
Instream Storage Structure, Khirasasan
Flow direction is straight flow is seen at RL- 211.700 against crest level RL- 210.900
93/100
Instream Storage Structure, Khirasasan
Flow direction is straight flow is seen at RL- 211.700 against crest level RL- 210.900. Water is flowing 0.8 m above the crest level
94/100
Instream Storage Structure, Khirasasan
Kuchinda Sub-Collector, SE, SDO, and JE Sir visited ISS -Kirasasan for inspection gate operation work.
95/100
Instream Storage Structure, Khirasasan
Flow direction is straight flow is seen at RL- 211.800 against crest level RL- 210.900. Water is flowing 0.9 m above the crest level
96/100
Instream Storage Structure, Khirasasan
View showing flow of river from u/s to d/s of river.
97/100
Instream Storage Structure, Khirasasan
View showing flow of river from u/s to d/s of river.
98/100
Instream Storage Structure, Khirasasan
Flow direction is straight flow is seen at RL- 212.000 against crest level RL- 210.900. Water is flowing 1.1 m above the crest level
99/100
Instream Storage Structure, Khirasasan
View showing flow of river from u/s to d/s of river.
100/100
Instream Storage Structure, Khirasasan
Flow direction is straight flow is seen at RL- 211.400 against crest level RL- 210.900. Water is flowing 0.5 m above the crest level
❮
❯