1/100
Instream Storage Structure, Hamirpur
Bay no 24 LHS column erection work is in progress
2/100
Instream Storage Structure, Hamirpur
By no 9/10 slab expansion joint concrete work
3/100
Instream Storage Structure, Hamirpur
Bay no 10 railing beam concrete work
4/100
Instream Storage Structure, Kudabega
Roof slab casting
5/100
Instream Storage Structure, Kudabega
roof slab cating 1st floor watcman cum operator shed
6/100
Instream Storage Structure, Kudabega
Roof slab casting 1st floor watchman cum operator hed
7/100
Instream Storage Structure, Kudabega
slump no-5 of roof slab 1st floor watchman cum operator shed
8/100
Instream Storage Structure, Kudabega
slump no-4 of roof slab of watchman cum operator shed
9/100
Instream Storage Structure, Kudabega
Slump No-3 of roof slab casting of watch man cum operator shed
10/100
Instream Storage Structure, Kudabega
Slump No-2 of 1st floor roof slab of watchman cum operator shed
11/100
Instream Storage Structure, Kudabega
Slump No-1 of Roof Slab
12/100
Integrated Barrage across river Kochila and across river Baitarini
ISS over Baitarani on 09.11.2026
13/100
Instream Storage Structure, Kudabega
Reinforcement checking of first floor slab by departmental Engineers
14/100
Instream Storage Structure, Jamutpali
Discussion with villagers nearby regarding land demarcation
15/100
Instream Storage Structure, Jamutpali
Land demarcation at site
16/100
Instream Storage Structure, Jamutpali
Geotechnical Site Investigation
17/100
Instream Storage Structure, Kuakhai
The SE, QAAD, Bhubaneswar, along with his team, inspected the ongoing concrete casting work of U/S Right side Devide wall.
18/100
Instream Storage Structure, Kuakhai
The SE, QAAD, Bhubaneswar, along with his team, inspected the ongoing concrete casting work of U/S Right side Devide wall.
19/100
Instream Storage Structure, Kuakhai
Casting of U/S Devide wall (R/S) from RL 16.65m to 18.05m with M25A20 concrete commenced in presence of AEE, ISS Kuakhai (I/C), QAAD team, OCCL.
20/100
Instream Storage Structure, Kuakhai
Casting of U/S Devide wall (R/S) from RL 16.65m to 18.05m with M25A20 concrete commenced in presence of AEE, ISS Kuakhai (I/C), QAAD team, OCCL.
21/100
Instream Storage Structure, Kushabhadra
Stop log gat gantry track alignment.
22/100
Instream Storage Structure, Kuakhai
Inspection and calibration of batching plant and sieve in presence of QAAD, Bhubaneswar team.
23/100
Instream Storage Structure, Kuakhai
Inspection and calibration of batching plant and sieve in presence of QAAD, Bhubaneswar team.
24/100
Instream Storage Structure, Kuakhai
Inspection and calibration of batching plant and sieve in presence of QAAD, Bhubaneswar team.
25/100
Instream Storage Structure, Near Village Basantpur across River Daya
Installation of Batching Plant completed.
26/100
Instream Storage Structure, Jamutpali
Pillar Posting at the banks of Jamutpali
27/100
Instream Storage Structure, Jamutpali
S/I work at ISS JAMUTPALI
28/100
Instream Storage Structure, Jamutpali
Drilling of Bore inside the river at Jamutpali
29/100
Instream Storage Structure, Kushabhadra
Compaction of GSB for the River Embankment Road
30/100
Instream Storage Structure, Jamutpali
Setting up of labour camp at Jamutpali
31/100
Instream Storage Structure, Kuakhai
Drone photos of ISS site before flood.
32/100
Instream Storage Structure, Near Village Basantpur across River Daya
Present Site condition.
33/100
Instream Storage Structure, Kuakhai
Drone photo of ISS before flood.
34/100
Instream Storage Structure, Near Village Basantpur across River Daya
Installation of Labour shed and material testing lab is under progress.
35/100
Instream Storage Structure, Jharbeda
Site clearing work is initiated
36/100
ISS AYODHYASAGAR
Camp Container at site
37/100
Instream Storage Structure, Budharaja
ISS budharaja at pond level
38/100
Instream Storage Structure, Kirasasan
ISS KIRASASAN
Water level -209.4m
Crest level -209.7m
Pond level -213m
39/100
Instream Storage Structure, Gudvella
D/s of ISS Gudvella.
40/100
Instream Storage Structure Across Bheden near village Saida
ISS Saida
41/100
Instream Storage Structure, Gudvella
U/s of ISS Gudvella.
42/100
Instream Storage Structure, Gochara
ISS Gocchra at pond level 230 m
43/100
Instream Storage Structure, Gochara
ISS GOCHHRA
44/100
Instream Storage Structure, Kuakhai
Earth work in construction of diversion channel to ensure smooth passage of river water to D/S .
45/100
Instream Storage Structure, Kuakhai
Construction of Coffer dam at R/S under sluice to isolate the area for dewatering
46/100
Instream Storage Structure, Kuakhai
Cleaning of R/S under sluice counterfort Zone-5
47/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning works at ISS Telkoi on 09.11.2026
48/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Dewatering in Progress at ISS Santeibhanja on 06.11.2026.
49/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering works in Right Abutment at ISS Santeibhanja on 09.11.2026.
50/100
Instream Storage Structure, Hamirpur
Bay no - 6, cross girder concreting is in progress
51/100
Instream Storage Structure, Hamirpur
Bay no - 9 & 10, expansion joint area shuttering work is in progress
52/100
Instream Storage Structure, Kushabhadra
canal road formation and subgrade preparation alignment marking work RD- 00+250M to 00+500M
53/100
Instream Storage Structure, Hamirpur
Bay no 24 Gate erection work in progress
54/100
Instream Storage Structure, Kushabhadra
Checking of canal road level & width.
55/100
Instream Storage Structure, Hamirpur
By no 10/9 slab expansion joint fixing work progress
56/100
Instream Storage Structure, Hamirpur
curing work in progress
57/100
Instream Storage Structure, Hamirpur
By no 7 Dec slab casting work complete
58/100
Instream Storage Structure, Hamirpur
Hamirpur site watchman Building columns deshuttering work is in progress
59/100
Instream Storage Structure , Tustapalli
The survey work is continuing for the 8th day and has now been completed up to the axis point of the ISS Tustapali on 06.11.2026
60/100
Instream Storage Structure , Tustapalli
The survey work is continuing for the 7th day and is currently in progress at a location approximately 1.5 km before Tustapali village on 05.11.2026
61/100
Instream Storage Structure , Tustapalli
The survey work is continuing for the 7th day and is currently in progress at a location approximately 1.5 km before Tustapali village on 05.11.2026
62/100
Instream Storage Structure , Tustapalli
The survey work is continuing for the 7th day and is currently in progress at a location approximately 1.5 km before Tustapali village on 05.11.2026
63/100
Instream Storage Structure, Hamirpur
Barrage way hoist bridge no 04 05 RDO and cdo and rop pully fitting with welding work in progress
64/100
Instream Storage Structure, Hamirpur
Hamirpur site watchman Building column concreting work is in progress
65/100
Instream Storage Structure, Hamirpur
Flared out wall 7th lift shuttering along with RR masonry work is in progress of block no. 5 ( D/S )
66/100
Instream Storage Structure, Kopsinga
LHS D/S River view on Dt.5.11.2026
67/100
Instream Storage Structure, Kopsinga
RHS U/S hand railing welding work is under progress
68/100
Instream Storage Structure, Kopsinga
Side rubber seal installation work in progress
69/100
Instream Storage Structure, Kopsinga
Walk way railing work
70/100
Instream Storage Structure, Nandagaon
Mechanical Works:- Alignment and erection of Rope Drum Hoists have been completed for 7 gates out of the total 14 gates. A total of 15 skilled labourers are presently engaged in the work. The executing agency has assured that the remaining mechnical work will be completed by 25th November 2026.
71/100
Instream Storage Structure, Nandagaon
Mechanical Works:- Alignment and erection of Rope Drum Hoists have been completed for 7 gates out of the total 14 gates. A total of 15 skilled labourers are presently engaged in the work. The executing agency has assured that the remaining mechnical work will be completed by 25th November 2026.
72/100
Instream Storage Structure, Nandagaon
Inspection conducted by the Quality Assurance Division, Bhawanipatna, at Nandagaon ISS.
73/100
Instream Storage Structure, Hamirpur
Bay no 6 cross girder reinforcement binding and shuttering work is in progress.
74/100
Instream Storage Structure, Hamirpur
Slab quring work progress
75/100
Instream Storage Structure, Hamirpur
Bay no 7 Deckslab reinforcement binding work is in progress
76/100
Instream Storage Structure, Hamirpur
Hamirpur site watchman Building footing column shuttering work is in progress
77/100
Instream Storage Structure, Hamirpur
Bay no 7 Deckslab reinforcement binding work is in progress.
78/100
Instream Storage Structure, Hamirpur
79/100
Instream Storage Structure, Hamirpur
80/100
Instream Storage Structure, Hamirpur
Bay no 8 Deckslab concreteing work.
81/100
Instream Storage Structure, Hamirpur
Colum base plate fixing work in progress at Pier no-25
82/100
Instream Storage Structure , Tustapalli
The survey work is continuing for the 6th day and is currently in progress near Tustapali village.
83/100
Instream Storage Structure , Tustapalli
The survey work is continuing for the 5th day. The survey work stopped due to rain fall 2nd half.
84/100
Instream Storage Structure , Tustapalli
The survey work is continuing successfully for the 4th day. At present, the survey team is working at Saitala Market.
85/100
Instream Storage Structure, Nandagaon
Concrete casting of the ground floor slab was completed today.
86/100
Instream Storage Structure, Kopsinga
RHS U/S hand railing welding work under progress
87/100
Instream Storage Structure, Kopsinga
Brick work of parapet wall on double storey building is under progress
88/100
Instream Storage Structure, Kopsinga
Walk way railing welding is under progress
89/100
Instream Storage Structure, Kopsinga
Flow direction is straight flow is seen at RL-216.300 against crest level RL-215.100(D/S)
90/100
Instream Storage Structure, Kopsinga
Walk way railing work under progress
91/100
Instream Storage Structure, Kopsinga
Side rubber sill work under progress
92/100
Instream Storage Structure, Kopsinga
Control building floor curing
93/100
Instream Storage Structure, Kopsinga
Double storey building first floor plastering work is under progress
94/100
Instream Storage Structure, Kopsinga
Flow direction is straight flow is seen at RL-216.400 against crest level RL-215.100(D/S)
95/100
Instream Storage Structure, Nandagaon
Reinforcement steel fixing for the ground floor slab is in progress.
96/100
Instream Storage Structure , Tustapalli
The survey work is continuing successfully for the 3rd day. At present, the survey team is working near Saitala Village.
97/100
Instream Storage Structure , Tustapalli
The survey work is continuing successfully for the 3rd day. At present, the survey team is working near Saitala Village.
98/100
Instream Storage Structure , Tustapalli
The survey work is continuing successfully for the 3rd day. At present, the survey team is working near Saitala Village.
99/100
Instream Storage Structure , Tustapalli
The survey work is continuing successfully for the 3rd day. At present, the survey team is working near Saitala Village.
100/100
Instream Storage Structure, Kudabega
Watchman cum operator building
❮
❯