Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Gudvella
Visited ISS Gudvella site along with IE expert. Dept SDO , Dept JE ,Site engineers of PMC n agency were present. 1. Casting of concrete RCC M25A20 grade at deck slab no - 8 in between P7 and P8 is in progress. 2. Slump checked at site and slump value is 80 mm 3. Casting of cubes done at site 4. Conducted test for 7 days compressive strength of concrete cube RCC M25A20 grade at field laboratory and result found 19.33 N/mm2 5. sieve analysis of sand done at site which found zone -2 and fineness modulus of sand found - 2.45 6. Conducted combined gradation of 20mm and 10mm coarse aggregate and result found satisfactory on 26.11.2025
2/100
Instream Storage Structure, Gudvella
Visited ISS Gudvella site along with IE expert. Dept SDO , Dept JE ,Site engineers of PMC n agency were present. 1. Casting of concrete RCC M25A20 grade at deck slab no - 8 in between P7 and P8 is in progress. 2. Slump checked at site and slump value is 80 mm 3. Casting of cubes done at site 4. Conducted test for 7 days compressive strength of concrete cube RCC M25A20 grade at field laboratory and result found 19.33 N/mm2 5. sieve analysis of sand done at site which found zone -2 and fineness modulus of sand found - 2.45 6. Conducted combined gradation of 20mm and 10mm coarse aggregate and result found satisfactory on 26.11.2025
3/100
Instream Storage Structure, Gudvella
Casting of concrete at deck slab number-08 in between P7 and P8 of grade M25A20 from RL 159.50 m to 160.30 m is underprogress through pump in the presence of SDO sir, IE expert sir,QC expert sir,Dept JE, PMC & agency site engineers. Slump achieved 80mm on 26.11.2025
4/100
Instream Storage Structure, Gudvella
Casting of concrete at deck slab number-08 in between P7 and P8 of grade M25A20 from RL 159.50 m to 160.30 m is underprogress through pump in the presence of SDO sir, IE expert sir,QC expert sir,Dept JE, PMC & agency site engineers. Slump achieved 80mm on 26.11.2025
5/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at Pier no.12/mid. right divide wall for 7th lift at U/S side and 8th lift at D/S side from RL-241.60m to RL-242.95m is in progress through concrete pump in presence of JE,KID, Site Engineers of PMC & EPC agency. Slump achieved 87mm on 26.11.2025
6/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at Pier no.12/mid. right divide wall for 7th lift at U/S side and 8th lift at D/S side from RL-241.60m to RL-242.95m is in progress through concrete pump in presence of JE,KID, Site Engineers of PMC & EPC agency. Slump achieved 87mm on 26.11.2025
7/100
Instream Storage Structure, Nandagaon
Columns fit up and base plate welding under progress on 26.11.2025
8/100
Instream Storage Structure, Nandagaon
• Monorail fit up and welding under progress on 26.11.2025
9/100
Integrated Barrage across river Kochila and across river Baitarini
BAITARANI -ISS Sluicebay abutment de shuttering work in progress-27.11.2025
10/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Sheet pile cutting work in progress at chaudharygada iss project-27.11.2025
11/100
UGPL, Left Lower Suktel Canal Division
20mm Dia galvanized steel Conduit pipe laying and wiring work is in progress for outdoor roof lighting work at Pump House.
12/100
UGPL, Right Lower Suktel Canal Division
Internal drain wall inside plastering work is in progress at Pump House.
13/100
UGPL, Right Lower Suktel Canal Division
Reinforcement binding work is in progress of internal RCC road at Pump House.
14/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for Dia 75mm HDPE pipeline LM - 17, LO330A OMS point at village Singhanimunda.
15/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for internal drainage near boundary wall at Pump House.
16/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cleaning & Vertical straightening of reinforcement for Divide wall, 3rd lift is under progress.
17/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Excavation of Gravity floor is under progress.
18/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
De-shuttering of Counter fort, 1st lift & 2nd lift is under progress.
19/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
De-shuttering of Divide wall, 2nd lift & 3rd lift is under progress.
20/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for Dia 350mm DI pipeline Lm-10 from J-85 to J-17 at village Khairpali.
21/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for Abutment & Counter fort is under progress.
22/100
Instream Storage Structure, KansariGanda
Curing continuing at site.
23/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning of D/S Gravity floor is under progress.
24/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS D/S Divide wall, 1st lift is under progress.
25/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Exp. along with Site engineers of PMC to the ISS site. Inspected the progress of work and Cube test conducted at site.
26/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Exp. along with Site engineers of PMC to the ISS site. Inspected the progress of work and Cube test conducted at site.
27/100
Instream Storage Structure, Jharbeda
Dewatering work is under progress.
28/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-6, 3rd lift is under progress.
29/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-5, 3rd lift is under progress.
30/100
Instream Storage Structure, Jharbeda
Cleaning of Floor area is under progress.
31/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 29.85/mm2 for 28 days) of Pier No-28, 10th lift and M25A20(Strength is 20.74/mm2 for 07 days) of Pier No-31, 4th lift has done in presence of Client & PSS team.
32/100
Instream Storage Structure, Hamirpur
Seal beam erection work is in progress of bay No-14.
33/100
Instream Storage Structure, Hamirpur
1st stage embedded parts erection work is in progress of Pier No-10, 2nd lift.
34/100
Instream Storage Structure, Hamirpur
Double pier hoist bridge platform welding work is in progress.
35/100
Instream Storage Structure, Hamirpur
Curing of Piers is under progress.
36/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-17, 8th lift at Block No-3 is under progress.
37/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-24, 13th lift at Block No-4 is under progress.
38/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-18, 8th lift at Block No-3 is under progress.
39/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-23, 11th lift at Block No-4 is under progress.
40/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-27, 13th lift at Block No-4 is under progress.
41/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-10, 3rd lift at Block No-2 is under progress.
42/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-31, 6th lift at Block No-5 is under progress.
43/100
Instream Storage Structure, Khalpal
Slump testing M20A40 (Value 65 mm) C.C Blocks done in presence of Client & PSS Team.
44/100
Instream Storage Structure, Khalpal
Casting of C.C Block (M20A40) is under progress in presence of Client & PSS Team.
45/100
UGPL, Left Lower Suktel Canal Division
MS Pipe to DI pipe Branch connection Pad plate Fit up work is in progress Dy-2 LM-11 at Village Tentulikhunti.
46/100
Instream Storage Structure across river Sapei near village Kinjirma
Complete to the casting of L.S double pier 6th lift
47/100
Instream Storage Structure across river Sapei near village Kinjirma
T.m 08 80mm
48/100
Instream Storage Structure across river Sapei near village Kinjirma
T.M 07 90mm
49/100
Instream Storage Structure across river Sapei near village Kinjirma
T.M 06 Slump 80mm (L.S double Pier 6th lift casting of continue)
50/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 80mm T.m 01
51/100
Instream Storage Structure, Budharaja
De-Shuttering work is in Progress LHS Divided Wall, Hoist Gate Portion.
52/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at Pier No: 7, Hoist Gate Portion.
53/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at Pier No: 6, Hoist Gate Portion.
54/100
Instream Storage Structure, Budharaja
De-Shuttering work is in Progress at Pier No: 1, Hoist Gate Portion.
55/100
Instream Storage Structure, Budharaja
Staff Quarter Brick work in progress and Curing .
56/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
57/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. Flow direction is straight. The direction of flow is seen in middle of the river. Now the flow level is 225.600mt against design crest level 225.500 i.e. flood lift 0.0mt.
58/100
Instream Storage Structure Across Bheden near village Saida
Reinforcement work progress in P-5, 10th lift. Rl-223.4 to 224.3
59/100
Instream Storage Structure, Kopsinga
LHS U/S Guided bond 37th layer FDD Check .
60/100
Instream Storage Structure, Kopsinga
28days cube test of P(13-14) u/s kerb and P(9-10) u/s kerb & LHS d/s flared wall 8th lift 7 days cube test of LHS flared wall 8th lift u/s and D/S divide wall final lift RHS .
61/100
Instream Storage Structure, Kopsinga
Slump-75mm, tm-2
62/100
Instream Storage Structure, Kopsinga
Slump-80mm ,LHS D/S flared wall 14th lift M20A20 .
63/100
Instream Storage Structure, Kopsinga
Chipping work under progress .
64/100
Instream Storage Structure, Kopsinga
Chipping work under progress .
65/100
Instream Storage Structure, Kopsinga
Chipping work under progress .
66/100
Instream Storage Structure, Kopsinga
LHS U/S Guided bond 35th layer FDD Check
67/100
Instream Storage Structure, Kopsinga
LHS D/S Guided bond 39th layer FDD Check
68/100
Instream Storage Structure, Khirasasan
Slump 80 mm
69/100
Instream Storage Structure, Khirasasan
Sir, checked placing and positioning of steel reinforcement, supporting bars and alignment of shuttering work in LHS d/s flared out 9th lift RL- 214.700 to 215.300 Now the area is ready for concrete casting M20 A20. So recommended for the purpose. Approved by AEE sir SID Sambalpur in presence of JE
70/100
Instream Storage Structure, Khirasasan
LHS D/S FLARED OUT wall 9th lift shuttering work completed and ready for concrete casting
71/100
Instream Storage Structure, Khirasasan
LHS U/S FLARED OUT WALL EXCAVATION WORK UNDER PROGRESS
72/100
Instream Storage Structure, Khirasasan
Pier no 3 Hoist portion shuttering work under progress.
73/100
Instream Storage Structure, Khirasasan
Pier no 2 Hoist portion shuttering work under progress.
74/100
Instream Storage Structure, Kudabega
Slump 85mm
75/100
Instream Storage Structure, Kudabega
Barrage bay-2 span no- 19 p-19 & p-18 for stoplog & service gate groove 2nd stage 2th lift M30A20 casting work in progress
76/100
Instream Storage Structure, Kudabega
Slump 80mm
77/100
Instream Storage Structure, Kudabega
Barrage bay-2 span no- 21 p-21R & p-20 for stoplog & service gate groove 2nd stage 5th lift M30A20 casting work in progress
78/100
Instream Storage Structure, Kudabega
Slump 85mm
79/100
Instream Storage Structure, Kudabega
Barrage bay-2 pier no-14 deck strip seal expansion joint M35A20 casting work in progress
80/100
Instream Storage Structure, Kudabega
ISS Kudabaga - 'Guide' fixing work is in progress for Span no - 16
81/100
Instream Storage Structure, Kudabega
Span no-12 kerb shuttering work in progress
82/100
Instream Storage Structure, Kudabega
ISS Kudabaga - 'Guide' fixing work is in progress for Span no - 20
83/100
Instream Storage Structure, Kudabega
Span no- 04 gate groove chipping work in progress.
84/100
Instream Storage Structure, Kudabega
Span no-14 raft gate groove bottom seal cleaning work in progress.
85/100
Instream Storage Structure, Kudabega
Span no-22 gate groove deshuttering & shuttering work in progress
86/100
Instream Storage Structure, Kudabega
RHS downstream Wing Wall deshuttering work in progress
87/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Trestle or Column's work is in progress
88/100
UGPL, Left Lower Suktel Canal Division
1Ha. outlet point fixing work is in progress of RO-290B,Z-5622 near village Pardhiapali.
89/100
Instream Storage Structure, Gudvella
Reinforcement at deck slab no 8 in between P7 & P8 is in progress on 25.11.2025
90/100
Instream Storage Structure, Gudvella
Reinforcement and shuttering at end sill portion from P5 to P9 is in progress on 25.11.2025
91/100
Instream Storage Structure, Nandagaon
Monorail fit up and welding under progress on 25.11.2025
92/100
Instream Storage Structure, Nandagaon
Gate no 3 both stoplog gate and barrage bay gate erection of 2nd stage embedded parts under progress on 25.11.2025
93/100
Integrated Barrage across river Kochila and across river Baitarini
Sluice Bay Abutment wall Reinforcement binding work is in progress at Baitarani ISS Project-26.11.2025
94/100
UGPL, Right Lower Suktel Canal Division
OCS fittings Installation work is in progress for OCS -0213119-C21A, at village Kasurpali in presence of AE, JE (DoWR) and PMC team.
95/100
UGPL, Right Lower Suktel Canal Division
Slump test is in progress for internal RCC road concreting of Pump House.
96/100
UGPL, Right Lower Suktel Canal Division
Internal RCC road reinforcement binding work is in progress at Pump House.
97/100
UGPL, Right Lower Suktel Canal Division
Internal drain wall inside plastering work is in progress at Pump House.
98/100
UGPL, Left Lower Suktel Canal Division
Butt fusion jointing work is in progress for 225mm Dia HDPE pipe line from node J-166 to J-188, (Zone-1) at Village Ramsingha.
99/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 280mm Dia HDPE pipeline from J-80 to J-440 (LM-6) at Village Gerdi.
100/100
UGPL, Left Lower Suktel Canal Division
Joint verification work is in progress for HDPE pipe line OMS point and outlet points of RO-56B(RM-3) at Village Ramshingha in presence of PMC team .