1/100
Instream Storage Structure, Gudvella
Cast of concrete 1st lift PCC M20A20 grade at U/s curtain wall from P2 to P8 with RL 147.10m to 147.70m is under progress in the presence of Dept JE, site engineer of PMC and agency. The slump test value is found 70mm on 10.03.2026
2/100
Instream Storage Structure, Gudvella
Cast of concrete 1st lift PCC M20A20 grade at U/s curtain wall from P2 to P8 with RL 147.10m to 147.70m is under progress in the presence of Dept JE, site engineer of PMC and agency. The slump test value is found 70mm on 10.03.2026
3/100
Instream Storage Structure, Gudvella
Roller fit up work at barrage gate is under progress on 10.03.2026
4/100
Instream Storage Structure, Gudvella
Final alignment (block out area) work at A1 & P1 is under progress on 10.03.2026
5/100
Instream Storage Structure, Gudvella
Placement of CC block at U/s of site is under progress on 10.03.2026
6/100
Instream Storage Structure, Gudvella
Brickwork at control room building is under progress on 10.03.2026
7/100
Instream Storage Structure, Gudvella
Shuttering work at u/s curtain wall is in progress on 10.03.2026
8/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade for gate grooves sill beam at bay-12 ( Barrage bay-10) is in progress in presence of PM EPC agency Site Engineers of PMC and EPC agency. The slump test value is 83mm on 10.03.2026
9/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade for gate grooves sill beam at bay-12 ( Barrage bay-10) is in progress in presence of PM EPC agency Site Engineers of PMC and EPC agency. The slump test value is 83mm on 10.03.2026
10/100
Instream Storage Structure, Nandagaon
• 1.The area of main & stoplog gate grooves at bay No.-12 ( Barrage bay no.-10) for erection of sill beams and its alignment, levels using TS has been checked and found correct by site Engineers mechanical of PMC on dt. 10.03.2026 as per the approved mechanical drawings.
(i) Sufficient nos. of dowel bars have been provided during fixing of beams.
(ii) The area is cleaned properly through air water jet and passed by SE,Kid, Bhawanipatna for placing with concrete M35A20 grade in presence of PM,EPC agency,Site Engineers of PMC & EPC agency on 10.03.2026
11/100
Instream Storage Structure, Nandagaon
Gate no 9 both barrage bay gate and stoplog gate 2nd stage embedded parts erection work under progress on 10.03.2026
12/100
Instream Storage Structure, Nandagaon
Curing at RCC deck slab is under progress on 10.03.2026
13/100
Instream Storage Structure, Nandagaon
De-Shuttering at D/S left flared out wall is in progress on 10.03.2026
14/100
Instream Storage Structure, Nandagaon
Gate no 12 both barrage bay gate and stoplog gate sil beam all measurement checked as per approved drawings, spirit level, water level checked. Hence ready for concrete on 10.03.2026
15/100
Instream Storage Structure, Nandagaon
Gate no 12 both barrage bay gate and stoplog gate sil beam all measurement checked as per approved drawings, spirit level, water level checked. Hence ready for concrete on 10.03.2026
16/100
Instream Storage Structure, Nandagaon
Shuttering for RCC deck slab at span-14 is in progress on 10.03.2026
17/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS-2305108 C06A at village Rambhasindhol in presence of PMC team.
18/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for laying of DN 75 mm Dia HDPE pipe for 1 Ha Sub-Chak of OCS No. 2305093-C02A at village Ghatkaintara.
19/100
UGPL, Right Lower Suktel Canal Division
Back filling and levelling work is in progress at Primary filtration unit area of Pump House..
20/100
UGPL, Left Lower Suktel Canal Division
Air Vacuum valve installation work is in progress at LM-7 LO-140B near village Uperuda .
21/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Cross Girder (Bay No-23) at Block No-4 done in presence of Client & PSS Team.
22/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Cross Girder (Bay No-23) at Block No-4 is under progress in presence of Client & PSS Team.
23/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Pier No-7, 14th lift with pier Cap at Block No-2 done in presence of Client & PSS Team.
24/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-7, 14th lift with pier Cap at Block No-2 is under progress in presence of Client & PSS Team.
25/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.94/mm2 for 28 days) of Pier No-13, 8th lift and (Strength is 21.63/mm2 for 07 days) of Pier No-13, 11th lift and (Strength is 31.11/mm2 for 28 days) of Pier No-9, 14th lift and M30A20 (Strength is 28.44/mm2 for 07 days) of Groove 2nd stage, 9th lift (Bay No-29) has done in presence of Client & PSS team.
26/100
Instream Storage Structure, Hamirpur
C.D.U assembly No-6 E.M brake fit up work is in progress.
27/100
Instream Storage Structure, Hamirpur
MS plate marking and cutting for under sluice hoist platform work is in progress.
28/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flared out wall, 2nd lift at Block No-5 is under progress.
29/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-30, 10th lift is under progress.
30/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-21, 6th lift is under progress.
31/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-20, 15th lift is under progress.
32/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-16, 8th lift is under progress.
33/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-15, 6th lift is under progress.
34/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Girder is under progress.
35/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-13, 12th lift is under progress.
36/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cube testing of Dalmia cement of M25A20 (Strength is 29.49/mm2) of Middle Cross Cut-off has done in presence of Client & PSS team.
37/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
De-shuttering of Wing wall Raft is under progress.
38/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Dewatering of Upstream Divide wall and Shuttering of Abutment & Counterfort, 6th lift is under progress.
39/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of Reinforcement for RHS Divide wall slope portion, 3rd lift is under progress.
40/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-6 lift is under progress.
41/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-8, 3rd lift is under progress.
42/100
Instream Storage Structure, Jharbeda
De-shuttering of Pier No-4 to Pier No-7, End sill is under progress.
43/100
Instream Storage Structure, Khalpal
Calibration of lab equipment in presence of Client & PSS team.
44/100
Instream Storage Structure, Khalpal
Testing of Cube Compressive strength has done in presence of Client & PSS team.
45/100
Instream Storage Structure, Khalpal
Checking of binding of reinforcement for Barrage Bay raft at Block No-4 in presence of Client & PSS team.
46/100
UGPL, Right Lower Suktel Canal Division
Inspected of BFV and BFV Chamber is in progress for 400mm DIa DI pipe from J-5040 to J-5051(p-5048) at village Bhaler.
47/100
UGPL, Right Lower Suktel Canal Division
OCS chamber above GL work is in progress of OCS No:- 0213119-C14A at village Bandhankata in presence of DoWR staff and PMC team.
48/100
Instream Storage Structure, Gudvella
Cast of concrete final lift PCC M20A20 grade at U/s curtain wall from A2 to P8 with RL 148.20m to 148.60m is under progress in the presence of Dept JE, site engineer of PMC and agency. The slump test value is found 75mm on 09.03.2026
49/100
Instream Storage Structure, Gudvella
Cast of concrete final lift PCC M20A20 grade at U/s curtain wall from A2 to P8 with RL 148.20m to 148.60m is under progress in the presence of Dept JE, site engineer of PMC and agency. The slump test value is found 75mm on 09.03.2026
50/100
Instream Storage Structure, Gudvella
Roller fit up work at barrage gate is under progress on 09.03.2026
51/100
Instream Storage Structure, Gudvella
Final alignment (block out area) work at A1 & P1 is under progress on 09.03.2026
52/100
Instream Storage Structure, Gudvella
Reinforcement and shuttering work at block out area of pier -6 is under progress on 09.03.2026
53/100
Instream Storage Structure, Gudvella
Shuttering at u/s curtain wall is under progress on 09.03.2026
54/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
PMC team-Chandikhole visited ISS- Chaudhurygada today to monitor Barragebay casting work.
55/100
Instream Storage Structure, Gudvella
Brick work at building area is under progress on 09.03.2026
56/100
Integrated Barrage across river Kochila and across river Baitarini
PMC team-Chandikhole visited ISS – Kochila & Baitarani today to monitor RCC work.
57/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 2nos. Cross girders at pier no.13 & right abutment is in progress through concrete pump in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is mm on 09.03.2026
58/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 2nos. Cross girders at pier no.13 & right abutment is in progress through concrete pump in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is mm on 09.03.2026
59/100
Instream Storage Structure, Nandagaon
• 2.Reinforcement works including shuttering for casting of 2nos. cross girders with RCC M35A20 grade at Pier No.:-13 & right abutment for span-14 of undersluice bay-4 is completed and checked in presence of PM,EPC agency, Site Engineers of PMC and Site Engineer of EPC Agency as follows:
(i)Laying & placing in proper position of 2 layers 16mm dia bottom main bars @ 3nos. at 1st.layer & 2nos. at 2nd layer tied with 10mm dia 2-Legged stirrups @150mm C/C including binding 10mm dia dist. bars on both sides of vertical faces of girders are completed.
(ii) Rigid and smooth shuttering with 40mm clear cover at bottom and both vertical faces are completed.
(iii) Fixing & placing of 8mm dia B-type mesh bars @ 2 layers at both end points of girder is completed.
(iv)The area is ready and passed by SE KID Bhawanipatna for placing with RCC M35A20 grade on 09.03.2026
60/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of 3nos. CC blocks at D/S left Flared out wall i.e 1no. of size 6.0x1.5x0.6m at sec.2-2 for 15th lift and 1no. of size 6.0x1.5x0.6m from sec. 4-4 to sec. 5-5 for 16th lift and 1no. of size 1.5x1.5x0.6m from sec.5-5 to sec.6-6 for 17th lift of 0.6m hight upto RL-244.80m is in progress in presence of PM EPC agency Site Engineers of PMC & EPC agency. The slump test value is 77mm on 09.03.2026
61/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of 3nos. CC blocks at D/S left Flared out wall i.e 1no. of size 6.0x1.5x0.6m at sec.2-2 for 15th lift and 1no. of size 6.0x1.5x0.6m from sec. 4-4 to sec. 5-5 for 16th lift and 1no. of size 1.5x1.5x0.6m from sec.5-5 to sec.6-6 for 17th lift of 0.6m hight upto RL-244.80m is in progress in presence of PM EPC agency Site Engineers of PMC & EPC agency. The slump test value is 77mm on 09.03.2026
62/100
Instream Storage Structure, Nandagaon
• 1.The casting of CC blocks at following area has been checked in presence of PM,EPC agency, Site Engineer of PMC & EPC Agency:
(i)3Nos. CC blocks at D/S left Flared out wall i.e 1no. of size 6.0x1.5x0.6m at sec.2-2 for 15th lift and 1no. of size 6.0x1.5x0.6m from sec. 4-4 to sec. 5-5 for 16th lift and 1no. of size 1.5x1.5x0.6m from sec.5-5 to sec.6-6 for 17th lift of 0.6m hight upto RL-244.80m is completed.
(ii). Filling of inverted filter materials covering with LDPE paper at adjacent to each CC block in earth side are done before placement.
(iii) Application of 2 coat bitumen paint at cj's concrete surface is done.
(iv). Area is ready and passed by SE KID, Bh. Patna to place concrete with PCC M20A20 grade on 09.03.2026
63/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of Reinforcement for RHS Divide wall, 3rd lift slope portion is under progress.
64/100
Instream Storage Structure, Nandagaon
Barrage bay gate no. 9 sill beam erection work under progress on 09.03.2026
65/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering & Binding of Reinforcement for LHS D/S Divide wall, 3rd lift is under progress.
66/100
Instream Storage Structure, Jharbeda
Slump testing M20A20 (Value 40 mm) of D/S Pier No-7 to Pier No-8 Gravity floor, 2nd lift done in presence of Client & PSS Team.
67/100
Instream Storage Structure, Nandagaon
Monorail walkway MIG welding under progress on 09.03.2026
68/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of D/S Pier No-7 to Pier No-8 Gravity floor, 2nd lift is under progress in presence of Client & PSS Team.
69/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for cross girder at right abutment & pier no.13 is in progress on 09.03.2026
70/100
Instream Storage Structure, Nandagaon
Shuttering for RCC deck slab at span-14 is in progress on 09.03.2026
71/100
Instream Storage Structure, Nandagaon
Curing at RCC deck slab. wall is in progress on 09.03.2026
72/100
Integrated Barrage across river Kochila and across river Baitarini
AEE and AE of Akhuapada irrigation Division visited ISS- Kochila & Baitarani today. PMC team- Chandikhole and representatives of Agency were also present at site.
73/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Installation of first-stage embedded parts (stoplog and service gate seal beams) is in progress at the Choudhary Gada ISS Project.
74/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay raft PCC work in progress at baitarani iss project.
75/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Site Visit of OCCL S.M and PMC MBBS chandikhol today to TIKHIRI ISS PROJECT and CHOUDHARY GADA ISS PROJECT Discussion about project work with agency.
76/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site.
77/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and Irr. Eng. Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site and U/S right side diaphragm wall panel no -57 casting, Right side pile no-144, 123 casting and Rhs under-sluice panel no- R61 concrete pouring.
78/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and Irr. Eng. Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site and U/S right side diaphragm wall panel no -57 casting, Right side pile no-144, 123 casting and Rhs under-sluice panel no- R61 concrete pouring.
79/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-7, 6th lift is under progress.
80/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-8, 3rd lift is under progress.
81/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
82/100
Instream Storage Structure, Jharbeda
Placing of CC Blocks for D/S Barrage portion work is under progress.
83/100
Instream Storage Structure, Jharbeda
Curing of Wearing coat is under progress.
84/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of D/S Flank wall Cut-off, 2nd lift at Block No-5 done in presence of Client & PSS Team.
85/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flank wall Cut-off, 2nd lift at Block No-5 is under progress in presence of Client & PSS Team.
86/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
87/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
88/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
89/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
90/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
91/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-6, 10th lift at Block No-2 done in presence of Client & PSS Team.
92/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-6, 10th lift at Block No-2 is under progress in presence of Client & PSS Team.
93/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
94/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
95/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
96/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
97/100
Instream Storage Structure, KansariGanda
Visit of SE, AEE, AE of Dept., QA/QC expert and Irr. Eng. Exp. along with Site engineers PMC to the ISS Site. Inspected the overall progress of site and Right side divide wall pile cage lowering, pile integrity test conducted and Concreting.
98/100
Instream Storage Structure, Hamirpur
Cleaning of reinforcement for U/S Abutment (A1) at Block No-1 is under progress by Sand blasting method.
99/100
Instream Storage Structure, Hamirpur
R.D.U assembly No-6 work is in progress.
100/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Cross Girder (Bay No-23) is under progress.
❮
❯