PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
UGPL, Right Lower Suktel Canal Division
OCS chamber piping work is in progress of OCS No-2305093-C10B at village Ghatkaintara in presence of SDO along with DoWR official and PMC team.
2/100
UGPL, Right Lower Suktel Canal Division
OCS verification work is in progress of OCS NO 0213055- C17A at Village Bubel in presence of DOWR SDO, AE, JE, PMC team and L&T personnel.
3/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door & angle fixing work is in progress OCS No:-0213084-C04B at village Niljipali in presence of PMC team.
4/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress of 75mm Dia HDPE pipe Main line Gap closing node from LO-307 to LO-307B,LM-16 near village Birkel.
5/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 140mm Dia HDPE pipe line from J-531 to RO-79, RM-4 near village Kirabahal in presence of DoWR JE and PMC team.
6/100
UGPL, Left Lower Suktel Canal Division
HDD machine road pushing work is in progress for road crossing work of 75mm Dia HDPE pipe line between at J-527 RO-241 RM-13 near village Kusang.
7/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-4, 5th lift done in presence of Client & PSS Team.
8/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-4, 5th lift is under progress in presence of Client & PSS Team.
9/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Pier No-21, 13th lift done in presence of Client & PSS Team.
10/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-2, 5th lift done in presence of Client & PSS Team.
11/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-2, 5th lift is under progress in presence of Client & PSS Team.
12/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-15, 12th lift done in presence of Client & PSS Team.
13/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-15, 12th lift is under progress in presence of Client & PSS Team.
14/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Cross Girder (Bay No-17) done in presence of Client & PSS Team.
15/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Cross Girder (Bay No-17) is under progress in presence of Client & PSS Team.
16/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall Raft at Block No-5 is under progress.
17/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.93/mm2 for 07 days) of Pier No-1, 3rd lift and (Strength is 21.48/mm2 for 07 days) of Fish pass Raft at Block No-1 and M15A40 (Strength is 13.18/mm2 for 07 days) of U/S Flared out cut-off wall at Block No-1 has done in presence of Client & PSS team.
18/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-3, 6th lift is under progress.
19/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-1, 4th lift is under progress.
20/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Abutment (A1), 8th lift at Block No-1 is under progress.
21/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4, 5th lift is under progress.
22/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-16, 14th lift is under progress.
23/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
24/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier no-13, 14th lift is under progress.
25/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for LHS Side Raft is under progress.
26/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 85 mm) of RHS Mid-pier, 2nd lift done in presence of Client & PSS Team.
27/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of RHS Mid-pier, 2nd lift is under progress in presence of Client & PSS Team.
28/100
Instream Storage Structure, Khalpal
Curing of Piers work is in progress.
29/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of Pier No-21, 1st lift done in presence of Client & PSS Team.
30/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-21, 1st lift is under progress in presence of Client & PSS Team.
31/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of Pier No-22, 1st lift done in presence of Client & PSS Team.
32/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-22, 1st lift is under progress in presence of Client & PSS Team.
33/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 80 mm) of Pier No-24 (Crest portion) done in presence of Client & PSS Team.
34/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-24 (Crest portion) is under progress in presence of Client & PSS Team.
35/100
Instream Storage Structure, Khalpal
LHS D/S side Divide wall verification of SBC plate Test started at foundation level in presence of Client & PSS team along with EPC agency.
36/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Visited by QC&QA Expert, PMU in presence of Dy. TL, QAE, PSE & IEE of PSS team, A.E.E & A.E, RDD along with representative of EPC agency regarding Shuttering, binding of reinforcement and checking of construction materials at Site.
37/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for LHS side Raft is under progress.
38/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for Abutment with Counterfort and De-Shuttering of Divide wall is under progress.
39/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Visited by QC&QA Expert, PMU in presence of Dy. TL, QAE, PSE & IEE of PSS team, A.E.E & A.E, RDD along with representative of EPC agency regarding checking for Shuttering, binding of reinforcement & Excavation and other ongoing activities at Site.
40/100
Instream Storage Structure, Jharbeda
Slump testing M25A20 (Value 85 mm) of Pier No-6, 8th lift done in presence of Client & PSS Team.
41/100
Instream Storage Structure, Jharbeda
Concreting M25A20 of Pier No-6, 8th lift is under progress in presence of Client & PSS Team.
42/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-5 is under progress.
43/100
Instream Storage Structure, Jharbeda
De-Shuttering of Pier No-6 is under progress.
44/100
Instream Storage Structure, Jharbeda
Shuttering of RHS (D2) D/S Footing, 2nd Layer is under progress.
45/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for (A2) Footing Top is under progress.
46/100
Instream Storage Structure, Jharbeda
Curing of End sill is under progress.
47/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
48/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-17 done in presence of Client & PSS Team.
49/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-17 is under progress in presence of Client & PSS Team.
50/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.94/mm2 for 28 days) of D/S Flared out Cut-off wall, 14th lift and M35A20 (Strength is 42.23/mm2 for 28 days) of Gantry Girder No-1 and M25A20 (Strength is 21.63/mm2 for 07 days) of Pier No-21, 11th lift has done in presence of Client & PSS team.
51/100
Instream Storage Structure, Hamirpur
Gantry girder's 1st stage embedded plate welding work is in progress.
52/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Abutment (A1), 8th lift at Block No-1 is under progress.
53/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall at Block No-1 is under progress.
54/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-1, 5th lift is under progress.
55/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4, 5th lift is under progress.
56/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-15, 12th lift is under progress.
57/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-16, pier Cap is under progress.
58/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
59/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier no-21, 13th lift is under progress.
60/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS-0213064-C015A at village Bhaler in presence of PMC team.
61/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door & angle fixing work is in progress OCS No:-021310A-C07A at village Kanheimunda in presence of PMC team.
62/100
UGPL, Right Lower Suktel Canal Division
1 Ha outlet point fixing and HDPE Pipe laying work is in progress of OCS No. 0213116-C04A at village Padiabahali in presnece of SDO along with DoWR JE, PMC team and EPC Official.
63/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 80 mm) of Barrage Bay No-2 Mid Cut-off, 2nd lift done in presence of Client & PSS Team
64/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Barrage Bay No-2 Mid Cut-off, 2nd lift is under progress in presence of Client & PSS Team.
65/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of Pier No-23 (Crest portion) done in presence of Client & PSS Team.
66/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-23 (Crest portion) is under progress in presence of Client & PSS Team.
67/100
Instream Storage Structure, Khalpal
Barrage bay No-2 verification of SBC plate Test started at foundation level in presence of Client & PSS team along with EPC agency.
68/100
UGPL, Right Lower Suktel Canal Division
Butterfly valve chamber pre- cast cover slab de shuttering work is in progress near Pump House.
69/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI to HDPE pipeline connection at J-153 to RO-103 RM-6 near village Kuturapali in presence of PMC team.
70/100
UGPL, Left Lower Suktel Canal Division
HDPE Tee (180 X 125 X 125)mm connection work is in progress at J-81, RM-4, near village Semilia in presence of DoWR JE and PMC team.
71/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE pipe connection at LO-293 to J-406, LM-15 near village Singhamunda in presences of DoWR AE and PMC team.
72/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
PMC team-Chandikhole visited ISS- Chaudhurygada today. The representatives of agency were present during inspection.
73/100
Integrated Barrage across river Kochila and across river Baitarini
PMC Experts- Chandikhol visited ISS- Baitarani to-day. Casting of Barrage Bay Raft is in progress . Representatives of agency were available at site.
74/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
CC block shuttering work in progress
75/100
Integrated Barrage across river Kochila and across river Baitarini
Casting of Barrage Bay Raft is in progress -14.04.2026
76/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
CC block shuttering work in progress.
77/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay Raft Casting work is in progress in presence of PMC and representative of Agency of Baitarani Iss-13.04.2026
78/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
CC block casting work in progress.
79/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay raft casting work is going on at ISS Baitarani.
80/100
Integrated Barrage across river Kochila and across river Baitarini
Slump test conducted for RCC(M25 A20) in Barrage bay Raft and found 90mm.
81/100
UGPL, Left Lower Suktel Canal Division
HDPE to HDPE pipeline Connection work is in progress at J-184, RM-4 at village Kagaon in presence of PMC team.
82/100
UGPL, Right Lower Suktel Canal Division
1Ha subchak excavation work is in progress for 75mm Dia HDPE pipe of OCS No. 0213087-C11B at village Lakhapali In presence of DoWR Staff and PMC team.
83/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS-0213080-C04A at village Bramhinpali in presence of DoWR Staff and PMC team.
84/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door & angle fixing work is in progress OCS No:-0213103-C07B at village Umuria in presence of CME (PSS) along with PMC team.
85/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS-0213060-C11B at village Bramhinpali in presence of CME (PSS) and PMC team.
86/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for Laying of 75mm Dia HDPE Pipes from OMS RO237B( Z-4285) RM-13 for Gap closing work near village Taliudar in presence of PMC team.
87/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI to HDPE pipeline TEE connection at J-518 RM-13 near village Taliudar in presence of PMC team.
88/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE pipe TEE connection at LO-377, LM-4 near village Amamunda in presence of PMC team.
89/100
UGPL, Left Lower Suktel Canal Division
HDPE Tee (125X 75 X 75)mm connection work is in progress at RO-67, RM-4, near village Khaliapali in presence of PMC team.
90/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for RHS Double pier, 5th lift & Divide wall, Final lift and Shuttering of D/S Wing wall is under progress.
91/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of RHS Mid-pier, 2nd lift is under progress.
92/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M20A20 (Value 70 mm) of RHS D/S Gravity floor, 2nd lift done in presence of Client & PSS Team.
93/100
Instream Storage Structure, Jharbeda
Slump testing M20A20 (Value 75 mm) of Pier No-8 to RHS (D2) U/S Gravity floor done in presence of Client & PSS Team.
94/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of Pier No-8 to RHS (D2) U/S Gravity floor is under progress in presence of Client & PSS Team.
95/100
Instream Storage Structure, Jharbeda
Cleaning work is under progress.
96/100
Instream Storage Structure, Jharbeda
Shuttering & Binding of reinforcement for RHS Divide wall pier portion Footing is under progress.
97/100
Instream Storage Structure, Jharbeda
Shuttering & Binding of reinforcement for Pier No-8 is under progress.
98/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-6 is under progress.
99/100
Instream Storage Structure, Jharbeda
De-Shuttering of Pier No-5 is under progress.
100/100
Instream Storage Structure, Jharbeda
Shuttering of RHS D/S Flank wall, 1st Layer is under progress.