GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Khirasasan
Slump 80mm
2/100
Instream Storage Structure, Khirasasan
checked placing supporting bars and alignment of shuttering work in LHS D/s flared out 15th step RL- 218.300 to 218.900 Now the area is ready for concrete casting M20 A20. So recommended for the purpose. Approved by AEE sir SID Sambalpur in presence of JE
3/100
Instream Storage Structure, Khirasasan
LHS ABUTMENT HOIST PORTION SHUTTERING WORK IS UNDER PROGRESS
4/100
Instream Storage Structure, Khirasasan
RHS d/s flank wall 4th lift shuttering work is under progress
5/100
Instream Storage Structure, Khirasasan
LHS d/s Flared out wall 15th lift shuttering work complete RL- 218.300 TO 218.900
6/100
Instream Storage Structure, Khirasasan
RHS DIVIDE WALL HOIST PORTION SHUTTERING WORK IS UNDER PROGRESS
7/100
Instream Storage Structure, Khirasasan
RHS D/s Flared out wall 5th step deshuttering work is under progress.
8/100
Instream Storage Structure, Khirasasan
LHS U/S FLARED OUT WALL 5TH STEP SHUTTERING WORK IS UNDER PROGRESS.
9/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
10/100
Instream Storage Structure, Budharaja
Shuttering and Reinforcement Work is in Progress at Staff Quarter Slab.
11/100
Instream Storage Structure, Budharaja
2nd Stage Shuttering (Gate Groove) Work is in Progress at Pier No:4.
12/100
Instream Storage Structure, Budharaja
De- Shuttering in 7th Step & Shuttering work is in Progress at RHS D/S Flared-Out Wall, 8th Step.
13/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S of river
14/100
Instream Storage Structure, Kopsinga
Slump 85mm,tm-2
15/100
Instream Storage Structure, Kopsinga
RHS Guide bond 19th layer FDD Check
16/100
Instream Storage Structure, Kopsinga
RHS Guide bond 19th layer FDD Check
17/100
Instream Storage Structure, Kopsinga
Cube test
18/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Trestle's or Column's work is in progress
19/100
Instream Storage Structure, Kopsinga
Slump-80,tm-1 LHS u/s flared wall 16th lift (M20A20)
20/100
Instream Storage Structure, Kopsinga
Slump-90mm Divided wall
21/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Side Roller - tracker fixing work is in progress for Service gate's or Barrage gate's at Span no -21
22/100
Instream Storage Structure, Gochara
View showing flow of river from D/S of river
23/100
Instream Storage Structure Across Bheden near village Saida
Guide installation work is in progress to the top level of the Pier in Pier no-2 LHS Side Gate Groove.
24/100
Instream Storage Structure Across Bheden near village Saida
Cleaning work progress in RHS d/s flank wall 4th lift
25/100
Instream Storage Structure Across Bheden near village Saida
Shuttering work progress in LHS u/s flared out wall step-3 RL - 215.200 to 215.800
26/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from U/S to D/S of river.
27/100
Instream Storage Structure, Kudabega
Slump-85mm, u/s Rt. Flank wall casting
28/100
Instream Storage Structure, Kudabega
Slump- 80mm
29/100
Instream Storage Structure, Kudabega
Slump-85mm (Rhs Abutment hoist portion )
30/100
Instream Storage Structure, Kudabega
Barrage bay-2 span no-15 bottom sill beam M30A20 casting work in progress
31/100
Instream Storage Structure, Kudabega
Slump 80mm, RHS Abutment hoist portion
32/100
Instream Storage Structure, Kudabega
Slump 85mm
33/100
Instream Storage Structure, Kudabega
Span no-20 gate groove deshuttering & shuttering work in progress
34/100
Instream Storage Structure, Kudabega
Span no-17 gate groove deshuttering & shuttering work in progress
35/100
Instream Storage Structure, KansariGanda
Curing continuing at site.
36/100
Instream Storage Structure, KansariGanda
Slump test and cube cast at site in presence of Geologist and Irr. Eng. Expert along with Site engineer PMC.
37/100
Instream Storage Structure, KansariGanda
Slump test and cube cast at site in presence of Geologist and Irr. Eng. Expert along with Site engineer PMC.
38/100
Instream Storage Structure, KansariGanda
Visit of Irr. Eng. Expert & Geologist Expert along with Site engineer and Mechanical team of PMC to the ISS site. Inspected the overall progress of work, 1st and 2nd Barrage gate work completed final welding in progress & other gate work also in progress , 2nd stage Embedded parts fabrication work completed and another 2 no. Fabrication beds work going on for fast fabrication & assembling gate components. Abutment pier & counter fort wall concreting is in progress and Pile test in progress.
39/100
Instream Storage Structure, KansariGanda
Visit of Irr. Eng. Expert & Geologist Expert along with Site engineer and Mechanical team of PMC to the ISS site. Inspected the overall progress of work, 1st and 2nd Barrage gate work completed final welding in progress & other gate work also in progress , 2nd stage Embedded parts fabrication work completed and another 2 no. Fabrication beds work going on for fast fabrication & assembling gate components. Abutment pier & counter fort wall concreting is in progress and Pile test in progress.
40/100
Instream Storage Structure, KansariGanda
Visit of Irr. Eng. Expert & Geologist Expert along with Site engineer and Mechanical team of PMC to the ISS site. Inspected the overall progress of work, 1st and 2nd Barrage gate work completed final welding in progress & other gate work also in progress , 2nd stage Embedded parts fabrication work completed and another 2 no. Fabrication beds work going on for fast fabrication & assembling gate components. Abutment pier & counter fort wall concreting is in progress and Pile test in progress.
41/100
Instream Storage Structure, KansariGanda
Visit of Irr. Eng. Expert & Geologist Expert along with Site engineer and Mechanical team of PMC to the ISS site. Inspected the overall progress of work, 1st and 2nd Barrage gate work completed final welding in progress & other gate work also in progress , 2nd stage Embedded parts fabrication work completed and another 2 no. Fabrication beds work going on for fast fabrication & assembling gate components. Abutment pier & counter fort wall concreting is in progress and Pile test in progress.
42/100
UGPL, Right Lower Suktel Canal Division
Pani panchayat awareness meeting is in progress in presence of DoWR staff and PMC team at village Belbahali.
43/100
UGPL, Right Lower Suktel Canal Division
Barmad fixing work is in progress of OCS, NO-0213115-C13A near Village Gandbahal in presence of PMC team.
44/100
Barrage across river Turi & Guntat
Site inspection of Quality Assurance CE, JEs, IKB CE, NID SE, SDO, JE'S along with PMC DTL, site engineers, and agency representatives to Turi & Guntat barrage site. During the visit, a thorough check of all construction materials was performed, including sand testing and cube testing for fine and coarse aggregates, to ensure strict quality compliance on-site.
45/100
Barrage across river Turi & Guntat
Site inspection of Quality Assurance CE, JEs, IKB CE, NID SE, SDO, JE'S along with PMC DTL, site engineers, and agency representatives to Turi & Guntat barrage site. During the visit, a thorough check of all construction materials was performed, including sand testing and cube testing for fine and coarse aggregates, to ensure strict quality compliance on-site.
46/100
Barrage across river Turi & Guntat
Site inspection of Quality Assurance CE, JEs, IKB CE, NID SE, SDO, JE'S along with PMC DTL, site engineers, and agency representatives to Turi & Guntat barrage site. During the visit, a thorough check of all construction materials was performed, including sand testing and cube testing for fine and coarse aggregates, to ensure strict quality compliance on-site.
47/100
Instream Storage Structure, Gudvella
Cast of concrete 13th lift PCC M20A20 grade at left side u/s flard out wall from sec 1-1 to 4-4 with RL 155.80m to 156.40m is under progress in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 68mm on 16.12.2025
48/100
Instream Storage Structure, Gudvella
Cast of concrete 13th lift PCC M20A20 grade at left side u/s flard out wall from sec 1-1 to 4-4 with RL 155.80m to 156.40m is under progress in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 68mm on 16.12.2025
49/100
Instream Storage Structure, Near Village Basantpur across River Daya
Area preparation for another testing site on the right side of ISS.
50/100
Instream Storage Structure, Gudvella
Roller track installation pier no 4 & 5 work under progress on 16.12.2025
51/100
Instream Storage Structure, Near Village Basantpur across River Daya
PSS Team with Asst. Er., Prachi conducting the test at testing location.
52/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at Pier no.12 for 10th lift at U/S side and 11th lift at D/S side from RL-244.30m to RL-245.10m(pier cap bottom) is in progress through concrete pump in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 85mm on 16.12.2025
53/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at Pier no.12 for 10th lift at U/S side and 11th lift at D/S side from RL-244.30m to RL-245.10m(pier cap bottom) is in progress through concrete pump in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 85mm on 16.12.2025
54/100
Instream Storage Structure, Near Village Basantpur across River Daya
PSS Team with Asst. Er., Prachi observing the load vs settlement at testing location.
55/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.3 & 4 of bay no.4 for 1st lift is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency,ISS Nandgaon. Slump achieved 75mm on 16.12.2025
56/100
Instream Storage Structure, Near Village Basantpur across River Daya
Settlement at four locations near SBC site.
57/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.3 & 4 of bay no.4 for 1st lift is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency,ISS Nandgaon. Slump achieved 75mm on 16.12.2025
58/100
Instream Storage Structure, Nandagaon
Chequere plate fit up and welding on hoist bridge under progress on 16.12.2025
59/100
Instream Storage Structure, Nandagaon
Monorail fit up and welding work under progress on 16.12.2025
60/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering at D/S right flank wall, Block-2 is in progress on 16.12.2025
61/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concreter for stoplog & main gate groove at Pier no. 3& 4,Block-1 is in progress on 16.12.2025
62/100
Instream Storage Structure, Near Village Basantpur across River Daya
Settlement reading at 22 ton load at the testing location.
63/100
Instream Storage Structure, Near Village Basantpur across River Daya
Gauge showing 22 ton load at the testing location.
64/100
Instream Storage Structure, Near Village Basantpur across River Daya
Discussion with PM, VARKS, PSS Team & Deptt. officials at the testing site.
65/100
Instream Storage Structure, Near Village Basantpur across River Daya
Addl. CE, CIC observing the load vs settlement at the testing site.
66/100
Instream Storage Structure, Near Village Basantpur across River Daya
CE, QC observing the load vs settlement at the testing site.
67/100
Instream Storage Structure, Near Village Basantpur across River Daya
Loading of sand bags at the testing site in progress for conducting SBC test.
68/100
Instream Storage Structure, Near Village Basantpur across River Daya
Preparation for sand bag packing over the structure point at the testing site.
69/100
Instream Storage Structure, Near Village Basantpur across River Daya
Packing of boulders with interstices filling with sand in progress at testing location.
70/100
Instream Storage Structure, Near Village Basantpur across River Daya
Boulder dumping at the testing site on the left side in progress.
71/100
Instream Storage Structure, Near Village Basantpur across River Daya
Boulder dumping for a thickness of 1 mtr. at the testing site on the left side in progress.
72/100
Instream Storage Structure, Near Village Basantpur across River Daya
Preparation for conducting SBC at the left side of ISS site in progress.
73/100
Instream Storage Structure, Near Village Basantpur across River Daya
CE, MKS, Addl. CE, CIC, SE, Prachi, TL and PMU Team observing the SBC Test at site.
74/100
Instream Storage Structure, Near Village Basantpur across River Daya
CE, MKS, TL, PMU with QC consultant with Deptt. & PSS Team observing the load vs settlement.
75/100
Instream Storage Structure, Near Village Basantpur across River Daya
Loading and gauge point at the testing site.
76/100
Instream Storage Structure, Near Village Basantpur across River Daya
Plate load test under progress in presence of PSS Team, SDO, Balianta & Asst. Er, Prachi.
77/100
Instream Storage Structure, Near Village Basantpur across River Daya
Loading of sand bags for Plate load test near axis point in progress.
78/100
Instream Storage Structure, Near Village Basantpur across River Daya
Base preparation for plate load test near the ISS site.
79/100
Instream Storage Structure, Near Village Basantpur across River Daya
PSS Team with the Agency marking & checking the Axis Location.
80/100
Instream Storage Structure, Near Village Basantpur across River Daya
Coffer dam at the U/s of Axis site in progress.
81/100
Instream Storage Structure, Near Village Basantpur across River Daya
Coffer dam work in progress at bifurcation point near bhargavi.
82/100
Instream Storage Structure, Near Village Basantpur across River Daya
Marking the Axis line of ISS Daya at the location.
83/100
Instream Storage Structure, Near Village Basantpur across River Daya
PSS Team with Engineers of the Agency at the ISS site.
84/100
Instream Storage Structure, Near Village Basantpur across River Daya
Addl. CE, CIC with PSS Team at Daya ISS site.
85/100
Instream Storage Structure, Near Village Basantpur across River Daya
Sand filling at the bifurcation point at river bhargavi.
86/100
Instream Storage Structure, Near Village Basantpur across River Daya
Bulllah piling near U/S of ISS site.
87/100
Instream Storage Structure, Near Village Basantpur across River Daya
Coffer dam at Axis site in progress.
88/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Upstream coffer dam sand bag packing and sand filling work in progress at ISS- Chaudhurygada project.
89/100
Instream Storage Structure, Near Village Basantpur across River Daya
Discussion with CE,MKS regarding soil testing at ISS site.
90/100
Instream Storage Structure, Near Village Basantpur across River Daya
Diversion channel at Axis site of ISS Daya in progress.
91/100
Integrated Barrage across river Kochila and across river Baitarini
Divide wall Shuttering work in progress at Baitarani ISS Project.
92/100
UGPL, Left Lower Suktel Canal Division
Gap closing work is in progress for 300mm Dia DI pipeline from node J-405 to J-406, LM-15 near village Singhanimunda
93/100
UGPL, Right Lower Suktel Canal Division
Gap closing work is in progress of Dia 300mm K7 DI pipeline at village Lokapada.
94/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for HDPE pipeline of OCS No-2305096-C03B, SC-04 at village Tilesara.
95/100
UGPL, Right Lower Suktel Canal Division
Stone pitching work is in progress of external drain type 03 of Pump House.
96/100
Instream Storage Structure, Kuakhai
Cleaning of sand and silt at left side D/S divide wall portion.
97/100
Instream Storage Structure, Kuakhai
Reinforcement binding is under progress at right side U/S divide wall raft portion.
98/100
Instream Storage Structure, Kuakhai
Pier no.6 left side Stoplog gate groove 1st stage embedded parts welding work in progress.
99/100
Instream Storage Structure, Kuakhai
Casting of CC M30A20 at left side Counterfort zone-5 from RL 5.85m to 7.05m is completed.
100/100
Instream Storage Structure, Kuakhai
Left side block, abutment casting work is under progress.

Enter Login Details

Forgot Password ?