1/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No- 0201345- C11B near village Balangir in presence of DoWR SDO, AE, JE and PMC team.
2/100
UGPL, Left Lower Suktel Canal Division
DI to HDPE connection work is in progress at Lm-10 J-515 village Kadajuri in presence of PMC team.
3/100
Instream Storage Structure, Gudvella
Curing at slab is under progress on 05.05.2026
4/100
Instream Storage Structure, Gudvella
Shuttering work of posts deck slab on 05.05.2026
5/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 05.05.2026
6/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 05.05.2026
7/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right divide wall for 9th lift upto RL-243.80m is in progress through concrete pump in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 88mm on 05.05.2026
8/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right divide wall for 9th lift upto RL-243.80m is in progress through concrete pump in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 88mm on 05.05.2026
9/100
Instream Storage Structure, Nandagaon
• 4.The area of placing concrete at U/S right divide wall has been checked before placement in presence of PM of EPC Agency, Site Engineer of PMC & EPC Agency as follows:
(i).The reinforcement in binding, tying n spacing of both vertical main & horiz. dist. bar and tie bars for casting of U/S right divide wall for 9th lift from RL-242.40m to RL-243.80m are found completed.
(ii).Rigid & smooth shuttering and maintained clear cover of 75mm from main bar to shutter plates are done.
(iii).The area is cleaned properly through air water jetting and passed by SE, KID, Bhawanipatna for placing with RCC M25A20 grade on 05.05.2026
10/100
Instream Storage Structure, Nandagaon
• 3.Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay No.-12 of Pier No.11&12 for 1st lift have been checked and found correct by HM Expert of PMC during his site visit on dt.05.05.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 05.05.2026
11/100
Instream Storage Structure, Nandagaon
• 2.Shuttering for Second Stage concrete for gate grooves at barrage bay 9,10&11 are kept ready since last two days for placing concrete at Block-2. Due to the breakdown of Batching plant concrete could not be done.
Due to inadequate numbers of placing gangs engaged at site, the entire area for 2nd. stage concreting at vertical gate grooves at Block-2 is very slow. @ PM, ISS Nandagaon is suggested to increase more manpower to complete the work in time on 05.05.2026
12/100
Instream Storage Structure, Nandagaon
• Side visit of ISS, Nandagaon by QAC, Expert along with the HME and Sr. Site Engineer of PMC in presence of PM of EPC Agency, Site Engineers of PMC and EPC Agency. During site visit, the following activities are in progress, :-
1. Reinforcement works in binding, placing in proper position, tying n maintaining clear cover for 9th lift at U/S right Divide wall including rigid & smooth n shuttering works are found completed on 05.05.2026
13/100
Instream Storage Structure, Nandagaon
• Side visit of ISS, Nandagaon by QAC, Expert along with the HME and Sr. Site Engineer of PMC in presence of PM of EPC Agency, Site Engineers of PMC and EPC Agency. During site visit, the following activities are in progress, :-
1. Reinforcement works in binding, placing in proper position, tying n maintaining clear cover for 9th lift at U/S right Divide wall including rigid & smooth n shuttering works are found completed on 05.05.2026
14/100
Instream Storage Structure, Nandagaon
Placing of CC blocks is in progress at D/S side on 05.05.2026
15/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress on 05.05.2026
16/100
Instream Storage Structure, Nandagaon
Hoist bridge sand blasting and painting work is under progress on 05.05.2026
17/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for Laying of 75mm Dia HDPE pipe line from node RO-144 to RO-144B RM-8 near village Bhainsa.
18/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for LHS side Raft is under progress.
19/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
visited by Sub-Collector, Pallahara along with Tahasildar at ISS site in presence of PSS Team & EPC Agency fixed for Site Selection Committee Meeting.
20/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Testing of Compressive M25A20 (Strength is 18.51/mm2 for 07 days) of RHS Flank wall and (Strength is 29.94/mm2 for 28 days) of LHS U/S Divide wall, Footing has done in presence of Client & PSS team.
21/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for RHS Counterfort & Abutment wall, 2nd lift is under progress.
22/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of RHS under sluice portion D/S Gravity floor, 3rd Layer is under progress in presence of Client & PSS Team.
23/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-5 is under progress.
24/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-8 is under progress.
25/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
26/100
Instream Storage Structure, Jharbeda
Curing of Gravity floor is under progress.
27/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Gantry Girder No-31 done in presence of Client & PSS Team.
28/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-31 is under progress in presence of Client & PSS Team.
29/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of U/S Flared out wall, 1st lift at Block No-1 (Bank side) done in presence of Client & PSS Team.
30/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of U/S Flared out wall, 1st lift at Block No-1 (Bank side) is under progress in presence of Client & PSS Team.
31/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Deck slab (Bay No-15) done in presence of Client & PSS Team.
32/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Deck slab (Bay No-15) is under progress in presence of Client & PSS Team.
33/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.20/mm2 for 28 days) of Pier No-1, 3rd lift and (Strength is 30.91/mm2 for 28 days) of Fish pass Raft at Block No-1 and (Strength is 31.41/mm2 for 28 days) of Pier No-4, 1st lift and M35A20 (Strength is 37.04/mm2 for 07 days) of Gantry Girder No-28 has done in presence of Client & PSS team.
34/100
Instream Storage Structure, Hamirpur
R.D.U no's of 10 set and C.D.U no's of 13 set fixing work is in progress.
35/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-5 girder's welding work is in progress.
36/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform No-5 girder's web & flange plate fixing work is in progress.
37/100
Instream Storage Structure, Hamirpur
MS plate marking and cutting for hoist platform girder's web plate work is in progress.
38/100
Instream Storage Structure, Hamirpur
Stop-log groove 2nd stage embedded parts guide and track alignment work is in progress at bay No-26.
39/100
Instream Storage Structure, Hamirpur
Gantry girder's 1st stage embedded plate fixing and welding work is in progress.
40/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-2, 6th lift is under progress.
41/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall, Raft at Block No-5 is under progress.
42/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flared wall, Raft at Block No-5 is under progress.
43/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Abutment (A1), 5th lift is under progress.
44/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
45/100
Instream Storage Structure, Khalpal
Curing of under sluice End sill is in progress.
46/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 165 mm) of U/S Panel No-09 at Barrage Bay No-1 1 done in presence of Client & PSS Team.
47/100
Instream Storage Structure, Khalpal
Concreting M25A20 of U/S Panel No-09 at Barrage Bay No-1 done in presence of Client & PSS Team
48/100
Instream Storage Structure, Khalpal
Diaphragm wall cage placing for U/S Panel No-09 at Barrage Bay No-1 in presence of Client & PSS Team.
49/100
Instream Storage Structure, Khalpal
End stopper fixing for U/S Panel No-09 at Barrage Bay No-1 in presence of Client & PSS Team.
50/100
Instream Storage Structure, Khalpal
Testing of Compressive M25A20 (Strength is 34.32/mm2 for 28 days) of Pier No-21 and (Strength is 33.33/mm2 for 28 days) of Mid Cut-off, 1st lift at Barrage Bay No-2 has done in presence of Client & PSS team.
51/100
Instream Storage Structure, Khalpal
Binding of reinforcement for Barrage Bay No-2, Raft is under progress.
52/100
Instream Storage Structure, Khalpal
Shuttering of Double pier No-25 is under progress.
53/100
Instream Storage Structure, Khalpal
Curing of Piers is in progress.
54/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., and Site Engineer PMC to the ISS Site. Inspected the overall progress of site, Cage lowering for panel R95 u/s flank-wall and concreting in progress.
55/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., QA&QC Expert along with Site Engineer PMC to the ISS Site. Inspected the overall progress of site, CC Blocks placing on the D/S barrage bay, Raft concreting progress and checking of girder beam reinforcement.
56/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., QA&QC Expert along with Site Engineer PMC to the ISS Site. Inspected the overall progress of site, CC Blocks placing on the D/S barrage bay, Raft concreting progress and checking of girder beam reinforcement.
57/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irrigation Eng. Expert along with Site Engineer PMC to the ISS Site. Inspected the overall progress of site, Right side pier -9 pile cap concreting continuing and Right-side Pier no-7 reinforcement binding & shuttering work is in progress.
58/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irrigation Eng. Expert along with Site Engineer PMC to the ISS Site. Inspected the overall progress of site, Right side pier -9 pile cap concreting continuing and Right-side Pier no-7 reinforcement binding & shuttering work is in progress.
59/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irrigation Eng. Expert along with Site Engineer PMC to the ISS Site. Inspected the overall progress of site, Right side pier -9 pile cap concreting continuing and Right-side Pier no-7 reinforcement binding & shuttering work is in progress.
60/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irrigation Eng. Expert along with Site Engineer PMC to the ISS Site. Inspected the overall progress of site, Right side pier -9 pile cap concreting continuing and Right-side Pier no-7 reinforcement binding & shuttering work is in progress.
61/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - 30th number Under-sluice gate's bottom part's work is in progress
62/100
UGPL, Right Lower Suktel Canal Division
External drain brick masonry work is in progress at Pump House.
63/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - 'Walk -Way' work is in progress
64/100
Instream Storage Structure, Kopsinga
D/S side gravity floor cleaning work under progress
65/100
Instream Storage Structure, Kopsinga
Double stored building 3rd lift column shuttering work under progress
66/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - 'Guide' fixing work is in progress of Barrage gate's at Span no - 4
67/100
Instream Storage Structure, Kopsinga
7/8/9 Vent 2nd stage casting under progress
68/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door and angle fixing work is in progress OCS No:-0201297- C15A at village Rinabachan in presence of PMC team.
69/100
Instream Storage Structure, Kopsinga
Slump-85mm Vent 2nd stage
70/100
Instream Storage Structure, Kopsinga
7/8/9 Span Vent 2nd stage Shuttering work complete now the area ready for casting
71/100
Instream Storage Structure, Kopsinga
D/S Gravity Floor cleaning work under progress
72/100
Instream Storage Structure, Kopsinga
Double stored building curing
73/100
Instream Storage Structure, Kopsinga
Pier no(1-2) span Bottom gate groove chipping work under progress
74/100
Instream Storage Structure, Kopsinga
Pier 16 Gate groove chipping work under progress
75/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Painting work is in progress of 'Walk - Way'
76/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Trestle's work is in progress
77/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Additional - secretary Madam of 'DoWR' Visited the ISS - Kopsingha Site in Presence of Department - Officer's.
78/100
Instream Storage Structure, Kopsinga
Span no(6 - 5) 2nd stage bottom sill shuttering checking now the area ready for casting
79/100
Instream Storage Structure, Kopsinga
LHS approach slab hand rail post reinforcement shuttering checking completed now the area ready for casting
80/100
Instream Storage Structure, Kopsinga
Pier no -6 2nd stage gate groove shuttering work is under progress
81/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - 30th number - Hoist-bridge Assembly work is in progress
82/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - 'Walk - Way' Work is in progress
83/100
Instream Storage Structure, Kopsinga
Pier no-7 2nd stage Vent shuttering work progress
84/100
Instream Storage Structure, Kopsinga
Pier no-16& P17 Gate Groove chipping work under progress
85/100
Instream Storage Structure, Kopsinga
Cube test..
86/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Roller-track fixing work is in progress of Stop - log gate at Span no - 5
87/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - 'Walk - Way' Work is in progress
88/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - 30th - number Hoist - bridge's assembly work is in progress Out of - 30
89/100
Instream Storage Structure, Kopsinga
Double storied building brick work under progress
90/100
Instream Storage Structure, Kopsinga
Cube test
91/100
Instream Storage Structure, Kopsinga
Pier 17 LHS Gate Groove chipping work under progress
92/100
Instream Storage Structure, Kopsinga
Pier no13 RHS Gate Groove chipping work under progress
93/100
Instream Storage Structure, Kopsinga
Double storied building brick work under progress
94/100
Instream Storage Structure, Kopsinga
Pier no-8/9/10/15 vent 2nd stage Shuttering work check now the area ready for casting.
95/100
Instream Storage Structure, Kopsinga
IEE & Geologist of PMC Sambalpur visited ISS Kopasinga. Gate Groove Shuttering work under progress. The PM of Agency is instructed to take up other ancillary works simultaneously for completion of the work in revised time period.
96/100
Instream Storage Structure, Kopsinga
Batching plant calibration in presence of Dept..QC
97/100
Instream Storage Structure, Kopsinga
PMC team, Sambalpur visited ISS kopsinga .AEE&JE of Dept &PM of the Agency were present.Gate groove shuttering of P9, P10 & P14 work under progress.
98/100
Instream Storage Structure, Kopsinga
Pier 18 gate grove chipping work under progress
99/100
Instream Storage Structure, Kopsinga
Pier 14 vent 2nd stage 4th lift Shuttering work under progress
100/100
Instream Storage Structure, Kopsinga
Gate grove cleaning work
❮
❯