GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Kuakhai
Reinforcements and the area ready for casting observed by SDO, ISS Kuakhai (I/C) . Today R/S D/S Flank wall 3rd lift from RL 11.10m to 12.50m M25 A20 casting to be commenced .
2/100
Instream Storage Structure, Hamirpur
Block no 5 d/s flared out wall boulder pitching work in progress
3/100
Instream Storage Structure, Hamirpur
By no 5 cross girder casting work progress
4/100
Instream Storage Structure, Hamirpur
Bay no - 18, gate groove 2nd stage 8th lift concreting is in progress
5/100
Instream Storage Structure , Tustapalli
The DGPS survey work is currently in progress from Saintala towards the Tustapali ISS site.
6/100
Instream Storage Structure, Gudvella
D/S OF ISS GUDVELLA.
7/100
Instream Storage Structure, Gudvella
U/S OF ISS GUDVELLA.
8/100
Instream Storage Structure, Kushabhadra
Barrage gate installation.
9/100
Instream Storage Structure, Kushabhadra
O&M Building 1st Floor Electrifications work is under progress.
10/100
Instream Storage Structure, Kushabhadra
Right side u/s guide bond area c&g with slope cutting work is progressing.
11/100
Instream Storage Structure, Kuakhai
AE,Prachi observing ongoing casting of RCC M30 A20 at right side counterfort (zone- 5) 5th lift from RL 11.45m to 12.80m is in progress.
12/100
Instream Storage Structure, Dhanei
Sand Blasting and Painting work ongoing of the gates at site
13/100
Barrage across river Turi & Guntat
Turi Barrage control room slab casting is going on
14/100
Barrage across river Turi & Guntat
Before slab casting on the control room of Turi Barrage
15/100
Barrage across river Turi & Guntat
Present status of Turi Barrage
16/100
Instream Storage Structure, Hamirpur
Bay no - 17, gate groove 2nd stage concreting is in progress
17/100
Instream Storage Structure, Hamirpur
Bay no-06 Deck slab concreting work in progress
18/100
Instream Storage Structure, Hamirpur
Bay no 10 - 2nd stage groove Wall concrete work in progress
19/100
Instream Storage Structure, Kuakhai
Casting of RCC M30 A20 at right side counterfort (zone- 5) 5th lift from RL 11.45m to 12.80m is in progress.
20/100
Instream Storage Structure , Tustapalli
The leveling survey using an Auto Level was completed on 06.11.2026. Following a break in the survey work, the DGPS survey has been resumed today i.e. on 17.11.2026, from Deogaon PWD IB in the presence of the Departmental Junior Engineer and the agency's survey team.
21/100
Instream Storage Structure , Tustapalli
The leveling survey using an Auto Level was completed on 06.11.2026. Following a break in the survey work, the DGPS survey has been resumed today i.e. on 17.11.2026, from Deogaon PWD IB in the presence of the Departmental Junior Engineer and the agency's survey team.
22/100
Instream Storage Structure , Tustapalli
The leveling survey using an Auto Level was completed on 06.11.2026. Following a break in the survey work, the DGPS survey has been resumed today i.e. on 17.11.2026 from Deogaon PWD IB in the presence of the Departmental Junior Engineer and the agency's survey team.
23/100
Instream Storage Structure, Gudvella
D/S SIDE OF ISS GUDVELLA ON 17.11.2026
24/100
Instream Storage Structure, Gudvella
U/S SIDE OF ISS GUDVELLA ON 17.11.2026
25/100
Instream Storage Structure, Gudvella
D/S SIDE OF ISS GUDVELLA ON 16.11.2026
26/100
Instream Storage Structure, Gudvella
U/S SIDE OF ISS GUDVELLA ON 16.11.2026
27/100
Instream Storage Structure, Gudvella
D/S SIDE OF ISS GUDVELLA ON 15.11.2026
28/100
Instream Storage Structure, Gudvella
DECKSLAB OF ISS GUDVELLA ON 15.11.2026
29/100
Instream Storage Structure, Gudvella
U/S SIDE OF ISS GUDVELLA ON 15.11.2026
30/100
Instream Storage Structure, Kushabhadra
Walkway bridge hand railing fixing work is under progress.
31/100
Instream Storage Structure, Kushabhadra
Making bed preparation for backfilling.
32/100
Instream Storage Structure, Kushabhadra
O&M Building 1st Floor Inside plastering work is under progress.
33/100
Instream Storage Structure, Kushabhadra
Canal Road 2nd layer laying work is under progress.
34/100
Instream Storage Structure, Hamirpur
Bay no - 17, gate groove 2nd stage 6th lift concreting is in progress
35/100
Instream Storage Structure, Hamirpur
Bay no-06 Deck slab shuttering with reinforcement binding work is in progress
36/100
Instream Storage Structure, Hamirpur
Bay no - 7/8, slab curing work is in progress
37/100
Instream Storage Structure, Dhanei
All three gates have been inverted to facilitate Sand blasting and painting of the opposite sides.
38/100
Instream Storage Structure, Dhanei
12 nos electrical Poles installation completed at site.
39/100
Instream Storage Structure, Dhanei
Electrical Pole installation started at site. Four nos of poles installed on that day.
40/100
Instream Storage Structure, Near Village Basantpur across River Daya
Coffer dam work is in progress
41/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning of Reinforcement in progress ISS Telkoi on 16.11.2026
42/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
ISS Santeibhanja 16.11.2026
43/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
cleaning work in progress ISS Santeibhanja on 16.11.2026
44/100
Instream Storage Structure, Nandagaon
Control Room construction work is in progress,
45/100
Instream Storage Structure, Kushabhadra
Right side Guide bund development is under progress.
46/100
Instream Storage Structure, Kushabhadra
Canal road second layer compaction is in progress.
47/100
Instream Storage Structure, Hamirpur
Bay no 6 Deckslab reinforcement binding work is in progress.
48/100
Instream Storage Structure, Hamirpur
Abutment A2 under sluice column erection with fitting work in progress
49/100
Instream Storage Structure, Hamirpur
Bay no 21stoplog side guide alignment with fitting work in progress
50/100
Instream Storage Structure, Kushabhadra
Hoist Bridge Alignement Work is in Progress
51/100
Instream Storage Structure, Kushabhadra
Building Electrification work is in Progress.
52/100
Instream Storage Structure, Kushabhadra
Laying of second layer for River embankment road.
53/100
Instream Storage Structure, Near Village Basantpur across River Daya
Coffee dam work is in progress.
54/100
Instream Storage Structure, Gudvella
D/S OF ISS GUDVELLA ON 14.11.2026
55/100
Instream Storage Structure, Gudvella
U/S OF ISS GUDVELLA ON 14.11.2026
56/100
Instream Storage Structure, Gudvella
D/S OF ISS GUDVELLA ON 13.11.2026
57/100
Instream Storage Structure, Gudvella
U/S OF ISS GUDVELLA. ON 13.11.2026.
58/100
Instream Storage Structure, Hamirpur
Block no 5 d/s flared out wall boulder pitching work in progress
59/100
Instream Storage Structure, Hamirpur
Bay no-06 Deck slab reinforcement placing work is in progress
60/100
Instream Storage Structure, Hamirpur
Bay no-12 gate groove 2nd stage concreting work in progress
61/100
Instream Storage Structure, Kuakhai
SE, Prachi along with G.M.( Civil), H.O. OCCL visited the ISS Kuakhai site in presence of concerned site engineers and PM, DDBL and instructed to expedite the progress as per the work programme submitted for timely completion of work by stipulated date i. e by March-27.
62/100
Instream Storage Structure, Kushabhadra
Embankment Road 2nd layer laying work is under progress.
63/100
Instream Storage Structure, Kushabhadra
O&M Building 1st Floor Inside plastering & Finishing work is under progress.
64/100
Instream Storage Structure, Gudvella
D/s of ISS Gudvella.
65/100
Instream Storage Structure, Gudvella
U/s of ISS Gudvella.
66/100
Instream Storage Structure, Hamirpur
Bay no - 22, gate groove 2nd stage 1st lift concreting is in progress
67/100
Instream Storage Structure, Hamirpur
Block no 5 d/s flared out wall 9th lift boulder spreading in progress
68/100
Instream Storage Structure, Hamirpur
Deck slab curing work is in progress
69/100
Instream Storage Structure, Kudabega
Unloading Stone at site
70/100
Instream Storage Structure, Kudabega
Electrical Lightening work in progress
71/100
Instream Storage Structure, Near Village Basantpur across River Daya
Site visit by Assistant Engineer to the confluence point of Daya & Bhargavi River to plan for the construction of Coffee dam.
72/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Dewatering in progress at ISS Santeibhanja on 11.11.2026
73/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Inspection of Control Room Building works at ISS Telkoi on 11.11.2026
74/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Joint Inspection of land at Telkoi (currently under the occupation of RWSS) by SE, RWSS Division and AEE, Rengali Dam Division in presence of field engineers and the agency on 11.11.2026
75/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Joint Inspection of land at Telkoi (currently under the occupation of RWSS) by SE, RWSS Division and AEE, Rengali Dam Division in presence of field engineers and the agency on date 11.11.2026
76/100
Instream Storage Structure, Gudvella
D/s of ISS Gudvella.
77/100
Instream Storage Structure, Gudvella
U/s of ISS Gudvella.
78/100
Instream Storage Structure, Hamirpur
Bay no - 17, gate groove 2nd stage 2nd lift concreting is in progress
79/100
Instream Storage Structure, Hamirpur
Bay no 21 LHS column erection work in progress
80/100
Instream Storage Structure, Kushabhadra
Fixation of alignment of Guide bund by SDO Balianta & Manager,OCCL and other field engineerd.
81/100
Instream Storage Structure, Kushabhadra
Rolling of GSB is ongoing.
82/100
Instream Storage Structure, Kopsinga
First floor of double storey building plastering is under progress
83/100
Instream Storage Structure, Kopsinga
Welding work of RHS D/S handrail is under progress
84/100
Instream Storage Structure, Kopsinga
Staircase welding work at RHS
85/100
Instream Storage Structure, Kopsinga
LHS D/S River view on Dt.11.11.2026
86/100
Instream Storage Structure, Dhanei
O&M building Coloring, Door/window, Tiles and Railing works completed.
87/100
Instream Storage Structure, Dhanei
O&M building Coloring, Door/window, Tiles and Railing works completed.
88/100
Barrage across river Turi & Guntat
Link channel TGIP
89/100
Barrage across river Turi & Guntat
Maintenance building work status at Turi Barrage
90/100
Barrage across river Turi & Guntat
Turi Barrage Gate
91/100
Barrage across river Turi & Guntat
Turi Barrage Down stream status
92/100
Integrated Barrage across river Kochila and across river Baitarini
Coffer dam & Approach road work started
93/100
Instream Storage Structure, Near Village Basantpur across River Daya
Labour shed preparation is ongoing.
94/100
Instream Storage Structure, Near Village Basantpur across River Daya
Development of Camp site work is in progress.
95/100
Instream Storage Structure, Kushabhadra
Canal Road GSB Preparations Work RD- 00+250M to 00+500M.
96/100
Instream Storage Structure, Kushabhadra
fabrication and mechanical installation work on the operating platform of barrage hoist gate system
97/100
Instream Storage Structure, Kushabhadra
Compaction of GSB by Vibro Roller at canal road
98/100
Instream Storage Structure, Kushabhadra
Making soil bond work is progressing at u/s river area ( for de watering purpose)
99/100
Instream Storage Structure, Hamirpur
Batching plant Calibration
100/100
Instream Storage Structure, Hamirpur
Mechanical SE site visit

Enter Login Details

Forgot Password ?