GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Gudvella
Paint work under progress on 04.04.2026
2/100
Instream Storage Structure, Gudvella
Gate installation work under progress at P8 on 04.04.2026
3/100
Instream Storage Structure, Gudvella
Brickwork underprogress at control room building on 04.04.2026
4/100
Instream Storage Structure, Gudvella
Placement of CC block is under progress at U/s of site on 04.04.2026
5/100
Instream Storage Structure, Gudvella
Clearance of loose material is under progress at left side under sluice bay on 04.04.2026
6/100
Instream Storage Structure, Gudvella
• Today SE, Balangir Irrigation Division, Balangir visited ISS Gudvella site. Department JE, PMC site engineers and agency representatives were present. 1. He inspected the overall site condition & instructed the agency to speed up the work and complete it on 03.04.2026
7/100
Instream Storage Structure, Gudvella
• Today SE, Balangir Irrigation Division, Balangir visited ISS Gudvella site. Department JE, PMC site engineers and agency representatives were present. 1. He inspected the overall site condition & instructed the agency to speed up the work and complete it on 03.04.2026
8/100
Instream Storage Structure, Gudvella
Casting of concrete at parapet wall of right side D/s wing wall including 5 nos CF with RL 159.50m to 160.40m is underprogress in the presence of Dept JE, site engineer of PMC and agency at site. The slump test value is 77mm on 03.04.2026
9/100
Instream Storage Structure, Gudvella
Casting of concrete at parapet wall of right side D/s wing wall including 5 nos CF with RL 159.50m to 160.40m is underprogress in the presence of Dept JE, site engineer of PMC and agency at site. The slump test value is 77mm on 03.04.2026
10/100
Instream Storage Structure, Gudvella
Curing at building slab on 03.04.2026
11/100
Instream Storage Structure, Gudvella
Shuttering work underprogress at A2 d/s wing wall for final lift RCC on 03.04.2026
12/100
Instream Storage Structure, Gudvella
Clearance of loose material is under progress at left side undesluice bay on 03.04.2026
13/100
Instream Storage Structure, Gudvella
Shuttering and reinforcement work is under progress at 1st floor of building column on 03.04.2026
14/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.1& left abutment for 9th lift of undersluice bay-1 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 85mm on 04.04.2026
15/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.1& left abutment for 9th lift of undersluice bay-1 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 85mm on 04.04.2026
16/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.1& left abutment for 9th lift of undersluice bay-1 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 83mm on 04.04.2026
17/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.1& left abutment for 9th lift of undersluice bay-1 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 83mm on 04.04.2026
18/100
Instream Storage Structure, Nandagaon
• 2.Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at undersluice bay No.-1 of Pier No.1& left abutment for 9th lift have been checked and found correct by HM Expert of PMC during his site visit on dt.01.04.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs. (i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows: (ii) Chipping of old vertical concrete surface is done. (iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 04.04.2026
19/100
Instream Storage Structure, Nandagaon
• 1 . Visited the site, ISS Nandagaon by QAC Expert & Site Engineer of PMC on dt. 04.04.2026 in presence of PM,EPC Agency, Site Engineers of PMC and site Engineer of EPC Agency, ISS Nandagaon. Observations/ suggestions are made during visit following components as follows: (a) Construction of RCC cutoff wall of U/S right Divide wall is already completed and the PCC with M15A40 grade at bottom of Raft foundation has also been completed on dt. 02.04.2026. (b) Reinforcement works in binding, placing in proper position, clear cover at bottom layer and sides are maintained using cover blocks including rigid n smooth shuttering at bottom layer for 1st lift of 0.60m ht. are completed as follows : (i) Binding of main Bar of 25mm dia n 16mm dia Dist. Bars at bottom layers including binding of vertical main pier bars of 20mm dia are completed. (ii) Rigid and Smooth shuttering by providing clear cover 75mm measured from main bar to shutter plate are done. (iii) Area is cleaned using air water jetting and passed by SE, KID, Bhawanipatna and ready to place concrete with RCC M25A20 grade upto RL-230.00m on 04.04.2026
20/100
Instream Storage Structure, Nandagaon
Pier no 14 trestle and column foundation bolt erection work under progress on 04.04.2026
21/100
Instream Storage Structure, Nandagaon
De-Shuttering & Shuttering for 2nd stage concrete is in progress at pier no.10 on 04.04.2026
22/100
Instream Storage Structure, Nandagaon
Gate no 13 both barrage bay gate and stoplog gate 2nd stage embedded parts erection work under progress on 04.04.2026
23/100
Instream Storage Structure, Nandagaon
Placing of CC blocks is in progress at U/s side on 04.04.2026
24/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress at pier no.7&8 on 04.04.2026
25/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering is in progress at U/S right divide wall raft bottom layer on 04.04.2026
26/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.9&10 for 2nd lift of bay-10 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 84mm on 03.04.2026
27/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.9&10 for 2nd lift of bay-10 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 84mm on 03.04.2026
28/100
Instream Storage Structure, Nandagaon
Gate no 11 both barrage bay gate and stoplog gate 2nd stage embedded parts erection work completed. Hence ready for concrete on 03.04.2026
29/100
Instream Storage Structure, Nandagaon
• 1. Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay No.-10 of Pier No.9&10 for 2nd lift have been checked and found correct by HM Expert of PMC during his site visit on dt.01.04.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs. (i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows: (ii) Chipping of old vertical concrete surface is done. (iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 03.04.2026
30/100
Instream Storage Structure, Nandagaon
Laying & placing in proper position and binding & tying of bottom main bar is in progress at U/S right divide wall on 03.04.2026
31/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no.7&9 on 03.04.2026
32/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 80 mm) of LHS sluice Bay Gravity floor (PCC) done in presence of Client & PSS Team.
33/100
Instream Storage Structure, Khalpal
Concreting M20A20 of LHS sluice Bay Gravity floor (PCC) is under progress in presence of Client & PSS Team.
34/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 90 mm) of Middle Cut-off barrage bay No-2 done in presence of Client & PSS Team.
35/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Middle Cut-off barrage bay No-2 is under progress in presence of Client & PSS Team.
36/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 90 mm) of Pier No-22, 1st lift done in presence of Client & PSS Team.
37/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-22, 1st lift is under progress in presence of Client & PSS Team.
38/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay Raft casting(M25 A20) work is in progress at Baitarani ISS.
39/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 02.04.2026
40/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 02.04.2026
41/100
Instream Storage Structure, Gudvella
Mechanical work is in progress on 02.04.2026
42/100
Instream Storage Structure, Gudvella
Reinforcement & shuttering work underprogress at A2 d/s wing wall for final lift RCC on 02.04.2026
43/100
Instream Storage Structure, Gudvella
Curing at building area on 02.04.2026
44/100
Instream Storage Structure, Gudvella
Reinforcement work of 1st floor column is under progress at building area on 02.04.2026
45/100
Instream Storage Structure, Gudvella
D/S view of ISS Gudvella on 01.04.2026
46/100
Instream Storage Structure, Gudvella
U/S view of ISS Gudvella on 01.04.2026
47/100
Instream Storage Structure, Gudvella
CC blocks shuttering work under progress on 01.04.2026
48/100
Instream Storage Structure, Gudvella
Reinforcement work is under progress at parapet wall of right side D/s wing wall on 01.04.2026
49/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A40 grade at U/S right divide wall raft bottom is in progress in presence of PM EPC agency,Site Engineer of PMC & EPC agency. The slump test value is 82mm on 02.04.2026
50/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A40 grade at U/S right divide wall raft bottom is in progress in presence of PM EPC agency,Site Engineer of PMC & EPC agency. The slump test value is 82mm on 02.04.2026
51/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no.7 is in progress in presence of PM EPC agency,Site Engineer of PMC & EPC agency. The slump test value is 84mm on 02.04.2026
52/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no.7 is in progress in presence of PM EPC agency,Site Engineer of PMC & EPC agency. The slump test value is 84mm on 02.04.2026
53/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.7&8 for 5th lift of bay-8 is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 81mm on 02.04.2026
54/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.7&8 for 5th lift of bay-8 is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 81mm on 02.04.2026
55/100
Instream Storage Structure, Nandagaon
• 4 (i) Excavation of raft foundation of U/S right divide wall is completed. (ii).Preparation of PCC bottom bed foundation for RCC raft is completed on finished well watered & compacted foundation base. (iii) The area is ready for concreting & passed by SE, KID, Bhwanipatna for placing with PCC M15A40 grade ISS Nandagaon on 02.04.2026
56/100
Instream Storage Structure, Nandagaon
• 3 (i).Fixing & fittings and alignment of All trestle and columns foundation bolts measurements has been checked at pier no.-7 for Blockout area of 6.8m length and found correct by HM Expert of PMC during his site visit on dt.19.03.2026 in presence of mechanical Site Engineers of PMC and EPC Agency. (ii) Rigid and smooth shuttering for Blockout area with M35A20 grade at pier no.-7 upto RL-247.00m are found completed. (iii).The area is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 02.04.2026
57/100
Instream Storage Structure, Nandagaon
• 2. Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay No.-8 of Pier No.7&8 for 5th lift have been checked and found correct by HM Expert of PMC during his site visit on dt.01.04.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs. (i) Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows: (ii) Chipping of old vertical concrete surface is done (iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 02.04.2026
58/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.8&9 for 4th lift of bay no.9 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 83mm on 02.04.2026
59/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.8&9 for 4th lift of bay no.9 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 83mm on 02.04.2026
60/100
Instream Storage Structure, Nandagaon
• 1. Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay No.-9 of Pier No.8&9 for 4th lift have been checked and found correct by HM Expert of PMC during his site visit on dt.01.04.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs. (i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows: (ii) Chipping of old vertical concrete surface is done. (iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 02.04.2026
61/100
Instream Storage Structure, Nandagaon
Gate no 14 both stoplog and barrage bay sil beam spirit level, water level and all measurements checked as per approved drawings. Hence ready for concrete on 02.04.2026
62/100
Instream Storage Structure, Nandagaon
Gate no 13 both barrage bay gate and stoplog gate 2nd stage embedded parts erection work under progress on 02.04.2026
63/100
Instream Storage Structure, Nandagaon
• 1).De-Shuttering is in progress at U/S right divide wall cut-off. 2). De-watering is in progress on 02.04.2026
64/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress at pier no.7 on 02.04.2026
65/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no.7&9 on 02.04.2026
66/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade for 2nd lift at U/S right divide wall cut-off is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 88mm on 01.04.2026
67/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade for 2nd lift at U/S right divide wall cut-off is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 88mm on 01.04.2026
68/100
Instream Storage Structure, Nandagaon
• 3.The area before placement of concrete at U/S right divide wall Cut-off foundation for 2nd lift has been checked and found ready during site visit of DTL, Tel Basin, QAC Expert, SHEE and Sr. Site Engineer of PMC as follows: (i)Reinforcement work in binding, tying, placing in proper position n spacing of vertical main & horizontal dist. bars are done. (ii) Rigid & smooth shuttering by providing clear cover of 75mm, measured from main bar to shutter plates are done. (iii) The surface area is cleaned properly through air water jetting and passed by SE, KID, Bhawanipatna on 01.04.2026
69/100
Instream Storage Structure, Nandagaon
• 2.Visited office building/ Control room area: (i) Foundation excavation is completed upto design depth. (ii) PCC has been completed with M15A40 grade with bed thickness of 100 mm on prepared well watered compacted bed surface. Marking for footing of columns is going on as per the approved drawing on 01.04.2026
70/100
Instream Storage Structure, Nandagaon
• Site visit of ISS, Nandagaon by DTL, Tel Basin Bhawanipatna today on dt. 01.04.2026 along with the QAC Expert, HME, SHEE and Sr. Site Engineer of PMC in presence of PM of EPC Agency, all Site Engineers of PMC n EPC Agency. 1.Visited the U/S right Divide wall foundation cutoff area and found the activities are seen as follows: (i) Reinforcement in binding, tying and proper placing of vertical main bar and dist. bar for 2nd. lift cutoff wall are completed and shuttering works is in progress and will be completed for placing concrete with RCC M25A20 grade by end of 2nd half on 01.04.2026
71/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion of 6.8m length at pier no.2&6 upto RL-247.00m is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 83mm on 01.04.2026
72/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion of 6.8m length at pier no.2&6 upto RL-247.00m is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 83mm on 01.04.2026
73/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.1& left abutment for 8th lift of undersluice bay-1 is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 84mm on 01.04.2026
74/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.1& left abutment for 8th lift of undersluice bay-1 is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 84mm on 01.04.2026
75/100
Instream Storage Structure, Nandagaon
• 2(i).Fixing & fittings and alignment of All trestle and columns foundation bolts measurements has been checked at pier no.-2&6 for Blockout area of 6.8m length and found correct by HM Expert of PMC during his site visit on dt.19.03.2026 in presence of mechanical Site Engineers of PMC and EPC Agency. (ii) Rigid and smooth shuttering for Blockout area with M35A20 grade at pier no.-2&6 upto RL-247.00m are found completed. (iii).The area is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 01.04.2026
76/100
Instream Storage Structure, Nandagaon
• 1.Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at under sluice bay No.-1 of Pier No.1& left abutment have been checked and found correct by HM Expert of PMC during his site visit on dt.19.03.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs. (i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows: (ii) Chipping of old vertical concrete surface is done. (iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 01.04.2026
77/100
Instream Storage Structure, Nandagaon
• 1) De-Shuttering is in progress at U/S right divide wall cut-off. 2) De-watering is in progress on 01.04.2026
78/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no.7,8&10 on 01.04.2026
79/100
Integrated Barrage across river Kochila and across river Baitarini
PMC team-Chandikhole inspecting the raft reinforcement at ISS Baitarani today-04.04.2026
80/100
Integrated Barrage across river Kochila and across river Baitarini
Barrage bay raft reinforcement fixing and shuttering work in progress at baitarani iss project.
81/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Left side under sluice steel placing work in progress.
82/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M20A20 (Value 80 mm) of Gravity floor done in presence of Client & PSS Team.
83/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 85 mm) of D/S Flank wall Cut-off done in presence of Client & PSS Team.
84/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of D/S Flank wall Cut-off is under progress in presence of Client & PSS Team.
85/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-15, 10th lift at Block No-3 done in presence of Client & PSS Team.
86/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-15, 10th lift at Block No-3 is under progress in presence of Client & PSS Team.
87/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of U/S Flank wall, Raft at Block No-1 done in presence of Client & PSS Team.
88/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of U/S Flank wall, Raft at Block No-1 is under progress in presence of Client & PSS Team.
89/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Gantry Girder No-11 done in presence of Client & PSS Team.
90/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-11 is under progress in presence of Client & PSS Team.
91/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.11/mm2 for 28 days) of Pier No-32, 15th lift and M35A20 (Strength is 42.34/mm2 for 28 days) of Deck slab (Bay No-25) and M15A40 (Strength is 20.74/mm2 for28 days) of D/S Flared wall (PCC) has done in presence of Client & PSS team.
92/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform No-1 assembly fit-up work is in progress.
93/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M25A20 (Value 85 mm) of Middle Pier, Final lift done in presence of Client & PSS Team.
94/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of Middle Pier, Final lift is under progress in presence of Client & PSS Team.
95/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 80 mm) of LHS D/S Counterfort & Wing wall, 2nd lift done in presence of Client & PSS Team.
96/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS D/S Counterfort & Wing wall, 2nd lift is under progress in presence of Client & PSS Team.
97/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Fish pass Raft at Block No-1 done in presence of Client & PSS Team.
98/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Fish pass Raft at Block No-1 is under progress in presence of Client & PSS Team.
99/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-16, 12th lift done in presence of Client & PSS Team.
100/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-16, 12th lift is under progress in presence of Client & PSS Team.