GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-18, 16th lift done in presence of Client & PSS Team.
2/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-18, 16th lift is under progress in presence of Client & PSS Team.
3/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.48/mm2 for 07 days) of Flank wall Raft and (Strength is 30.94/mm2 for 28 days) of Abutment (A1), 7th lift and M35A20 (Strength is 37.33/mm2 for 07 days) of Gantry Girder No-41 and M15A40 (Strength is 20.44/mm2 for 28 days) of Staff building foundation PCC and M30A20 (Strength is 37.78/mm2 for 28 days) of Groove 2nd stage (Bay No-8) has done in presence of Client & PSS team.
4/100
Instream Storage Structure, Hamirpur
C.D.U frame drilling work is in progress.
5/100
Instream Storage Structure, Hamirpur
C.D.U frame welding work is in progress.
6/100
Instream Storage Structure, Hamirpur
R.D.U fit-up work is in progress.
7/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Gantry Girder is under progress.
8/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-25, 14th lift is under progress.
9/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-17, 16th lift is under progress.
10/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall, 3rd lift at Block No-5 is under progress.
11/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall, 8th lift at Block No-5 is under progress.
12/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Present status of river Samakoi at Santeibhanja site.
13/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at Telkoi site.
14/100
Instream Storage Structure, Khalpal
Testing of Compressive M20A20 (Strength is 29.75/mm2 for 28 days) of Barrage Bay No-2 Gravity floor has done in presence of Client & PSS team.
15/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 56.15m.
16/100
Instream Storage Structure across river Sapei near village Kinjirma
View showing flow of river from D/S Side (D/S of River) . * Flow direction is straight flow is seen at RL- 207.250 against crest level RL- 206.250 . * Water is flowing 1m above the crest level .
17/100
Instream Storage Structure across river Sapei near village Kinjirma
U/S view No ancillary work today.
18/100
Instream Storage Structure across river Sapei near village Kinjirma
U/S site view No ancillary work today.
19/100
Instream Storage Structure across river Sapei near village Kinjirma
U/S site view No ancillary work .
20/100
Instream Storage Structure, Kopsinga
Work is stop due to heavy rain fall ISS Kopsingha site Water level -215.700 against crest level-215.100
21/100
Instream Storage Structure, Kopsinga
Double storied building slab shuttering work under progress
22/100
Instream Storage Structure, Kopsinga
Double storied building column Reinforcement with shuttering work under progress
23/100
Instream Storage Structure, Kopsinga
Water level -215.600 against crest level-215.100
24/100
Instream Storage Structure, Kopsinga
Double storied building FIRST FLOOR Roof slab shuttering work is under progress
25/100
Instream Storage Structure, Kopsinga
Control building column reinforcement with shuttering work is under progress
26/100
Instream Storage Structure, Kopsinga
Double storied building column reinforcement with shuttering work under progress
27/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Railling fixing work is in progress of Hoist-bridge
28/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Bracket fixing work is in progress of Barrage gates
29/100
Instream Storage Structure, Kopsinga
Double storied building Roof beam with slab shuttering work under progress
30/100
Instream Storage Structure, Kopsinga
Double stored building roof beam with slab shuttering work under progress
31/100
Instream Storage Structure, Kopsinga
Control building brick work under progress
32/100
Instream Storage Structure, Kopsinga
SS Kopsingha - Chakkar plate fixing work is in progress of Hoist-bridge
33/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Bracket fixing work is in progress of Barrage gates
34/100
Instream Storage Structure, Kudabega
View of the river from D/S. Water level R/L -206.980
35/100
Instream Storage Structure, Kudabega
Binding of steel of control room at Belaigarh
36/100
Instream Storage Structure, Kudabega
Tree demarcation of road at Bilaigarh
37/100
Instream Storage Structure, Kudabega
Stone Boulder pitching of us afflux bund
38/100
Instream Storage Structure, Kudabega
Water level 206.830m
39/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Top Guide fixing work is in progress of Barrage gates
40/100
Instream Storage Structure, Kudabega
Rod binding work of control room Building in progress
41/100
Instream Storage Structure, Kudabega
Stone Boulder packing of us afflux bund, left side
42/100
Instream Storage Structure, Kudabega
Stone pitching of left side Afflux bund
43/100
Instream Storage Structure, Kudabega
Steel binding work in progress of controll room Building
44/100
Instream Storage Structure, Kudabega
RHS Site control building slab shuttering & reinforcement work in progress
45/100
Instream Storage Structure, Kudabega
Slump 75mm
46/100
Instream Storage Structure, Kudabega
Slump 80mm
47/100
Instream Storage Structure, Kudabega
barrage bay-01 & 02 D/S & U/S wearing coat casting work in progress
48/100
Instream Storage Structure, Gudvella
Erection of stoplog gate is under progress at site on 06.07.2026
49/100
Instream Storage Structure, Gudvella
Plastering work is under progress at building area on 06.07.2026
50/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 06.07.2026
51/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 06.07.2026
52/100
Instream Storage Structure, Nandagaon
No activity due to rainfall on 06.07.2026
53/100
Instream Storage Structure, Nandagaon
Erection work has been stopped due to heavy rainfall on 06.07.2026
54/100
Instream Storage Structure, Dhanei
Outer side plastering of the O&M building in progress.
55/100
Instream Storage Structure, Dhanei
Sand blasting of hoist bridges in progress.
56/100
Instream Storage Structure, Dhanei
Dewatering is under progress in the under sluice bay.
57/100
Instream Storage Structure, Dhanei
The TPSODL team visited ISS, Sanabaragam site today for a joint site inspection in connection with the proposed new electricity connection and the shifting of the existing electric poles from the afflux bund side.
58/100
Instream Storage Structure, Dhanei
The TPSODL team visited ISS, Sanabaragam site today for a joint site inspection in connection with the proposed new electricity connection and the shifting of the existing electric poles from the afflux bund side.
59/100
Instream Storage Structure, Dhanei
Priming work of mechanical items ongoing.
60/100
Instream Storage Structure, Dhanei
O&M building plastering ongoing
61/100
Instream Storage Structure, Dhanei
1st lift secondary concreting of the under sluice bay guide channel casted.
62/100
Instream Storage Structure, Dhanei
1st lift secondary concreting of the under sluice bay guide channel casted.
63/100
Instream Storage Structure, Dhanei
Visit of SD Expert to the Sarpanch of Nimina Gram Panchayat(Sri Tapasa Sahu) and briefed him about the ISS Sanabaragrama project. I informed him about the minimum land required for the project and sought his cooperation in facilitating the successful conduct of the Palli Sabha for the land acquisition process. The Sarpanch responded positively and assured his full cooperation and support in the matter
64/100
Instream Storage Structure, Budharaja
The flow level is 207.050 m against the design RL: 206.700, i.e., 0.350 m flood lif
65/100
Instream Storage Structure, Budharaja
Staff Quarter plastering work is in Progress.
66/100
Instream Storage Structure, Budharaja
View showing flow of river from U/S of river.
67/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S of river.
68/100
Instream Storage Structure, Dhanei
Today, I visited the Block Development Officer, Polasara (Sri Sashibhusan Mahapatra, OAS), and apprised him of the ISS Sanabaragrama project. I informed him about the BDO's initiative in requesting the concerned Sarpanch to organize the Palli Sabha for land acquisition related to the project and sought his cooperation in the matter. The BDO responded positively and assured that he would extend the necessary cooperation as soon as he receives the official communication from the Department of Water Resources (DoWR).
69/100
Instream Storage Structure, Gochara
No work activity at Site due to heavy rain.
70/100
Instream Storage Structure, Dhanei
Guide channel, Track and Side sill on Under sluice both Service and Stoplog groove placement and alignment work done.
71/100
Instream Storage Structure, Dhanei
Guide channel, Track and Side sill on Under sluice both Service and Stoplog groove placement and alignment work done.
72/100
Instream Storage Structure, Dhanei
Guide channel, Track and Side sill on Under sluice both Service and Stoplog groove placement and alignment work done.
73/100
Instream Storage Structure, Dhanei
O&M building plastering work is ongoing
74/100
Instream Storage Structure, Dhanei
After dewatering the guide channel fixation for the under sluice bay resumed
75/100
Instream Storage Structure, Dhanei
After dewatering the guide channel fixation for the under sluice bay resumed
76/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. The flow level is 225.650mt against design crest level 225.500 i.e. flood lift 0.150mt.
77/100
Instream Storage Structure, Gochara
View showing flow of river from U/S of river.
78/100
Instream Storage Structure, Dhanei
DP test in welding portion of Barrage and Under sluice Gate check done
79/100
Instream Storage Structure, Dhanei
DP test in welding portion of Barrage and Under sluice Gate check done
80/100
Instream Storage Structure, Dhanei
DP test in welding portion of Barrage and Under sluice Gate check done
81/100
Instream Storage Structure, Dhanei
DP test in welding portion of Barrage and Under sluice Gate check done
82/100
Instream Storage Structure, Dhanei
DP test in welding portion of Barrage and Under sluice Gate check done
83/100
Instream Storage Structure, Gochara
View showing flow of river from D/S of river.
84/100
Instream Storage Structure, Dhanei
Dewatering under progress for sluice bay guide channel installation.
85/100
Instream Storage Structure, Dhanei
Pipe laying work is ongoing for the second inlet.
86/100
Instream Storage Structure, Gochara
Staff quarter 1st floor out side brick wall work in progress....
87/100
Instream Storage Structure, Gochara
View showing flow of river from U/S of river.
88/100
Instream Storage Structure, Gochara
View showing flow of river from D/S of river.
89/100
Instream Storage Structure, Dhanei
Visit of AEE of Dept., DyTL and SD Expert of PMC to the ISS site. Inspected the overall progress of site.
90/100
Instream Storage Structure, Dhanei
Visit of AEE of Dept., DyTL and SD Expert of PMC to the ISS site. Inspected the overall progress of site.
91/100
Instream Storage Structure, Dhanei
Visit of AEE of Dept., DyTL and SD Expert of PMC to the ISS site. Inspected the overall progress of site.
92/100
Instream Storage Structure, Dhanei
Prime coating work in progress
93/100
Instream Storage Structure, Dhanei
Sand blasting of trestle column in progress
94/100
Instream Storage Structure, Dhanei
Second inlet work in progress
95/100
Instream Storage Structure, Dhanei
Second inlet work in progress
96/100
Instream Storage Structure, Dhanei
2nd lift of headwall completed.
97/100
Instream Storage Structure, Dhanei
Head wall second lift shuttering in progress
98/100
Instream Storage Structure, Dhanei
Second stage embedded part installation in progress on U/S gate groove
99/100
Instream Storage Structure, Dhanei
1st lift of inlet head walls completed.
100/100
Instream Storage Structure, Dhanei
After flipping over Barrage Bay and Under-sluice Bay gate welding work in progress.

Enter Login Details

Forgot Password ?