GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site. Water level RL 59.100m.
2/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site. Water level RL 193.400m.
3/100
Instream Storage Structure, Hamirpur
SDE visited S.E, RID office, Rourkela and discussed with A.E, RID and representative of EPC agency on the progress of land acquisition. Also contacted with Tahasildar, Kuanramunda at his office along with A.E, RID to expedite the land alienation proposal submitted.
4/100
Instream Storage Structure, Hamirpur
Shuttering of Abutment wall (A2), 11th lift at Block No-5 is under progress.
5/100
Instream Storage Structure, Hamirpur
Shuttering of Girder No-26 is under progress.
6/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Girder No-23 is under progress.
7/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Girder No-24 & 25 is under progress.
8/100
Instream Storage Structure, Kuakhai
SDO, Balianta, Manager, OCCL along with PSS Team observing the flood situation of River.
9/100
Instream Storage Structure, Kuakhai
The 1st flood water passes through the structure.
10/100
Instream Storage Structure, Kuakhai
Backfilling activities in progress.
11/100
Instream Storage Structure, Kuakhai
SE, Prachi discussing with the Agency to take immediate required measures for protection and to avoid further erosion of slope.
12/100
Instream Storage Structure, Kuakhai
SE, Prachi along with SDO, Balianta inspecting the ongoing back filling work.
13/100
Instream Storage Structure, Kuakhai
Back filling on right side under sluice in progress.
14/100
Instream Storage Structure, Kuakhai
SE, Prachi inspecting the ongoing shifting of machineries and materials at site.
15/100
Instream Storage Structure, Kuakhai
Irr. Expert, PSS verifying the gradient at R/S Undersluice.
16/100
UGPL, Left Lower Suktel Canal Division
PLC panel Instrumentation Cable dressing and Glanding work is in progress at PLC Room of Pump House.
17/100
Instream Storage Structure, Kuakhai
Shifting of materials and machineries from worksite due to flood urgent.
18/100
Instream Storage Structure, Kuakhai
Glacis top concrete finishing work is currently under progress.
19/100
Instream Storage Structure, Kuakhai
Concreting work is going on at R/s under sluice raft.
20/100
Instream Storage Structure, Kuakhai
Ongoing concrete laying in Zone-3, glacis top at R/S Under sluice.
21/100
Instream Storage Structure, Kuakhai
Casting of RCC M30A20 in right under sluice raft (zone-1 to 3) including slope portion from RL 7.25m to RL 8.35m in progress.
22/100
Instream Storage Structure, Kuakhai
DTL, MKS with Irr. expert & Manager, OCCL discussing regarding the timely completion of the final layer concrete work at the right side undersluice.
23/100
Instream Storage Structure, Kuakhai
Casting of RCC M30A20 in R/s under sluice raft (Zone-1 & 2, final layer) is completed.
24/100
UGPL, Left Lower Suktel Canal Division
Boundary wall column reinforcement binding & shuttering work is in progress in presence of PMC team of Pump House.
25/100
Instream Storage Structure, Kuakhai
Ongoing concreting work at R/s under sluice raft (zone-1 & 2, final layer).
26/100
Instream Storage Structure, Kushabhadra
7 days and 28 days cube test for CC M25A20 done at field laboratory of ISS. Average compressive strengths are 22.30N/mm2 and 32.08N/mm2.
27/100
Instream Storage Structure, Kushabhadra
SE, Prachi inspecting the ongoing works at site.
28/100
Instream Storage Structure, Kushabhadra
7 days cube test for CC M20A20 & 28 days cube test for CC M-25A20 done at field laboratory of the ISS.
29/100
Instream Storage Structure, Kushabhadra
Left U/S abutment & counter-fort concrete laying from RL 21.90m to 22.90m is under progress.
30/100
Instream Storage Structure, Kushabhadra
7 days cube test for CC M25A20 and 28 days cube test for CC M25A20 conducted at field laboratory of the ISS.
31/100
Instream Storage Structure, Kushabhadra
Shuttering of Deck Slab in between pier no.1 & 2 in progress.
32/100
Instream Storage Structure, Kushabhadra
Right D/S flank wall shuttering work in progress.
33/100
Instream Storage Structure, Kushabhadra
Deck slab shuttering in between pier no.1 & 2 in progress.
34/100
Instream Storage Structure, Kushabhadra
Left D/S flared out wall balance cut-off area excavation work in progress.
35/100
Instream Storage Structure, Kushabhadra
Left D/S flank wall concrete laying from RL12.70m to 14.10m ( Sec.A-A to A-A) in progress.
36/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 83mm) of Girder No-22 done in presence of Client & PSS Team.
37/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Girder No-22 is under progress in presence of Client & PSS Team.
38/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85mm) of Girder No-21 done in presence of Client & PSS Team.
39/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Girder No-21 is under progress in presence of Client & PSS Team.
40/100
Instream Storage Structure, Hamirpur
Curing of Girders is under progress.
41/100
Instream Storage Structure, Hamirpur
Shuttering of Abutment wall (A2), 11th lift at Block No-5 is under progress.
42/100
Instream Storage Structure, Hamirpur
Shuttering of Girder No-23 is under progress.
43/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Girder No-23 is under progress.
44/100
Instream Storage Structure, Jharbeda
Inflow of Storm water in the River at ISS Jharbeda.
45/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site.Water level RL 58.200m.
46/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.37/mm2 for 28 days) of Pier No-10, 2nd lift and M15A40(Strength is 20.69/mm2 for 28 days) of Flank wall Raft at Block No-5 and M25A20 (Strength is 21.78/mm2 for 28 days) of Abutment wall (A2), 9th lift at Block No-5 has done in presence of Client & PSS team.
47/100
Instream Storage Structure, Hamirpur
De-Shuttering of Abutment wall (A2), 10th lift is under progress.
48/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Girder No-24 is under progress.
49/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Girder No-22 & 23 is under progress.
50/100
Instream Storage Structure, Hamirpur
Shuttering of Girder No-21 is under progress.
51/100
Instream Storage Structure, Jharbeda
Inflow of Storm water in the River at ISS Jharbeda.
52/100
Instream Storage Structure, Sirigida
Consultation meeting held with prospective land loosers by Sub-Collector, Talcher, Tahasildar, Talcher and R.I, Godibandha in presence of S.E, A.E.E, A.E, AID and Dy. TL & SDE of PSS to obtain the consent of land owners to finalise the DCAC proposal.
53/100
Instream Storage Structure, Gudvella
Reinforcement at left side u/s flank wall including returning wall for 3rd lift RCC work is under progress on 06.07.2025
54/100
Instream Storage Structure, Gudvella
Trestle base plate welding work under progress on 05.07.2025
55/100
Instream Storage Structure, Gudvella
1. Reinforcement & shuttering work is under progress at left side d/s wing wall for 5th lift RCC. 2. Reinforcement & shuttering work is under progress at left side d/s flank wall for 2nd lift RCC on 05.07.2025
56/100
Instream Storage Structure, Nandagaon
Centring & Shuttering for RCC deck slab at span-2 of under sluice bay, Block-1 is in progress on 06.07.2025
57/100
Instream Storage Structure, Nandagaon
Reinforcement binding of RCC main girder is in progress on 06.07.2025
58/100
Instream Storage Structure, Nandagaon
Reinforcement binding, centring & Shutteringat pier no. 7, Block-2 is in progress on 06.07.2025
59/100
Instream Storage Structure, Nandagaon
Reinforcement binding, centring & Shuttering at pier no. 7, Block-2 is in progress on 05.07.2025
60/100
Instream Storage Structure, Nandagaon
Centring & Shuttering for RCC deck slab at span-2 of under sluice bay, Block-1 is in progress on 05.07.2025
61/100
Instream Storage Structure, Nandagaon
Curing of RCC deck slab at Span-1 of under sluice bay,Block-1 is in progress on 05.07.2025
62/100
Instream Storage Structure, Mahulpali
D/S view of ISS Mahulpali on 06.07.2025
63/100
Instream Storage Structure, Mahulpali
U/S view of ISS Mahulpali on 06.07.2025
64/100
Instream Storage Structure, Mahulpali
D/S view of ISS Mahulpali on 05.07.2025
65/100
Instream Storage Structure, Mahulpali
U/S view of ISS Mahulpali on 05.07.2025
66/100
Instream Storage Structure, Chhatamakhana
D/S view of the ISS Chhatamakhana on 06.07.2025
67/100
Instream Storage Structure, Chhatamakhana
U/S view of the ISS Chhatamakhana on 06.07.2025
68/100
Instream Storage Structure, Chhatamakhana
D/S view of the ISS Chhatamakhana on 05.07.2025
69/100
Instream Storage Structure, Chhatamakhana
U/S view of the ISS Chhatamakhana on 05.07.2025
70/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site.
71/100
Instream Storage Structure, KansariGanda
Visit of Irrigation Eng. Expert along with Site Engineer to the ISS Site. Inspected the Pier No.-1 and pier no.-3, 1st lift Reinforcement and Concreting work.
72/100
Instream Storage Structure, KansariGanda
Visit of Irrigation Eng. Expert along with Site Engineer to the ISS Site. Inspected the Pier No.-1 and pier no.-3, 1st lift Reinforcement and Concreting work.
73/100
Instream Storage Structure, KansariGanda
Visit of Irrigation Eng. Expert along with Site Engineer to the ISS Site. Inspected the Pier No.-1 and pier no.-3, 1st lift Reinforcement and Concreting work.
74/100
Instream Storage Structure, KansariGanda
Visit of Irrigation Eng. Expert along with Site Engineer to the ISS Site. Inspected the Pier No.-1 and pier no.-3, 1st lift Reinforcement and Concreting work.
75/100
Barrage across river Turi & Guntat
Guntat site status.
76/100
Barrage across river Turi & Guntat
Turi site status.
77/100
Instream Storage Structure, Budharaja
The flow level is 208.700 m against the design RL: 206.700, i.e., 2.0 m flood lift.
78/100
Instream Storage Structure, Khirasasan
The flow level is 211.700 m against the design RL: 210.900, i.e., 0.8 m flood lift.
79/100
Instream Storage Structure, Kopsinga
Cube test iss Kopsingha
80/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. Flow direction is straight. The direction of flow is seen in middle of the river. Now the flow level is 226.500mt against design crest level 225.500 i.e. flood lift 1mt.
81/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-215.900 mtr against design crest level RL- 215.000 mtr .i.e 0.9mtr flood lift .
82/100
UGPL, Right Lower Suktel Canal Division
Visited JE(DoWR) along with PMC team 300mm Dia DI ( k7) pipe laying Gap closing work is in progress At Village Chhtamakhana J-2548 to J-2551.
83/100
UGPL, Right Lower Suktel Canal Division
Instrumentation Cable laying work is in progress at free filtration unit of Pump House.
84/100
UGPL, Right Lower Suktel Canal Division
225mm thickness rubbles filling work is in progress at fire fighting system before grade slab casting in presence of PMC team at Pump House.
85/100
UGPL, Left Lower Suktel Canal Division
Pressure indicating transmitter Instrumentation Cable (1p×1sq.mm) Glanding work is in progress at left Pump House.
86/100
UGPL, Left Lower Suktel Canal Division
DPI (differential pressure switch) , pressure gauge and its isolation valve installation work is in progress in FWLS (force water lubrication system) of VT pumps at left Pump House.
87/100
UGPL, Left Lower Suktel Canal Division
Boundary wall column 2nd lift reinforcement binding work & shuttering work is in progress at left Pump House.
88/100
UGPL, Left Lower Suktel Canal Division
Approach channel front side soil excavation work is in progress at Pump House.
89/100
Instream Storage Structure, Dhanei
Visit of Irrigation Eng. Expert along with Site Engineer to the ISS Site. Inspected the Road bridge kerb parapet reinforcement and shuttering alignment check.
90/100
Instream Storage Structure, Dhanei
Visit of Irrigation Eng. Expert along with Site Engineer to the ISS Site. Inspected the Road bridge kerb parapet reinforcement and shuttering alignment check.
91/100
Instream Storage Structure, KansariGanda
Under sluice End seal final layer shutter is in progress. Curing continuing at site.
92/100
Instream Storage Structure, KansariGanda
Under sluice End seal final layer shutter is in progress. Curing continuing at site.
93/100
Instream Storage Structure, KansariGanda
Cube cast at site.
94/100
Instream Storage Structure, Gudvella
Trestle base plate welding work under progress on 04.07.2025
95/100
Instream Storage Structure, KansariGanda
Curing continuing at site.
96/100
Instream Storage Structure, Gudvella
1. Reinforcement at left side u/s wing wall including 2nos of counter fort wall for 6th lift RCC work is under progress. 2. Deshuttering work at left side u/s flank wall including returning wall is under progress on 04.07.2025
97/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site.
98/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert along with Site Engineer to the ISS Site. Inspected the End seal concrete casting.
99/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert along with Site Engineer to the ISS Site. Inspected the End seal concrete casting.
100/100
Instream Storage Structure, Nandagaon
Centring & Shuttering for RCC deck slab at span-2 of under sluice bay, Block-1 is in progress on 04.07.2025

Enter Login Details

Forgot Password ?