1/100
UGPL, Right Lower Suktel Canal Division
Reservoir water level at RL 201.570m
2/100
Instream Storage Structure, Gudvella
Placement of filler material is under progress before placing of building tiles on 29.07.2026
3/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 29.07.2026
4/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 28.07.2026
5/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 28.07.2026
6/100
Instream Storage Structure, Nandagaon
No work, due to heavy rain on 29.07.2026
7/100
Instream Storage Structure, Dhanei
Fixation of Anchor Bolts in Trestle blockout is in progress in presence of QA/QC expert along with site engineer mechanical.
8/100
Instream Storage Structure, Dhanei
Fixation of Anchor Bolts in Trestle blockout is in progress in presence of QA/QC expert along with site engineer mechanical.
9/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of 8nos. Post at deck slab no. 14 right side is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 83mm on 28.07.2026
10/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of 8nos. Post at deck slab no. 14 right side is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 83mm on 28.07.2026
11/100
Instream Storage Structure, Nandagaon
Hoist bridge erection work under progress over 1st under sluice gate on 28.07.2026
12/100
Instream Storage Structure, Dhanei
One side sand blasting and colouring of all three gates completed.
13/100
Instream Storage Structure, Dhanei
One side sand blasting and colouring of all three gates completed.
14/100
Instream Storage Structure, Nandagaon
Stone pitching work at U/S right embankment is in progress on 28.07.2026
15/100
Instream Storage Structure, Nandagaon
De-Shuttering & Shuttering for CC block at U/S left flared out wall on 28.07.2026
16/100
Instream Storage Structure, Dhanei
Inside and outside plastering completed of the O&M building.
17/100
Instream Storage Structure, Dhanei
Secondary concreting of the Under sluice bay achieved RL 56.9 meter out of 57.3 meter on sluice bay. 28.07.26
18/100
Instream Storage Structure, Gudvella
Placement of aggregate around transformer area is under progress on 27.07.2026
19/100
Instream Storage Structure, Dhanei
Palli Sabha meetings were conducted on 21.07.2026 at 11:00 AM in Nimina Village and at 2:00 PM in Sanabaragam Village. The required quorum was duly achieved in both meetings.
The meetings were attended by the BDO and WEO, Polasara Block, Sarpanch,PEO, Zilla Parishad Member,Ward Members of Nimina Gram Panchayat, the majority of the identified land losers, the SDO and AE from the department, as well as the Social Development Expert from the PMC.
20/100
Instream Storage Structure, Dhanei
Palli Sabha meetings were conducted on 21.07.2026 at 11:00 AM in Nimina Village and at 2:00 PM in Sanabaragam Village. The required quorum was duly achieved in both meetings.
The meetings were attended by the BDO and WEO, Polasara Block, Sarpanch,PEO, Zilla Parishad Member,Ward Members of Nimina Gram Panchayat, the majority of the identified land losers, the SDO and AE from the department, as well as the Social Development Expert from the PMC.
21/100
Instream Storage Structure, Dhanei
Palli Sabha meetings were conducted on 21.07.2026 at 11:00 AM in Nimina Village and at 2:00 PM in Sanabaragam Village. The required quorum was duly achieved in both meetings.
The meetings were attended by the BDO and WEO, Polasara Block, Sarpanch,PEO, Zilla Parishad Member,Ward Members of Nimina Gram Panchayat, the majority of the identified land losers, the SDO and AE from the department, as well as the Social Development Expert from the PMC.
22/100
Instream Storage Structure, Dhanei
Palli Sabha meetings were conducted on 21.07.2026 at 11:00 AM in Nimina Village and at 2:00 PM in Sanabaragam Village. The required quorum was duly achieved in both meetings.
The meetings were attended by the BDO and WEO, Polasara Block, Sarpanch,PEO, Zilla Parishad Member,Ward Members of Nimina Gram Panchayat, the majority of the identified land losers, the SDO and AE from the department, as well as the Social Development Expert from the PMC.
23/100
Instream Storage Structure, Dhanei
Palli Sabha meetings were conducted on 21.07.2026 at 11:00 AM in Nimina Village and at 2:00 PM in Sanabaragam Village. The required quorum was duly achieved in both meetings.
The meetings were attended by the BDO and WEO, Polasara Block, Sarpanch,PEO, Zilla Parishad Member,Ward Members of Nimina Gram Panchayat, the majority of the identified land losers, the SDO and AE from the department, as well as the Social Development Expert from the PMC.
24/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 27.07.2026
25/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 27.07.2026
26/100
Instream Storage Structure, Dhanei
Secondary concreting of the guide channel achieved 55.3 meter on Sluice bay. 17.07.26
27/100
Instream Storage Structure, Dhanei
Secondary concreting of the guide channel achieved 55.3 meter on Sluice bay. 17.07.26
28/100
Instream Storage Structure, Dhanei
Secondary concreting achieved RL 53.7meter out of 57.3 meter on Sluice bay
29/100
Instream Storage Structure, Gudvella
Due to heavy rainfall, no work is going on on 26.07.2026
30/100
Instream Storage Structure, Dhanei
Sand blasting and Priming of the gates ongoing at site.
31/100
Instream Storage Structure, Gudvella
The installation of barbed wire fencing with angle posts around the transformer area is in progress on 25.07.2026
32/100
Instream Storage Structure, Dhanei
Visit of DTL, IEE including Site Engineers to this Site.
Sluice Bay Stop log & Service gate groove 2nd stage Shuttering is continuing
33/100
Instream Storage Structure, Dhanei
Visit of DTL, IEE including Site Engineers to this Site.
Sluice Bay Stop log & Service gate groove 2nd stage Shuttering is continuing
34/100
Instream Storage Structure, Gudvella
Adjustment of rubber seal of mechanical gate is under progress at site on 25.07.2026
35/100
Instream Storage Structure, Gudvella
Curing of wearing coat at deck slab is under progress at site on 25.07.2026
36/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 25.07.2026
37/100
Instream Storage Structure, KansariGanda
Work stop due to heavy rainfall. 28.07.26
38/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 25.07.2026
39/100
Instream Storage Structure, KansariGanda
RHS GIRDER NO 40 RAINFORCEMENT BINDING CHECK AND AFTER THAT CONCRETING IS IN PROGRESS IN PRESENCE OF SITE ENGINEER PMC.
40/100
Instream Storage Structure, KansariGanda
RHS GIRDER NO 40 RAINFORCEMENT BINDING CHECK AND AFTER THAT CONCRETING IS IN PROGRESS IN PRESENCE OF SITE ENGINEER PMC.
41/100
Instream Storage Structure, Nandagaon
Concrete casting with M20A20 grade of CC block at U/S left flared out wall is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 83mm on 27.07.2026
42/100
Instream Storage Structure, Nandagaon
Concrete casting with M20A20 grade of CC block at U/S left flared out wall is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 83mm on 27.07.2026
43/100
Instream Storage Structure, Nandagaon
• 1.The casting of the CC block at the following area has been checked in the presence of PM, EPC agency, Site Engineers of PMC & EPC Agency:
(i) Shuttering for CC block at U/S left flared out wall of 27.75m length & 0.6m ht. from RL-244.80m to RL-245.40m is completed.
(ii). Filling of inverted filter materials covering with LDPE paper at adjacent to each CC block in earth side are done before placement.
(iii) Application of 2 coat bitumen paint at cj's concrete surface is done.
(iv). Area is ready and passed by SE KID, Bh. Patna to place concrete with PCC M20A20 grade on 27.07.2026
44/100
Instream Storage Structure, Nandagaon
Stone pitching work at U/S right embankment is in progress on 27.07.2026
45/100
Instream Storage Structure, KansariGanda
Gurder No 39 concreting in progress and slump cone test conducted at site in presence of Irr. Eng. Expert along with site engineer PMC
46/100
Instream Storage Structure, KansariGanda
Gurder No 39 concreting in progress and slump cone test conducted at site in presence of Irr. Eng. Expert along with site engineer PMC
47/100
Instream Storage Structure, Nandagaon
Shuttering for CC block is in progress at U/S left flared out wall on 27.07.2026
48/100
Instream Storage Structure, KansariGanda
24.07.26- Water Level RL 2.70 mt
49/100
Instream Storage Structure, KansariGanda
24.07.26- Water Level RL 2.70 mt
50/100
Instream Storage Structure, KansariGanda
23.07.26- Water level 2.5
51/100
Instream Storage Structure, Nandagaon
Work stopped due to heavy rainfall on 26.07.2026
52/100
Instream Storage Structure, KansariGanda
22.07.26- Water level 2.2
53/100
Instream Storage Structure, KansariGanda
22.07.26- Water level 2.2
54/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of 8nos. Post at deck slab no. 4 left side is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 85mm on 25.07.2026
55/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade of 8nos. Post at deck slab no. 4 left side is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 85mm on 25.07.2026
56/100
Instream Storage Structure, KansariGanda
Gramakantha Settlement (Khatiaramachandrapur): Two stakeholders have yet to submit their settlement applications. The RI, Panibandha has assured that the settlement proceedings will be processed in accordance with the applicable rules upon receipt of the requisite applications from the concerned stakeholders
57/100
Instream Storage Structure, KansariGanda
22.07.26 -Water level 2.00
58/100
Instream Storage Structure, Nandagaon
Stone pitching work at U/S right embankment is in progress on 25.07.2026
59/100
Instream Storage Structure, KansariGanda
palli Sabha on 21.07.2026 at Barada village Sidheswar thakura Pujari committee ,in the presence Dep staff and agency.
60/100
Instream Storage Structure, KansariGanda
21.07.26
61/100
Instream Storage Structure, Nandagaon
De-Shuttering & Shuttering for CC block at U/S left flared out wall on 25.07.2026
62/100
Instream Storage Structure, KansariGanda
Water level 2.1
63/100
Instream Storage Structure, KansariGanda
Water level 2.1
64/100
Instream Storage Structure, KansariGanda
Water level 2.1
65/100
Instream Storage Structure, KansariGanda
Girder NO 37 concrete pouring is progress in presence of Irr. Eng. Expert along with site engineer PMC.
66/100
Instream Storage Structure, KansariGanda
18.07.26
67/100
Instream Storage Structure, KansariGanda
2nd palli Sabha on 17.07.2026 at Raulibandha in the presence of Tahasildar,Addl Tahasildar,BDO,ABDO ,Ganjam alongwith Sarapancha,PEO,Ward members of the Malada GP.
68/100
Instream Storage Structure, KansariGanda
2nd palli Sabha on 17.07.2026 at Raulibandha in the presence of Tahasildar,Addl Tahasildar,BDO,ABDO ,Ganjam alongwith Sarapancha,PEO,Ward members of the Malada GP.
69/100
Instream Storage Structure, KansariGanda
17.07.26
70/100
Instream Storage Structure, KansariGanda
Water Level RL 1.90
71/100
Instream Storage Structure, KansariGanda
.
72/100
Instream Storage Structure, KansariGanda
A meeting with temple land beneficiaries (ISS Kansariganda)conducted at Sidheswara temple campus for acquiring temple land.However,due to rain only few members gathered.So,it is decided to conduct next time.Tentatively 21.7.2026 is fixed for the meeting.
73/100
Instream Storage Structure, Hamirpur
Shuttering of Gantry Girder is under progress.
74/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
75/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall, 5th lift at Block No-5 is under progress.
76/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for U/S Flank wall, 12th lift at Block No-5 is under progress.
77/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly no-1 Shaft fixing work is in progress for C.D.U to R.D.U.
78/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 181.310m.
79/100
Instream Storage Structure, Khalpal
Observed of Sieve analysis of Coarse aggregate and Fine aggregate in presence of Client & PSS team along with EPC agency.
80/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 61.9m.
81/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Present status of river Samakoi at Santeibhanja site.
82/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at Telkoi site.
83/100
Barrage across river Turi & Guntat
Site Visit of Chief Engineer along with Additional Chief Engineer, Superintending Engineer Nabarangapur and other staffs to Turi -Guntat Irrigation Project on 28th July.
84/100
Barrage across river Turi & Guntat
Site Visit of Chief Engineer along with Additional Chief Engineer, Superintending Engineer Nabarangapur and other staffs to Turi -Guntat Irrigation Project on 28th July.
85/100
Barrage across river Turi & Guntat
Site Visit of Chief Engineer along with Additional Chief Engineer, Superintending Engineer Nabarangapur and other staffs to Turi -Guntat Irrigation Project on 28th July.
86/100
Instream Storage Structure, Gudvella
• Today SE Madam, SDO and JE from the Quality Assurance Division, Balangir visited the ISS Gudvella. During the inspection the departmental JE, PMC site engineers and the contractor's engineer were present.
The following quality inspections were carried out:
1. The team inspected the overall quality aspects of the project. A slump test was conducted in the field for the deck slab wearing coat concrete and the slump value was found to be 60 mm which is within the satisfactory range.
2. The thickness of the GSB layer was checked and found to be as per the approved design.
3. A NDT was conducted on the building slab and columns and the average compressive strength was found to be 37.83 N/mm² against the M25A20 RCC grade which is satisfactory.
4. Another NDT was conducted on the upstream flared out wall at A1 and the compressive strength was found to be 26 N/mm² against the M20A20 PCC grade which is satisfactory on 24.07.2026
87/100
Instream Storage Structure, Gudvella
• Today SE Madam, SDO and JE from the Quality Assurance Division, Balangir visited the ISS Gudvella. During the inspection the departmental JE, PMC site engineers and the contractor's engineer were present.
The following quality inspections were carried out:
1. The team inspected the overall quality aspects of the project. A slump test was conducted in the field for the deck slab wearing coat concrete and the slump value was found to be 60 mm which is within the satisfactory range.
2. The thickness of the GSB layer was checked and found to be as per the approved design.
3. A NDT was conducted on the building slab and columns and the average compressive strength was found to be 37.83 N/mm² against the M25A20 RCC grade which is satisfactory.
4. Another NDT was conducted on the upstream flared out wall at A1 and the compressive strength was found to be 26 N/mm² against the M20A20 PCC grade which is satisfactory on 24.07.2026
88/100
Instream Storage Structure, Gudvella
Finishing work (M25A20 PCC grade) at wearing coat of deck slab is under progress in the presence of Dept JE , site engineer of PMC and agency at site. The slump test value is 60mm on 24.07.2026
89/100
Instream Storage Structure, Gudvella
Finishing work (M25A20 PCC grade) at wearing coat of deck slab is under progress in the presence of Dept JE , site engineer of PMC and agency at site. The slump test value is 60mm on 24.07.2026
90/100
Instream Storage Structure, Gudvella
Curing of wearing coat at deck slab is under progress at site on 24.07.2026
91/100
Instream Storage Structure, Gudvella
Cast of concrete PCC M25A20 grade for wearing coat at deck slab is under progress in the presence of Dept JE, site engineers of PMC & agency at site The slump test value is 62mm on 23.07.2026
92/100
Instream Storage Structure, Gudvella
Cast of concrete PCC M25A20 grade for wearing coat at deck slab is under progress in the presence of Dept JE, site engineers of PMC & agency at site The slump test value is 62mm on 23.07.2026
93/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 23.07.2026
94/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 23.07.2026
95/100
Instream Storage Structure, Gudvella
Cast of concrete PCC M25A20 grade for wearing coat at span -10 is underprogress in the presence of Dept JE, site engineers of PMC n agency at site. The slump test value is 61mm on 22.07.2026
96/100
Instream Storage Structure, Gudvella
Cast of concrete PCC M25A20 grade for wearing coat at span -10 is underprogress in the presence of Dept JE, site engineers of PMC n agency at site. The slump test value is 61mm on 22.07.2026
97/100
Instream Storage Structure, Gudvella
• Today the Superintending Engineer, Electrical Division, Balangir, visited the ISS Gudvella project site. During the inspection, the Department JE, PMC Site Engineer and Agency Engineer were present.
1. He inspected the electrical installations, including the power cables, panel boards, control room, transformer and DG set. He expressed satisfaction with the quality and progress of the work. The inspection report will be submitted shortly. Also instructed to agency 8 numbers of earthing provided for gate.
2. Regarding the DG set, the Superintending Engineer clarified that a separate inspection report is not required for the installed DG set. Inspection reports are mandatory only for DG sets having a capacity of 500 kVA and above on 22.07.2026
98/100
Instream Storage Structure, Gudvella
• Today the Superintending Engineer, Electrical Division, Balangir, visited the ISS Gudvella project site. During the inspection, the Department JE, PMC Site Engineer and Agency Engineer were present.
1. He inspected the electrical installations, including the power cables, panel boards, control room, transformer and DG set. He expressed satisfaction with the quality and progress of the work. The inspection report will be submitted shortly. Also instructed to agency 8 numbers of earthing provided for gate.
2. Regarding the DG set, the Superintending Engineer clarified that a separate inspection report is not required for the installed DG set. Inspection reports are mandatory only for DG sets having a capacity of 500 kVA and above on 22.07.2026
99/100
Instream Storage Structure, Gudvella
Installation work of the shutter plate at the building area is under progress on 22.07.2026
100/100
Instream Storage Structure, Gudvella
Erection of stoplog gate is under progress at site on 22.07.2026
❮
❯