GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Gudvella
Stone pitching work at u/s side of A1 on 07.06.2026
2/100
Instream Storage Structure, Gudvella
Plastering work is in progress on 07.06.2026
3/100
Instream Storage Structure, Gudvella
Mechanical work is in progress on 07.06.2026
4/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 07.06.2026
5/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M20A20 (Value 80 mm) of RHS Gravity floor done in presence of Client & PSS Team.
6/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 07.06.2026
7/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-33 done in presence of Client & PSS Team.
8/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-33 is under progress in presence of Client & PSS Team.
9/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 80 mm) of Barrage Bay No-2 Gravity floor done in presence of Client & PSS Team.
10/100
Instream Storage Structure, Gudvella
• Visited SDO, AE at ISS Gudvella site. Department JE, Site engineers of PMC n agency were present 1. Checked all of the progress of the site. 2. Instructed to agency to complete the stone pitching work, gate work and building work before 15 June 2026 on 06.06.2026
11/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Barrage Bay No-2 Gravity floor is under progress in presence of Client & PSS Team.
12/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 80 mm) of RHS Double Pier No-25, 1st lift done in presence of Client & PSS Team.
13/100
Instream Storage Structure, Gudvella
Railing work is under progress at host bridge on 06.06.2026
14/100
Instream Storage Structure, Khalpal
Concreting M25A20 of RHS Double Pier No-25, 1st lift is under progress in presence of Client & PSS Team.
15/100
Instream Storage Structure, Gudvella
Plastering work is under progress at building area at site on 06.06.2026
16/100
Instream Storage Structure, Khalpal
Testing of Compressive M25A20 (Strength is 34.46/mm2 for 28 days) of LHS D/S Divide wall Raft has done in presence of Client & PSS team.
17/100
Instream Storage Structure, Gudvella
Arrangement of rope wire at gates are under progress at site on 06.06.2026
18/100
Instream Storage Structure, Khalpal
Shuttering of LHS U/S Divide wall, 3rd lift is under progress.
19/100
Instream Storage Structure, Gudvella
Stone pitching work at u/s side is under progress at site on 06.06.2026
20/100
Instream Storage Structure, Khalpal
Shuttering of RHS Double Pier No-25, 1st lift is under progress.
21/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
22/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 06.06.2026
23/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Pier No-21, 15th lift done in presence of Client & PSS Team.
24/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 06.06.2026
25/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-21, 15th lift is under progress in presence of Client & PSS Team.
26/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-2, 8th lift done in presence of Client & PSS Team.
27/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-2, 8th lift is under progress in presence of Client & PSS Team.
28/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 20.89/mm2 for 07 days) of Pier No-5, 3rd lift and (Strength is 21.78/mm2 for 28 days) of Pier No-4, 3rd lift and (Strength is 30.86/mm2 for 28 days) of Abutment wall, 5th lift Block No-1 has done in presence of Client & PSS team.
29/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no. 11,12&13 of bay-12&13 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 89mm on 07.06.2026
30/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no. 11,12&13 of bay-12&13 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 89mm on 07.06.2026
31/100
Instream Storage Structure, Hamirpur
Barrage bay groove roller track alignment work is in progress at Bay No-12.
32/100
Instream Storage Structure, Nandagaon
• 1.Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay no.12 of pier no.11 for 9th lift 8th lift & pier no. 12 for 9th lift of stoplog gate and main gate groove and bay no.13 of pier no. 12& 13 for 8th & 9th lift have been checked and found correct by HM Expert of PMC during his site visit on dt.01.06.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs. (i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows: (ii) Chipping of old vertical concrete surface is done. (iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for M35A20 grade on 07.06.2026
33/100
Instream Storage Structure, Hamirpur
Stop-log groove 2nd stage embedded parts side guide erection work is in progress at (Bay No-12).
34/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no. 12,13&14 on 07.06.2026
35/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Flank wall Raft at Block No-1 is under progress.
36/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-2, 9th lift is under progress.
37/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4, 5th lift is under progress.
38/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Deck slab (Bay No-11) is under progress.
39/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Abutment (A1), 7th lift at Block No-1 is under progress.
40/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.12,13 & right abutment is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 86mm on 06.06.2026
41/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.12,13 & right abutment is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 86mm on 06.06.2026
42/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Abutment (A1), 10th lift at Block No-1 is under progress.
43/100
Instream Storage Structure, Nandagaon
• 1.Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay no.13 of pier no.12&13 for 7th lift & 8th lift and bay no. 14 at pier no. 13 & right abutment for 1st lift of stoplog gate groove have been checked and found correct by HM Expert of PMC during his site visit on dt.01.06.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs. (i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows: (ii) Chipping of old vertical concrete surface is done. (iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for M35A20 grade on 06.06.2026
44/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
DCAC meeting conducted on 06.06.2026 at Collectorate, Angul for acquisition of 0.57 Acre of Private land in Barnamuhan village of ISS Santeibhanja in presence of ADM (Revenue), Angul, Sub-Collector,Pallahara, Tahasildar, Pallahra, S.E & A.E.E, RDD, Sub-Registrara, Pallahra along with R.Ts.
45/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of D/S Wing wall, 3rd lift is under progress in presence of Client & PSS Team.
46/100
Instream Storage Structure, Nandagaon
Under sluice gate sand blasting under progress on 06.06.2026
47/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 80 mm) of RHS Divide wall, 3rd lift done in presence of Client & PSS Team.
48/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of RHS Divide wall, 3rd lift is under progress in presence of Client & PSS Team.
49/100
Instream Storage Structure, Nandagaon
Placing of CC blocks is in progress at D/S side on 06.06.2026
50/100
Instream Storage Structure, Khalpal
Inspection of SE,AID Angul, Dy. TL and IEE of PSS team along with EPC agency the RHS side of Khalpal ISS for computation of land available.
51/100
Instream Storage Structure, Khalpal
Binding of reinforcement for LHS U/S Divide wall, 3rd lift is under progress.
52/100
Instream Storage Structure, Khalpal
Shuttering of RHS Double Pier No-25, 1st lift is under progress.
53/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering is in progress at D/S right abutment on 06.06.2026
54/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
55/100
Instream Storage Structure, Nandagaon
Monorail walkway top and bottom drilling work under progress on 06.06.2026
56/100
Instream Storage Structure, KansariGanda
Visit of Add. CE, SE and other dept. official to the ISS Site. Inspected the Overall progress of site.
57/100
Instream Storage Structure, KansariGanda
Visit of Add. CE, SE and other dept. official to the ISS Site. Inspected the Overall progress of site.
58/100
Instream Storage Structure, KansariGanda
Curing continuing at site.
59/100
Instream Storage Structure, KansariGanda
Slump cone test conducted in progress.
60/100
Instream Storage Structure, KansariGanda
Gravity floor pcc laying in progress
61/100
Instream Storage Structure, KansariGanda
Gravity floor pcc laying in progress
62/100
Instream Storage Structure, KansariGanda
Gravity floor pcc laying in progress
63/100
Instream Storage Structure, KansariGanda
NDT test for precast girders in presence of QA&QC Dept. and QA/QC Expert PMC and Dept. Officials
64/100
Instream Storage Structure, KansariGanda
NDT test for precast girders in presence of QA&QC Dept. and QA/QC Expert PMC and Dept. Officials
65/100
Instream Storage Structure, KansariGanda
Slump cone test conducted in progress.
66/100
Instream Storage Structure, KansariGanda
Pile no-229 sample check, depth check, cage lowering and concreting in presence of QA/QC Expert PMC and Dept. Officials.
67/100
Instream Storage Structure, KansariGanda
Pile no-229 sample check, depth check, cage lowering and concreting in presence of QA/QC Expert PMC and Dept. Officials.
68/100
Instream Storage Structure, KansariGanda
Pile no-229 sample check, depth check, cage lowering and concreting in presence of QA/QC Expert PMC and Dept. Officials.
69/100
Instream Storage Structure, KansariGanda
Pile no-229 sample check, depth check, cage lowering and concreting in presence of QA/QC Expert PMC and Dept. Officials.
70/100
Instream Storage Structure, KansariGanda
Pouring of concrete zone 5 between p7-p9 is in progress and Right side filter media work is in progress in presence of Irrigation engineering Expert.
71/100
Instream Storage Structure, KansariGanda
Pouring of concrete zone 5 between p7-p9 is in progress and Right side filter media work is in progress in presence of Irrigation engineering Expert.
72/100
Instream Storage Structure, KansariGanda
Pile no-170 depth check, cage lowering, Concreting in presence of QA/QC Expert PMC
73/100
Instream Storage Structure, KansariGanda
Pile no-170 depth check, cage lowering, Concreting in presence of QA/QC Expert PMC
74/100
Instream Storage Structure, KansariGanda
Pile no-170 depth check, cage lowering, Concreting in presence of QA/QC Expert PMC
75/100
Instream Storage Structure, KansariGanda
Left side U/S flank wall reinforcement binding and shuttering work in progress.
76/100
Instream Storage Structure, KansariGanda
Slump cone test conducted in progress.
77/100
Instream Storage Structure, KansariGanda
Right side middle pier no-7 concrete casting with grade M25A20 is in progress in presence of Irrigation Eng. Expert along with site engineer PMC.
78/100
Instream Storage Structure, KansariGanda
Curing continuing at site.
79/100
Instream Storage Structure, KansariGanda
Slump cone test conducted in progress.
80/100
Instream Storage Structure, KansariGanda
Barrage Bay Gravity Floor wearing coat concreting in presence of Irrigation Eng. Expert along with Site engineer PMC.
81/100
Instream Storage Structure, KansariGanda
Barrage Bay Gravity Floor wearing coat concreting in presence of Irrigation Eng. Expert along with Site engineer PMC.
82/100
Instream Storage Structure, KansariGanda
Barrage Bay Gravity Floor wearing coat concreting in presence of Irrigation Eng. Expert along with Site engineer PMC.
83/100
Instream Storage Structure, KansariGanda
Right side Pile no-AB 197 Depth check, cage lowering, concrete pouring and Right side Girder no-24 casting with grade of concrete in presence of QA/QC Expert along with site engineer PMC and Dept. Officials.
84/100
Instream Storage Structure, KansariGanda
Right side Pile no-AB 197 Depth check, cage lowering, concrete pouring and Right side Girder no-24 casting with grade of concrete in presence of QA/QC Expert along with site engineer PMC and Dept. Officials.
85/100
Instream Storage Structure, KansariGanda
Right side Pile no-AB 197 Depth check, cage lowering, concrete pouring and Right side Girder no-24 casting with grade of concrete in presence of QA/QC Expert along with site engineer PMC and Dept. Officials.
86/100
Instream Storage Structure, KansariGanda
Left side U/s flank wall 1st lift (M25 A20) concrete casting work in progress in presence of irrigation expert along with site engineer of PMC.
87/100
Instream Storage Structure, KansariGanda
Left side U/s flank wall 1st lift (M25 A20) concrete casting work in progress in presence of irrigation expert along with site engineer of PMC.
88/100
Instream Storage Structure, KansariGanda
Right side Pier no-9 shuttering work is in progress,
89/100
Instream Storage Structure, KansariGanda
Cube test conducted at site lab.
90/100
Instream Storage Structure, KansariGanda
Right side pier no-6 ,7 and 8 reinforcement binding and shuttering work in progress, Right side pier no-10 pile cap foundation 2nd layer concrete pouring and Right side gravity floor bay no - 8 to 9 concrete pouring in presence of Irrigation Expert along with site engineer PMC.
91/100
Instream Storage Structure, KansariGanda
Right side pier no-6 ,7 and 8 reinforcement binding and shuttering work in progress, Right side pier no-10 pile cap foundation 2nd layer concrete pouring and Right side gravity floor bay no - 8 to 9 concrete pouring in presence of Irrigation Expert along with site engineer PMC.
92/100
Instream Storage Structure, KansariGanda
Right side pier no-6 ,7 and 8 reinforcement binding and shuttering work in progress, Right side pier no-10 pile cap foundation 2nd layer concrete pouring and Right side gravity floor bay no - 8 to 9 concrete pouring in presence of Irrigation Expert along with site engineer PMC.
93/100
Instream Storage Structure, KansariGanda
Right side pier no-6 concrete pouring completed.
94/100
Instream Storage Structure, KansariGanda
Slump cone test done at site
95/100
Instream Storage Structure, KansariGanda
Right side pier no-6 and 7 reinforcement binding and shuttering work in progress and Left side Barrage bay no-6 crest portion wearing coat laying
96/100
Instream Storage Structure, KansariGanda
Right side pier no-6 and 7 reinforcement binding and shuttering work in progress and Left side Barrage bay no-6 crest portion wearing coat laying
97/100
Instream Storage Structure, KansariGanda
Right side pier no-6 and 7 reinforcement binding and shuttering work in progress and Left side Barrage bay no-6 crest portion wearing coat laying
98/100
Instream Storage Structure, KansariGanda
Left Barrage Bay No 4 Crest portion wearing coat is in progress.
99/100
Instream Storage Structure, KansariGanda
Slump cone test done at site
100/100
Instream Storage Structure, KansariGanda
Right Intermediate Pier No 8 4th lift wall concreting is in progress.

Enter Login Details

Forgot Password ?