1/100
Barrage across river Turi & Guntat
Preparatory work for erection of gates at Guntat site started. PMC Engineer, AEE & SE NID are present.
2/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Curing of Counter fort & Abutment wall is under progress.
3/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cleaning & Dewatering of Gravity floor is under progress.
4/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cleaning of reinforcement for Middle pier is under progress.
5/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cube casting & Slump testing M20A20 (Value 80 mm) of LHS D/S Gravity floor done in presence of Client & PSS Team.
6/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M20A20 of LHS D/S Gravity floor PCC is under progress in presence of Client & PSS Team.
7/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Testing of Compressive M20A20 (Strength is 17.48/mm2 for 07 days) of LHS Gravity floor PCC has done in presence of Client & PSS team.
8/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS Counter fort & Abutment wall, 2nd lift is under progress.
9/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS Divide wall, 3rd lift is under progress.
10/100
Instream Storage Structure, Jharbeda
Cleaning of Pier No-4 to Pier No-7 Gravity floor is under progress.
11/100
Instream Storage Structure, Jharbeda
Excavation of Pier No-7 to RHS Abutment is under progress.
12/100
Instream Storage Structure, Hamirpur
Seal beam groove chipping work is in progress.
13/100
Instream Storage Structure, Hamirpur
Hoist bridge platform No-19 welding work is in progress.
14/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-23, 13th lift at Block No-4 done in presence of Client & PSS Team.
15/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-23, 13th lift at Block No-4 is under progress in presence of Client & PSS Team.
16/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-17, 10th lift at Block No-3 done in presence of Client & PSS Team.
17/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-17, 10th lift at Block No-3 is under progress in presence of Client & PSS Team.
18/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-9, 6th lift at Block No-2 is under progress by Sand blasting method.
19/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-18, 11th lift at Block No-3 is under progress.
20/100
Instream Storage Structure, Hamirpur
Curing of Piers is under progress.
21/100
Instream Storage Structure, Hamirpur
Shuttering & binding of reinforcement for Pier No-10, 7th lift at Block No-2 is under progress.
22/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-22, 9th lift at Block No-4 is under progress.
23/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-31, 9th lift at Block No-5 is under progress.
24/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 160 mm) of D/S Barrage bay Panel No-23 done in presence of Client & PSS Team.
25/100
Instream Storage Structure, Khalpal
Concreting M25A20 of D/S Barrage bay Panel No-23 done in presence of Client & PSS Team.
26/100
Instream Storage Structure, Khalpal
End stopper fixing for D/S Barrage bay Panel No-23 in presence of Client & PSS Team.
27/100
Instream Storage Structure, Khalpal
Diaphragm wall cage placing for D/S Barrage bay Panel No-23 in presence of Client & PSS Team.
28/100
Instream Storage Structure, Khalpal
Chipping of Left sluice diaphragm Wall work in progress.
29/100
Instream Storage Structure, KansariGanda
Curing continuing at site.
30/100
Instream Storage Structure, KansariGanda
Slump test and cube cast at site in presence of Geologist and Irr. Eng. Expert along with Site engineer
PMC.
31/100
Instream Storage Structure, KansariGanda
Slump test and cube cast at site in presence of Geologist and Irr. Eng. Expert along with Site engineer
PMC.
32/100
Instream Storage Structure, KansariGanda
Visit of Irr. Eng. Expert & Geologist Expert along with Site engineer PMC to the ISS site. Inspected the overall
progress of work, Pouring of concrete of Peir No. 4, 5th lift, 1st layer.
33/100
Instream Storage Structure, KansariGanda
Visit of Irr. Eng. Expert & Geologist Expert along with Site engineer PMC to the ISS site. Inspected the overall
progress of work, Pouring of concrete of Peir No. 4, 5th lift, 1st layer.
34/100
Instream Storage Structure, KansariGanda
Visit of Irr. Eng. Expert & Geologist Expert along with Site engineer PMC to the ISS site. Inspected the overall
progress of work, Pouring of concrete of Peir No. 4, 5th lift, 1st layer.
35/100
UGPL, Right Lower Suktel Canal Division
Pani panchayat awareness meeting is in progress in presence of DoWR JE and PMC team at village Tulandi and Chandanbhati.
36/100
Instream Storage Structure, Gudvella
Cast of concrete 2nd layer RCC M25A20 grade at Barrage bay crest -8 in between P9 and P8 from RL 148.90m to 149.60 m is under progress through pump in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 91mm on 11.12.2025
37/100
Instream Storage Structure, Gudvella
Cast of concrete 2nd layer RCC M25A20 grade at Barrage bay crest -8 in between P9 and P8 from RL 148.90m to 149.60 m is under progress through pump in the presence of Dept JE, site engineer of PMC and agency at site. Slump achieved 91mm on 11.12.2025
38/100
Instream Storage Structure, Gudvella
reinforcement at right side D/s wing wall including 5nos CF for 1st lift RCC is in progress on 11.12.2025
39/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at D/S right flank wall for 1st lift (hunch portion) from RL-234.00m to RL-234.30m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 77mm on 11.12.2025
40/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at D/S right flank wall for 1st lift (hunch portion) from RL-234.00m to RL-234.30m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 77mm on 11.12.2025
41/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 1no. of CC block of size 5.5x1.5x0.6m at U/S right flared out wall from sec.2-2 to sec.4-4 for 4th lift of 0.6m hight from RL-238.20m to RL-238.80m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 73mm on 11.12.2025
42/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for 1no. of CC block of size 5.5x1.5x0.6m at U/S right flared out wall from sec.2-2 to sec.4-4 for 4th lift of 0.6m hight from RL-238.20m to RL-238.80m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 73mm on 11.12.2025
43/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at U/S right flared out wall from sec.1-1 to sec.2-2 for 8th lift of 0.6m hight from RL-238.20m to RL-238.80m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 78mm on 11.12.2025
44/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at U/S right flared out wall from sec.1-1 to sec.2-2 for 8th lift of 0.6m hight from RL-238.20m to RL-238.80m is in progress in presence of JE,KID, PM EPC agency, Site Engineers of PMC & EPC agency. Slump achieved 78mm on 11.12.2025
45/100
Instream Storage Structure, Nandagaon
Trestle bracing welding work under progress on 11.12.2025
46/100
Instream Storage Structure, Nandagaon
Hoist bridge MIG welding work under progress on 11.12.2025
47/100
Instream Storage Structure, Nandagaon
Reinforcement binding & shuttering of pier cap at pier no-12, Block-2 is in progress on 11.12.2025
48/100
Integrated Barrage across river Kochila and across river Baitarini
Site Visit of PMC MBBS chandikhol to Kochila-Baitarani ISS project today to monitor the ongoing casting for abutment and wingwall-12.12.2025
49/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Site Visit of PMC MBBS chandikhol to Chaudhary gada and tikhiri ISS project. Discussion about project work with the Agency-12.12.2025
50/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cube casting & Slump testing M25A20 (Value 80 mm) of RHS Divide wall, 4th lift done in presence of Client & PSS Team.
51/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of RHS Divide wall, 4th lift is under progress in presence of Client & PSS Team.
52/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering & reinforcement checked by A.E.E, RDD in presence of QAE & Site Engineer of PSS team along with representative of EPC agency.
53/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Curing of Counter fort & Abutment wall is under progress.
54/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cleaning of Gravity floor is under progress.
55/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cleaning of reinforcement for Counter fort & Abutment is under progress.
56/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cube casting & Slump testing M20A20 (Value 85 mm) of LHS D/S Gravity floor done in presence of Client & PSS Team.
57/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M20A20 of LHS D/S Gravity floor PCC is under progress in presence of Client & PSS Team.
58/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Testing of Compressive M20A20 (Strength is 17.78/mm2 for 07 days) of LHS Gravity floor PCC has done in presence of Client & PSS team.
59/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning of RHS Raft area is under progress.
60/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS Divide wall, 2nd lift is under progress.
61/100
Instream Storage Structure, Jharbeda
Dewatering work is under progress.
62/100
Instream Storage Structure, Jharbeda
Excavation of Pier No-7 to RHS Abutment is under progress.
63/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.63/mm2 for 07 days) of Pier No-24, 14th lift has done in presence of Client & PSS team.
64/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-9, 5th lift at Block No-2 done in presence of Client & PSS Team.
65/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-9, 5th lift at Block No-2 is under progress in presence of Client & PSS Team.
66/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 86 mm) of Pier No-22, 8th lift at Block No-4 done in presence of Client & PSS Team.
67/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-22, 8th lift at Block No-4 is under progress in presence of Client & PSS Team.
68/100
Instream Storage Structure, Hamirpur
Cleaning of reinforcement for Pier No-19 at Block No-3 is under progress by Sand blasting method.
69/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-10, 7th lift at Block No-2 is under progress.
70/100
Instream Storage Structure, Hamirpur
Curing of Piers is under progress.
71/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-17, 10th lift at Block No-3 is under progress.
72/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-23, 13th lift at Block No-4 is under progress.
73/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-31, 9th lift at Block No-5 is under progress.
74/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 170 mm) of D/S Barrage bay Panel No-21 done in presence of Client & PSS Team.
75/100
Instream Storage Structure, Khalpal
Concreting M25A20 of D/S Barrage bay Panel No-21 done in presence of Client & PSS Team.
76/100
Instream Storage Structure, Khalpal
End stopper fixing for D/S Barrage bay Panel No-21 in presence of Client & PSS Team.
77/100
Instream Storage Structure, Khalpal
Diaphragm wall cage placing for D/S Barrage bay Panel No-21 in presence of Client & PSS Team.
78/100
UGPL, Left Lower Suktel Canal Division
Outlet verification work is in progress for HDPE pipe line of OMS 204B, LM-10 near village Jharmunda.
79/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for laying of 75mm Dia HDPE pipe of 1Ha OCS No-0213080- C12A at village Gaintala in presence of DoWR SDO, JE and PMC team.
80/100
UGPL, Right Lower Suktel Canal Division
L-bend jointing work is in progress of OCS 1Ha. outlet at village Malmunda.
81/100
UGPL, Right Lower Suktel Canal Division
Back filling and levelling work is in progress Before turfing work Infront of the PLC room at Pump House.
82/100
UGPL, Right Lower Suktel Canal Division
Internal drain plastering work is in progress at Pump House.
83/100
UGPL, Right Lower Suktel Canal Division
Door fixing work is in progress of OCS chamber OCS No. 0213115- C12A at village Junapadar.
84/100
UGPL, Left Lower Suktel Canal Division
1 Hectare outlet point fixing work is in progress of LO-290B (Z-6262),LM-15 at village Singhanimunda in presence of DoWR AE and PMC team.
85/100
UGPL, Left Lower Suktel Canal Division
2.5 sq mm flexible wire laying work is in progress through 20mm Dia galvanized steel Conduit pipe for switch gear room indoor Lighting at Pump House.
86/100
Instream Storage Structure, KansariGanda
Curing continuing at site.
87/100
Instream Storage Structure, KansariGanda
No 1pile test nearer toBH17 and 18 in presence of Geologist and Irr. Expert along with Site engineer
PMC.
88/100
Instream Storage Structure, KansariGanda
No 1pile test nearer toBH17 and 18 in presence of Geologist and Irr. Expert along with Site engineer
PMC.
89/100
Instream Storage Structure, KansariGanda
Visit of CE & BM of RV Basin, ACE, AEE, AE department and Irr. Eng. Expert & Geologist Expert along with Site
engineer PMC to the ISS site. Inspected the overall progress of work, Double Pier Reinforcement Checking and
Guide Wall Concreting.
90/100
Instream Storage Structure, KansariGanda
Visit of CE & BM of RV Basin, ACE, AEE, AE department and Irr. Eng. Expert & Geologist Expert along with Site
engineer PMC to the ISS site. Inspected the overall progress of work, Double Pier Reinforcement Checking and
Guide Wall Concreting.
91/100
Instream Storage Structure, KansariGanda
Visit of CE & BM of RV Basin, ACE, AEE, AE department and Irr. Eng. Expert & Geologist Expert along with Site
engineer PMC to the ISS site. Inspected the overall progress of work, Double Pier Reinforcement Checking and
Guide Wall Concreting.
92/100
Instream Storage Structure, KansariGanda
Visit of CE & BM of RV Basin, ACE, AEE, AE department and Irr. Eng. Expert & Geologist Expert along with Site
engineer PMC to the ISS site. Inspected the overall progress of work, Double Pier Reinforcement Checking and
Guide Wall Concreting.
93/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
94/100
Instream Storage Structure, Khirasasan
Slump 80 mm
95/100
Instream Storage Structure, Khirasasan
checked placing supporting bars and alignment of shuttering work in LHS u/s flared out 2nd step RL- 211.100 to 211.700 Now the area is ready for concrete casting M20 A20. So recommended for the purpose. Approved by AEE sir SID Sambalpur in presence of JE
96/100
Instream Storage Structure, Khirasasan
SHUTTERING work of LHS d/s Flared out wall 14th th lift under progress.
97/100
UGPL, Right Lower Suktel Canal Division
Pani panchayat awareness meeting is in progress in presence of DoWR JE and PMC team at village salepali.
98/100
Instream Storage Structure, Khirasasan
Abutment Hoist portion shuttering work under progress.
99/100
Instream Storage Structure, Khirasasan
Pier 1 hoist portion shuttering work under progress.
100/100
Instream Storage Structure, Khirasasan
Divide wall Hoist portion shuttering work under progress.
❮
❯