1/100
Instream Storage Structure across river Sapei near village Kinjirma
Review meeting conducted by the CE&BM, Mahanadi Basin, Burla on developmental activities of ISS Budharaja, Kirasasan, Saida, Gochhara & Kinjirma in presence of the departmental officers, PMC team & representatives of RSA infra Ltd
2/100
Instream Storage Structure across river Sapei near village Kinjirma
Site view of d/s side .
3/100
Instream Storage Structure across river Sapei near village Kinjirma
Site view of u/s side .
4/100
Instream Storage Structure across river Sapei near village Kinjirma
CE & BM Hirakud dam circle inspected ISS Kinjirma All departmental officers, DTL of PMC and representative of agency were present. CE instructed to expedite the progress of diaphragm wall in war foot manner so as to complete the balance work in targeted timeline.
5/100
Instream Storage Structure across river Sapei near village Kinjirma
CE & BM Hirakud dam circle inspected ISS Kinjirma All departmental officers, DTL of PMC and representative of agency were present. CE instructed to expedite the progress of diaphragm wall in war foot manner so as to complete the balance work in targeted timeline.
6/100
Instream Storage Structure across river Sapei near village Kinjirma
CE & BM Hirakud dam circle inspected ISS Kinjirma All departmental officers, DTL of PMC and representative of agency were present. CE instructed to expedite the progress of diaphragm wall in war foot manner so as to complete the balance work in targeted timeline.
7/100
Instream Storage Structure across river Sapei near village Kinjirma
Site view of d/s side .
8/100
Instream Storage Structure across river Sapei near village Kinjirma
Site view of u/s side .
9/100
Instream Storage Structure, Budharaja
Review meeting conducted by the CE&BM, Mahanadi Basin, Burla on developmental activities of ISS Budharaja, Kirasasan, Saida, Gochhara & Kinjirma in presence of the departmental officers, PMC team & representatives of RSA infra Ltd
10/100
Instream Storage Structure, Budharaja
De-Shuttering in 16th step & Shuttering Work is in Progress at LHS U/S Flared-Out Wall, 17th Step. RL: 215.300 to 215.900.
11/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at RHS U/S Flared-Out Wall, 14th Step. RL: 213.500 to 214.100.
12/100
Instream Storage Structure, Budharaja
De-Shuttering in 16th step & Shuttering Work is in Progress at RHS D/S Flared-Out Wall, 17th Step. RL: 215.300 to 215.900.
13/100
Instream Storage Structure, Budharaja
CE & BM , Mahanadi Basin Burla, ACE Canal Circle, SE SID Sambalpur, DTL & Departmental Officers inspected ISS Budharaja. Representatives of EPC Agency were present. Instructed to complete The Balance Work in targeted timeline.
14/100
Instream Storage Structure, Budharaja
CE & BM , Mahanadi Basin Burla, ACE Canal Circle, SE SID Sambalpur, DTL & Departmental Officers inspected ISS Budharaja. Representatives of EPC Agency were present. Instructed to complete The Balance Work in targeted timeline.
15/100
Instream Storage Structure, Budharaja
De-Shuttering work is in Progress at RHS U/S Flared-Out Wall, 13th Step. RL: 212.900 to 213.500.
16/100
Instream Storage Structure, Budharaja
De-Shuttering in 15th step & Shuttering Work is in Progress at RHS D/S Flared-Out Wall, 16th Step. RL: 214.700 to 215.300.
17/100
Instream Storage Structure, Budharaja
Curing Work is in Progress.
18/100
Instream Storage Structure, Gochara
Review meeting conducted by the CE&BM, Mahanadi Basin, Burla on developmental activities of ISS Budharaja, Kirasasan, Saida, Gochhara & Kinjirma in presence of the departmental officers, PMC team & representatives of RSA infra Ltd
19/100
Instream Storage Structure, Gochara
CE & BM , Mahanadi Basin Burla,ACE Canal Circle, SE SID Sambalpur, DTL & Departmental Officers inspected ISS GOCHARA. Representatives of EPC Agency were present. Instructed to complete The Balance Work in targeted timeline.
20/100
Instream Storage Structure, Gochara
CE & BM , Mahanadi Basin Burla,ACE Canal Circle, SE SID Sambalpur, DTL & Departmental Officers inspected ISS GOCHARA. Representatives of EPC Agency were present. Instructed to complete The Balance Work in targeted timeline.
21/100
Instream Storage Structure, Khirasasan
Review meeting conducted by the CE&BM, Mahanadi Basin, Burla on developmental activities of ISS Budharaja, Kirasasan, Saida, Gochhara & Kinjirma in presence of the departmental officers, PMC team & representatives of RSA infra Ltd
22/100
Instream Storage Structure, Khirasasan
RHS D/S FLANK WALL 8TH LIFT SHUTTERING WORK COMPLETE AND ready for concrete casting
23/100
Instream Storage Structure, Khirasasan
RHS d/s Flared out wall 14th step shuttering work complete and ready for concrete casting
24/100
Instream Storage Structure, Khirasasan
RHS divide wall hoist portion shuttering work under progress
25/100
Instream Storage Structure, Khirasasan
RHS ABUTMENT HOIST PORTION SHUTTERING WORK UNDER PROGRESS
26/100
Instream Storage Structure, Khirasasan
RHS D/S C F WING WALL 10 TH LIFT SHUTTERING WORK COMPLETE AND ready for concrete casting
27/100
Instream Storage Structure, Khirasasan
LHS us flared out wall 14th step shuttering work completed and ready for concrete casting
28/100
Instream Storage Structure, Khirasasan
CE & BM , Mahanadi Basin Burla, ACE Canal Circle, SE SID Sambalpur, DTL & Departmental Officers inspected ISS Kirasasan. Representatives of EPC Agency, Instructed to completed erection work in timeline.
29/100
Instream Storage Structure, Khirasasan
View showing flow of river from D/S of the river.
30/100
Instream Storage Structure, Khirasasan
shuttering work of counter fort 10th lift is under progress.
31/100
Instream Storage Structure, Khirasasan
RHS d/s Flared out wall 14th step shuttering work is under progress.
32/100
Instream Storage Structure, Khirasasan
LHS us flared out wall 14th step shuttering work is under progress.
33/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
34/100
Instream Storage Structure, Kudabega
Slump 80mm
35/100
Instream Storage Structure, Kudabega
Slump 80mm
36/100
Instream Storage Structure, Kudabega
Barrage bay-1 u/s Toe wall casting work in progress
37/100
Instream Storage Structure, Kudabega
Span no-09 gate groove deshuttering & Shuttering work in progress
38/100
Instream Storage Structure, Kudabega
Flared wall LHS U/S section 7/7 13th step Deshuttering work in progress.
39/100
Instream Storage Structure, Kudabega
Fish pass portion sand shifting and cleaning work in progress.
40/100
Instream Storage Structure, Kudabega
Soil compaction test
41/100
Instream Storage Structure, Kopsinga
Slump-90mm
42/100
Instream Storage Structure, Kopsinga
Divided wall (D1) final lift ready for casting
43/100
Instream Storage Structure, Kopsinga
Slump-90mm
44/100
Instream Storage Structure, Kopsinga
Slump-85mm
45/100
Instream Storage Structure, Kopsinga
Slump-85mm
46/100
Instream Storage Structure, Kopsinga
Slump-90mm
47/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - 2nd stage Gate Groove's Concerting work is in progress at Span no - 22
48/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Barrage gate's Guide Fixing work is in progress at Span no - 18
49/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Walk-Way's work is in progress
50/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Hoist bridge's 21th platform assembly work is in progress
51/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Trestle's or Column's work is in progress
52/100
Instream Storage Structure Across Bheden near village Saida
Review meeting conducted by the CE&BM, Mahanadi Basin, Burla on developmental activities of ISS Budharaja, Kirasasan, Saida, Gochhara & Kinjirma in presence of the departmental officers, PMC team & representatives of RSA infra Ltd
53/100
Instream Storage Structure Across Bheden near village Saida
Guide alignment work is in progress of Barrage Bay no-7.
54/100
Instream Storage Structure Across Bheden near village Saida
Bay no- 6, deck slab Shuttering work in progress
55/100
Instream Storage Structure Across Bheden near village Saida
shuttering work progress in LHS d/S Flared out wall step-6
56/100
Instream Storage Structure Across Bheden near village Saida
CE & BM , Mahanadi Basin Burla,ACE Canal Circle, SE SID Sambalpur, DTL & Departmental Officers inspected ISS SAIDA . Representatives of EPC Agency were present. Instructed to complete The Balance Work in targeted timeline.
57/100
Instream Storage Structure Across Bheden near village Saida
RHS U/S Flared out wall mud cleaning work is going on .
58/100
Instream Storage Structure Across Bheden near village Saida
P-5 to RHS Divide wall between mid portion Deck slab staging work is in progress .
59/100
Instream Storage Structure, Kopsinga
RHS Abutment - P1 Deck slab reinforcement work under progress
60/100
Instream Storage Structure, Kopsinga
Cube test
61/100
Instream Storage Structure, Kopsinga
RHS Guide bond 34th layer FDD check
62/100
Instream Storage Structure, Kopsinga
RHS D/S wing wall Shuttering work under progress
63/100
UGPL, Left Lower Suktel Canal Division
Internal Approach road block casting is in progress Right sight block (1&3) at Pump House.
64/100
UGPL, Left Lower Suktel Canal Division
Slump testing work is in progress for internal approach road concrete casting at Pump House in presence of DoWR JE, PMC team and MEIL staff.
65/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of D/S Divide wall is under Progress.
66/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
LHS side Earth excavation is under progress.
67/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Testing of Compressive M25A20 (Strength is 31.35/mm2 for 28 days) of Middle pier, 1st lift and M20A20 (Strength is 24.02/mm2 for 28 days) of Gravity floor end seal has done in presence of Client & PSS team.
68/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for RHS Barrage bay, raft is under Progress.
69/100
Instream Storage Structure, Gudvella
Cast of concrete 4th lift PCC M15A40 grade at right side u/s flared out wall from RL 150.40m to 151.00m is under progress in the presence of Dept JE, site engineer of PMC and agency forman . The slump test value is 68mm on 20.01.2026
70/100
Instream Storage Structure, Gudvella
Cast of concrete 4th lift PCC M15A40 grade at right side u/s flared out wall from RL 150.40m to 151.00m is under progress in the presence of Dept JE, site engineer of PMC and agency forman . The slump test value is 68mm on 20.01.2026
71/100
Instream Storage Structure, Gudvella
Cast of concrete 4th lift PCC M15A40 grade at right side u/s flared out wall from RL 150.40m to 151.00m is under progress in the presence of Dept JE, site engineer of PMC and agency forman . The slump test value is 68mm on 20.01.2026
72/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS Mid-pier, 6th lift is under Progress.
73/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS Counterfort & Abutment wall, 6th lift is under Progress.
74/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
De-shuttering of LHS Counterfort & Abutment wall, 5th lift is under Progress.
75/100
Instream Storage Structure, Gudvella
Cast of concrete 5th lift PCC M20A20 grade at right side D/s flared out wall from sec 3-3 to 4-4 with RL 151.00m to 151.60m is under progress in the presence of Dept JE, site engineer of PMC and agency forman. The slump test value is 70mm on 20.01.2026
76/100
Instream Storage Structure, Gudvella
Cast of concrete 5th lift PCC M20A20 grade at right side D/s flared out wall from sec 3-3 to 4-4 with RL 151.00m to 151.60m is under progress in the presence of Dept JE, site engineer of PMC and agency forman. The slump test value is 70mm on 20.01.2026
77/100
Instream Storage Structure, Gudvella
Cast of concrete 5th lift PCC M20A20 grade at right side D/s flared out wall from sec 3-3 to 4-4 with RL 151.00m to 151.60m is under progress in the presence of Dept JE, site engineer of PMC and agency forman. The slump test value is 70mm on 20.01.2026
78/100
Instream Storage Structure, Jharbeda
Slump testing M20A20 (Value 50 mm) of Pier No-4 to Pier No-5 U/S Gravity floor, 3rd lift done in presence of Client & PSS Team.
79/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of Pier No-4 to Pier No-5 U/S Gravity floor, 3rd lift is under progress in presence of Client & PSS Team.
80/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-6, 4th lift is under Progress.
81/100
Instream Storage Structure, Gudvella
Cast of concrete 5th lift PCC M20A20 grade at right side D/s flared out wall from sec 3-3 to 4-4 with RL 151.00m to 151.60m is under progress in the presence of Dept JE, site engineer of PMC and agency forman. The slump test value is 69mm on 20.01.2026
82/100
Instream Storage Structure, Gudvella
Cast of concrete 5th lift PCC M20A20 grade at right side D/s flared out wall from sec 3-3 to 4-4 with RL 151.00m to 151.60m is under progress in the presence of Dept JE, site engineer of PMC and agency forman. The slump test value is 69mm on 20.01.2026
83/100
Instream Storage Structure, Gudvella
Cast of concrete 5th lift PCC M20A20 grade at right side D/s flared out wall from sec 3-3 to 4-4 with RL 151.00m to 151.60m is under progress in the presence of Dept JE, site engineer of PMC and agency forman. The slump test value is 69mm on 20.01.2026
84/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for Pier No-4 to Pier No-6 D/S End seal is under Progress.
85/100
Instream Storage Structure, Hamirpur
Slump testing M15A40 (Value 45 mm) of U/S Flared out wall, 4th lift at Block No-5 done in presence of Client & PSS Team.
86/100
Instream Storage Structure, Gudvella
Cast of concrete 6th lift PCC M15A40 grade at right side D/s flared out wall from sec 1-1 to 3-3 with RL 151.60m to 152.20m is under progress in the presence of Dept JE site engineer of PMC and agency forman. The slump test value is 70mm on 20.01.2026
87/100
Instream Storage Structure, Gudvella
Cast of concrete 6th lift PCC M15A40 grade at right side D/s flared out wall from sec 1-1 to 3-3 with RL 151.60m to 152.20m is under progress in the presence of Dept JE site engineer of PMC and agency forman. The slump test value is 70mm on 20.01.2026
88/100
Instream Storage Structure, Gudvella
Cast of concrete 6th lift PCC M15A40 grade at right side D/s flared out wall from sec 1-1 to 3-3 with RL 151.60m to 152.20m is under progress in the presence of Dept JE site engineer of PMC and agency forman. The slump test value is 70mm on 20.01.2026
89/100
Instream Storage Structure, Hamirpur
Concreting M15A40 of U/S Flared out wall, 4th lift at Block No-5 is under progress in presence of Client & PSS Team.
90/100
UGPL, Right Lower Suktel Canal Division
OCS chamber piping work is in progress of OCS No- 2305022-C17A at village Kekatpali in presence of DoWR SDO, PMC team and L&T personnel .
91/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-11, 10th lift at Block No-2 done in presence of Client & PSS Team.
92/100
Instream Storage Structure, Gudvella
• Today, the Additional Chief Engineer, Balangir Irrigation Circle along with JE Madam (BIC), visited the ISS Gudvella site. The Department JE, PMC site engineers, and the agency’s senior site engineer were present during the visit.
1. Inspected the building works and all right-side walls and instructed the agency personnel to speed up the work and complete it within the approved EOT period on 20.01.2026
93/100
Instream Storage Structure, Gudvella
• Today, the Additional Chief Engineer, Balangir Irrigation Circle along with JE Madam (BIC), visited the ISS Gudvella site. The Department JE, PMC site engineers, and the agency’s senior site engineer were present during the visit.
1. Inspected the building works and all right-side walls and instructed the agency personnel to speed up the work and complete it within the approved EOT period on 20.01.2026
94/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-11, 10th lift at Block No-2 is under progress in presence of Client & PSS Team.
95/100
Instream Storage Structure, Hamirpur
Column trestle fixing and welding work is in progress.
96/100
Instream Storage Structure, Gudvella
Reinforcement work at right side D/s flank wall for 5th lift RCC is under progress on 20.01.2026
97/100
Instream Storage Structure, Hamirpur
Slab staging work at Block No-5 is in progress.
98/100
Instream Storage Structure, Gudvella
Shuttering work at right side D/s wing wall for 4th lift RCC is under progress on 20.01.2026
99/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-8, 11th lift is under progress.
100/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-10, 13th lift is under progress.
❮
❯