1/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 450mm Dia DI pipe line Laying and Gap closing LM-18, from J-459 to J-206 at village Birkel in presence of PMC team.
2/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 12.04.2026
3/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 12.04.2026
4/100
Instream Storage Structure, Gudvella
Curing of railing is under progress at site on 12.04.2026
5/100
Instream Storage Structure, Gudvella
• 1. Curing work at building.
2. Brick work at building is under progress on 12.04.2026
6/100
Instream Storage Structure, Gudvella
Casting of precast railing over the parapet wall is in progress with dimensions 1.424 m × 0.13 m × 0.17 m on 11.04.2026
7/100
Instream Storage Structure, Gudvella
Paint work is under progress on 11.04.2026
8/100
Instream Storage Structure, Gudvella
Hoist bridge installation work is under progress at P4 to P5 on 11.04.2026
9/100
Instream Storage Structure, Gudvella
Shuttering and de-shuttering work of deck slab railing is underprogress at site on 11.04.2026
10/100
Instream Storage Structure, Gudvella
Brickwork is under progress at control room building on 11.04.2026
11/100
Instream Storage Structure, Gudvella
Paint work under progress on 10.04.2026
12/100
Instream Storage Structure, Gudvella
Hoist bridge installation work under progress at P4 to P5 on 10.04.2026
13/100
Instream Storage Structure, Gudvella
Brickwork is under progress at control room building on 10.04.2026
14/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of gate grooves sill beam of bay no. 14 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 83mm on 12.04.2026
15/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of gate grooves sill beam of bay no. 14 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 83mm on 12.04.2026
16/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A40 grade at U/S right divide wall for 1st lift from RL-231.90m to RL-232.90m is in progress through concrete pump in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 83mm on 12.04.2026
17/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A40 grade at U/S right divide wall for 1st lift from RL-231.90m to RL-232.90m is in progress through concrete pump in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 83mm on 12.04.2026
18/100
Instream Storage Structure, Nandagaon
• 1.The area of main & stoplog gate grooves at bay No.-14 for erection of sill beams and its alignment, levels using TS has been checked and found correct by site Engineers mechanical of PMC on dt. 02.04.2026 as per the approved mechanical drawings.
(i) Sufficient nos. of dowel bars have been provided during fixing of beams.
(ii) The area is cleaned properly through air water jet and passed by SE,Kid, Bhawanipatna for placing with concrete M35A20 grade in presence of PM,EPC agency,Site Engineers of PMC & EPC agency on 12.04.2026
19/100
Instream Storage Structure, Nandagaon
• 1.Checked the area before placement of concrete at U/S right divide wall Raft top PCC with following activities in presence of PM,EPC agency,Site Engineer of PMC & Site Engineer of EPC Agency, ISS, Nandagaon:
(i).Shuttering of U/S right divide wall raft top PCC with M20A40 grade for 1st lift from RL-231.90m to RL-232.90m is completed.
(ii).The concrete surface is cleaned properly through air water jetting and passed by SE, KID Bhawanipatna for placing concrete with PCC M20A40 grade on 12.04.2026
20/100
Instream Storage Structure, Nandagaon
De-Shuttering & Shuttering is in progress at U/S right divide wall on 12.04.2026
21/100
Instream Storage Structure, Nandagaon
Placing of CC blocks is in progress at U/S side on 12.04.2026
22/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress at left abutment on 12.04.2026
23/100
Instream Storage Structure, Nandagaon
De-Shuttering & Shuttering for 2nd stage concrete is in progress at pier no.10 on 11.04.2026
24/100
Instream Storage Structure, Nandagaon
• 1)De-Shuttering & Shuttering is in progress at U/s right divide wall.
2) Curing is in progress.
3) De-watering is in progress through well point system on 11.04.2026
25/100
Instream Storage Structure, Nandagaon
Placing of CC blocks is in progress at U/S side on 11.04.2026
26/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress at pier no.1&8 on 11.04.2026
27/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right divide wall raft for 4th/final lift upto RL-231.90m is in progress through concrete pump in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 86mm on 10.04.2026
28/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right divide wall raft for 4th/final lift upto RL-231.90m is in progress through concrete pump in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 86mm on 10.04.2026
29/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no. 9&10 for 3rd lift of bay no.10 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 84mm on 10.04.2026
30/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no. 9&10 for 3rd lift of bay no.10 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 84mm on 10.04.2026
31/100
Instream Storage Structure, Nandagaon
• 1. Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay No.-10 of Pier No. 9&10 for 3rd lift have been checked and found correct by HM Expert of PMC during his site visit on dt.01.04.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 10.04.2026
32/100
Instream Storage Structure, Nandagaon
Gate no 12 both barrage bay gate and stoplog gate 2nd stage embedded parts erection work under progress on 10.04.2026
33/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.10&11 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 85mm on 10.04.2026
34/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.10&11 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 85mm on 10.04.2026
35/100
Instream Storage Structure, Nandagaon
• 1) Reinforcement binding & Shuttering is in progress at U/S right divide wall.
2) De-watering is in progress on 10.04.2026
36/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Pier No-4, 2nd lift at Block No-1 done in presence of Client & PSS Team.
37/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-4, 2nd lift at Block No-1 is under progress in presence of Client & PSS Team.
38/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of D/S Abutment (A1), 8th lift done in presence of Client & PSS Team.
39/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Abutment (A1), 8th lift is under progress in presence of Client & PSS Team.
40/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Abutment (A1), 3rd lift done in presence of Client & PSS Team.
41/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Abutment (A1), 3rd lift is under progress in presence of Client & PSS Team.
42/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-18 done in presence of Client & PSS Team.
43/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-18 is under progress in presence of Client & PSS Team.
44/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.04/mm2 for 28 days) of Pier No-15, 7th lift has done in presence of Client & PSS team.
45/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-3 girder's welding work is in progress.
46/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-2 welding work is in progress.
47/100
Instream Storage Structure, Hamirpur
D/S Flared out wall Raft at Block No-5 Reinforcement Checked by A.E RID at site.
48/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4, 5th lift is under progress.
49/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-3, 6th lift is under progress.
50/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Pier No-1, 4th is under progress.
51/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
52/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier no-15, 14th lift is under progress.
53/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for LHS Side under sluice portion is under progress.
54/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 80 mm) of U/S Divide wall, 2nd lift done in presence of Client & PSS Team.
55/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of U/S Divide wall, 2nd lift is under progress in presence of Client & PSS Team.
56/100
Instream Storage Structure, Jharbeda
Slump testing M20A20 (Value 60 mm) of RHS D/S Training wall, 1st layer done in presence of Client & PSS Team.
57/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of RHS D/S Training wall, 1st layer is under progress in presence of Client & PSS Team.
58/100
Instream Storage Structure, Jharbeda
Slump testing M25A20 (Value 85 mm) of Pier No-7, 7th lift done in presence of Client & PSS Team.
59/100
Instream Storage Structure, Jharbeda
Concreting M25A20 of Pier No-7, 7th lift is under progress in presence of Client & PSS Team.
60/100
Instream Storage Structure, Jharbeda
Curing of pier No-5 is under progress.
61/100
Instream Storage Structure, Jharbeda
Cutting & bending for reinforcement is under progress.
62/100
Instream Storage Structure, Jharbeda
Shuttering of RHS (D2) pier portion Footing, 1st lift is under progress.
63/100
Instream Storage Structure, Jharbeda
Shuttering of (A2) Footing, 2nd lift is under progress.
64/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
65/100
Instream Storage Structure, Khalpal
Concreting M15A40 of Barrage Bay No-2 Raft PCC is under progress in presence of Client & PSS Team.
66/100
Instream Storage Structure, Khalpal
Site Inspection by S.E, AID in presence of A.E AID, CME & Site Engineer of PSS team along with EPC Agency regarding inspected the Central Barrage bay (PCC), Raft, Gravity floor of Barrage bay No-3 and Checked the filter media of gravity floor. Stressed for proper curing in piers & wing wall.
67/100
Instream Storage Structure, Khalpal
Curing of Piers, Cut-off & Barrage Bay (Raft) work is in progress.
68/100
UGPL, Right Lower Suktel Canal Division
OCS chamber piping work is in progress of OCS No-2305093-C10B at village Ghatkaintara in presence of SDO along with DoWR official and PMC team.
69/100
UGPL, Right Lower Suktel Canal Division
OCS verification work is in progress of OCS NO 0213055- C17A at Village Bubel in presence of DOWR SDO, AE, JE, PMC team and L&T personnel.
70/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door & angle fixing work is in progress OCS No:-0213084-C04B at village Niljipali in presence of PMC team.
71/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress of 75mm Dia HDPE pipe Main line Gap closing node from LO-307 to LO-307B,LM-16 near village Birkel.
72/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 140mm Dia HDPE pipe line from J-531 to RO-79, RM-4 near village Kirabahal in presence of DoWR JE and PMC team.
73/100
UGPL, Left Lower Suktel Canal Division
HDD machine road pushing work is in progress for road crossing work of 75mm Dia HDPE pipe line between at J-527 RO-241 RM-13 near village Kusang.
74/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-4, 5th lift done in presence of Client & PSS Team.
75/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-4, 5th lift is under progress in presence of Client & PSS Team.
76/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Pier No-21, 13th lift done in presence of Client & PSS Team.
77/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-2, 5th lift done in presence of Client & PSS Team.
78/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-2, 5th lift is under progress in presence of Client & PSS Team.
79/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-15, 12th lift done in presence of Client & PSS Team.
80/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-15, 12th lift is under progress in presence of Client & PSS Team.
81/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Cross Girder (Bay No-17) done in presence of Client & PSS Team.
82/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Cross Girder (Bay No-17) is under progress in presence of Client & PSS Team.
83/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall Raft at Block No-5 is under progress.
84/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.93/mm2 for 07 days) of Pier No-1, 3rd lift and (Strength is 21.48/mm2 for 07 days) of Fish pass Raft at Block No-1 and M15A40 (Strength is 13.18/mm2 for 07 days) of U/S Flared out cut-off wall at Block No-1 has done in presence of Client & PSS team.
85/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-3, 6th lift is under progress.
86/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-1, 4th lift is under progress.
87/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Abutment (A1), 8th lift at Block No-1 is under progress.
88/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4, 5th lift is under progress.
89/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-16, 14th lift is under progress.
90/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
91/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier no-13, 14th lift is under progress.
92/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for LHS Side Raft is under progress.
93/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 85 mm) of RHS Mid-pier, 2nd lift done in presence of Client & PSS Team.
94/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of RHS Mid-pier, 2nd lift is under progress in presence of Client & PSS Team.
95/100
Instream Storage Structure, Khalpal
Curing of Piers work is in progress.
96/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of Pier No-21, 1st lift done in presence of Client & PSS Team.
97/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-21, 1st lift is under progress in presence of Client & PSS Team.
98/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of Pier No-22, 1st lift done in presence of Client & PSS Team.
99/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-22, 1st lift is under progress in presence of Client & PSS Team.
100/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 80 mm) of Pier No-24 (Crest portion) done in presence of Client & PSS Team.
❮
❯