GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
UGPL, Right Lower Suktel Canal Division
Joint verification work is in progress of outlet OCS No. 0213105-CO4A at village Kandapali in the presence of SDO along with DOWR officials, PMC team and L&T Team.
2/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE Tee (75 X 125 ×75)mm connection at RO-104 ,RM-6, near village Kuturapali in presence of PMC team.
3/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE to HDPE line connection Rm-6, Ro-104 at village Kuturapali.
4/100
UGPL, Left Lower Suktel Canal Division
MS line Land Levelling work is in progress J-108 to J-416 at village Kushmel in presence of PMC team.
5/100
Barrage across river Turi & Guntat
Today Chief Engineer, I & K Basin, Bariniput, Jaypur met with Hon'ble M. L. A., Nabarangapur at District Planning Board Office.
6/100
Barrage across river Turi & Guntat
Today Chief Engineer, I &K Basin, Bariniput, Jaypur met with Collector & D. M., Nabarangapur.
7/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door and angle fixing work is in progress OCS No-: 0213131-C08B at village Kulthipali in presence of PMC team.
8/100
UGPL, Left Lower Suktel Canal Division
A video conference meeting was held under the chairmanship of PMU TL in the office chamber of the CCE regarding the progress and balance work of Pump House, Pipe laying, all valves fitting of pipe line network, OMS instrumentation installation, chamber erection, outlet fixing, kilometre marking, Scada system and formation of Pani panchayat in presence of CCE, SE, SDO and other departmental of DoWR, TL (PES & PSS), RE of PSS, PMC team along with representative of Agency.
9/100
UGPL, Right Lower Suktel Canal Division
A video conference meeting was held under the chairmanship of PMU TL in the office chamber of the CCE regarding the progress and balance work of Pump House, Pipe laying, all valves fitting of pipe line network, OCS instrumentation installation, chamber erection, outlet fixing, kilometre marking, Scada system and formation of Pani panchayat in presence of SE, SDO and other departmental of DoWR, TL (PES & PSS), RE of PSS, PMC team along with representative of Agency.
10/100
Instream Storage Structure, Gudvella
• Visited SE to ISS Gudvella. During his visit the Department JE, PMC site engineers and agency engineers were present. 1. Inspected the overall site conditions and instructed the agency to expedite and complete the remaining works at the earliest. 2. Checked the mechanical works and observed the operation of one gate, which was found to be functioning satisfactorily on 10.06.2026
11/100
Instream Storage Structure, Gudvella
• Visited SE to ISS Gudvella. During his visit the Department JE, PMC site engineers and agency engineers were present. 1. Inspected the overall site conditions and instructed the agency to expedite and complete the remaining works at the earliest. 2. Checked the mechanical works and observed the operation of one gate, which was found to be functioning satisfactorily on 10.06.2026
12/100
Instream Storage Structure, Gudvella
Today the Vice President of Zilla Parishad, Balangir visited ISS Gudvella on 10.06.2026
13/100
Instream Storage Structure, Gudvella
Today the Vice President of Zilla Parishad, Balangir visited ISS Gudvella on 10.06.2026
14/100
Instream Storage Structure, Gudvella
Stone packing work is under progress at d/s side on 10.06.2026
15/100
Instream Storage Structure, Gudvella
Mechanical work under progress at site on 10.06.2026
16/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 10.06.2026
17/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 10.06.2026
18/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A40 grade at D/S curtain wall of undersluice bay area is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 85mm on 10.06.2026
19/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A40 grade at D/S curtain wall of undersluice bay area is in progress in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 85mm on 10.06.2026
20/100
Instream Storage Structure, Nandagaon
• 2.(i) Checked the area before placement of concrete at D/S curtain wall stared from right divide wall with PCC M15A40 grade of 2.0m width & 0.50m thickness with following activities in presence of PM of EPC Agency,Site Engineers of PMC & EPC Agency: (ii) The area has been excavated upto the design depth and foundation bottom is well watered compacted by mechanical means. (iii)The area is ready and passed by SE, KID Bhawanipatna for placing concrete with PCC M15A40 grade on 10.06.2026
21/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no. 12,13& right abutment is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 84mm on 10.06.2026
22/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no. 12,13& right abutment is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 84mm on 10.06.2026
23/100
UGPL, Right Lower Suktel Canal Division
OCS pre-cast chamber installation work is in progress of OCS no-0213122-C06A near village Bhursipali in presence of PMC team.
24/100
Instream Storage Structure, Nandagaon
• 1.Fixing & fittings and alignment of 2nd. stage embedded parts and numbers of dowel bars provided as per approved drawing at roller tracks of both stoplog & service gate grooves at bay no.13 of pier no.12 for 10th lift & 8th lift and pier no.13 for 10th lift & 9th lift and bay no.14 of pier no. 13&right abutment for 2nd &3rd lift have been checked and found correct by HM Expert of PMC during his site visit on dt.01.06.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs. (i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows: (ii) Chipping of old vertical concrete surface is done. (iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for M35A20 grade on 10.06.2026
25/100
Instream Storage Structure, Nandagaon
Pier no 3 barrage bay gate groove cleaning process under progress on 10.06.2026
26/100
Instream Storage Structure, Nandagaon
Shuttering for Block out portion is in progress at right abutment on 10.06.2026
27/100
Instream Storage Structure, Nandagaon
Shuttering for plinth beam of office building is in progress on 10.06.2026
28/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for fixing of branch Tee (110 X 75×75)mm connection from J-0213119- C20 to J-02013119- C20B, at village Bileisarda in presence of PMC team.
29/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.86/mm2 for 28 days) of U/S Flared out Cut-off wall at Block No-1 and (Strength is 30.87/mm2 for 28 days) of Pier No-15, 14th lift and (Strength is 21.18/mm2 for 07 days) of Flank wall Cut-off, 1st lift at Block No-1 and (Strength is 20.89/mm2 for 07 days) of Pier No-1, 10th lift has done in presence of Client & PSS team.
30/100
Instream Storage Structure, Hamirpur
Pier No-16 & 17 Girder is being lifted for fixing in (Bay 14) work is in progress.
31/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-7 bracket plate welding work is in progress.
32/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
33/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-4, 5th lift is under progress.
34/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Pier No-1, 10th lift is under progress.
35/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Pier No-2, 9th lift is under progress.
36/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Abutment (A1), 8th lift at Block No-1 is under progress.
37/100
UGPL, Left Lower Suktel Canal Division
OMS manifold installation work is in progress at RO-242A, RM-13, near village Kusang in presence of PMC team.
38/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE to HDPE connection at Lm-5 j- 270, near village sujia in presence of PMC team.
39/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI to HDPE connection at Lm-5 j-356, near village sujia in presence of PMC team visited by DoWR SDO.
40/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall Cut-off at Block No-1 is under progress.
41/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE Tee (75 X 140 ×75)mm connection at LO-193, LM-10, near village Kandajuri in presence of DoWR AE and PMC team.
42/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for OMS manifold installation at RO-242A, RM-13 near village Kusanga in presence of PMC team.
43/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M20A20 (Value 85 mm) of Gravity floor done in presence of Client & PSS Team.
44/100
Instream Storage Structure, Jharbeda
Cleaning of Pier No-9 area work is in progress.
45/100
Instream Storage Structure, Jharbeda
Shuttering & Binding of reinforcement for U/S Pier No-7 to Pier No-8 wearing coat is under progress.
46/100
Instream Storage Structure, Jharbeda
Shuttering of RHS U/S Flank wall is under progress.
47/100
Instream Storage Structure, Jharbeda
De-Shuttering of RHS D/S Training wall is under progress.
48/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 85 mm) of Barrage Bay No-2 Gravity floor done in presence of Client & PSS Team.
49/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Barrage Bay No-2 Gravity floor is under progress in presence of Client & PSS Team.
50/100
Instream Storage Structure, Khalpal
Binding of reinforcement for RHS Double pier No-25, 2nd lift is in progress.
51/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
52/100
Instream Storage Structure, Gudvella
The DCAC meeting for the Right Side Land Acquisition was successfully held under the chairmanship of the Collector Sir Sir. The meeting was attended by the ADM Revenue, LAO Balangir, Tahsildar Tusura, Horticulture Officer, Forest Officers, SE, SDO, AE and JE of the Irrigation Department. All concerned officials participated in the discussion regarding the land acquisition process on 09.06.2026
53/100
Instream Storage Structure, Gudvella
Plastering work is under progress at control room building on 09.06.2026
54/100
Instream Storage Structure, Gudvella
Stone packing under progress at d/s side on 09.06.2026
55/100
Instream Storage Structure, Gudvella
Mechanical work under progress at site on 09.06.2026
56/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 09.06.2026
57/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 09.06.2026
58/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no. 11, 12 & 13 on 09.06.2026
59/100
Instream Storage Structure, Nandagaon
Shuttering for plinth beam of office building is in progress on 09.06.2026
60/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-34 done in presence of Client & PSS Team.
61/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-34 is under progress in presence of Client & PSS Team.
62/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of D/S Flank Cut-off wall, 2nd lift (River side) at Block No-1 done in presence of Client & PSS Team.
63/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flank Cut-off wall, 2nd lift (River side) at Block No-1 is under progress in presence of Client & PSS Team.
64/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Pier No-3, 10th lift done in presence of Client & PSS Team.
65/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-3, 10th lift is under progress in presence of Client & PSS Team.
66/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.33/mm2 for 07 days) of Pier No-3, 9th lift and (Strength is 21.63/mm2 for 07 days) of U/S Flared out wall Raft at Block No-1 and M15A40 (Strength is 20.65/mm2 for 28 days) of D/S Flared out wall (PCC) at Block No-5 and M30A20 (Strength is 27.85/mm2 for 07 days) of Groove 2nd stage, 3rd lift (Bay No-28) has done in presence of Client & PSS team.
67/100
Instream Storage Structure, Hamirpur
Drive unit assembly fit-up work is in progress.
68/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-8 welding work is in progress.
69/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for D/S Abutment (A1), 10th lift at Block No-1 is under progress.
70/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-2, 9th lift is under progress.
71/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-1, 10th lift is under progress.
72/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M25A20 (Value 90 mm) of LHS D/S Abutment Counterfort glacis portion done in presence of Client & PSS Team.
73/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M15A40 of LHS Divide wall Raft (PCC) is under progress in presence of Client & PSS Team.
74/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of RHS D/S Counterfort & Wing wall, 2nd lift and De-Shuttering of RHS D/S Counterfort & Wing wall, 1st lift is under progress.
75/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of RHS D/S Training wall, 2nd lift is under progress in presence of Client & PSS Team.
76/100
Instream Storage Structure, Khalpal
Slump testing M20A20 (Value 80 mm) of Barrage Bay No-2 Gravity floor done in presence of Client & PSS Team.
77/100
Instream Storage Structure, Khalpal
Concreting M20A20 of Barrage Bay No-2 Gravity floor is under progress in presence of Client & PSS Team.
78/100
Instream Storage Structure, Khalpal
Shuttering of LHS U/S divide wall, 3rd lift is in progress.
79/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
80/100
UGPL, Left Lower Suktel Canal Division
OMS chamber fixing work is in progress at LO-7A, LM-1 near village Kusmel in presence of PMC team and EPC Agency.
81/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for DI to HDPE connection at J-388, RM-2, near village Kushmel.
82/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progrress for 1HA outlet subchak installation of OCS no-0201207-C01A at-Chubandh
83/100
Instream Storage Structure, Gudvella
• HM Expert visited ISS Gudvella. During the visit, the Department JE, PMC site engineers and agency engineers were present. 1. The mechanical work was inspected and the operation of three gates was tested. 2. Rubber seal fixing work is in progress. 3. The agency was instructed to complete the erection of the stoplog gates and staircase at the earliest on 08.06.2026
84/100
Instream Storage Structure, Gudvella
Mechanical and electrical work is under progress at site on 08.06.2026
85/100
Instream Storage Structure, Gudvella
Stone pitching work is under progress at site on 08.06.2026
86/100
Instream Storage Structure, Gudvella
Plastering work at building area is under progress at site on 08.06.2026
87/100
UGPL, Left Lower Suktel Canal Division
HDD machine road pushing work is in progress (road crossing) of 75mm Dia HDPE pipe between LO-230A(Z-2471) LM-12 near village Kandajhuri in presence of PMC team.
88/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 08.06.2026
89/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 08.06.2026
90/100
UGPL, Left Lower Suktel Canal Division
Butt fusion joint work is in progress of 140mm Dia HDPE node from J-560 to LO-228, LM-12 near village Kandajuri in presence of PMC team.
91/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M25A20 grade for wearing coat at bay no.-3 is in progress in presence of SDO, ISS Nandgaon, QAC,Expert of PMC,PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 85mm on 08.06.2026
92/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M25A20 grade for wearing coat at bay no.-3 is in progress in presence of SDO, ISS Nandgaon, QAC,Expert of PMC,PM EPC agency, Site Engineer's of PMC & EPC agency. The slump test value is 85mm on 08.06.2026
93/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.13&A2 of bay-14 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 85mm on 08.06.2026
94/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.13&A2 of bay-14 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 85mm on 08.06.2026
95/100
Instream Storage Structure, Nandagaon
2.(i) Cleaning of all deposited silt,sand and debris from crest,glacis and stilling basin area of bay -3 at barrage bay-1 is completed in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. (ii) The area is cleaned through air water jetting and passed by SE, Kid, Bhawanipatna for placing wearing coat concrete with PCC M25A20 grade on 08.06.2026
96/100
Instream Storage Structure, Nandagaon
1.Fixing & fittings and alignment of 2nd. stage embedded parts and numbers of dowel bars provided as per approved drawing at roller tracks of both stoplog & service gate grooves at bay no.14 of pier no.13 & A2 for 2nd lift at stoplog gate & 1st lift at main gate grooves have been checked and found correct by HM Expert of PMC during his site visit on dt.01.06.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs. (i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows: ii) Chipping of old vertical concrete surface is done.(iii).The area is cleaned on 08.06.2026
97/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no.11&12 on 08.06.2026
98/100
Instream Storage Structure, Nandagaon
Shuttering is in progress at D/S right flared out wall on 08.06.2026
99/100
Instream Storage Structure, Hamirpur
Concreting M15A40 of Staf quater Building foundation is under progress in presence of Client & PSS Team.
100/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of U/S Flared out wall Raft done in presence of Client & PSS Team.