PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
UGPL, Right Lower Suktel Canal Division
OCS chamber piping work is in progress of OCS No- 0213087-C02A at village Puintala in presence of PMC team.
2/100
UGPL, Right Lower Suktel Canal Division
OCS chamber above GL finishing work is in progress of OCS No:- 0213052-C09B at village Kekatpali.
3/100
Instream Storage Structure, Gudvella
Cast of concrete 1st lift PCC M20A20 grade at 1st row of D/s curtain wall from P2 to P6 with RL 147.10m to 147.70m is under progress in the presence of Dept JE, site engineer of PMC and agency forman. The slump test value is 76mm on 09.02.2026
4/100
Instream Storage Structure, Gudvella
Cast of concrete 1st lift PCC M20A20 grade at 1st row of D/s curtain wall from P2 to P6 with RL 147.10m to 147.70m is under progress in the presence of Dept JE, site engineer of PMC and agency forman. The slump test value is 76mm on 09.02.2026
5/100
Instream Storage Structure, Gudvella
Cast of concrete 15th lift PCC M20A20 grade at right side U/s flard out wall from RL 157.00m to 157.60m is under progress in the presence of Dept JE, site engineer of PMC and agency forman. The slump test value is 71mm on 09.02.2026
6/100
Instream Storage Structure, Gudvella
Cast of concrete 15th lift PCC M20A20 grade at right side U/s flard out wall from RL 157.00m to 157.60m is under progress in the presence of Dept JE, site engineer of PMC and agency forman. The slump test value is 71mm on 09.02.2026
7/100
Instream Storage Structure, Gudvella
Column assembly and welding work is under progress on 09.02.2026
8/100
Instream Storage Structure, Gudvella
Column assembly and welding work is under progress on 09.02.2026
9/100
Instream Storage Structure, Gudvella
Column assembly and welding work is under progress on 09.02.2026
10/100
Instream Storage Structure, Gudvella
Roller track and guide installation work at barrage bay no 9 is under progress on 09.02.2026
11/100
Instream Storage Structure, Gudvella
Roller track and guide installation work at barrage bay no 9 is under progress on 09.02.2026
12/100
Instream Storage Structure, Gudvella
Shuttering work at d/s flared out wall is under progress on 09.02.2026
13/100
Instream Storage Structure, Gudvella
Shuttering work at u/s flared out wall at D/s side is under progress on 09.02.2026
14/100
UGPL, Left Lower Suktel Canal Division
Cable cellar room indoor wiring work is in progress at Pump House in presence of PMC team.
15/100
Instream Storage Structure, Gudvella
Reinforcement work at deck slab no-10 in between P9 and A2 is under progress on 09.02.2026
16/100
Instream Storage Structure, Gudvella
Shuttering work at d/s 1st row curtain wall is under progress on 09.02.2026
17/100
UGPL, Left Lower Suktel Canal Division
Internal Approach road block No. 7 concrete pouring work is in progress near MSDSS area at Pump House In presence of DoWR JE and PMC team.
18/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade of foundation concrete at D/S right Flared out wall 2nd panel for 3rd lift upto RL-234.0m and 4th panel for 2nd lift upto RL-233.70m is in progress in presence of PM EPC agency,Site Engineer of PMC & EPC agency. The slump test value is 78mm on 09.02.2026
19/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade of foundation concrete at D/S right Flared out wall 2nd panel for 3rd lift upto RL-234.0m and 4th panel for 2nd lift upto RL-233.70m is in progress in presence of PM EPC agency,Site Engineer of PMC & EPC agency. The slump test value is 78mm on 09.02.2026
20/100
Instream Storage Structure, Nandagaon
• 5. Checked the area before placement of concrete at D/S right flared out wall foundation with following activities : (i) Shuttering of D/S right flared out wall foundation for 2nd panel for 3rd lift upto RL-234.0m and 4th panel for 2nd lift upto RL-233.70m of 9.375m length each are completed. (ii) Application of 2 coat bitumen paint at CJ's concrete surface is done. (iii) The concrete surface is cleaned properly through air water jetting and passed by SE, KID Bhawanipatna for placing concrete with PCC M15A20 grade on 09.02.2026
21/100
UGPL, Left Lower Suktel Canal Division
Slump testing work is in progress for internal approach road block casting at Pump House in presence of DoWR JE, PMC team and MEIL staff.
22/100
Instream Storage Structure, Nandagaon
Conducted 3 nos. cube tests of RCC M25A20 grade at site Lab in presence of SE, QAD, Bhawanipata, AEE & JE of QAD, SDO, ISS Nandagaon, Sr. Site Engineer of PMC, PM of EPC Agency and site Engineer of PMC and EPC Agency. Found the result of 28days compressive strength 34.81N/mm² (Avg) on 09.02.2026
23/100
Instream Storage Structure, Nandagaon
Conducted 3 nos. cube tests of RCC M25A20 grade at site Lab in presence of SE, QAD, Bhawanipata, AEE & JE of QAD, SDO, ISS Nandagaon, Sr. Site Engineer of PMC, PM of EPC Agency and site Engineer of PMC and EPC Agency. Found the result of 28days compressive strength 34.81N/mm² (Avg) on 09.02.2026
24/100
Instream Storage Structure, Nandagaon
3. Reinforcement works including shuttering works at right abutbent with it's counter fort walls are in progress on 09.02.2026
25/100
UGPL, Left Lower Suktel Canal Division
Gap closing work is in progress for 400mm Dia DI pipeline from node J-1 to J-644, RM1 near village Gerdi.
26/100
Instream Storage Structure, Nandagaon
2. Inspected the D/S right Flared out wall mass concrete area. Shuttering works were in progress and will be ready for placing concrete with PCC M15A20 grade for 2nd lift upto RL- 233.70m on 09.02.2026
27/100
Instream Storage Structure, Nandagaon
2. Inspected the D/S right Flared out wall mass concrete area. Shuttering works were in progress and will be ready for placing concrete with PCC M15A20 grade for 2nd lift upto RL- 233.70m on 09.02.2026
28/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of 3Nos. CC blocks at U/S right Flared out wall i.e 1no. of size 3.75x1.5x0.6m from at sec.5-5 for 14th lift and 1no. of size 6.0x1.5x0.6m from sec. 2-2 to sec. 4-4 for 13th lift and 1no. 6.0x1.5x0.6m from sec.1-1 to 2-2 for 8th lift upto RL-244.20m is in progress in presence of SE,QAD, Bhawanipatna, SDO& JE,QAD, Bpt., SDO, kid, Sr. Site Engineer of PMC,PM EPC agency,Site Engineer of PMC & EPC agency. The slump test value is 95mm on 09.02.2026
29/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of 3Nos. CC blocks at U/S right Flared out wall i.e 1no. of size 3.75x1.5x0.6m from at sec.5-5 for 14th lift and 1no. of size 6.0x1.5x0.6m from sec. 2-2 to sec. 4-4 for 13th lift and 1no. 6.0x1.5x0.6m from sec.1-1 to 2-2 for 8th lift upto RL-244.20m is in progress in presence of SE,QAD, Bhawanipatna, SDO& JE,QAD, Bpt., SDO, kid, Sr. Site Engineer of PMC,PM EPC agency,Site Engineer of PMC & EPC agency. The slump test value is 95mm on 09.02.2026
30/100
Instream Storage Structure, Nandagaon
• Site inspection of S.E. QAD, Bhawanipatna along with the AEE & JE, QAD, Bhawanipatna in presence of SDO, ISS Nandagaon, Sr. Site Engineer of PMC, PM of EPC Agency,Site Engineers of PMC & EPC Agency. During site visit the following activities are seen at site: 1. The casting of CC blocks at following area have been checked in presence of PM, EPC agency, Site Engineers of PMC & EPC Agency: (i) 3Nos. CC blocks at U/S right Flared out wall i.e 1no. of size 3.75x1.5x0.6m from at sec.5-5 for 14th lift and 1no. of size 6.0x1.5x0.6m from sec. 2-2 to sec. 4-4 for 13th lift and 1no. 6.0x1.5x0.6m from sec.1-1 to 2-2 for 8th lift upto RL-244.20m is completed. (ii). Filling of inverted filter materials covering with LDPE paper adjacent to each CC block in earth side are done before placement. (iii) Application of 2 coat bitumen paint at cj's concrete surface is done. (iv) Area is ready and passed by SE KID, Bh. Patna to place concrete with PCC M20A20 grade on 09.02.2026
31/100
Instream Storage Structure, Nandagaon
Trestle fitup, assembly and welding under progress on 09.02.2026
32/100
Instream Storage Structure, Nandagaon
Monorail walkway fitup and welding work is in progress on 09.02.2026
33/100
Instream Storage Structure, Nandagaon
1st nos of under sluice gate both barrage bay gate and stoplog gate side sil beam, roller track and centre guide erection work under progress on 09.02.2026
34/100
Instream Storage Structure, Nandagaon
1st nos of under sluice gate both barrage bay gate and stoplog gate side sil beam, roller track and centre guide erection work under progress on 09.02.2026
35/100
Instream Storage Structure, Nandagaon
Shuttering at D/S right flared out wall, Block-2 is in progress on 09.02.2026
36/100
Instream Storage Structure, Nandagaon
Reinforcement binding & shuttering at right abutment, Block-2 is in progress on 09.02.2026
37/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete at pier no.6&7,bay-7 work is under progress on 09.02.2026
38/100
Instream Storage Structure, Nandagaon
Shuttering for CC blocks at U/S right flared out wall is in progress on 09.02.2026
39/100
UGPL, Left Lower Suktel Canal Division
Cable cellar room indoor wiring work is in progress at Pump House in presence of PMC team.
40/100
UGPL, Left Lower Suktel Canal Division
Internal Approach road block shuttering board fixing work is in progress near MSDSS area at Pump House in presence of PMC team.
41/100
Instream Storage Structure Across Mahanadi at Choudhrygada and across Paika at Tikhiri
Epoxy paint coating work is going on at choudhary gada iss project.
42/100
UGPL, Left Lower Suktel Canal Division
Tee connection work is in progress for DI to 225mm Dia HDPE Pipe node from J-28 to J-452 Nera village Semelia in presence of PMC team.
43/100
Integrated Barrage across river Kochila and across river Baitarini
Site Visit of PMC MBBS chandikhol to Kochila-Baitarani ISS project today. Detailed discussions were held with the agency about project work-10.02.2026
44/100
UGPL, Left Lower Suktel Canal Division
Internal Approach road block No. 5 concrete pouring work is in progress near MSDSS area at Pump House In presence of DoWR JE and PMC team.
45/100
UGPL, Left Lower Suktel Canal Division
Slump testing work is in progress for internal approach road block casting at Pump House in presence of DoWR JE, PMC team and MEIL staff.
46/100
UGPL, Left Lower Suktel Canal Division
Approach road base compaction work is in progress of Pump House in presence of PMC team.
47/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE Pipe TEE connection at J-20 near village Taliudar in presence of PMC team.
48/100
UGPL, Left Lower Suktel Canal Division
Gap closing work is in progress from node J -115 to J-253, for laying of 800mm Dia DI pipeline near village Birkel.
49/100
UGPL, Left Lower Suktel Canal Division
Internal Approach road block shuttering board fixing work is in progress near MSDSS area at Pump House in presence of PMC team.
50/100
UGPL, Left Lower Suktel Canal Division
Indoor lighting DB installation & connection work is in progress of cable cellar room in presence of PMC team.
51/100
UGPL, Left Lower Suktel Canal Division
DI to 250mm Dia HDPE pipe Connection work is in progress node from J-227 to J-468 at village Manhira in presence of PMC team.
52/100
UGPL, Left Lower Suktel Canal Division
Internal Approach road block No. 5 concrete pouring work is in progress at Pump House In presence of DoWR JE and PMC team.
53/100
UGPL, Left Lower Suktel Canal Division
Slump testing work is in progress for internal approach road block casting at Pump House in presence of DoWR JE, PMC team and MEIL staff.
54/100
UGPL, Left Lower Suktel Canal Division
Tee connection work is in progress with HDPE Pipeline on J-550 , RM -5 near village Semilia in presence of DoWR SE, SDO and PMC team.
55/100
UGPL, Left Lower Suktel Canal Division
Cable cellar room indoor wiring work is in progress at Pump House in presence of PMC team.
56/100
UGPL, Left Lower Suktel Canal Division
Butt fusion joint work in progress of 75mm Dia HDPE pipe with L bend fixing on outlet point LO-283A,Z-6074 near village Buromunda.
57/100
UGPL, Left Lower Suktel Canal Division
Excavation work is under progress for 75mm Dia HDPE pipeline OMS point LO 283A, Z-6074 , LM-15 for 1 hectare connection near village Buromunda.
58/100
UGPL, Left Lower Suktel Canal Division
Internal Approach road block shuttering board fixing work is in progress near MSDSS area at Pump House in presence of PMC team.
59/100
Instream Storage Structure, Kushabhadra
Laying of CC M30A20 in Pier no-7 Right Barrage gate secondary gate groove from RL 21.90m to 23.70m in progress.
60/100
UGPL, Left Lower Suktel Canal Division
HDPE pipe Dia 280mm butt fusion joint and TEE connection work in progress DI to HDPE pipe node from J-227 to J-228 at village Manhira in presence of PMC team.
61/100
UGPL, Left Lower Suktel Canal Division
Internal Approach road block No. 7 concrete pouring work is in progress at Pump House In presence of DoWR JE and PMC team.
62/100
UGPL, Left Lower Suktel Canal Division
Slump testing work is in progress for internal approach road block casting at Pump House in presence of DoWR JE, PMC team and MEIL staff.
63/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cube casting & Slump testing M25A20 (Value 85 mm) of Double pier, 1st lift done in presence of Client & PSS Team.
64/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of Double pier, 1st lift is under progress in presence of Client & PSS Team.
65/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of Middle Cross cut-off, 3rd lift is under Progress.
66/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of D/S Divide wall, 5th lift is under Progress.
67/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cube casting & Slump testing M25A20 (Value 80 mm) of RHS Raft done in presence of Client & PSS Team.
68/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of RHS Raft is under progress in presence of Client & PSS Team.
69/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS Double pier, 6th lift is under Progress.
70/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of RHS under sluice slope portion is under Progress.
71/100
Instream Storage Structure, Jharbeda
Slump testing M20A20 (Value 85 mm) of Pier No-5 to Pier No-6 U/S Gravity floor, 5th lift Layer PCC done in presence of Client & PSS Team.
72/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of Pier No-5 to Pier No-6 U/S Gravity floor, 5th lift Layer PCC is under progress in presence of Client & PSS Team.
73/100
Instream Storage Structure, Jharbeda
RHS Abutment (A2) for Anchoring work is under Progress.
74/100
Instream Storage Structure, Jharbeda
Curing of Gravity floor is under Progress.
75/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-8 Footing, 2nd lift is under Progress.
76/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-5 is under Progress.
77/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-4 to Pier No-7 End seal, 1st lift is under Progress.
78/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
79/100
Instream Storage Structure, Hamirpur
Slump testing M15A40 (Value 45 mm) of U/S Flared out wall, 7th lift at Block No-5 done in presence of Client & PSS Team.
80/100
Instream Storage Structure, Hamirpur
Concreting M15A40 of U/S Flared out wall, 7th lift at Block No-5 is under progress in presence of Client & PSS Team.
81/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Pier No-22, 14th lift with pier Cap at Block No-4 done in presence of Client & PSS Team.
82/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-22, 14th lift with pier Cap at Block No-4 is under progress in presence of Client & PSS Team.
83/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-7, 8th lift at Block No-2 done in presence of Client & PSS Team.
84/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-7, 8th lift at Block No-2 is under progress in presence of Client & PSS Team.
85/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-12, 13th lift done in presence of Client & PSS Team.
86/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-12, 13th lift is under progress in presence of Client & PSS Team.
87/100
Instream Storage Structure, Hamirpur
2nd stage embedded parts erection work is in progress at (Bay No-21).
88/100
Instream Storage Structure, Hamirpur
R.D.U assembly welding work is in progress.
89/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.99/mm2 for 28 days) of Pier No-20, 10th lift and (Strength is 21.68/mm2 for 07 days) of Pier No-10, 7th lift and M30A20 (Strength is 38.08/mm2 for 28 days) of Seal beam (Bay No-7) and M15A40 (Strength is 13.33/mm2 for 07 days) of U/S Core wall, 6th lift at Block No-5 and M30A20 (Strength is 28.30/mm2 for 07 days) of Groove 2nd stage 2nd lift (Bay No-24) has done in presence of Client & PSS team.
90/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-11, 14th lift is under progress.
91/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-13, 8th lift is under progress.
92/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-14, 11th lift is under progress.
93/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-16, 4th lift is under progress.
94/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-19, 12th lift is under progress.
95/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-20, 14th is under progress.
96/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-30, 8th lift is under progress.
97/100
Instream Storage Structure, Khalpal
Barrage bay (Block No-04) verification of SBC plate Test started at foundation level RL 53.550m in presence of Client & PSS team along with EPC agency.
98/100
Instream Storage Structure, Khalpal
Slump testing M35A20 (Value 80 mm) of Girder No-41 done in presence of Client & PSS Team.
99/100
Instream Storage Structure, Khalpal
Concreting M35A20 of Girder No-41 is under progress in presence of Client & PSS Team.
100/100
Instream Storage Structure, Dhanei
Visit of SD Expert along with Site engineer PMC to the ISS Site. Inspected the O & M building 1st floor brick work, Trestle Assembly in progress and U/S right side flared-out wall CC block casting.