1/100
Instream Storage Structure, Gudvella
Cast of concrete 5th lift PCC M15A40 grade at left side D/s flard out wall from sec 1-1 to sec 3-3 with RL 151.00m to 151.60m is under progress through chute in the presence of Dept JE, site engineers of PMC n agency at site. Slump achieved 68mm on 06.11.2025
2/100
Instream Storage Structure, Gudvella
Cast of concrete 5th lift PCC M15A40 grade at left side D/s flard out wall from sec 1-1 to sec 3-3 with RL 151.00m to 151.60m is under progress through chute in the presence of Dept JE, site engineers of PMC n agency at site. Slump achieved 68mm on 06.11.2025
3/100
UGPL, Right Lower Suktel Canal Division
Turfing work is in progress at free space of Pump House village Khuntpali.
4/100
Instream Storage Structure, Gudvella
Cast of CC block at left side D/s flard out wall from sec 3-3 to sec 4-4 with RL 150.40m to 151.00m is under progress through chute in the presence of Dept JE, site engineers of PMC n agency at site. Slump achieved 67mm on 06.11.2025
5/100
Instream Storage Structure, Gudvella
Cast of CC block at left side D/s flard out wall from sec 3-3 to sec 4-4 with RL 150.40m to 151.00m is under progress through chute in the presence of Dept JE, site engineers of PMC n agency at site. Slump achieved 67mm on 06.11.2025
6/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at D/S left flared out wall from sec-2-2 to sec-4-4 for 5th lift from RL-236.40m to RL-237.00m is in progress through concrete pump in presence of JE,KID, Sr. site engineer,HME of PMC, PM n Site Engineers of PMC & EPC agency. Slump achieved 84m on 06.11.2025
7/100
UGPL, Right Lower Suktel Canal Division
Back filling work is in progress free space area of Pump House In the presence of CME (PSS).
8/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at D/S left flared out wall from sec-2-2 to sec-4-4 for 5th lift from RL-236.40m to RL-237.00m is in progress through concrete pump in presence of JE,KID, Sr. site engineer,HME of PMC, PM n Site Engineers of PMC & EPC agency. Slump achieved 84m on 06.11.2025
9/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at D/S left flared out wall from sec-1-1 to sec-2-2 for 6th lift from RL-237.00m to RL-237.60m is in progress through concrete pump in presence of SDO & JE,KID, Sr. site engineer,HME of PMC, PM n Site Engineers of PMC & EPC agency. Slump achieved 82mm on 06.11.2025
10/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at D/S left flared out wall from sec-1-1 to sec-2-2 for 6th lift from RL-237.00m to RL-237.60m is in progress through concrete pump in presence of SDO & JE,KID, Sr. site engineer,HME of PMC, PM n Site Engineers of PMC & EPC agency. Slump achieved 82mm on 06.11.2025
11/100
Instream Storage Structure, Nandagaon
Hoist bridge MIG welding under progress on 06.11.2025
12/100
Instream Storage Structure, Nandagaon
Chequer plate cutting for hoist bridge under progress on 06.11.2025
13/100
UGPL, Right Lower Suktel Canal Division
Internal drain inside plastering work is in progress In presence of CME (PSS).
14/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 200mm Dia HDPE pipeline pond connection between J-61 to J-433 to pond at Village Ramsingha.
15/100
UGPL, Left Lower Suktel Canal Division
Soil levelling work is in progress at free space area of Pump House.
16/100
UGPL, Left Lower Suktel Canal Division
Soil compaction work is in progress at free space area of Pump House.
17/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-28, 12th lift at Block No-4 done in presence of Client & PSS Team.
18/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-28, 12th lift at Block No-4 is under progress in presence of Client & PSS Team.
19/100
Instream Storage Structure, Hamirpur
Hoist bridge's girder fixing and welding work is in progress.
20/100
Instream Storage Structure, Hamirpur
Curing of Girders is under progress.
21/100
Instream Storage Structure, Hamirpur
Shuttering of RHS U/S Flank wall, 4th lift at Block No-5 is under progress.
22/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-31, 2nd lift at Block No-5 is under progress.
23/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-18, 6th lift at Block No-3 is under progress.
24/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-23, 8th lift at Block No-4 is under progress.
25/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-27, 11th lift at Block No-4 is under progress.
26/100
Instream Storage Structure, Khalpal
Slump testing M20A40 (Value 60 mm) C.C Blocks done in presence of Client & PSS Team.
27/100
Instream Storage Structure, Khalpal
Casting of C.C Block (M20A40) is under progress in presence of Client & PSS Team.
28/100
Instream Storage Structure, Jharbeda
Construction of Coffer dam is under progress.
29/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cleaning of debris & mud at Raft area is under progress.
30/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning of debris & mud at Raft area is under progress.
31/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
32/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. Flow direction is straight. The direction of flow is seen in middle of the river. Now the flow level is 225.600mt against design crest level 225.500 i.e. flood lift 0.1mt.
33/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S of river.
The flow level is 207.050 m against the design RL: 206.700, i.e., 0.350 m flood lift.
34/100
Instream Storage Structure, Budharaja
View Showing Flow of river From U/S to D/S ( From U/S of river)
35/100
Instream Storage Structure, Khirasasan
View showing flow of river from D/S of river
36/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
37/100
Instream Storage Structure, Kudabega
Pier no- 25 RHS side gate groove second stage shuttering work in progress.
38/100
Instream Storage Structure, Kudabega
Span no-05 deck slab shuttering work in progress
39/100
Instream Storage Structure, Kopsinga
P no 11-12 Span D/S Kerb Shuttering work
40/100
Instream Storage Structure, Kopsinga
P no 10-11 Span D/S Steel placing
41/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - Hoist bridge's single girder's work is in progress
42/100
UGPL, Right Lower Suktel Canal Division
200 mm Dia Butterfly valve fixing work is in progress on HDPE pipe line from J-5174 to J-5283 at village Junapadar in presence of JE( DoWR) and PMC team.
43/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - 'Walk-Way' work is in progress
44/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - 'Walk-Way' work is in progress
45/100
UGPL, Right Lower Suktel Canal Division
Back filling work is in progress at Pump House.
46/100
UGPL, Right Lower Suktel Canal Division
Pump House internal drain wall bricks masonry work is in progress.
47/100
Instream Storage Structure, Gudvella
Cast of concrete 4th lift PCC M15A40 grade at left side D/s flard out from sec 1-1 to sec 3-3 with RL 150.40m to 151.00m is under progress in the presence of Dept JE, site engineers of PMC n agency at site. Slump achieved 69mm on 05.11.2025
48/100
Instream Storage Structure, Gudvella
Cast of concrete 4th lift PCC M15A40 grade at left side D/s flard out from sec 1-1 to sec 3-3 with RL 150.40m to 151.00m is under progress in the presence of Dept JE, site engineers of PMC n agency at site. Slump achieved 69mm on 05.11.2025
49/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at D/S left flared out wall from sec-1-1 to sec-2-2 for 5th lift from RL-236.40m to RL-237.00m is in progress through concrete pump in presence of JE,KID, DTL,Tel basin, Bhawanipatna,QAQC expert,Sr. site engineer,SHEE,HME of PMC, PM n Site Engineers of PMC & EPC agency. Slump achieved 85mm on 05.11.2025
50/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at D/S left flared out wall from sec-1-1 to sec-2-2 for 5th lift from RL-236.40m to RL-237.00m is in progress through concrete pump in presence of JE,KID, DTL,Tel basin, Bhawanipatna,QAQC expert,Sr. site engineer,SHEE,HME of PMC, PM n Site Engineers of PMC & EPC agency. Slump achieved 85mm on 05.11.2025
51/100
Instream Storage Structure, Nandagaon
Measured the dimensions of Hoist bridge structure as per approved drawings. welding work is under progress .Instructed to agency engineer after completion of the welding slag should be removed immediately on 05.11.2025
52/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 20.74/mm2 for 07 days) of Pier No-28, 10th lift has done in presence of Client & PSS team.
53/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-30, 2nd lift at Block No-5 is under progress in presence of Client & PSS Team.
54/100
Instream Storage Structure, Hamirpur
1st stage embedded parts erection work is in progress of Pier No-28, 12th lift and Pier No-31, 2nd lift.
55/100
Instream Storage Structure, Hamirpur
Curing of Piers & Abutments is under progress.
56/100
Instream Storage Structure, Hamirpur
Shuttering of RHS U/S Flank wall, 4th lift at Block No-5 is under progress.
57/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-28, 12th lift at Block No-4 is under progress.
58/100
Instream Storage Structure, Khalpal
Slump testing M20A40 (Value 60 mm) C.C Blocks done in presence of Client & PSS Team.
59/100
Instream Storage Structure, Khalpal
Casting of C.C Block (M20A40) is under progress in presence of Client & PSS Team.
60/100
Instream Storage Structure, Jharbeda
Construction of Coffer dam is under progress.
61/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Cleaning of debris & mud at Raft area is under progress.
62/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river . Flow direction is straight & flow can seen at RL-215.000 mtr against design crest level RL- 215.000 mtr .i.e 0.0 mtr flood lift .
63/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from U/S to D/S (From U/S of river)
64/100
Instream Storage Structure across river Sapei near village Kinjirma
Casting work is under progress of Tie Beam
65/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump-85mm,tm-2
66/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 80mm
T.M. 01
67/100
Instream Storage Structure across river Sapei near village Kinjirma
Shuttering work under progress of d/s divide wall 6th lift(RHS) .
68/100
Instream Storage Structure across river Sapei near village Kinjirma
Cleaning &Reinforcement work under progress of R.H'.S counter fort wing wall 3rd lift
69/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S (From U/S of river) .
70/100
Instream Storage Structure, Gochara
View showing flow of river from D/S side. Flow direction is straight. The direction of flow is seen in middle of the river. Now the flow level is 225.600mt against design crest level 225.500 i.e. flood lift 0.1mt.
71/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S of river.
The flow level is 207.050 m against the design RL: 206.700, i.e., 0.350 m flood lift.
72/100
Instream Storage Structure, Budharaja
View Showing Flow of river From U/S to D/S ( From U/S of river)
73/100
Instream Storage Structure, Kopsinga
Slump-85 MM
74/100
Instream Storage Structure, Kopsinga
Chipping work is under progress
75/100
Instream Storage Structure, Kopsinga
Pier no -26 Gate grove chipping work
76/100
Instream Storage Structure, Khirasasan
Plant Calibration work is in Progress. In the presence of Department JE & PMC site Engineer.
77/100
Instream Storage Structure, Khirasasan
View showing flow of river from D/S of river
78/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
79/100
Instream Storage Structure, Kudabega
Barrage bay-3 span no-06 M35A20 deck slab (Rl-217.440 to Rl-217.740) casting work in completed
80/100
Instream Storage Structure, Kudabega
Barrage bay-3 span no-06 M35A20 deck slab (Rl-217.440 to Rl-217.740) casting work in progress in presence of dept AE JE and PMC
81/100
Instream Storage Structure, Kudabega
Slump 80MM (Tm-4)
82/100
Instream Storage Structure, Kudabega
Slump 85mm
83/100
Instream Storage Structure, Kudabega
Slump 85mm
84/100
Instream Storage Structure, Kudabega
Slump 80mm
85/100
Instream Storage Structure, Kudabega
Barrage bay-3 span no-06 M35A20 deck slab (Rl-217.440 to Rl-217.740) casting work in progress in presence of dept AE JE and PMC
86/100
Instream Storage Structure, Kudabega
Barrage bay-3 span no-06 M35A20 deck slab (Rl-217.440 to Rl-217.740) casting work in progress in presence of dept AE JE and PMC
87/100
Instream Storage Structure, Kudabega
Pier no-25 LHS side gate groove second stage De shuttering & shuttering work in progress.
88/100
Instream Storage Structure, Kudabega
Span no-06 deck slab Reinforcement binding work in progress.
89/100
Instream Storage Structure, Kudabega
Span no-23 raft gate groove bottom seal cleaning work in progress.
90/100
Instream Storage Structure, Kudabega
River water level at : 8: 41 am. => 206.800 m.
91/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Hoist bridge's 26th number platform assembly work is in progress
92/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Monorail Trestle's work is in progress
93/100
UGPL, Right Lower Suktel Canal Division
200 mm Dia Butterfly valve fixing work is in progress to HDPE pipe line from J-5174 to J-5283 at village Junapadar.
94/100
Integrated Barrage across river Kochila and across river Baitarini
BAITARANI -ISS C.C Block casting work in site camp at kochila baitarani Iss- 05.11.2025.
95/100
Instream Storage Structure, Gudvella
Visited ISS Gudvella site along with IE expert . Dept JE ,Site engineers of PMC n agency were present.
1. Conducted test for 28 days compressive strength of concrete cube PCC M15A40 grade at field laboratory and result found 18.02 N/mm2
2. As regard to the quality control, no specific people have been engaged for preparation of cube , slump test etc for which it is difficult to arrange for preparation of the same
Suggested to the agency site engineer to depute the perfect person in the quality control laboratory to achieve the all activities in quality work.
SDO and AE of balangir irrigation division are requested to depute a person in the quality control laboratory to perform the work on quality aspect on 04.11.2025
96/100
Instream Storage Structure, Nandagaon
Hoist bridge MIG welding work under progress on 04.11.2025
97/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at D/S left flared out wall from sec-2-2 to sec-4-4 for 4th lift from RL-235.80m to RL-236.40m is in progress through concrete pump in presence of JE,KID,PM n Site Engineers of PMC & EPC agency. Slump achieved 83mm on 04.11.2025
98/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M15A20 grade at D/S left flared out wall from sec-2-2 to sec-4-4 for 4th lift from RL-235.80m to RL-236.40m is in progress through concrete pump in presence of JE,KID,PM n Site Engineers of PMC & EPC agency. Slump achieved 83mm on 04.11.2025
99/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for total of 3nos. of CC block alternatively at D/S left flared out wall from sec-5-5 to sec-6-6 for 1st lift upto RL-235.80m is in progress through concrete pump in presence of JE,KID,PM n Site Engineers of PMC & EPC agency. Slump achieved 87mm on 04.11.2025
100/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade for total of 3nos. of CC block alternatively at D/S left flared out wall from sec-5-5 to sec-6-6 for 1st lift upto RL-235.80m is in progress through concrete pump in presence of JE,KID,PM n Site Engineers of PMC & EPC agency. Slump achieved 87mm on 04.11.2025
❮
❯