1/100
Barrage across river Turi & Guntat
Work is in progress at Turi guntat site.
2/100
Barrage across river Turi & Guntat
Work is in progress at Turi guntat site.
3/100
Instream Storage Structure, Gudvella
The installation of electrical lights is in progress on 05.06.2026
4/100
Instream Storage Structure, Gudvella
• Today DTL and HM Expert visited the ISS Gudvella site. During the visit, the Department JE, PMC Site Engineers and the Agency Site Engineer were present.
1. The mechanical works were inspected by HM Expert, instructed the agency to expedite and complete the work at the earliest.
2. The building works were inspected by DTL, instructed the agency to complete the plastering works within 10 days on 05.06.2026
5/100
Instream Storage Structure, Gudvella
Railing work is under progress at host bridge area at site on 05.06.2026
6/100
Instream Storage Structure, Gudvella
Plastering work is under progress at building area on 05.06.2026
7/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 05.06.2026
8/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 05.06.2026
9/100
Instream Storage Structure, Nandagaon
• 1. Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay no.12 of pier no.11 for 8th lift of main gate & 7th lift of stoplog gate grooves and Pier no. 12 for 8th lift of both gate grooves have been checked and found correct by HM Expert of PMC during his site visit on dt.01.06.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for M35A20 grade on 05.06.2026
10/100
Instream Storage Structure, Nandagaon
• 1. Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay no.12 of pier no.11 for 8th lift of main gate & 7th lift of stoplog gate grooves and Pier no. 12 for 8th lift of both gate grooves have been checked and found correct by HM Expert of PMC during his site visit on dt.01.06.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for M35A20 grade on 05.06.2026
11/100
Instream Storage Structure, Nandagaon
• 1. Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay no.12 of pier no.11 for 8th lift of main gate & 7th lift of stoplog gate grooves and Pier no. 12 for 8th lift of both gate grooves have been checked and found correct by HM Expert of PMC during his site visit on dt.01.06.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for M35A20 grade on 05.06.2026
12/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering is in progress at right abutment on 05.06.2026
13/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no. 12&13 on 05.06.2026
14/100
Instream Storage Structure, Nandagaon
Monorail walkway top and bottom drilling work under progress on 05.06.2026
15/100
Instream Storage Structure, Nandagaon
Gate no 14 Undersluice both barrage bay and stoplog gate 2nd stage embedded parts erection work under progress on 05.06.2026
16/100
Instream Storage Structure, Nandagaon
Placing of CC blocks is in progress at D/S side on 05.06.2026
17/100
Instream Storage Structure, Khalpal
Gravity Floor at Barrage Bay No-2 Preparation of filter bed and perforated pipe laying work in progress.
18/100
Instream Storage Structure, Khalpal
Shuttering of RHS Double Pier No-25, 1st lift is under progress.
19/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
20/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 42.22/mm2 for 27 days) of Cross Girder (Bay No-19) and M25A20 (Strength is 30.96/mm2 for 28 days) of D/S Flared our wall Raft at Block No-5 (Bank side) and (Strength is 21.48/mm2 for 07 days) of Abutment wall, 6th lift has done in presence of Client & PSS team.
21/100
Instream Storage Structure, Hamirpur
R.D.U frame welding work is in progress.
22/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-8 stiffener fixing work is in progress.
23/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
24/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-2, 8th lift is under progress.
25/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-3, 9th lift is under progress.
26/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Abutment (A1), 10th lift at Block No-1 is under progress.
27/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-7, pier Cap is under progress.
28/100
Instream Storage Structure, Jharbeda
Binding of reinforcement for RHS (D2) Middle portion pier is under progress.
29/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Curing of Raft is under progress.
30/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M25A20 (Value 85 mm) of RHS D/S Divide wall, 8th lift done in presence of Client & PSS Team.
31/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of RHS D/S Divide wall, 8th lift is under progress in presence of Client & PSS Team.
32/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 85 mm) of RHS D/S Counterfort & Wing wall, 1st lift- 2nd layer done in presence of Client & PSS Team.
33/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of RHS D/S Counterfort & Wing wall, 1st lift- 2nd layer is under progress in presence of Client & PSS Team.
34/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE Tee (125 X 75 ×75)mm connection at RO-26, near village Kusmel in presence of PMC team.
35/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress of OCS NO-0201211-CO5B 1HA outlet fixing work is in progress at village Sindurbahal in presence of PMC team.
36/100
UGPL, Right Lower Suktel Canal Division
OCS chamber above GL work is in progress of OCS No:- 0213109- C07B at village Kulthipali in presence of PMC team.
37/100
UGPL, Right Lower Suktel Canal Division
Joint verification is in progress for outlet of OCS 0213136-CO3B at village Keserkela in presence of PMC team and L&T personal.
38/100
UGPL, Left Lower Suktel Canal Division
Approach channel bell mouth portion stone pitching work is in progress at Pump House visited by DoWR SE.
39/100
UGPL, Left Lower Suktel Canal Division
HDD machine road pushing work is in progress (road crossing) of 75mm Dia HDPE pipe between RO-156 to RO-156A near village Manhira in presence of PMC team.
40/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for laying of 140mm Dia HDPE pipe Node J-71 to LO-174 LM-9, near village Bhadra in presence of PMC team.
41/100
UGPL, Left Lower Suktel Canal Division
Approach channel bell mouth portion stone pitching work is in progress at Pump House.
42/100
UGPL, Right Lower Suktel Canal Division
OCS chamber installation work is in progress of OCS no-0213131-C06B near village Takarla in presence of PMC team.
43/100
UGPL, Right Lower Suktel Canal Division
OCS chamber Below GL work is in progress of OCS No. 0213131-C10A at village Lokapara in presence of PMC team.
44/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for 75mm Dia HDPE pipe laying of OCS no-2305095-C08B-P08 and 1HA outlet subchak installation at village Jarajaraing.
45/100
UGPL, Right Lower Suktel Canal Division
OCS pre-cast chamber installation work is in progress of OCS no-2305095-C06A near village Jarajaring in presence of PMC team.
46/100
UGPL, Right Lower Suktel Canal Division
External drain Back filling work is in progress at Pump House.
47/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of U/S Flank wall, 2nd lift at Block No-1 done in presence of Client & PSS Team.
48/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of U/S Flank wall, 2nd lift at Block No-1 is under progress in presence of Client & PSS Team.
49/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE(225mm) to HDPE (125mm)pipe connection at J-294, RM-2 near village Kushmel in presence of PMC team.
50/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 21.48/mm2 for 07 days) of U/S Flared our wall Raft at Block No-1 (Bank side) and M25A20 (Strength is 21.18/mm2 for 07 days) of U/S Flared our wall Raft at Block No-1 (River side) and M30A20 (Strength is 28.15/mm2 for 07 days) of Groove 2nd stage, 5th lift (Bay No-9) has done in presence of Client & PSS team.
51/100
UGPL, Left Lower Suktel Canal Division
100mm Stem pipe fixing work is progress on Rm -13, from J-518 to J-247 at village Kusang.
52/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4, 5th lift is under progress.
53/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-, 9th lift is under progress.
54/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Abutment (A1), 7th lift at Block No-1 is under progress.
55/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for D/S Abutment (A1), 10th lift at Block No-1 is under progress.
56/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 80 mm) of RHS D/S Counterfort & Abutment wall, 1st lift done in presence of Client & PSS Team.
57/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of RHS D/S Counterfort & Abutment wall, 1st lift is under progress in presence of Client & PSS Team.
58/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Testing of Compressive M25A20 (Strength is 19.56/mm2 for 07 days) of RHS Divide wall, 2nd lift and M25A20 (Strength is 30.66/mm2 for 28 days) of RHS Double pier, 1st lift has done in presence of Client & PSS team.
59/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering & binding of reinforcement for RHS D/S Counterfort & Wing wall, 1st lift is under progress.
60/100
Instream Storage Structure, Jharbeda
Slump testing M25A20 (Value 55 mm) of RHS U/S Divide wall Footing, 1st lift done in presence of Client & PSS Team.
61/100
Instream Storage Structure, Jharbeda
Concreting M25A20 of RHS U/S Divide wall Footing, 1st lift is under progress in presence of Client & PSS Team.
62/100
Instream Storage Structure, Jharbeda
Slump testing M25A20 (Value 90 mm) of Pier No-6, Pier Cap done in presence of Client & PSS Team.
63/100
Instream Storage Structure, Jharbeda
Concreting M25A20 of Pier No-6, Pier Cap is under progress in presence of Client & PSS Team.
64/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency
65/100
Instream Storage Structure, Jharbeda
Curing of RHS (D2) pier portion wall is under progress.
66/100
Instream Storage Structure, Khalpal
Shuttering & Binding of reinforcement for RHS Double Pier No-25, 1st lift is under progress.
67/100
Instream Storage Structure, Khalpal
Curing of Gravity floor, Piers, Divide wall and Barrage Bay No-2 Raft is in progress.
68/100
Instream Storage Structure, Gudvella
Earthwork excavation is under progress at u/s side of ISS Gudvella on 04.06.2026
69/100
Instream Storage Structure, Gudvella
Connection of rope way is under progress at mechanical area on 04.06.2026
70/100
Instream Storage Structure, Gudvella
Plastering work at building area is under progress at site on 04.06.2026
71/100
Instream Storage Structure, Gudvella
D/s side view of ISS Gudvella on 04.06.2026
72/100
Instream Storage Structure, Gudvella
U/s side view of ISS Gudvella on 04.06.2026
73/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.10,11&12 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 87mm on 04.06.2026
74/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.10,11&12 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 87mm on 04.06.2026
75/100
Instream Storage Structure, Nandagaon
M25 A20 grade concrete wearing casting at bay no. 1 under sluice (from left side) is under progress. The slump test value is 86mm on 04.06.2026
76/100
Instream Storage Structure, Nandagaon
M25 A20 grade concrete wearing casting at bay no. 1 under sluice (from left side) is under progress. The slump test value is 86mm on 04.06.2026
77/100
Instream Storage Structure, Nandagaon
Painting work has been stopped due to labour issues on 04.06.2026
78/100
Instream Storage Structure, Nandagaon
2.(i) Cleaning of all deposited silt, sand and debris from crest, glacis and stilling basin area of bay -1 at undersluice area is completed in presence of PM EPC agency, Site Engineer's of PMC & EPC agency. (ii) The area is cleaned through air water jetting and passed by SE, Kid, Bhawanipatna for placing wearing coat concrete with PCC M25A20 grade on 04.06.2026
79/100
Instream Storage Structure, Nandagaon
• 1. Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay no.10 of pier no.10,11&12 for 4th lift have been checked and found correct by HM Expert of PMC during his site visit on dt.2.06.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs. (i) Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for M35A20 grade on 04.06.2026
80/100
Instream Storage Structure, Nandagaon
Gate no 14 Undersluice both barrage bay and stoplog gate 2nd stage embedded parts erection work under progress on 04.06.2026
81/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for OMS Line Z-3895, RO-27B, RM-2 at Kusmel is in presence of PMC team.
82/100
UGPL, Left Lower Suktel Canal Division
Approach channel bell mouth portion stone pitching work is in progress at Pump House.
83/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of D/S Flank wall Cut-off, 1st lift at Block No-1 done in presence of Client & PSS Team.
84/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S Flank wall Cut-off, 1st lift at Block No-1 is under progress in presence of Client & PSS Team.
85/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-1, 10th lift done in presence of Client & PSS Team.
86/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-1, 10th lift is under progress in presence of Client & PSS Team.
87/100
Instream Storage Structure, Hamirpur
MS plate marking and cutting for column work is in progress.
88/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-8 fixing work is in progress.
89/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
90/100
Instream Storage Structure, Hamirpur
Shuttering of Deck slab (Bay No-10 & 11) is under progress.
91/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 42.44/mm2 for 28 days) of Gantry Girder No-32 and M25A20 (Strength is 30.96/mm2 for 28 days) of Pier No-2, 6th lift and (Strength is 21.04/mm2 for 07 days) of Pier No-6, 14th lift and (Strength is 21.63/mm2 for 07 days) of Pier No-26, 13th lift and (Strength is 30.86/mm2 for 28 days) of D/S Flared out wall Raft (Bank side) has done in presence of Client & PSS team.
92/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4, 5th lift is under progress.
93/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall at Block No-1 is under progress.
94/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flank wall Cut-off at Block No-1 is under progress.
95/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Abutment (A1), 7th lift at Block No-1 is under progress.
96/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Abutment (A1), 10th lift at Block No-1 is under progress.
97/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M25A20 (Value 95 mm) of LHS Barrage Bay Raft, Final layer done in presence of Client & PSS Team.
98/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of LHS Barrage Bay Raft, Final layer is Completed in presence of Client & PSS Team.
99/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering & alignment of Gate groove is under progress.
100/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
De-Shuttering of Pier Cap is under progress.
❮
❯