GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Gudvella
Primer painting at building area is under progress at site on 18.08.2026
2/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 12nos. precast railing is in progress in presence of Site Engineers of PMC & EPC agency. The slump test value is 84mm on 18.08.2026
3/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 12nos. precast railing is in progress in presence of Site Engineers of PMC & EPC agency. The slump test value is 84mm on 18.08.2026
4/100
Instream Storage Structure, Nandagaon
Fixing of precast railing is in progress at deck slab no.6 on 18.08.2026
5/100
Barrage across river Turi & Guntat
The inspection walkway of Turi barrage is completed.
6/100
Barrage across river Turi & Guntat
Construction of Control room is in progress at Turi barrage site.
7/100
Instream Storage Structure, Gudvella
Putty work is under progress at control room of building area on 17.08.2026
8/100
Instream Storage Structure, Gudvella
Electrical wiring work is under progress at building area on 17.08.2026
9/100
Instream Storage Structure, Gudvella
Electrical wiring is under progress at building area at site on 16.08.2026
10/100
Instream Storage Structure, Gudvella
Primer painting at building area is under progress at site on 16.08.2026
11/100
Instream Storage Structure, Gudvella
Finishing work of putty and electrical wiring is under progress at building area on 15.08.2026
12/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 15.08.2026
13/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 15.08.2026
14/100
Instream Storage Structure, Gudvella
Celebrated the 80th Independence Day at ISS Gudvella on 15.08.2026
15/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 16nos. post at deck slab no. 7 is in progress in presence of Site Engineers of PMC & EPC agency on 17.08.2026
16/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 13nos. precast railing is in progress in presence of Site Engineers of PMC & EPC agency. The slump test value is 82mm on 17.08.2026
17/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 13nos. precast railing is in progress in presence of Site Engineers of PMC & EPC agency. The slump test value is 82mm on 17.08.2026
18/100
Instream Storage Structure, Nandagaon
Fixing of precast railing is in progress at deck slab no.7 on 17.08.2026
19/100
Instream Storage Structure, Nandagaon
Fixing of precast railing is in progress at deck slab no.7 on 16.08.2026
20/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 16nos. post at deck slab no.8 is in progress in presence of Site Engineers of PMC & EPC agency on 15.08.2026
21/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 14nos. precast railing is in progress in presence of Site Engineers of PMC & EPC agency. The slump test value is 83mm on 15.08.2026
22/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 14nos. precast railing is in progress in presence of Site Engineers of PMC & EPC agency. The slump test value is 83mm on 15.08.2026
23/100
Instream Storage Structure, Nandagaon
Fixing of precast railing is in progress at deck slab no.8 on 15.08.2026
24/100
Instream Storage Structure, Hamirpur
Testing of Compressive M35A20 (Strength is 38.07/mm2 for 07 days) of Gantry Girder No-57 has done in presence of Client & PSS team.
25/100
Instream Storage Structure, Hamirpur
Column base plate drilling work is in progress.
26/100
Instream Storage Structure, Hamirpur
MS angle plate marking and cutting for Column bracing work is in progress.
27/100
Instream Storage Structure, Hamirpur
Column Trestle No-23 welding work is in progress.
28/100
Instream Storage Structure, Hamirpur
Shuttering & binding of reinforcement for U/S Flank wall, 13th lift at Block No-5 is under progress.
29/100
Instream Storage Structure, Hamirpur
Shuttering & binding of reinforcement for D/S Flank wall, 7th lift at Block No-5 is under progress.
30/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 180.720m.
31/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 60.7m.
32/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at Telkoi site.
33/100
Instream Storage Structure, Gudvella
Electrical wiring work is under progress at building area on 14.08.2026
34/100
Instream Storage Structure, Gudvella
Finishing work of putty is under progress at building area on 14.08.2026
35/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 14.08.2026
36/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 14.08.2026
37/100
Instream Storage Structure, Gudvella
Putty work at the building area is under progress at site on 13.08.2026
38/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 13.08.2026
39/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 13.08.2026
40/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 16nos. post at deck slab no.9 is in progress in presence of Site Engineers of PMC & EPC agency on 14.08.2026
41/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 21nos. precast railing is in progress in presence of Site Engineers of PMC & EPC agency. The slump test value is 82mm on 14.08.2026
42/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 21nos. precast railing is in progress in presence of Site Engineers of PMC & EPC agency. The slump test value is 82mm on 14.08.2026
43/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for precast railing is in progress on 14..08.2026
44/100
Instream Storage Structure, Nandagaon
Fixing of precast railing is in progress at deck slab no.8&9 on 14.08.2026
45/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 19nos. precast railing is in progress in presence of Site Engineers of PMC & Site Engineer of EPC agency on 13.08.2026
46/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 16nos. post at deck slab no.10 is in progress in presence of Site Engineers of PMC & EPC agency. The slump test value is 85mm on 13.08.2026
47/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M35A20 grade for 16nos. post at deck slab no.10 is in progress in presence of Site Engineers of PMC & EPC agency. The slump test value is 85mm on 13.08.2026
48/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering for precast railing is in progress on 13.08.2026
49/100
Instream Storage Structure, Dhanei
Visit of SD Expert PMC, both the RIs of Chirikipada and Laxmanapali and also agency staff attend during inspection. Physically observed the afflux bond by walkway survey.
50/100
Instream Storage Structure, Dhanei
Visit of SD Expert PMC, both the RIs of Chirikipada and Laxmanapali and also agency staff attend during inspection. Physically observed the afflux bond by walkway survey.
51/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.63/mm2 for 07 days) of Flank wall, 6th lift has done in presence of Client & PSS team.
52/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 181.260m.
53/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.78/mm2 for 07 days) of Flank wall, 12th lift and (Strength is 31.16/mm2 for 28 days) of Pier No-25, 13th lift and M35A20 (Strength is 37.48/mm2 for 07 days) of Gantry Girder No-56 has done in presence of Client & PSS team.
54/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 181.900m.
55/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Present status of river Samakoi at Santeibhanja site.
56/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Deck Slab Railing Beam (Bay No-26, 27, 28 & 29) at Block No-5 done in presence of Client & PSS Team.
57/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Deck Slab Railing Beam (Bay No-26, 27, 28 & 29) at Block No-5 is under progress in presence of Client & PSS Team.
58/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-59, 60, 61 & 62 done in presence of Client & PSS Team.
59/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-59, 60, 61 & 62 is under progress in presence of Client & PSS Team.
60/100
Instream Storage Structure, Hamirpur
Column Trestle bracing fixing work is in progress.
61/100
Instream Storage Structure, Hamirpur
Shuttering & binding of reinforcement for U/S Flank wall, 13th lift at Block No-5 is under progress.
62/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
63/100
Instream Storage Structure, Hamirpur
Shuttering of D/S Flank wall, 7th lift at Block No-5 is under progress.
64/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 181.880m.
65/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.99/mm2 for 28 days) of Flank wall, 3rd lift and M35A20 (Strength is 42.45/mm2 for 28 days) of Gantry Girder No-48 has done in presence of Client & PSS team.
66/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 180.310m.
67/100
Instream Storage Structure, KansariGanda
Visit of SD Expert of PMC and Amin along with two officials from the agency to the ISS site. during inspection they are exposed to the afflux bond from UDSpur to towards down stream. Around 2 km walkway visit and random measurement is done. Due to rain and bushy jungal, they could not complete it. Around 1 km of mid part remained unexplored.
68/100
Instream Storage Structure, KansariGanda
Visit of SD Expert of PMC and Amin along with two officials from the agency to the ISS site. during inspection they are exposed to the afflux bond from UDSpur to towards down stream. Around 2 km walkway visit and random measurement is done. Due to rain and bushy jungal, they could not complete it. Around 1 km of mid part remained unexplored.
69/100
Instream Storage Structure, KansariGanda
Visit of SD Expert of PMC and Amin along with two officials from the agency to the ISS site. during inspection they are exposed to the afflux bond from UDSpur to towards down stream. Around 2 km walkway visit and random measurement is done. Due to rain and bushy jungal, they could not complete it. Around 1 km of mid part remained unexplored.
70/100
Instream Storage Structure, KansariGanda
Visit of SD Expert of PMC and Amin along with two officials from the agency to the ISS site. during inspection they are exposed to the afflux bond from UDSpur to towards down stream. Around 2 km walkway visit and random measurement is done. Due to rain and bushy jungal, they could not complete it. Around 1 km of mid part remained unexplored.
71/100
Instream Storage Structure, Khalpal
Slump testing M35A20 (Value 85 mm) of Girder No-58 done in presence of Client & PSS Team.
72/100
Instream Storage Structure, Khalpal
Concreting M35A20 of Girder No-58 is under progress in presence of Client & PSS Team.
73/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 59.74m.
74/100
Instream Storage Structure, KansariGanda
Visit of SD Expert PMC and the newly joined Amin along with two officials from the agency is taken to the afflux bond with map and ROR and practically shown the affected area. Walked around 2 km from barrage towards upstream to observe the land. It will help the newly joined Amin to work with the people when re-demarcation is initiated.
75/100
Instream Storage Structure, KansariGanda
Visit of SD Expert PMC and the newly joined Amin along with two officials from the agency is taken to the afflux bond with map and ROR and practically shown the affected area. Walked around 2 km from barrage towards upstream to observe the land. It will help the newly joined Amin to work with the people when re-demarcation is initiated.
76/100
Instream Storage Structure, KansariGanda
Visit of SD Expert PMC and the newly joined Amin along with two officials from the agency is taken to the afflux bond with map and ROR and practically shown the affected area. Walked around 2 km from barrage towards upstream to observe the land. It will help the newly joined Amin to work with the people when re-demarcation is initiated.
77/100
Instream Storage Structure, KansariGanda
14.08.26 -water level 2.5
78/100
Instream Storage Structure, KansariGanda
10.08.26 -water level 2.5
79/100
Instream Storage Structure, KansariGanda
09.08.26 -water level 2.6
80/100
Instream Storage Structure, KansariGanda
08.08.26 -water level 2.6
81/100
Instream Storage Structure, KansariGanda
08.08.26 -water level 2.6
82/100
Instream Storage Structure, KansariGanda
07.08.26 -water level 2.5
83/100
Instream Storage Structure, Jharbeda
Present flow condition of river at Jharbeda site water level RL 192.6m.
84/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at Telkoi site.
85/100
Instream Storage Structure, Gudvella
Putty work at the building area is under progress at site on 12.08.2026
86/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 12.08.2026
87/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 12.08.2026
88/100
Instream Storage Structure, Nandagaon
Mechanical erection work has been stopped today due to labour issues on 12.08.2026
89/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.99/mm2 for 28 days) of Flank wall, 9th lift at Block No-5 and M30A20 (Strength is 37.48/mm2 for 28 days) of Groove 2nd stage, 1st lift (Bay No-21, 22 & 27) has done in presence of Client & PSS team.
90/100
Instream Storage Structure, Hamirpur
Column Trestle No-22 welding work is in progress.
91/100
Instream Storage Structure, Hamirpur
Column base plate drilling work is in progress.
92/100
Instream Storage Structure, Hamirpur
Shuttering & binding of reinforcement for U/S Flank wall, 13th lift at Block No-5 is under progress.
93/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
94/100
Instream Storage Structure, Hamirpur
Shuttering & binding of reinforcement for D/S Flank wall, 7th lift at Block No-5 is under progress.
95/100
Instream Storage Structure, Hamirpur
Present flow condition of river at Hamirpur site water level RL 180.740m.
96/100
Instream Storage Structure, Khalpal
Binding of reinforcement for Girder No-58 is under progress.
97/100
Instream Storage Structure, Khalpal
Curing of Girders is under progress.
98/100
Instream Storage Structure, Khalpal
Present flow condition of river at Khalpal site water level RL 58.8m.
99/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Present status of river Samakoi at Telkoi site.
100/100
Instream Storage Structure across river Sapei near village Kinjirma
Flow direction is straight flow is seen at RL- 207.00 against crest level RL- 206.25 . . Water is flowing 0.75m above the crest l

Enter Login Details

Forgot Password ?