1/100
Instream Storage Structure, Hamirpur
Girder No-10th & 11th is being lifted for fixing in the middle of 26th Span at Block No-5.
2/100
Instream Storage Structure, Hamirpur
D/S approne stone packing is under progress.
3/100
Instream Storage Structure, Hamirpur
Concreting M15A40 of U/S Flared out wall, 5th lift at Block No-5 is under progress in presence of Client & PSS Team.
4/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of D/S End sill (Bay No-11) at Block No-2 done in presence of Client & PSS Team.
5/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of D/S End sill (Bay No-11) at Block No-2 is under progress in presence of Client & PSS Team.
6/100
Instream Storage Structure, Hamirpur
Hoist bridge platform girder welding work is in progress.
7/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-14, 9th lift is under progress.
8/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-11, 11th lift is under progress.
9/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-20, 12th lift is under progress.
10/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-22, 13th lift is under progress.
11/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of Pier No-6 to Pier No-7 D/S Gravity floor, 1st lift PCC is under progress in presence of Client & PSS Team.
12/100
Instream Storage Structure, Jharbeda
Curing of Pier No-6 is under progress.
13/100
Instream Storage Structure, Jharbeda
Slump testing M20A20 (Value 50 mm) of Pier No-7 D/S Gravity floor, 2nd lift PCC done in presence of Client & PSS Team.
14/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of Pier No-7 D/S Gravity floor, 2nd lift PCC is under progress in presence of Client & PSS Team.
15/100
Instream Storage Structure, Jharbeda
De-shuttering of Pier No-6, 4th lift is under Progress.
16/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
17/100
Instream Storage Structure, Khalpal
Visited by QC&QA Expert, PMU in presence of Dy. TL, CME, QAE, IEE of PSS team, A.E.E & A.E, AID along with representative of EPC agency regarding checking for binding of reinforcement & concreting of Raft, Shuttering & binding of reinforcement for Girders and other ongoing activities at Site.
18/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 95 mm) of Left under sluice bay (Raft Concreting) done in presence of Client & PSS Team.
19/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Left under sluice bay (Raft Concreting) is under progress in presence of Client & PSS Team.
20/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of D/S Divide wall, 2nd lift is under Progress.
21/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of Middle pier, 5th lift is under Progress.
22/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for D/S Wing wall is under progress.
23/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
De-Shuttering of LHS Mid-pier, 6th lift is under Progress.
24/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Testing of Compressive M25A20 (Strength is 30.05/mm2 for 28 days) of LHS Counterfort & Abutment wall, 3rd lift and M20A20 (Strength is 23.77/mm2 for 07 days) of Gravity floor has done in presence of Client & PSS team.
25/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS Counterfort & Abutment wall, 6th lift is under Progress.
26/100
UGPL, Right Lower Suktel Canal Division
Internal drain top portion plastering work in progress at Pump House.
27/100
UGPL, Right Lower Suktel Canal Division
OCS Chamber Below NGL levelling OCS erection work is in progress of OCS no 0213080-C16B at village Gaintala
28/100
UGPL, Left Lower Suktel Canal Division
Internal Approach road left side block No01) & right side block No-(01) casting work is in progress at Pump House.
29/100
UGPL, Left Lower Suktel Canal Division
Slump testing work is in progress for internal approach road block casting at Pump House in presence of DoWR JE with department QA/QC, PMC team and MEIL staff.
30/100
Instream Storage Structure, Kopsinga
Slump-90mm
31/100
Instream Storage Structure, Kopsinga
Pier no (21-22) span Vent 22 2nd stage shuttering work check now the area ready for casting.
32/100
Instream Storage Structure, Kopsinga
Wing wall 7th lift shuttering work
33/100
Instream Storage Structure, Kopsinga
Pier no 6 gate grove chipping work
34/100
Instream Storage Structure, Budharaja
Curing Work is in Progress.
35/100
Instream Storage Structure, Budharaja
De-Shuttering work in 13th Step & Shuttering Work is in Progress at RHS U/S Flared-Out Wall, 14th Step. RL: 214.100 to 214.700.
36/100
Instream Storage Structure, Budharaja
Shuttering Work is in Progress at LHS U/S Flared-Out Wall, 17th Step. RL: 215.300 to 215.900.
37/100
Instream Storage Structure Across Bheden near village Saida
Foundation excavation of RHS u/s flared out wall completed. Rock outcrops are noticed at left corner of flank wall & right u/s corner of flared out wall .Advised to go for anchoring on rock strata& remove slushy soil from other portion before laying PCC.
38/100
UGPL, Left Lower Suktel Canal Division
Laying work is in progress of 75mm Dia HDPE pipe of OMS LO-285B ,Z-7149 ,LM-15 near village Buromunda.
39/100
Instream Storage Structure Across Bheden near village Saida
Checked centering, shuttering as well as reinforcement of deck slab in between P5 & RHS divide wall.
40/100
Instream Storage Structure Across Bheden near village Saida
Checked centering, shuttering as well as reinforcement of deck slab in between P5 & RHS divide wall.
41/100
Instream Storage Structure Across Bheden near village Saida
Trestle or column's Block out area Base plate fit up work is in progress of Barrage Bay no-1.
42/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 280mm Dia HDPE pipeline from node J-576 to J-431, LM-16 near Sargad.
43/100
UGPL, Left Lower Suktel Canal Division
Butt fusion joint work is in progress of 280mm Dia HDPE pipe node from J-576 to J-431 LM-16 near village Sargad in presence of PMC team.
44/100
Instream Storage Structure Across Bheden near village Saida
RHS U/S Flared out wall mud cleaning work is going on .
45/100
Instream Storage Structure Across Bheden near village Saida
RHS U/S Flank wall curing work is going on .
46/100
Instream Storage Structure Across Bheden near village Saida
P-5 to RHS Divide wall between mid portion Deck slab staging work is in progress .
47/100
Instream Storage Structure, Gochara
Inspection of Electrical Panels (MDB,SDBs & LCPs) for ISS Gochhara has been carried out today at the Works(M/s Sri Sai Engineering, Jharsuguda) of EPC Agency. The tests were witnessed by Dept AEE,E&A Expert of PMC in presence of Elect Engineer of Agency. The Agency has been instructed to submit Inspection Reports for approval.
48/100
Instream Storage Structure, Gochara
Staff quarter brick work is on progress.
49/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
50/100
Instream Storage Structure, Khirasasan
LHS U/S FLARED OUT WALL 14 LIFT deshuttring work under progress
51/100
Instream Storage Structure, Khirasasan
LHS D/S FLARED OUT WALL FINAL LIFT SHUTTERING WORK UNDER PROGRESS
52/100
Instream Storage Structure, Khirasasan
RHS D/S FLANK WALL 8TH LIFT SHUTTERING WORK COMPLETE AND ready for concrete casting
53/100
Instream Storage Structure, Khirasasan
RHS divide wall hoist portion shuttering work under progress
54/100
Instream Storage Structure, Khirasasan
RHS D/S C F WING WALL 10 TH LIFT SHUTTERING WORK COMPLETE AND ready for concrete casting
55/100
Instream Storage Structure, Khirasasan
RHS ABUTMENT HOIST PORTION SHUTTERING WORK UNDER PROGRESS
56/100
Instream Storage Structure, Kudabega
Slump 80mm
57/100
Instream Storage Structure, Kudabega
Barrage bay-3 span no-05 p-05 & p-04 M30A20 for stoplog & service gate groove 2nd stage 1th lift casting work in progress
58/100
Instream Storage Structure, Kudabega
Span no-03 service gate erection work in progress.
59/100
Instream Storage Structure, Kudabega
Span no-03 D/S Handrail beam fixing with Post shuttering work in progress
60/100
Instream Storage Structure, Kudabega
Span no-01 Kerb deshuttering work in progress
61/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Monorail girder's joints work is in progress
62/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Hoist bridge's 30th platform assembly work is in progress
63/100
Instream Storage Structure, Kuakhai
Casting of RCC M25A20 at L/s block, U/S flank wall raft is under progress.
64/100
Instream Storage Structure, Kuakhai
Reinforcement binding at Left U/S divide wall pier is under progress.
65/100
Instream Storage Structure, Kuakhai
Side shuttering in progress at left side counterfort wall portion.
66/100
Instream Storage Structure, Kuakhai
Flank wall raft rebar arrangement at D/s side of L/s block.
67/100
Instream Storage Structure, Kuakhai
Casting of RCCM25A20 at Left block, U/s Flank wall raft from RL 6.5m to 7.8m in progress.
68/100
Instream Storage Structure, Kuakhai
Casting of RCC M25A20 at L/s block, U/s divide wall, 4th lift from RL 12.55m to 13.95m is completed.
69/100
Instream Storage Structure, Kuakhai
Pier cap reinforcement bar arrangement in progress at Pier no.11.
70/100
Instream Storage Structure, Kuakhai
Casting of 4th lift of L/s block, U/s divide wall from RL 12.55m to 13.95m in progress.
71/100
Instream Storage Structure, Kuakhai
Casting of RCC M25A20 at Pier no.9 (Block out portion) in progress.
72/100
Instream Storage Structure, Kuakhai
Reinforcement binding in progress at left side upstream flankwall raft portion.
73/100
Instream Storage Structure, Kuakhai
Ongoing reinforcement binding at left side D/S flank wall raft portion.
74/100
Instream Storage Structure, Kuakhai
Casting of RCC M30A20 at L/s abutment 4th lift of Zone- 5 from RL 10.05m to 11.45m in progress.
75/100
Instream Storage Structure, Kuakhai
U/s flank wall reinforcement bar arrangement in progress at L/s block.
76/100
Instream Storage Structure, Kuakhai
28 days Cube test for RCCM25A20 done at field laboratory of the ISS.
77/100
Instream Storage Structure, Kuakhai
L/s block, D/s flank wall raft reinforcement bar arrangement in progress.
78/100
Instream Storage Structure, Kuakhai
Reinforcement binding and side shuttering in progress at left side U/s flankwall raft, left side counterfort wall.
79/100
Instream Storage Structure, Kuakhai
Casting of RCC M25A20 at Pier no.3 (6th lift) from RL 13.35m to 14.75m in progress.
80/100
Instream Storage Structure, Kuakhai
Reinforcement binding inn progress at left side barrage bay piers.
81/100
Instream Storage Structure, Kuakhai
L/s block, U/s flank wall reinforcement bar arrangement is in progress
82/100
Instream Storage Structure, Kuakhai
Casting of RCC M25A20 in pier no.6 in progress.
83/100
Instream Storage Structure, Kuakhai
Slump test done at site, slump value is 90mm.
84/100
Instream Storage Structure, Kuakhai
Casting of RCC M25A20 in Pier no. 6 from RL 14.75m to 16.15m in progress.
85/100
Instream Storage Structure, Kuakhai
Boulder packing in progress at left side D/S flank wall raft portion.
86/100
Instream Storage Structure, Kuakhai
Inspection of ongoing reinforcement binding at left side upstream flank wall raft by PSS Team.
87/100
Instream Storage Structure, Kuakhai
Casting of M30A20 at L/s abutment, 3rd lift of (Zone-3 & 4) from RL 8.65m to RL 10.05m is completed.
88/100
Instream Storage Structure, Kuakhai
SDO, balianta observing the ongoing casting work at pier no.5.
89/100
Instream Storage Structure, Kuakhai
Slump test done at site, slump value is 90mm.
90/100
Instream Storage Structure, Kuakhai
Curing of piers in progress.
91/100
Instream Storage Structure, Kuakhai
Irr. Expert, PSS verifying the blockout reinforcement bar arrangement and binding work at Pier no.12A.
92/100
Instream Storage Structure, Kuakhai
Casting of RCC M25A20 at pier no.5, 4th lift from RL 10.55m to 11.95m in progress.
93/100
Instream Storage Structure, Kuakhai
Inspection of ongoing reinforcement binding at left side U/S flank wall raft by PSS Team, Deptt., OCCL & the Agency.
94/100
Instream Storage Structure, Kuakhai
Casting of M30A20 at Left abutment, 3rd lift casing portion of Zone-3 & 4 from RL 8.65m to RL 10.05m in progress.
95/100
Instream Storage Structure, Kuakhai
Reinforcement binding in progress at left U/S flank wall raft.
96/100
Instream Storage Structure, Kuakhai
Casting of RCC M25A20 at left U/S divide wall pier 3rd lift is completed.
97/100
Instream Storage Structure, Kuakhai
Casting of RCC M25A20 at left D/S flank wall cutoff is completed.
98/100
Instream Storage Structure, Kuakhai
Casting of RCC M25A20 at left U/S divide wall pier 3rd lift from RL 11.15m to 12.55m in progress.
99/100
Instream Storage Structure, Kuakhai
Casting of RCC M25A20 at Left D/S divide wall (1st lift) from RL 7.85m to 9.25m is completed.
100/100
Instream Storage Structure, Kuakhai
Curing of piers in progress.
❮
❯