1/100
Instream Storage Structure, Gudvella
• 1. Cast of concrete RCC M25A20 grade at plinth beam of building is in progress
2. Slump checked at site and slump value is 70mm.
3. Casting of cubes done at site.
4. Conducted test for 7 days compressive strength of concrete cube RCC M25 A20 grade at field. laboratory and result found 23.18 N/mm2.
5. Conducted test for 7 days compressive strength of concrete cube PCC M15A40 grade and result found 15.99 N/mm2.
6. Conducted 7 days compressive strength of concrete cube PCC M20A20 grade and result found 18.36 N/mm2
7. Test for 28 days compressive strength of concrete cube RCC M25 A20 grade conducted and result found 35.29 N/mm2 on 03.02.2026
2/100
Instream Storage Structure, Gudvella
• 1. Cast of concrete RCC M25A20 grade at plinth beam of building is in progress
2. Slump checked at site and slump value is 70mm.
3. Casting of cubes done at site.
4. Conducted test for 7 days compressive strength of concrete cube RCC M25 A20 grade at field. laboratory and result found 23.18 N/mm2.
5. Conducted test for 7 days compressive strength of concrete cube PCC M15A40 grade and result found 15.99 N/mm2.
6. Conducted 7 days compressive strength of concrete cube PCC M20A20 grade and result found 18.36 N/mm2
7. Test for 28 days compressive strength of concrete cube RCC M25 A20 grade conducted and result found 35.29 N/mm2 on 03.02.2026
3/100
Instream Storage Structure, Gudvella
• During visit of the ISS work at Gudvela, it was observed that the RHS A2 body wall shuttering is in progress up to level 159.50 m. The upstream (U/s) flank wall and wing wall have been completed in all respects.
On the downstream (D/s) side, the wing wall has been completed up to RL 154.15 m, and the flank wall shuttering has been completed for the final lift up to RL 159.50 m. The flared-out walls on both U/s and D/s sides have been completed up to RL 156.40 m.
Further, the placing of CC blocks on the D/s side is presently in progress and is being carried out as per the approved drawings.
Further suggested the site engineers of the agency to submit drawings and design of approach road, affix bund and sluice gate required u/s side on 03.02.2026
4/100
Instream Storage Structure, Gudvella
• During visit of the ISS work at Gudvela, it was observed that the RHS A2 body wall shuttering is in progress up to level 159.50 m. The upstream (U/s) flank wall and wing wall have been completed in all respects.
On the downstream (D/s) side, the wing wall has been completed up to RL 154.15 m, and the flank wall shuttering has been completed for the final lift up to RL 159.50 m. The flared-out walls on both U/s and D/s sides have been completed up to RL 156.40 m.
Further, the placing of CC blocks on the D/s side is presently in progress and is being carried out as per the approved drawings.
Further suggested the site engineers of the agency to submit drawings and design of approach road, affix bund and sluice gate required u/s side on 03.02.2026
5/100
Instream Storage Structure, Gudvella
Casting of concrete RCC M25A20 grade at plinth beam of building is under progress in the presence of IE expert sir, QC expert sir, Dept JE, site engineer of PMC and agency. The slump test value is 70mm on 03.02.2026
6/100
Instream Storage Structure, Gudvella
Casting of concrete RCC M25A20 grade at plinth beam of building is under progress in the presence of IE expert sir, QC expert sir, Dept JE, site engineer of PMC and agency. The slump test value is 70mm on 03.02.2026
7/100
Instream Storage Structure, Gudvella
Cast of concrete RCC M25A20 grade at plinth beam of building is under progress in the presence of Dept JE, site engineer of PMC and agency. The slump test value is 85mm on 03.02.2026
8/100
Instream Storage Structure, Gudvella
Cast of concrete RCC M25A20 grade at plinth beam of building is under progress in the presence of Dept JE, site engineer of PMC and agency. The slump test value is 85mm on 03.02.2026
9/100
Instream Storage Structure, Gudvella
Column assembly work is under progress on 03.02.2026
10/100
Instream Storage Structure, Gudvella
Roller track and guide installation work at barrage bay no 6 is under progress on 03.02.2026
11/100
Instream Storage Structure, Gudvella
Roller track and guide installation work at barrage bay no 6 is under progress on 03.02.2026
12/100
Instream Storage Structure, Gudvella
Curing work is under progress on 03.02.2026
13/100
Instream Storage Structure, Gudvella
Reinforcement work at right side D/s abutment A2 for 9th lift RCC is under progress on 03.02.2026
14/100
Instream Storage Structure, Gudvella
Reinforcement work at A2 d/s flank wall for 8th lift RCC is under progress on 03.02.2026
15/100
Instream Storage Structure, Gudvella
Placement of CC block at D/s side is under progress on 03.02.2026
16/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade for right abutment wall along with CF walls from double CF wall CJ to U/S EJ for 6th lift at D/S area and 5th lift at U/S side upto RL-240.35m is in progress through concrete pump in presence of PM,EPC agency,Site Engineers of PMC & Site Engineer of EPC agency. The slump test value is 81mm on 03.02.2026
17/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade for right abutment wall along with CF walls from double CF wall CJ to U/S EJ for 6th lift at D/S area and 5th lift at U/S side upto RL-240.35m is in progress through concrete pump in presence of PM,EPC agency,Site Engineers of PMC & Site Engineer of EPC agency. The slump test value is 81mm on 03.02.2026
18/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.6&7 for 5th lift of bay no.7 is in progress in presence of PM,EPC agency,Site Engineers of PMC & Site Engineer of EPC agency. The slump test value is 86mm on 03.02.2026
19/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade for 2nd stage concrete for stoplog & service gate grooves at Pier no.6&7 for 5th lift of bay no.7 is in progress in presence of PM,EPC agency,Site Engineers of PMC & Site Engineer of EPC agency. The slump test value is 86mm on 03.02.2026
20/100
Instream Storage Structure, Nandagaon
• 3. Checked the area of right abutment along with CF walls with following activities in presence of PM, EPC agency, Site Engineers of PMC & Site Engineer of EPC agency:-
(i).Checked the reinforcement in binding, tying n spacing of both vertical main & horiz. dist. bars of right abutment along with CF walls from double CF wall CJ to U/S EJ for 6th lift at U/S floor and 6th lift at D/S portion of stilling basin area from RL-239.05m to RL-239.35m completed.
(ii) Rigid n smooth shuttering with 75mm clear cover using cover blocks of 75mm are done.
(iii) Placing of expansion joint material along the EJ between U/S right flank wall & abutment wall is done as per approved drawing n design.
(iv) The concrete surface is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with RCC M25A20 grade on 03.02.2026
21/100
Instream Storage Structure, Nandagaon
• 2. Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay No.7 of Pier No. 6&7 for 5th lift has been checked and found correct by HM Expert of PMC during his site visit on dt.02.02.2026 in presence of all civil n mechanical Site Engineers of PMC & EPC Agency as per the approved Mechanical drawing & designs.
(i)Accordingly the rigid n smooth shuttering for placing the 2nd stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii) The area is cleaned properly through air water jetting and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 03.02.2026
22/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of 2nos. CC blocks at U/S right Flared out wall i.e 1no. at sec.4-4 for 10th lift and 1no. from sec. 1-1 to sec. 2-2 for 5th lift of 0.6m ht. upto RL-242.40m is in progress in presence of PM EPC agency,Site Engineer of PMC & EPC agency. The slump test value is 82mm on 03.02.2026
23/100
Instream Storage Structure, Nandagaon
Concrete casting with PCC M20A20 grade of 2nos. CC blocks at U/S right Flared out wall i.e 1no. at sec.4-4 for 10th lift and 1no. from sec. 1-1 to sec. 2-2 for 5th lift of 0.6m ht. upto RL-242.40m is in progress in presence of PM EPC agency,Site Engineer of PMC & EPC agency. The slump test value is 82mm on 03.02.2026
24/100
Instream Storage Structure, Nandagaon
• 1.The casting of CC blocks at following area have been checked in presence of PM, EPC agency, Site Engineers of PMC & EPC Agency:
(i) 2Nos. CC blocs at U/S right Flared out wall i.e 1no. of size 6.0x1.5x0.6m at sec.4-4 for 10th lift and 1no. of size 6.0x1.5x0.6m from sec. 1-1 to sec. 2-2 for 5th lift upto RL-242.40m is completed. (ii) Filling of inverted filter materials covering with LDPE paper adjacent to each CC block in earth side are done before placement.
(iii) Application of 2 coat bitumen paint at cj's concrete surface is done.
(iv). Area is ready and passed by SE KID, Bh. Patna to place concrete with PCC M20A20 grade on 03.02.2026
25/100
Instream Storage Structure, Nandagaon
Monorail girder MIG welding under progress on 03.02.2026
26/100
Instream Storage Structure, Nandagaon
Trestle fit up, assembly and welding under progress on 03.02.2026
27/100
Instream Storage Structure, Nandagaon
2nd nos of under sluice gate both barrage bay gate and stoplog gate side sil beam, roller track and centre guide erection work under progress on 03.02.2026
28/100
Instream Storage Structure, Nandagaon
Reinforcement binding, shuttering & curing at right abutment Block-2 is in progress on 03.02.2026
29/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete at pier no 6&7, bay-7 Block-1 is in progress on 03.02.2026
30/100
Instream Storage Structure, Nandagaon
Curing at U/S right flared out wall, Block-2 is under progress on 03.02.2026
31/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-19, 11th lift at Block No-3 is under progress in presence of Client & PSS Team.
32/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-9, 13th lift at Block No-2 is under progress in presence of Client & PSS Team.
33/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-14, 10th lift done in presence of Client & PSS Team.
34/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-14, 10th lift is under progress in presence of Client & PSS Team.
35/100
Instream Storage Structure, Hamirpur
Column trestle welding work is in progress.
36/100
Instream Storage Structure, Hamirpur
C.D.U frame work is in progress.
37/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Deck slab is under progress.
38/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-30, 7th lift is under progress.
39/100
Integrated Barrage across river Kochila and across river Baitarini
PMC-MBBS chandikhol visite ISS-Kochila-Baitarani ISS project today. Discussion was held about project work with the Agency-04.02.2026
40/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-16, 4th lift is under progress.
41/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-10, 14th lift is under progress.
42/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-8, 13th is under progress.
43/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-7, 8th lift is under progress.
44/100
Instream Storage Structure, Jharbeda
Slump testing M25A20 (Value 80 mm) of Pier No-8 Footing, 1st lift done in presence of Client & PSS Team.
45/100
Instream Storage Structure, Jharbeda
Concreting M25A20 of Pier No-8 Footing, 1st lift is under progress in presence of Client & PSS Team.
46/100
Instream Storage Structure, Jharbeda
Drilling & Excavation of RHS D/S under sluice Overburden Rock Breaking work is under progress.
47/100
Instream Storage Structure, Jharbeda
De-Shuttering of Pier No-5 is under Progress.
48/100
Instream Storage Structure, Jharbeda
Cleaning of RHS Abutment area is in Progress.
49/100
Instream Storage Structure, Jharbeda
De-Shuttering of U/S Gravity floor Pier No-6 to Pier No-7 is under Progress.
50/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
51/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 150 mm) of U/S Left sluice bay Flank wall cross cut-off Panel No-20 done in presence of Client & PSS Team.
52/100
Instream Storage Structure, Khalpal
Concreting M25A20 of U/S Left sluice bay Flank wall cross cut-off Panel No-20 done in presence of Client & PSS Team
53/100
Instream Storage Structure, Khalpal
Slump testing M35A20 (Value 80 mm) of Girder No-36 done in presence of Client & PSS Team.
54/100
Instream Storage Structure, Khalpal
Concreting M35A20 of Girder No-36 is under progress in presence of Client & PSS Team.
55/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of Middle cross cut-off, 2nd lift is under progress in presence of Client & PSS Team.
56/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Testing of Compressive M25A20 (Strength is 20.29/mm2 for 07 days) of Divide wall, 2nd lift has done in presence of Client & PSS team.
57/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for of Divide wall, 6th lift and Divide wall, 4th and Abutment counterfort, 4th lift is under Progress.
58/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Excavation of LHS side Abutment cut-off is under Progress.
59/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 85 mm) of LHS Divide wall, 5th lift done in presence of Client & PSS Team.
60/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS Divide wall, 5th lift is under progress in presence of Client & PSS Team.
61/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Shuttering of LHS Counterfort & Abutment, 7th lift is under Progress.
62/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for RHS Barrage bay Raft is under Progress.
63/100
Instream Storage Structure Across Bheden near village Saida
Shuttering work progress in RHS d/s flank wall 4th lift
64/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from D/S of river
65/100
Instream Storage Structure, Budharaja
Slump Value: 60mm.
66/100
Instream Storage Structure, Budharaja
checked placing and positioning of Supporting bars and alignment of shuttering work in RHS U/S Flaired-Out wall, 18th Step. RL: 215.900 to 216.500. Now the area is ready for concrete casting M20 A20. So recommended for the purpose.
Approved by AEE sir SID Sambalpur in the presence of JE sir.
67/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at RHS D/S Flared-Out Wall, 21th Step. RL: 217.700 to 218.300.
68/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at RHS U/S Flared-Out Wall, 18th Step. RL: 215.900 to 216.500.
69/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S
70/100
Instream Storage Structure, Kudabega
Slump 80mm
71/100
Instream Storage Structure, Kudabega
Barrage bay-3 span no-05 p-05 & p-04 M30A20 for stoplog & service gate groove 2nd stage 5th top lift casting work in progress
72/100
Instream Storage Structure, Kudabega
Slump 85mm
73/100
Instream Storage Structure, Kudabega
Barrage bay-3 span no-07 p-07 & p-06 M30A20 for stoplog & service gate groove 2nd stage 3rd lift casting work in progress
74/100
Instream Storage Structure, Kudabega
Reinforcement of staff quarter building
75/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Hoist bridge's 32th & 33th platform assembly work is in progress
76/100
Instream Storage Structure, Khirasasan
Slump 80mm
77/100
Instream Storage Structure, Khirasasan
checked placing supporting bars and alignment of shuttering work in RHS U/S FLANK WALL PROFILE 1ST LIFT RL- 209.900 to 211.200 Now the area is ready for concrete casting M20 A20. So recommended for the purpose. Approved by AEE sir SID Sambalpur in presence of JE
78/100
Instream Storage Structure, Khirasasan
RHS d/s Flank wall 9th lift shuttering work is under progress.
79/100
Instream Storage Structure, Khirasasan
RHS Divide wall Hoist portion shuttering work has completed and ready for casting.
80/100
Instream Storage Structure, Khirasasan
RHS Abutment Hoist portion shuttering work is under progress
81/100
Instream Storage Structure, Khirasasan
RHS D/S FLARED OUT WALL 17TH STEP SHUTTERING WORK IS UNDER PROGRESS.
82/100
Instream Storage Structure, Khirasasan
RHS C F WING WALL 11 TH LIFT DE SHUTTERING WORK IS UNDER PROGRESS.
83/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
84/100
Instream Storage Structure, Gochara
Staff quarter roof shuttering work on progress .
85/100
Instream Storage Structure, Gochara
Stone pitching in LHS D/S guide bund in progress.
86/100
Instream Storage Structure, Gochara
View showing flow of river from U/S to D/S of river.
87/100
Instream Storage Structure across river Sapei near village Kinjirma
D/S site view
88/100
Instream Storage Structure across river Sapei near village Kinjirma
U/S site view
89/100
Instream Storage Structure, Kopsinga
Control building preparation of PCC is under progress in presence of Dept.JE Medam
90/100
Instream Storage Structure, Kopsinga
Cube test
91/100
Instream Storage Structure, Kopsinga
RHS wing wall curing work in Progress
92/100
UGPL, Right Lower Suktel Canal Division
OCS chamber piping work is in progress of OCS No- 0213052-C09B at village Bichupali in presence of PMC team.
93/100
UGPL, Right Lower Suktel Canal Division
OCS Chamber Below NGL Erection work is in progress of OCS no 2305010- C18B at village Takarala in presence of PMC team.
94/100
UGPL, Right Lower Suktel Canal Division
Stone pitching work is in progress of external drain type 03 of Pump House in presence of PMC team.
95/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door & angle fixing work is in progress OCS No:- 0213136-C06A at village Keserkela in presence of PMC team and L&T staff.
96/100
UGPL, Left Lower Suktel Canal Division
Internal Approach road block concrete pouring work is in progress at Pump House In presence of DoWR JE and PMC team.
97/100
UGPL, Left Lower Suktel Canal Division
Slump testing work is in progress for internal approach road block casting at Pump House in presence of DoWR JE, PMC team and MEIL staff.
98/100
Instream Storage Structure, Gudvella
Cast of concrete 13th lift PCC M20A20 grade at right side u/s flared out wall from sec 1-1 to 4-4 with RL 155.80m to 156.40m is under progress in the presence of Dept JE, site engineer of PMC and agency forman. The slump test value is 69mm on 02.02.2026
99/100
Instream Storage Structure, Gudvella
Cast of concrete 13th lift PCC M20A20 grade at right side u/s flared out wall from sec 1-1 to 4-4 with RL 155.80m to 156.40m is under progress in the presence of Dept JE, site engineer of PMC and agency forman. The slump test value is 69mm on 02.02.2026
100/100
Instream Storage Structure, Gudvella
Cast of concrete 7th lift RCC M25A20 grade at right side D/s flank wall including return wall from RL 156.34 m to 157.84m is under progress through pump in the presence of Dept JE, site engineer of PMC and agency forman. The slump test value is 89mm on 02.02.2026
❮
❯