Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Kuakhai
DTL & team observing flood conditions at site, Now water level is RL 14.75m.
2/100
Instream Storage Structure, Kuakhai
Water level at site is RL 16.85m.
3/100
Instream Storage Structure, Kuakhai
Water level RL 12.98m.
4/100
Instream Storage Structure, Kuakhai
At RL 13.34m, flood water elapses through the structure.
5/100
Instream Storage Structure, Kuakhai
DTL & Team observing back-filling at right side.
6/100
Instream Storage Structure, Kuakhai
Water level RL 12.6m.
7/100
Instream Storage Structure, Kuakhai
Water level RL 13.815m on 8th July.
8/100
Instream Storage Structure, Kuakhai
SE, Prachi division, SDO, balianta with OCC & PSS Team observing the first flood water passes through the structure.
9/100
Instream Storage Structure, Kuakhai
Back-filling behind R/S structure continues.
10/100
Instream Storage Structure, Kuakhai
Work stopped at site due to entry of flood water in the river.
11/100
Instream Storage Structure, Kuakhai
View of ISS from D/S side.
12/100
Instream Storage Structure, Kuakhai
Right side upstream Flankwall raft final lift is completed, Counter-fort side shuttering is under progress.
13/100
Instream Storage Structure, Kuakhai
Right side upstream flank-wall raft casting is on progress & concrete area well covered with polythene for rain.
14/100
Instream Storage Structure, Kuakhai
Casting of RCC M25A20 at right side upstream flank-wall raft From RL 6.50m to 8.50m.
15/100
Instream Storage Structure, Kuakhai
U/S Flank-wall raft reinforcement bar binding, including arrangement of shear bars is in progress.
16/100
Instream Storage Structure, Kuakhai
Reinforcement binding and side shuttering is on progress at right side downstream flank wall.
17/100
Instream Storage Structure, Kuakhai
Irrigation expert observing ongoing reinforcement binding at right side upstream flank-wall raft.
18/100
Instream Storage Structure, Kuakhai
R/S block, U/S Flank-wall raft reinforcement bar arrangement is in progress.
19/100
Instream Storage Structure, Kuakhai
Casting of RCC M30A20 at L/S block, fish pass portion from RL 9.75m to 10.70m is on progress.
20/100
Instream Storage Structure, Kuakhai
R/S block, D/S Flaredout wall excavation is underway.
21/100
Instream Storage Structure, Kuakhai
Pier polishing work is in progress.
22/100
Instream Storage Structure, Kuakhai
PSS Team observing the ongoing concreting work.
23/100
Instream Storage Structure, Kuakhai
Reinforcement bars of the R/S block, U/S divide wall are being prepared for embedding with M25 grade concrete from RL 13.95m to 15.35m.
24/100
Instream Storage Structure, Kuakhai
L/S block, U/S Flared-out wall casting is carried out with M20 grade concrete.
25/100
Instream Storage Structure, Kuakhai
Rebar binding and shutter plate arrangement is currently under progress at R/S block, U/S divide wall portion, from RL 13.95m to 15.35m.
26/100
Instream Storage Structure, Kuakhai
Chief Engineer, MKS, SE, Prachi division with deptt. along with Manager OCCL , DTL & PMC team Visited at work site .
27/100
Instream Storage Structure, Kuakhai
Casting of M25A20 at right side downstream divide wall raft is in progress.
28/100
Instream Storage Structure, Kuakhai
Irrigation Expert observing ongoing stone pitching in wire crated gabions at downstream of the barrage .
29/100
Instream Storage Structure, Kuakhai
Gabion wire-wrapped boulder packing work is in progress.
30/100
Instream Storage Structure, Kuakhai
Gabion wire-wrapped boulder packing work is in progress.
31/100
Instream Storage Structure, Kuakhai
Raft reinforcement bar arrangement and binding at R/S block, D/S Divide wall portion.
32/100
Instream Storage Structure, Kuakhai
Counter-fort shuttering arrangement is currently in progress.
33/100
Instream Storage Structure, Kuakhai
Reinforcement bar arrangement & binding at R/S block, U/S Flank-wall portion.
34/100
Instream Storage Structure, Kuakhai
Placement of D/S Divide wall Raft reinforcement bars at R/S block.
35/100
Instream Storage Structure, Kuakhai
Casting of M25A20 at Right side u/s flank wall cutoff is completed.Total quantity executed 39cum.
36/100
Instream Storage Structure, Kuakhai
casting of RCC M25A20 at R/s D/s flank wall raft from RL 6.0m to 8.0m is in progress.
37/100
Instream Storage Structure, Kuakhai
Shuttering and reinforcement binding of R/s U/s flank wall cutoff is in progress.
38/100
Instream Storage Structure, Kuakhai
DTL, MKS along with PMC Expert observing the ongoing casting of RCC M25A20 at Right D/s flank wall raft from RL 6.0m to 8.0m is in progress.
39/100
Instream Storage Structure, Kuakhai
Casting of M25A20 Right side block d/s flank wall raft from RL 6.00m to 8.00m has been completed.
40/100
Instream Storage Structure, Kuakhai
Slump test conducted at site in presence of Quality control Bhubaneswar, PMC, OCCL ,Dept & Slump value comes as 96mm .
41/100
Instream Storage Structure, Kuakhai
Kind inspection of Additional Chief engineer quality control along with SE quality control & team to the ISS site in presence of SDO, Balianta, OCCL, PMC expert and site engineers.
42/100
Instream Storage Structure, Kuakhai
Shuttering alignment at R/S block, D/S divide wall is in progress for further lift casting.
43/100
Instream Storage Structure, Kuakhai
R/S block, D/S flank wall raft casting is in progress from RL 6.00m to 8.00m.
44/100
Instream Storage Structure, Kuakhai
Casting of RCC M30A20 in progress at R/S block abutment portion zone-3&4.
45/100
Instream Storage Structure, Kuakhai
Casting of RCC M30A20 at L/s block abutment portion ,zone 5, 12th lift from RL 21.25m to RL 22.65m is under progress.
46/100
Instream Storage Structure, Kuakhai
Excavation of right side upstream flank wall is in progress.
47/100
Instream Storage Structure, Kuakhai
Casting of RCC M25A20 at R/S D/S divide wall cutoff from RL 2.85m to RL 4.05m is in progress.
48/100
Instream Storage Structure, Kuakhai
Excavation of right side upstream flank wall is in progress.
49/100
Instream Storage Structure, Kuakhai
Irrigation Expert, PSS observing reinforcement binding of R/s D/s divide wall cutoff is in progress.
50/100
Instream Storage Structure, Kuakhai
R/S undersluice counterfort from RL 7.25 to RL 8.65 shuttering work is under progress.
51/100
Instream Storage Structure, Kuakhai
Alignment checked with Amin in presence of AE,Prachi, in Govt. land, found correct.
52/100
Instream Storage Structure, Kuakhai
Another 6 no.s of bearing pads are perfectly fixed with epoxy adhesive on pier no. 9. Totally 45 no.s of bearing pads are placed.
53/100
Instream Storage Structure, Kuakhai
Reinforcement binding at L/s counter-fort is in progress.
54/100
Instream Storage Structure, Kuakhai
R/S block, U/S divide wall (3rd lift) casting completed from RL 11.15m to 12.55m.
55/100
Instream Storage Structure, Kuakhai
Boulder packing and gabion wrapping are underway at the downstream end of the structure.
56/100
Instream Storage Structure, Kuakhai
L/S block, Counter-fort 11th lift portion, including its stem (Zone 3 & 4) from RL 19.85m to 21.25m is preparing to receive M30 grade
57/100
Instream Storage Structure, Kuakhai
16 pairs of denil shuttering & reinforcement arrangement, in the fishway of left side block
58/100
Instream Storage Structure, Kuakhai
Ten precast concrete girders were successfully lifted and positioned on the bearing pads.
59/100
Instream Storage Structure, Kuakhai
Casting of CC M20A20 at L/S block U/S flared-out wall from RL 16.3m to 16.9m is completed.
60/100
Instream Storage Structure, Kuakhai
Casting of CC M20A20 at L/S block U/S flared-out wall from RL 16.3m to 16.9m is under progress.
61/100
Instream Storage Structure, Kuakhai
From 72 bearing pads, 21 are perfectly fixed on pier pedestal by aligning the centre line.
62/100
Instream Storage Structure, Kuakhai
Six no. of girder of 15.35m span were successfully launched and positioned on the bearing pads of Pier No. 6, 7a, 7b and 8 by maintaining accurate centre line. Simultaneously, additional 3 pairs of bearing pads were fixed accordingly for 14.1m girder placement on Pier no. 5 & 6.
63/100
Instream Storage Structure, Kuakhai
CE, MKS with SE, Prachi division, Manager, OCCL ,DTL, MKS with PMC experts visited at work site.
64/100
Instream Storage Structure, Kuakhai
SDO Balianta along with PSS Team observing the ongoing girder lifting.
65/100
Instream Storage Structure, Kuakhai
1st pre-cast girder placed perfectly.
66/100
Instream Storage Structure, Kuakhai
Lifting of pre-cast concrete girders.
67/100
Instream Storage Structure, Kuakhai
Three elastrometric bearing pads were fixed on the top of the pedestal of Pier no. 7B, using epoxy adhesive resin and levelled by aligning the centre line.
68/100
Instream Storage Structure, Kuakhai
Shifting of precast concrete girders.
69/100
Instream Storage Structure, Kuakhai
Shifting of precast concrete girders.
70/100
Instream Storage Structure, Kuakhai
Irr. Expert, PSS observing the ongoing works at right side.
71/100
Instream Storage Structure, Kuakhai
U/S Flared-out wall shuttering arrangement is in progress from RL 15.1m to 15.7m.
72/100
Instream Storage Structure, Kuakhai
Visit of Chief Engineer, Jalaprabhari, Khordha at ISS Kuakhai site.
73/100
Instream Storage Structure, Kuakhai
Side shuttering is on progress at left side down stream flaredout Wall.
74/100
Instream Storage Structure, Kuakhai
Irrigation expert, PSS observing the ongoing side shuttering of left side upstream flared-out Wall from RL 13.5m to 14.5m.
75/100
Instream Storage Structure, Kuakhai
Ongoing Reinforcement binding and side shuttering at left side counter-fort wall.
76/100
Instream Storage Structure, Kuakhai
Cleaning of sand and silt at bay no.2 for wearing coat.
77/100
Instream Storage Structure, Kuakhai
CE, MKS visited the ISS worksite.
78/100
Instream Storage Structure, Kuakhai
Reinforcement bar arrangement including shuttering alignment is in progress for final layer of 5 no. Counter-fort including its stem at Zone- 5, from RL 21.25m to 22.286m.
79/100
Instream Storage Structure, Kuakhai
Fishway- Denil shuttering arrangement is in progress.
80/100
Instream Storage Structure, Kuakhai
Casting of PCC M25A20 wearing coat at bay no.10 endsill slope portion is in progress.
81/100
Instream Storage Structure, Kuakhai
SDO, balianta with irrigation expert, PSS observing the ongoing work at site.
82/100
Instream Storage Structure, Kuakhai
QAQC expert, PMU inspecting the ongoing Casting of PCC M25A20 at bay no.11 slope portion.
83/100
Instream Storage Structure, Kuakhai
Laying of M25 grade wearing coat started in the cistern basin area of Bay no. 10 from RL 6.35m to 6.50m.
84/100
Instream Storage Structure, Kuakhai
Casting of Pier no. 5 12th lift from RL 21.75m to 22.286m is in progress.
85/100
Instream Storage Structure, Kushabhadra
Railing installation and hoist bridge alignment is under progress.
86/100
Instream Storage Structure, Kushabhadra
O&M building column reinforcement work in progress.
87/100
Instream Storage Structure, Kushabhadra
3 nos. of moter and railing material and rope-way 6 gearbox has arrived at the site.
88/100
Instream Storage Structure, Kushabhadra
O&M Building ground floor brick work is under progress.
89/100
Instream Storage Structure, Kushabhadra
O&M Building 1st floor beam De-shuttering work in progress.
90/100
Instream Storage Structure, Kushabhadra
O&M Building ground floor brick work is under progress.
91/100
Instream Storage Structure, Kushabhadra
Present water flood level, RL- 12.100m.
92/100
Instream Storage Structure, Kushabhadra
O&M Building ground floor brick work is under progress.
93/100
Instream Storage Structure, Kushabhadra
O&M Building ground floor brick work is under progress.
94/100
Instream Storage Structure, Kushabhadra
Flood water level RL 15.66m.
95/100
Instream Storage Structure, Kushabhadra
Flood water level RL 15.80m.
96/100
Instream Storage Structure, Kushabhadra
O&M Building ground floor brick work is under progress.
97/100
Instream Storage Structure, Kushabhadra
Casting of RCC M25A20 in 1st floor roof slab of O&M building is completed.
98/100
Instream Storage Structure, Kushabhadra
Casting of RCC M25A20 in O&M building 1st floor roof slab.
99/100
Instream Storage Structure, Kushabhadra
Slump test carried out at the worksite. Slump value comes as 85mm.
100/100
Instream Storage Structure, Kushabhadra
O&M building 1st floor slab concrete pipelining & area preparation for concrete work.