1/100
Instream Storage Structure, Kushabhadra
Right Side U/S guide bund gap filling work is under progress.
2/100
Instream Storage Structure, Kushabhadra
Canal Road 2nd layer laying & finishing work is under progress.
3/100
Instream Storage Structure, Dhanei
Painting of Barrage bay gates ongoing
4/100
Instream Storage Structure, Dhanei
Sand Blasting and Primming of Barrage bay gates ongoing.
5/100
Instream Storage Structure, Kushabhadra
Compaction of 2nd layer Vibro Roller at canal road .
6/100
Instream Storage Structure, Kushabhadra
Right Side U/S guide bund gap filling work is under progress.
7/100
Instream Storage Structure, Kuakhai
Casting of M25A20 at R/S D/S divide wall form RL10.65m to RL 12.05m is in progress.
8/100
Instream Storage Structure, Kuakhai
SDO along with AE Prachi observing D/S R/S divide wall before casting.
9/100
Instream Storage Structure, Kuakhai
Assistant Manager (OCCL) observing the work at site.
10/100
Instream Storage Structure, Kuakhai
Casting of M25 A20 R/S D/S flank wall (4th lift) from RL 12.50m to RL 13.9m is in progress.
11/100
Instream Storage Structure, Kuakhai
SDO observing the R/S D/S flank wall before casting.
12/100
Instream Storage Structure, Kuakhai
Sand blasting at R/S U/S flank wall is in progress.
13/100
Instream Storage Structure, Kushabhadra
Right Side U/S guide bund gap filling work is under progress.
14/100
Instream Storage Structure, Kushabhadra
Canal Road 2nd layer laying & finishing work is under progress.
15/100
Instream Storage Structure, Near Village Basantpur across River Daya
Coffer dam work in progress
16/100
Barrage across river Turi & Guntat
Excavation of link channel is under progress
17/100
Barrage across river Turi & Guntat
Excavation of Link channel is under progress
18/100
Barrage across river Turi & Guntat
Pvt. Land acquisition procedures
19/100
Instream Storage Structure, Kushabhadra
Left Side U/S soil cutting and shifting to Right Side U/S guide bund gap filling work is under progress.
20/100
Instream Storage Structure, Kushabhadra
Canal Road 2nd layer finishing work is under progress.
21/100
Instream Storage Structure, Nandagaon
Building 2nd floor Slab Shuttering is in progress.
22/100
Instream Storage Structure, Gudvella
D/S OF ISS GUDVELLA.
23/100
Instream Storage Structure, Gudvella
U/S OF ISS GUDVELLA.
24/100
Instream Storage Structure, Kuakhai
SDO & AE (Prachi) observing cleaning and sand blasting at placing site.
25/100
Instream Storage Structure, Kuakhai
G.M and manager (Occl ) along with AE (Prachi) visited the ISS Kuakhai site in presence of concerned site engineers and PM (DDBL) and instructed to expedite the progress as per the work programme.
26/100
Instream Storage Structure, Kushabhadra
Canal Road WBM 2nd layer work is in progress.
27/100
Instream Storage Structure, Kushabhadra
Left u/s cutting soil shifting to right u/s guide bund gap filling
28/100
Instream Storage Structure, Kushabhadra
Stop log gat gantry track work under process.
29/100
Instream Storage Structure, Kushabhadra
Canal Road side Shoulder work is under progress.
30/100
Instream Storage Structure, Kushabhadra
canal road surface preparation RD- chainge- 00m to 250 m work is currently in progress .
31/100
Instream Storage Structure, Kushabhadra
U/s river area soil loading work is progressing.
32/100
Instream Storage Structure, Gudvella
D/S OF ISS GUDVELLA ON 24.11.2026.
33/100
Instream Storage Structure, Gudvella
U/S OF ISS GUDVELLA ON 24.11.2026.
34/100
Instream Storage Structure, Kuakhai
AE, Prachi observing ongoing casting of RCC M30A20 at Right side Counterfort (Zone-5) 6th lift from RL 12.80m to 14.2m.
35/100
Instream Storage Structure, Kuakhai
Side shuttering and reinforcement binding is on progress at R/S counterfort in presence of SDO, ISS Kuakhai (I/C).
36/100
Instream Storage Structure , Tustapalli
After 2 days break the DGPS survey work has been resumed towards the left side of the u/s area of ISS Tustapali for afflux assessment.
37/100
Instream Storage Structure, Gudvella
U/S OF ISS GUDVELLA ON 23.11.2026
38/100
Instream Storage Structure, Gudvella
D/S OF ISS GUDVELLA ON 23.11.2026
39/100
Instream Storage Structure, Gudvella
D/S OF ISS GUDVELLA ON 22.11.2026
40/100
Instream Storage Structure, Gudvella
U/S OF ISS GUDVELLA ON 22.11.2026
41/100
Instream Storage Structure, Kushabhadra
Hoist bridge railing work is under progress.
42/100
Instream Storage Structure, Kushabhadra
Compaction of 2nd layer Vibro Roller at canal road .
43/100
Instream Storage Structure, Kushabhadra
Right side u/s guide bond area making ramp with bed levelling work is progressing
44/100
Instream Storage Structure, Kudabega
CWC Team visit to ISS Kudabaga
45/100
Instream Storage Structure, Near Village Basantpur across River Daya
coffer dam
46/100
Instream Storage Structure, Near Village Basantpur across River Daya
bullaha piling work for construction of coffer dam
47/100
Instream Storage Structure, Nandagaon
Transformer installation is in progress
48/100
Instream Storage Structure, Gudvella
D/S OF ISS GUDVELLA.
49/100
Instream Storage Structure, Gudvella
U/S OF ISS GUDVELLA.
50/100
Instream Storage Structure, Gudvella
D/S OF ISS GUDVELLA ON 20.11.2026
51/100
Instream Storage Structure, Gudvella
U/S OF ISS GUDVELLA ON 20.11.2026
52/100
Instream Storage Structure, Kushabhadra
Hoist - Rope Drum alignment work is under progress.
53/100
Instream Storage Structure, Kushabhadra
Canal Road 2nd layer finishing work is under progress.
54/100
Instream Storage Structure, Kushabhadra
Canal Road 2nd layer laying work is under progress.
55/100
Instream Storage Structure, Kushabhadra
Right side D/S guide bond area c&g with slope cutting work is under progress.
56/100
Instream Storage Structure, Kudabega
Payment for afflux bundh of ISS Kudabaga for Khata No-46 (37 member) through Direct Purchase
57/100
Instream Storage Structure, Kudabega
Payment for afflux bundh of ISS Kudabaga for Khata No-46 (37 member) through Direct Purchase
58/100
Instream Storage Structure, Nandagaon
11 KV line and Transformer erection is in progress.
59/100
Instream Storage Structure, Kuakhai
During the visit, the SE, Prachi, briefed the Hon’ble MP on the current progress of the project, the proposed plan for further execution of works, and the major constraints and hindrances affecting the timely completion of the project.
60/100
Instream Storage Structure, Kuakhai
Hon’ble Member of Parliament, Bhubaneswar, Smt. Aparajita Sarangi, kindly visited the ongoing construction site of the In-Stream Storage Structure (ISS) across River Kuakhai. The Superintending Engineer, Prachi Division, along with the concerned site engineers were present during the visit.
61/100
Instream Storage Structure across river Sapei near village Kinjirma
CTM Caliberation of ISS Kinjirma
62/100
Instream Storage Structure, Kudabega
Light Testing of ISS Kudabaga barrage
63/100
Instream Storage Structure , Tustapalli
The DGPS survey work has been successfully completed up to the axis of ISS Tustapali. The survey work is currently in progress towards the upstream side for afflux assessment in the presence of the SE Sir, JE and the agency's survey team.
64/100
Instream Storage Structure , Tustapalli
The DGPS survey work has been successfully completed up to the axis of ISS Tustapali. The survey work is currently in progress towards the upstream side for afflux assessment in the presence of the SE Sir, JE and the agency's survey team.
65/100
Instream Storage Structure , Tustapalli
The DGPS survey work has been successfully completed up to the axis of ISS Tustapali. The survey work is currently in progress towards the upstream side for afflux assessment in the presence of the SE Sir, JE and the agency's survey team.
66/100
Instream Storage Structure , Tustapalli
The DGPS survey work has been successfully completed up to the axis of ISS Tustapali. The survey work is currently in progress towards the upstream side for afflux assessment in the presence of the SE Sir, JE and the agency's survey team.
67/100
Instream Storage Structure , Tustapalli
The DGPS survey work has been successfully completed up to the axis of ISS Tustapali. The survey work is currently in progress towards the upstream side for afflux assessment in the presence of the SE Sir, JE and the agency's survey team.
68/100
Instream Storage Structure , Tustapalli
The DGPS survey work has been successfully completed up to the axis of ISS Tustapali. The survey work is currently in progress towards the upstream side for afflux assessment in the presence of the SE Sir, JE and the agency's survey team.
69/100
Instream Storage Structure, Gudvella
D/S OF ISS GUDVELLA.
70/100
Instream Storage Structure, Gudvella
U/S OF ISS GUDVELLA.
71/100
Instream Storage Structure, Nandagaon
Gate Erection is in progress.
72/100
Instream Storage Structure, Nandagaon
Building 2nd floor Slab Shuttering is in progress.
73/100
Instream Storage Structure, Hamirpur
Hoist Column stiffner plate fixing work is in progress
74/100
Instream Storage Structure, Hamirpur
Bay no 9 Deckslab railing beam post fixing and shuttering work is in progress
75/100
Instream Storage Structure, Hamirpur
Block No-5 d/s Flared out wall curing work & deshuttering is in progress
76/100
Instream Storage Structure, Dhanei
Painting work of the Under-Sluice gate ongoing at site
77/100
Instream Storage Structure, Dhanei
The RI, Chirikipada Sasan, along with the sub division team, revisited the ISS Sanabaragam site to address the grievances raised by villagers following the land demarcation carried out in October 2026 for private land acquisition. The team reviewed the issues raised by the affected villagers and took necessary steps towards their resolution.
78/100
Instream Storage Structure, Dhanei
The Superintending Engineer, Mechanical Division, Brahmapur visited the ISS Sanabaragam site on our request and inspected the progress of the work in detail, particularly the mechanical gate components. He also provided valuable technical guidance regarding the erection procedure and the materials required for successful completion of the gate erection work.
79/100
Instream Storage Structure, Near Village Basantpur across River Daya
collection of pilling materials for construction of coffer dam
80/100
Instream Storage Structure, Near Village Basantpur across River Daya
Coffer dam work in progress
81/100
Instream Storage Structure, Kuakhai
Reinforcements and the area ready for casting observed by SDO, ISS Kuakhai (I/C) . Today R/S D/S Flank wall 3rd lift from RL 11.10m to 12.50m M25 A20 casting to be commenced .
82/100
Instream Storage Structure, Hamirpur
Block no 5 d/s flared out wall boulder pitching work in progress
83/100
Instream Storage Structure, Hamirpur
By no 5 cross girder casting work progress
84/100
Instream Storage Structure, Hamirpur
Bay no - 18, gate groove 2nd stage 8th lift concreting is in progress
85/100
Instream Storage Structure , Tustapalli
The DGPS survey work is currently in progress from Saintala towards the Tustapali ISS site.
86/100
Instream Storage Structure, Gudvella
D/S OF ISS GUDVELLA.
87/100
Instream Storage Structure, Gudvella
U/S OF ISS GUDVELLA.
88/100
Instream Storage Structure, Kushabhadra
Barrage gate installation.
89/100
Instream Storage Structure, Kushabhadra
O&M Building 1st Floor Electrifications work is under progress.
90/100
Instream Storage Structure, Kushabhadra
Right side u/s guide bond area c&g with slope cutting work is progressing.
91/100
Instream Storage Structure, Kuakhai
AE,Prachi observing ongoing casting of RCC M30 A20 at right side counterfort (zone- 5) 5th lift from RL 11.45m to 12.80m is in progress.
92/100
Instream Storage Structure, Dhanei
Sand Blasting and Painting work ongoing of the gates at site
93/100
Barrage across river Turi & Guntat
Turi Barrage control room slab casting is going on
94/100
Barrage across river Turi & Guntat
Before slab casting on the control room of Turi Barrage
95/100
Barrage across river Turi & Guntat
Present status of Turi Barrage
96/100
Instream Storage Structure, Hamirpur
Bay no - 17, gate groove 2nd stage concreting is in progress
97/100
Instream Storage Structure, Hamirpur
Bay no-06 Deck slab concreting work in progress
98/100
Instream Storage Structure, Hamirpur
Bay no 10 - 2nd stage groove Wall concrete work in progress
99/100
Instream Storage Structure, Kuakhai
Casting of RCC M30 A20 at right side counterfort (zone- 5) 5th lift from RL 11.45m to 12.80m is in progress.
100/100
Instream Storage Structure , Tustapalli
The leveling survey using an Auto Level was completed on 06.11.2026. Following a break in the survey work, the DGPS survey has been resumed today i.e. on 17.11.2026, from Deogaon PWD IB in the presence of the Departmental Junior Engineer and the agency's survey team.
❮
❯