PMIS for ISS/MMIPs/UGPL Projects

Total No of Schemes – 53 nos ( ISS-46, MMIPs-6, UGPL-1 )
1/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-21, 12th lift done in presence of Client & PSS Team.
2/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-21, 12th lift is under progress in presence of Client & PSS Team.
3/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 80 mm) of Abutment wall (A1), 7th lift at Block No-1 done in presence of Client & PSS Team.
4/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Abutment wall (A1), 7th lift at Block No-1 is under progress in presence of Client & PSS Team.
5/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-1, 4th lift done in presence of Client & PSS Team.
6/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-1, 4th lift is under progress in presence of Client & PSS Team.
7/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-16 done in presence of Client & PSS Team.
8/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-16 is under progress in presence of Client & PSS Team.
9/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.92/mm2 for 28 days) of Pier No-16, 8th lift and (Strength is 30.89/mm2 for 28 days) of Pier No-15, 6th lift and (Strength is 21.63/mm2 for 07 days) of U/S Flank wall at block No-1 has done in presence of Client & PSS team.
10/100
Instream Storage Structure, Hamirpur
Stop-log groove 2nd stage embedded parts guide erection work is in progress at Bay No-9.
11/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform No-3 girder's fit-up work is in progress.
12/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-1 welding work is in progress.
13/100
Instream Storage Structure, Hamirpur
MS plate marking and cutting for hoist platform girder's flange work is in progress.
14/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4 is under progress.
15/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-3, 6th lift is under progress.
16/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Flank wall at Block No-1 is under progress.
17/100
Instream Storage Structure, Hamirpur
Shuttering of U/S Flank wall at Block No-1 is under progress.
18/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-1, 3rd lift is under progress.
19/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-15, 13th lift is under progress.
20/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall at Block no-5 is under progress.
21/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Gantry Girder is under progress.
22/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Pier no-2, 5th lift is under progress.
23/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of RHS Mid-pier Cap is under progress.
24/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for RHS Double pier, 5th lift is under progress.
25/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering & binding of reinforcement for RHS Counterfort with Wing wall, 2nd lift is under progress.
26/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 85 mm) of LHS D/S Divide wall, 5th lift done in presence of Client & PSS Team.
27/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of LHS D/S Divide wall, 5th lift is under progress in presence of Client & PSS Team.
28/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 50 mm) of RHS (A2) Footing, 2nd Layer done in presence of Client & PSS Team.
29/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of RHS (A2) Footing, 2nd Layer is under progress in presence of Client & PSS Team.
30/100
Instream Storage Structure, Hamirpur
Cleaning of Pier No-8 to RHS (D2) U/S Gravity floor is under progress.
31/100
Instream Storage Structure, Hamirpur
Cutting & bending for reinforcement is under progress.
32/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-8, 4th lift is under progress.
33/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for RHS (D2) D/S Footing, 2nd Layer is under progress.
34/100
Instream Storage Structure, Hamirpur
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
35/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 80 mm) of Barrage Bay No-2 Mid Cut-off, 2nd lift done in presence of Client & PSS Team.
36/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Barrage Bay No-2 Mid Cut-off, 2nd lift is under progress in presence of Client & PSS Team.
37/100
Instream Storage Structure, Khalpal
Curing of Piers is under progress.
38/100
Instream Storage Structure across river Sapei near village Kinjirma
85mm Tm-17
39/100
Instream Storage Structure across river Sapei near village Kinjirma
RHS U/S divide wall raft M25A20 casting work in progress
40/100
Instream Storage Structure across river Sapei near village Kinjirma
80mm Tm-15
41/100
Instream Storage Structure across river Sapei near village Kinjirma
85mm Tm-14
42/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 80mm,tm-13
43/100
Instream Storage Structure across river Sapei near village Kinjirma
80mm Tm-12
44/100
Instream Storage Structure across river Sapei near village Kinjirma
80mm Tm-11
45/100
Instream Storage Structure across river Sapei near village Kinjirma
RHS U/S divide wall raft M25A20 casting work in progress
46/100
Instream Storage Structure across river Sapei near village Kinjirma
Tm-10 85mm
47/100
Instream Storage Structure across river Sapei near village Kinjirma
Concrete work under progress of u/s divide wall raft(M25A20) in presence of dept. AEE,AE & JE .
48/100
Instream Storage Structure across river Sapei near village Kinjirma
90mm,tm-9
49/100
Instream Storage Structure across river Sapei near village Kinjirma
Casting of raft foundation witnessed by IEE and QCE in presence of AEE.
50/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 80mm,tm-8
51/100
Instream Storage Structure across river Sapei near village Kinjirma
Raft Foundation casting of RHS U/S divide wall is in progress.
52/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 85mm,tm-7
53/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 85mm,tm-6
54/100
Instream Storage Structure across river Sapei near village Kinjirma
Concrete work under progress of u/s divide wall raft(M25A20) in presence of dept.AEE , IEE & QCE of PMC Sambalpur.
55/100
Instream Storage Structure across river Sapei near village Kinjirma
Concrete work under progress of u/s divide wall raft(M25A20) in presence of dept. AEE , IEE & QCE of PMC Sambalpur.
56/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 75mm,tm-5
57/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 90mm,tm-4
58/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 80mm,tm-3
59/100
Instream Storage Structure across river Sapei near village Kinjirma
D-shuttering work under progress of pier no 4 .
60/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump 80mm,tm-2
61/100
Instream Storage Structure across river Sapei near village Kinjirma
Slump-80mm,tm-1 (M25A20)
62/100
Instream Storage Structure, Budharaja
Staff Quarter ground floor plastering work is in Progress.
63/100
Instream Storage Structure, Budharaja
Rock Breaking and Cleaning work is in Progress at LHS Under sluice bay Portion.
64/100
Instream Storage Structure, Budharaja
View showing flow of river from U/S to D/S of river.
65/100
Instream Storage Structure, Kopsinga
Pier no 22 Expansion joint chipping work under progress
66/100
Instream Storage Structure, Kopsinga
Double storied building curing work under progress
67/100
Instream Storage Structure, Kopsinga
Double storied building Brick work under progress ISS Kopsingha
68/100
Instream Storage Structure, Kopsinga
ISS Kopsingha - 5th Under-sluice gate's work is in progress out of - 6
69/100
Instream Storage Structure, Khirasasan
Slump 80mm
70/100
Instream Storage Structure, Khirasasan
checked placing supporting bars and alignment of shuttering work in RHS U/S flared out profile 8th step RL- 214.100 to 214.700 Now the area is ready for concrete casting M20 A20. So recommended for the purpose. Approved by AEE sir SID Sambalpur in presence of JE
71/100
Instream Storage Structure, Khirasasan
RHS U/S FLARED out wall profile 8th lift shuttering work under progress
72/100
Instream Storage Structure, Khirasasan
View showing flow of river from D/S of the river.
73/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
74/100
Instream Storage Structure, Gochara
E & A of PMC Sambalpur visited ISS Gochhra.
75/100
Instream Storage Structure, Gochara
P1 cement washing work in progress.
76/100
Instream Storage Structure, Gochara
Electric panel fixing work is in progress to the top of the Hoist bridge's Platform.
77/100
Instream Storage Structure, Gochara
Lifting bracket fixing work is in progress of Barrage Bay Gate no-1.
78/100
Instream Storage Structure, Kudabega
Casting of D/S gravity floor RHS sluice bay
79/100
Instream Storage Structure, Kudabega
Slump 80mm of ds gravity floor of right sluice Bay
80/100
Instream Storage Structure, Kudabega
Casting of RHS sluice bay D/S gravity floor
81/100
Instream Storage Structure, Kudabega
Slump 80mm (RHS ds wearing coat)
82/100
Instream Storage Structure, Kudabega
Cleaning the D/S RHS Gravity floor
83/100
Instream Storage Structure, Kudabega
Preparation for wearing coat for D/S gravity floor
84/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Panting work is in progress of CDU & ERU
85/100
Instream Storage Structure, Kudabega
ISS Kudabaga - Chakkar - Plate's fixing work is in progress
86/100
Instream Storage Structure Across Bheden near village Saida
LHS U/S Flared out wall curing work is going on .
87/100
Instream Storage Structure Across Bheden near village Saida
P-5 gate groves chipping work is in progress .
88/100
Instream Storage Structure Across Bheden near village Saida
De-Shuttering work progress in RHS u/s flared out wall step-10
89/100
Instream Storage Structure Across Bheden near village Saida
De-Shuttering work progress in RHS d/s flared out wall step-4 & shuttering work progress in step-5
90/100
UGPL, Left Lower Suktel Canal Division
HDPE Tee (75X 125 X 75)mm connection work is in progress at RO-78, RM-4, near village Semelia in presence of PMC team.
91/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-15, 11th lift done in presence of Client & PSS Team.
92/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-15, 11th lift is under progress in presence of Client & PSS Team.
93/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Gantry Girder No-15 done in presence of Client & PSS Team.
94/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-15 is under progress in presence of Client & PSS Team.
95/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.96/mm2 for 28 days) of Abutment (A1), 4th lift at Block No-1 and (Strength is 21.48/mm2 for 07 days) of Pier No-5, 4th lift and (Strength is 21.04/mm2 for 07 days) of Fish pass Raft at Block No-1 has done in presence of Client & PSS team.
96/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform No-3 girder's welding work is in progress.
97/100
Instream Storage Structure, Hamirpur
Single Pier hoist bridge platform assembly No-17 welding work is in progress.
98/100
Instream Storage Structure, Hamirpur
MS plate marking and cutting for hoist bridge platform stiffener work is in progress.
99/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-4, 5th lift is under progress.
100/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-3, 6th lift is under progress.