1/100
Instream Storage Structure, Nandagaon
• 2.(i) Checked the area before placement of concrete at D/S curtain wall with following activities in presence of PM of EPC Agency,Site Engineers of PMC & EPC Agency:
(ii) Rigid and smooth shuttering for curtain wall with PCC M15A40 grade for 1st. lift of 1.00 mt. ht. and 1.0m width from RL-232.50m to RL-233.50m are found completed.
(iii)The concrete surface is cleaned properly through air water jetting and passed by SE, KID Bhawanipatna for placing concrete with PCC M15A40 grade on 06.05.2026
2/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no.11 upto RL-246.30m is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 84mm on 06.05.2026
3/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no.11 upto RL-246.30m is in progress in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 84mm on 06.05.2026
4/100
Instream Storage Structure, Nandagaon
• 1(i).Fixing & fittings and alignment of All trestle and columns foundation bolts measurements has been checked at pier no.-11,12&13for Blockout area of 6.8m length and found correct by HM Expert of PMC during his site visit on dt.06.05.2026 in presence of mechanical Site Engineers of PMC and EPC Agency.
(ii) Rigid and smooth shuttering for Blockout area with M35A20 grade at pier no.-7 upto RL-247.00m and pier no.9 from RL-245.40m to RL-246.30m are found completed.
(iii).The area is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with M35A20 grade on 06.05.2026
5/100
Instream Storage Structure, Nandagaon
Placing of CC blocks is in progress at D/S side on 06.05.2026
6/100
Instream Storage Structure, Nandagaon
Reinforcement binding & Shuttering is in progress at U/S right divide wall on 06.05.2026
7/100
Instream Storage Structure, Nandagaon
Hoist bridge painting work under progress on 06.05.2026
8/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for gap closing of 300mm Dia DI pipeline between J-470 to J-443, RM-3 near village Jamutia in presence of PMC team.
9/100
Instream Storage Structure, Budharaja
Staff Quarter 1st floor plastering work is in Progress.
10/100
Instream Storage Structure, Budharaja
Shuttering and Cleaning work is in progress at LHS D/S Flared-out Wall Portion.
11/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S of river.
12/100
Instream Storage Structure, Budharaja
Staff Quarter 1st floor plastering work is in Progress.
13/100
Instream Storage Structure, Budharaja
Shuttering and Cleaning work is in progress at LHS D/S Flared-out Wall Portion.
14/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S of river.
15/100
Instream Storage Structure, Budharaja
Staff Quarter 1st floor plastering work is in Progress.
16/100
Instream Storage Structure, Budharaja
Shuttering work is in progress at LHS D/S Flared-out Wall Portion.
17/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S of river.
18/100
Instream Storage Structure, Budharaja
Staff Quarter 1st floor plastering work is in Progress.
19/100
Instream Storage Structure, Budharaja
Shuttering and Cleaning work is in progress at LHS D/S Flared-out Wall Portion.
20/100
Instream Storage Structure, Budharaja
View showing flow of river from D/S of river.
21/100
Instream Storage Structure, Budharaja
Today no working activities at site due to Labour day.
22/100
Instream Storage Structure Across Bheden near village Saida
RHS D/S Flared out of step -12th de-shuttering work is going on .
23/100
Instream Storage Structure Across Bheden near village Saida
Staff quarters plinth beam Reinforcement bar binding work is in progress .
24/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from U/S to D/S of river.
25/100
Instream Storage Structure Across Bheden near village Saida
Staff quarters plinth beam Reinforcement bar binding work is going on .
26/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from U/S to D/S of river.
27/100
Instream Storage Structure Across Bheden near village Saida
LHS divide wall to p-1 hoist column gate erection work in progress.
28/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from U/S to D/S of river.
29/100
Instream Storage Structure Across Bheden near village Saida
RHS U/S Flared out wall step - 16th de-shuttering work is going on .
30/100
Instream Storage Structure Across Bheden near village Saida
LHS Undersluice hoist column erection work in progress.
31/100
Instream Storage Structure Across Bheden near village Saida
P-5 hoist portion shuttering work is going on .
32/100
Instream Storage Structure Across Bheden near village Saida
View showing flow of river from U/S to D/S of river.
33/100
Instream Storage Structure Across Bheden near village Saida
Today no work at site due Labours day
34/100
UGPL, Right Lower Suktel Canal Division
HDPE Tee (140 x 110 x140)mm connection work is in progress at J-5338 near village Jarajirang in presence of PMC team.
35/100
UGPL, Right Lower Suktel Canal Division
Excavation work is in progress for fixing of 1HA outlet of OCS -02305095-C06A at village Jarajaring in presence of PMC team.
36/100
UGPL, Right Lower Suktel Canal Division
OCS chamber above GL finishing work is in progress of OCS No:- 0213136-CO5B at village Timapali in presence of PMC team.
37/100
UGPL, Right Lower Suktel Canal Division
External drain brick masonry work is in progress at Pump House.
38/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No- 0213112-C04A near village Kadalipalli in presence of PMC team.
39/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door and angle fixing work is in progress OCS No:-0201297- C02A at village Rinabachan in presence of PMC team.
40/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 250mm Dia HDPE pipeline gap closing between J-203 to J-383, LM-7 near Uparudar.
41/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS No- 0201345- C11B near village Balangir in presence of DoWR SDO, AE, JE and PMC team.
42/100
UGPL, Left Lower Suktel Canal Division
DI to HDPE connection work is in progress at Lm-10 J-515 village Kadajuri in presence of PMC team.
43/100
Instream Storage Structure, Gudvella
Curing at slab is under progress on 05.05.2026
44/100
Instream Storage Structure, Gudvella
Shuttering work of posts deck slab on 05.05.2026
45/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 05.05.2026
46/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 05.05.2026
47/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right divide wall for 9th lift upto RL-243.80m is in progress through concrete pump in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 88mm on 05.05.2026
48/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at U/S right divide wall for 9th lift upto RL-243.80m is in progress through concrete pump in presence of PM EPC agency, Site Engineer of PMC & EPC agency. The slump test value is 88mm on 05.05.2026
49/100
Instream Storage Structure, Nandagaon
• 4.The area of placing concrete at U/S right divide wall has been checked before placement in presence of PM of EPC Agency, Site Engineer of PMC & EPC Agency as follows:
(i).The reinforcement in binding, tying n spacing of both vertical main & horiz. dist. bar and tie bars for casting of U/S right divide wall for 9th lift from RL-242.40m to RL-243.80m are found completed.
(ii).Rigid & smooth shuttering and maintained clear cover of 75mm from main bar to shutter plates are done.
(iii).The area is cleaned properly through air water jetting and passed by SE, KID, Bhawanipatna for placing with RCC M25A20 grade on 05.05.2026
50/100
Instream Storage Structure, Nandagaon
• 3.Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at bay No.-12 of Pier No.11&12 for 1st lift have been checked and found correct by HM Expert of PMC during his site visit on dt.05.05.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i)Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 05.05.2026
51/100
Instream Storage Structure, Nandagaon
• 2.Shuttering for Second Stage concrete for gate grooves at barrage bay 9,10&11 are kept ready since last two days for placing concrete at Block-2. Due to the breakdown of Batching plant concrete could not be done.
Due to inadequate numbers of placing gangs engaged at site, the entire area for 2nd. stage concreting at vertical gate grooves at Block-2 is very slow. @ PM, ISS Nandagaon is suggested to increase more manpower to complete the work in time on 05.05.2026
52/100
Instream Storage Structure, Nandagaon
• Side visit of ISS, Nandagaon by QAC, Expert along with the HME and Sr. Site Engineer of PMC in presence of PM of EPC Agency, Site Engineers of PMC and EPC Agency. During site visit, the following activities are in progress, :-
1. Reinforcement works in binding, placing in proper position, tying n maintaining clear cover for 9th lift at U/S right Divide wall including rigid & smooth n shuttering works are found completed on 05.05.2026
53/100
Instream Storage Structure, Nandagaon
• Side visit of ISS, Nandagaon by QAC, Expert along with the HME and Sr. Site Engineer of PMC in presence of PM of EPC Agency, Site Engineers of PMC and EPC Agency. During site visit, the following activities are in progress, :-
1. Reinforcement works in binding, placing in proper position, tying n maintaining clear cover for 9th lift at U/S right Divide wall including rigid & smooth n shuttering works are found completed on 05.05.2026
54/100
Instream Storage Structure, Nandagaon
Placing of CC blocks is in progress at D/S side on 05.05.2026
55/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress on 05.05.2026
56/100
Instream Storage Structure, Nandagaon
Hoist bridge sand blasting and painting work is under progress on 05.05.2026
57/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for Laying of 75mm Dia HDPE pipe line from node RO-144 to RO-144B RM-8 near village Bhainsa.
58/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Binding of reinforcement for LHS side Raft is under progress.
59/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
visited by Sub-Collector, Pallahara along with Tahasildar at ISS site in presence of PSS Team & EPC Agency fixed for Site Selection Committee Meeting.
60/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Testing of Compressive M25A20 (Strength is 18.51/mm2 for 07 days) of RHS Flank wall and (Strength is 29.94/mm2 for 28 days) of LHS U/S Divide wall, Footing has done in presence of Client & PSS team.
61/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Binding of reinforcement for RHS Counterfort & Abutment wall, 2nd lift is under progress.
62/100
Instream Storage Structure, Jharbeda
Concreting M20A20 of RHS under sluice portion D/S Gravity floor, 3rd Layer is under progress in presence of Client & PSS Team.
63/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-5 is under progress.
64/100
Instream Storage Structure, Jharbeda
Shuttering of Pier No-8 is under progress.
65/100
Instream Storage Structure, Jharbeda
Observed of Sieve analysis of Coarse aggregate (10mm & 20mm) and Fine aggregate in presence of Client & PSS team along with EPC agency.
66/100
Instream Storage Structure, Jharbeda
Curing of Gravity floor is under progress.
67/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Gantry Girder No-31 done in presence of Client & PSS Team.
68/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-31 is under progress in presence of Client & PSS Team.
69/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of U/S Flared out wall, 1st lift at Block No-1 (Bank side) done in presence of Client & PSS Team.
70/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of U/S Flared out wall, 1st lift at Block No-1 (Bank side) is under progress in presence of Client & PSS Team.
71/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 90 mm) of Deck slab (Bay No-15) done in presence of Client & PSS Team.
72/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Deck slab (Bay No-15) is under progress in presence of Client & PSS Team.
73/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 31.20/mm2 for 28 days) of Pier No-1, 3rd lift and (Strength is 30.91/mm2 for 28 days) of Fish pass Raft at Block No-1 and (Strength is 31.41/mm2 for 28 days) of Pier No-4, 1st lift and M35A20 (Strength is 37.04/mm2 for 07 days) of Gantry Girder No-28 has done in presence of Client & PSS team.
74/100
Instream Storage Structure, Hamirpur
R.D.U no's of 10 set and C.D.U no's of 13 set fixing work is in progress.
75/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform assembly No-5 girder's welding work is in progress.
76/100
Instream Storage Structure, Hamirpur
U/S hoist bridge platform No-5 girder's web & flange plate fixing work is in progress.
77/100
Instream Storage Structure, Hamirpur
MS plate marking and cutting for hoist platform girder's web plate work is in progress.
78/100
Instream Storage Structure, Hamirpur
Stop-log groove 2nd stage embedded parts guide and track alignment work is in progress at bay No-26.
79/100
Instream Storage Structure, Hamirpur
Gantry girder's 1st stage embedded plate fixing and welding work is in progress.
80/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-2, 6th lift is under progress.
81/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flank wall, Raft at Block No-5 is under progress.
82/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Flared wall, Raft at Block No-5 is under progress.
83/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Abutment (A1), 5th lift is under progress.
84/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Gantry Girder is under progress.
85/100
Instream Storage Structure, Khalpal
Curing of under sluice End sill is in progress.
86/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 165 mm) of U/S Panel No-09 at Barrage Bay No-1 1 done in presence of Client & PSS Team.
87/100
Instream Storage Structure, Khalpal
Concreting M25A20 of U/S Panel No-09 at Barrage Bay No-1 done in presence of Client & PSS Team
88/100
Instream Storage Structure, Khalpal
Diaphragm wall cage placing for U/S Panel No-09 at Barrage Bay No-1 in presence of Client & PSS Team.
89/100
Instream Storage Structure, Khalpal
End stopper fixing for U/S Panel No-09 at Barrage Bay No-1 in presence of Client & PSS Team.
90/100
Instream Storage Structure, Khalpal
Testing of Compressive M25A20 (Strength is 34.32/mm2 for 28 days) of Pier No-21 and (Strength is 33.33/mm2 for 28 days) of Mid Cut-off, 1st lift at Barrage Bay No-2 has done in presence of Client & PSS team.
91/100
Instream Storage Structure, Khalpal
Binding of reinforcement for Barrage Bay No-2, Raft is under progress.
92/100
Instream Storage Structure, Khalpal
Shuttering of Double pier No-25 is under progress.
93/100
Instream Storage Structure, Khalpal
Curing of Piers is in progress.
94/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., and Site Engineer PMC to the ISS Site. Inspected the overall progress of site, Cage lowering for panel R95 u/s flank-wall and concreting in progress.
95/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., QA&QC Expert along with Site Engineer PMC to the ISS Site. Inspected the overall progress of site, CC Blocks placing on the D/S barrage bay, Raft concreting progress and checking of girder beam reinforcement.
96/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., QA&QC Expert along with Site Engineer PMC to the ISS Site. Inspected the overall progress of site, CC Blocks placing on the D/S barrage bay, Raft concreting progress and checking of girder beam reinforcement.
97/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irrigation Eng. Expert along with Site Engineer PMC to the ISS Site. Inspected the overall progress of site, Right side pier -9 pile cap concreting continuing and Right-side Pier no-7 reinforcement binding & shuttering work is in progress.
98/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irrigation Eng. Expert along with Site Engineer PMC to the ISS Site. Inspected the overall progress of site, Right side pier -9 pile cap concreting continuing and Right-side Pier no-7 reinforcement binding & shuttering work is in progress.
99/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irrigation Eng. Expert along with Site Engineer PMC to the ISS Site. Inspected the overall progress of site, Right side pier -9 pile cap concreting continuing and Right-side Pier no-7 reinforcement binding & shuttering work is in progress.
100/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept., Irrigation Eng. Expert along with Site Engineer PMC to the ISS Site. Inspected the overall progress of site, Right side pier -9 pile cap concreting continuing and Right-side Pier no-7 reinforcement binding & shuttering work is in progress.
❮
❯