1/100
UGPL, Left Lower Suktel Canal Division
225mm Dia HDPE pipe laying work is in progress node from J-467 to J-25 near village Chhatabahal in presence of PMC team.
2/100
Instream Storage Structure, Gudvella
Casting of concrete at P9 middle pier of grade M25A20 from RL 158.50 m to 159.50 m (9th lift RCC) is completed in the presence of Dept JE, PMC & agency site engineers at site on 19.11.2025
3/100
Instream Storage Structure, Gudvella
Casting of concrete at P9 middle pier of grade M25A20 from RL 158.50 m to 159.50 m (9th lift RCC) is completed in the presence of Dept JE, PMC & agency site engineers at site on 19.11.2025
4/100
Instream Storage Structure, Gudvella
Conducted slump test for concreting at P9 middle portion of grade M25A20 from RL158.50m to 159.50m (9th lift RCC) in the presence of Dept JE, PMC & agency site engineers at site, where slump value found 84mm & 89mm on 19.11.2025
5/100
Instream Storage Structure, Gudvella
Conducted slump test for concreting at P9 middle portion of grade M25A20 from RL158.50m to 159.50m (9th lift RCC) in the presence of Dept JE, PMC & agency site engineers at site, where slump value found 84mm & 89mm on 19.11.2025
6/100
Instream Storage Structure, Gudvella
Cement slurry spread before concreting at middle portion of P9 for 9th lift rcc on 19.11.2025
7/100
Instream Storage Structure, Gudvella
• The reinforcement work at the right-side middle portion of P9 has been checked, where:
1. Main bars: 20 mm @ 120 mm c/c.
2. Distribution bars: 12 mm @ 110 mm c/c.
3. Length: 17.7 m.
4. Cover blocks have been placed as per the approved design and drawing on 19.11.2025
8/100
Instream Storage Structure, Gudvella
• The reinforcement work at the right-side middle portion of P9 has been checked, where:
1. Main bars: 20 mm @ 120 mm c/c.
2. Distribution bars: 12 mm @ 110 mm c/c.
3. Length: 17.7 m.
4. Cover blocks have been placed as per the approved design and drawing on 19.11.2025
9/100
Instream Storage Structure, Gudvella
• The reinforcement work at the right-side middle portion of P9 has been checked, where:
1. Main bars: 20 mm @ 120 mm c/c.
2. Distribution bars: 12 mm @ 110 mm c/c.
3. Length: 17.7 m.
4. Cover blocks have been placed as per the approved design and drawing on 19.11.2025
10/100
Instream Storage Structure, Gudvella
Erection of pylon at deck slab no 8 in between P7 & P8 is underprogress on 19.11.2025
11/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at Pier no.12/mid. divide wall for 6th lift at U/S side and 7th lift at D/S side from RL-240.25m to RL-241.60m is completed in presence of JE,KID, PM n Site Engineers of PMC & EPC agency on 19.11.2025
12/100
Instream Storage Structure, Nandagaon
Concrete casting with RCC M25A20 grade at Pier no.12/mid. divide wall for 6th lift at U/S side and 7th lift at D/S side from RL-240.25m to RL-241.60m is completed in presence of JE,KID, PM n Site Engineers of PMC & EPC agency on 19.11.2025
13/100
Instream Storage Structure, Nandagaon
Conducted additional slump test for casting with RCC M25A20 grade at Pier no.12/mid. divide wall for 6th lift at U/S side and 7th lift at D/S side from RL-240.25m to RL-241.60m in presence of JE,KID, PM n Site Engineers of PMC & EPC agency and found value is 88mm at placing site on 19.11.2025
14/100
Instream Storage Structure, Nandagaon
Conducted slump test for casting with RCC M25A20 grade at Pier no.12/mid. divide wall for 6th lift at U/S side and 7th lift at D/S side from RL-240.25m to RL-241.60m in presence of JE,KID, PM n Site Engineers of PMC & EPC agency and found value is 83mm at placing site on 19.11.2025
15/100
Instream Storage Structure, Nandagaon
• 1. Measurement of pier no. 12 (divied wall) for lift 6th lift.
(i) Checking of vertical main bar 20mm dia and found 125mm C/C.
(ii) Checking of horiz. dist. bar 16mm dia and found 150mm C/C.
(iii) Checked the clear cover b/w reinforcement & shuttering plate and found 75mm.
(iv) Checked the width of the pier and found 2.0m on 19.11.2025
16/100
Instream Storage Structure, Nandagaon
• 1. Measurement of pier no. 12 (divied wall) for lift 6th lift.
(i) Checking of vertical main bar 20mm dia and found 125mm C/C.
(ii) Checking of horiz. dist. bar 16mm dia and found 150mm C/C.
(iii) Checked the clear cover b/w reinforcement & shuttering plate and found 75mm.
(iv) Checked the width of the pier and found 2.0m on 19.11.2025
17/100
Instream Storage Structure, Nandagaon
• 1. Measurement of pier no. 12 (divied wall) for lift 6th lift.
(i) Checking of vertical main bar 20mm dia and found 125mm C/C.
(ii) Checking of horiz. dist. bar 16mm dia and found 150mm C/C.
(iii) Checked the clear cover b/w reinforcement & shuttering plate and found 75mm.
(iv) Checked the width of the pier and found 2.0m on 19.11.2025
18/100
Instream Storage Structure, Nandagaon
Cleaning of reinforcement using gunny bag before concrete at pier no. 12 for 6th lift at U/S side upto RL-241.60m on 19.11.2025
19/100
Instream Storage Structure, Nandagaon
Monorail fit up and welding work under progress on 19.11.2025
20/100
Instream Storage Structure, Nandagaon
Curing at D/S left flared out wall is in progress on 19.11.2025
21/100
Instream Storage Structure, Nandagaon
Hoist bridge MIG welding under progress on 19.11.2025
22/100
Instream Storage Structure, Nandagaon
Gate no 5 stoplog gate measurement checked as per drawing. Centre guide distance 10.400m, roller track ss plate centre to centre distance 10.200m on 19.11.2025
23/100
Instream Storage Structure, Nandagaon
Gate no 5 stoplog gate measurement checked as per drawing. Centre guide distance 10.400m, roller track ss plate centre to centre distance 10.200m on 19.11.2025
24/100
UGPL, Left Lower Suktel Canal Division
Extension work is in progress of Outlet from Ro-256B, Z-7129 RM-14 near village Luchkibahal.
25/100
UGPL, Left Lower Suktel Canal Division
Joint verification is in progress for HDPE pipe line of OMS point and outlet points RO-256B (RM-14) in presence of PMC team near village Luchkibahal.
26/100
Integrated Barrage across river Kochila and across river Baitarini
C C Block curing work in progress at Kochila Baitarani ISS Project- 20.11.2025
27/100
UGPL, Left Lower Suktel Canal Division
20mm Dia galvanized steel Conduit pipe laying is in progress for Pump House inner lighting work.
28/100
UGPL, Right Lower Suktel Canal Division
Bermad's instrument installation work is in progress of OCS (0201228-C08A) at village Sialbahali in presence of SE (DoWR), PMC team, EPC and Bermad officials .
29/100
UGPL, Right Lower Suktel Canal Division
Operator/ Watchman Quarters Ramp portion PCC concrete pouring work is in progress of Pump House.
30/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress of Dia 450mm DI pipe line for Gap closing work, node from J-254 to J-38, RM-15, near village Birkel.
31/100
Instream Storage Structure, KansariGanda
Calibration of Plant in progress.
32/100
Instream Storage Structure, KansariGanda
Calibration of Plant in progress.
33/100
Instream Storage Structure, KansariGanda
Visit of QA/Qc Expert along with Site engineer PMC and AE, AEE Dept. to the ISS Site. Inspected the overall progress of
post-monsoon activity and De rusting, to-player chiseling, debris cleaning work in progress.
34/100
Instream Storage Structure, KansariGanda
Visit of QA/Qc Expert along with Site engineer PMC and AE, AEE Dept. to the ISS Site. Inspected the overall progress of
post-monsoon activity and De rusting, to-player chiseling, debris cleaning work in progress.
35/100
Instream Storage Structure, Dhanei
Visit of Irr. Eng. Expert along with Site Engineer PMC to the ISS site. Surplus water from Dhanei Reservoir
is flowing through the ISS Structure. Instructed the agency's representative to have fresh stock of cement
including required quantity of coarse & fine aggregates as per ISI specifications before resuming the
concreting work.
36/100
UGPL, Right Lower Suktel Canal Division
Internal Approach road soil compaction work is in progress for RCC of Pump House.
37/100
UGPL, Right Lower Suktel Canal Division
Internal drain brick masonry plastering work is in progress of Pump House.
38/100
UGPL, Left Lower Suktel Canal Division
Boundary wall outer side plastering work is in progress of Pump House.
39/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M25A20 (Value 80 mm) of RHS Divide wall done in presence of Client & PSS Team.
40/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of RHS Divide wall under sluice portion is under progress in presence of Client & PSS Team.
41/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Gramsabha conducted for diversion of Forest land required for afflux bund at Khuntapada of Telkoi in presence of Sarpanch participated by all the Voters in the meeting S.E, RDD, A.E.E’s, RDD, SDE & PSE of PSS team and representative of EPC agency participated.
42/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning & Vertical straightening of reinforcement for Divide wall is under progress.
43/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Cleaning of silt at RHS Raft area is under progress.
44/100
Instream Storage Structure, Jharbeda
Excavation of Pier No-7 to Divide wall-2 is under progress.
45/100
Instream Storage Structure, Jharbeda
Dewatering work is under progress.
46/100
Instream Storage Structure, Jharbeda
Cleaning & De-shuttering of Pier No-5 is under progress.
47/100
Instream Storage Structure, Hamirpur
MS plate marking and Cutting for hoist stiffener work is in progress.
48/100
Instream Storage Structure, Hamirpur
Hoist bridge platform welding work is in progress.
49/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-31, 4th lift at Block No-5 done in presence of Client & PSS Team.
50/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-31, 4th lift at Block No-5 is under progress in presence of Client & PSS Team.
51/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 21.18/mm2 for 07 days) of Flank wall at Block No-5 and M25A20(Strength is 30.47/mm2 for 28 days) of Pier No-29, 7th lift has done in presence of Client & PSS team.
52/100
Instream Storage Structure, Hamirpur
Curing of Flank wall is under progress.
53/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-18, 6th lift at Block No-3 is under progress.
54/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-17, 7th lift at Block No-3 is under progress.
55/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-27, 13th lift is under progress.
56/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for RHS U/S Flank wall, 6th lift at Block No-5 is under progress.
57/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-29, 10th lift at Block No-4 is under progress.
58/100
Instream Storage Structure, Hamirpur
Shuttering of Pier No-23, 10th lift at Block No-4 is under progress.
59/100
Instream Storage Structure, Khalpal
Hirakud Government Lab mix design trial mix conducted at site laboratory of M30A20, 07 days cube (Strength 26.81 N/mm²) and samal mix design M20A40, 14 days cube (Strength 33.94 N/mm²) and samal mix design M25A20, 14 days cube (Strength 36.31 N/mm²)in presence of S.E, AID & A.E.E, AID and PSS Team of Angul.
60/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 170 mm) of Left sluice cross cut-off Panel No-28 done in presence of Client & PSS Team.
61/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Left sluice cross cut-off Panel No-28 done in presence of Client & PSS Team.
62/100
Instream Storage Structure, Khalpal
End stopper fixing for Left sluice cross cut-off Panel No-28 in presence of Client & PSS Team.
63/100
Instream Storage Structure, Khalpal
Diaphragm wall cage placing for Left sluice cross cut-off Panel No-28 in presence of Client & PSS Team.
64/100
Instream Storage Structure, Khalpal
Excavation of Diaphragm wall Left sluice cross cut-off Panel No-28 is under progress in presence of Client & PSS Team.
65/100
Instream Storage Structure across river Sapei near village Kinjirma
Building staff quarter and Control room plinth beam reinforcement and shuttering work under progress .
66/100
Instream Storage Structure Across Bheden near village Saida
Slump value-80MM
67/100
Instream Storage Structure Across Bheden near village Saida
Shuttering & alignment checking in RHS divide wall Pier portion 10th lift.Rl-222.800 to 224.100
68/100
Instream Storage Structure Across Bheden near village Saida
Curing work progress in Deck slab
69/100
Instream Storage Structure, Budharaja
Slump Value: 60mm.
70/100
Instream Storage Structure, Budharaja
Slump Value: 55mm.
71/100
Instream Storage Structure, Budharaja
Curing work is in Progress at Pier No: 2, Hoist Gate Portion.
72/100
Instream Storage Structure, Budharaja
Curing work is in Progress at Pier No: 2, Hoist Gate Portion.
73/100
Instream Storage Structure, Budharaja
Curing work is in Progress at LHS Abutment, Hoist Gate Portion.
74/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at Pier No: 5, Hoist Gate Portion.
75/100
Instream Storage Structure, Budharaja
Shuttering work is in Progress at Pier No: 4, Hoist Gate Portion.
76/100
Instream Storage Structure, Khirasasan
LHS D/S FLARED OUT WALL 7TH LIFT concrete casting complete
77/100
Instream Storage Structure, Khirasasan
View showing flow of river from U/S to D/S of river.
78/100
Instream Storage Structure, Khirasasan
Pier no. 6 hoist portion shuttering work is in progress
79/100
Instream Storage Structure, Khirasasan
Pier no. 5 hoist portion shuttering work completed and ready for casting.
80/100
Instream Storage Structure, Khirasasan
View showing flow of river from D/S of river
81/100
Instream Storage Structure, KansariGanda
Season's 1st concreting started for ISS Kansariganda. Observed Slump is 80mm. All in concerned officials CE & BM, RBVN, BASIN, ACE, QAD.Bam, SE, BeID, SE, QAD, Bam SE, QA&QC Expert of PMU, BBSR has checked area before concreting of Pier No1.
82/100
Instream Storage Structure, KansariGanda
Concreting is in progress.
83/100
Instream Storage Structure, KansariGanda
Concreting is in progress.
84/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert of PMU, BBSR, CE & BM RBVN basin, ACE, QA, Berhampur , SE BeID, SE QA Divn.,AE and AEE of Dept., PMC team comprising Dy TL, Irrigation Engg expert and QA&QC expert along with Site engineers to the ISS Site. Agency has kept ready area for concreting of Pier No1. Cleaning of old concreting surface, de-rusting of MS reinforcement were also done. Scaffolding arrangements were made for inspection of the concrete was also made. He has also visited the construction materials dump yard near batching plant and materials were found satisfactory. Gradation of CA aggregate was done during the visit. Vivid discussion on different issues on quality aspects and executional aspects was done. Some pics of the are posted below.
85/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert of PMU, BBSR, CE & BM RBVN basin, ACE, QA, Berhampur , SE BeID, SE QA Divn.,AE and AEE of Dept., PMC team comprising Dy TL, Irrigation Engg expert and QA&QC expert along with Site engineers to the ISS Site. Agency has kept ready area for concreting of Pier No1. Cleaning of old concreting surface, de-rusting of MS reinforcement were also done. Scaffolding arrangements were made for inspection of the concrete was also made. He has also visited the construction materials dump yard near batching plant and materials were found satisfactory. Gradation of CA aggregate was done during the visit. Vivid discussion on different issues on quality aspects and executional aspects was done. Some pics of the are posted below.
86/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert of PMU, BBSR, CE & BM RBVN basin, ACE, QA, Berhampur , SE BeID, SE QA Divn.,AE and AEE of Dept., PMC team comprising Dy TL, Irrigation Engg expert and QA&QC expert along with Site engineers to the ISS Site. Agency has kept ready area for concreting of Pier No1. Cleaning of old concreting surface, de-rusting of MS reinforcement were also done. Scaffolding arrangements were made for inspection of the concrete was also made. He has also visited the construction materials dump yard near batching plant and materials were found satisfactory. Gradation of CA aggregate was done during the visit. Vivid discussion on different issues on quality aspects and executional aspects was done. Some pics of the are posted below.
87/100
Instream Storage Structure, KansariGanda
Visit of QA&QC Expert of PMU, BBSR, CE & BM RBVN basin, ACE, QA, Berhampur , SE BeID, SE QA Divn.,AE and AEE of Dept., PMC team comprising Dy TL, Irrigation Engg expert and QA&QC expert along with Site engineers to the ISS Site. Agency has kept ready area for concreting of Pier No1. Cleaning of old concreting surface, de-rusting of MS reinforcement were also done. Scaffolding arrangements were made for inspection of the concrete was also made. He has also visited the construction materials dump yard near batching plant and materials were found satisfactory. Gradation of CA aggregate was done during the visit. Vivid discussion on different issues on quality aspects and executional aspects was done. Some pics of the are posted below.
88/100
Instream Storage Structure, KansariGanda
Visit of CE RBVN Basin, Addl CE, SE QA Divn, Berhampur including SE BeID with his team, PMC team comprising Dy TL, Irrigation Engg expert and QA&QC expert along with Site Engineers to the ISS site. He has reviewed preparatory arrangements at ISS site after post monsoon. Agency has kept ready area for concreting of Peir No1. Cleaning of old concreting surface, de-rusting of MS reinforcement were in progress. CE has also inspected the construction materials near batching plant.
89/100
Instream Storage Structure, KansariGanda
Visit of CE RBVN Basin, Addl CE, SE QA Divn, Berhampur including SE BeID with his team, PMC team comprising Dy TL, Irrigation Engg expert and QA&QC expert along with Site Engineers to the ISS site. He has reviewed preparatory arrangements at ISS site after post monsoon. Agency has kept ready area for concreting of Peir No1. Cleaning of old concreting surface, de-rusting of MS reinforcement were in progress. CE has also inspected the construction materials near batching plant.
90/100
Instream Storage Structure, KansariGanda
Visit of CE RBVN Basin, Addl CE, SE QA Divn, Berhampur including SE BeID with his team, PMC team comprising Dy TL, Irrigation Engg expert and QA&QC expert along with Site Engineers to the ISS site. He has reviewed preparatory arrangements at ISS site after post monsoon. Agency has kept ready area for concreting of Peir No1. Cleaning of old concreting surface, de-rusting of MS reinforcement were in progress. CE has also inspected the construction materials near batching plant.
91/100
Instream Storage Structure, KansariGanda
Visit of CE RBVN Basin, Addl CE, SE QA Divn, Berhampur including SE BeID with his team, PMC team comprising Dy TL, Irrigation Engg expert and QA&QC expert along with Site Engineers to the ISS site. He has reviewed preparatory arrangements at ISS site after post monsoon. Agency has kept ready area for concreting of Peir No1. Cleaning of old concreting surface, de-rusting of MS reinforcement were in progress. CE has also inspected the construction materials near batching plant.
92/100
UGPL, Left Lower Suktel Canal Division
Trench Excavation work is in progress for Laying of Dia 350mm DI pipe line node from J-99 to J-193 at village Singhanimunda.
93/100
Instream Storage Structure, Gudvella
D/S side view of ISS Gudvella on 18.11.2025
94/100
Instream Storage Structure, Gudvella
U/S side view of ISS Gudvella on 18.11.2025
95/100
Instream Storage Structure, Kudabega
Slump 80mm
Tm-4
96/100
Instream Storage Structure, Gudvella
1. Erection of pylon at deck slab no -8 in between P7 and P8 is under progress.
2. Shuttering work at right side middle portion of divide wall for 9th lift RCC is under progress on 18.11.2025
97/100
Instream Storage Structure, Kudabega
Slump 85mm
Tm-3
98/100
Instream Storage Structure, Gudvella
• Visited by: SE Sir, Balangir Irrigation Division
Location: ISS Gudvella Site
Present: Department JE, PMC Site Engineers, and Agency Representatives Observations and Instructions
1. The agency was instructed to deploy additional manpower to expedite the ongoing construction works.
2. The agency was advised to immediately commence the second stage of mechanical works.
3. The agency was directed to submit the Afflux Survey Report and the approach road data of the site at the earliest.
4. The agency was instructed to start the building works without any further delay.
Remarks / Conclusion
The overall progress of the work was reviewed during the visit. The agency was advised to enhance the pace of execution and ensure timely submission of all required data and reports. The quality of work must be maintained strictly as per specifications under the close supervision of PMC and departmental officials on 17.11.2025
99/100
Instream Storage Structure, Gudvella
• Visited by: SE Sir, Balangir Irrigation Division
Location: ISS Gudvella Site
Present: Department JE, PMC Site Engineers, and Agency Representatives Observations and Instructions
1. The agency was instructed to deploy additional manpower to expedite the ongoing construction works.
2. The agency was advised to immediately commence the second stage of mechanical works.
3. The agency was directed to submit the Afflux Survey Report and the approach road data of the site at the earliest.
4. The agency was instructed to start the building works without any further delay.
Remarks / Conclusion
The overall progress of the work was reviewed during the visit. The agency was advised to enhance the pace of execution and ensure timely submission of all required data and reports. The quality of work must be maintained strictly as per specifications under the close supervision of PMC and departmental officials on 17.11.2025
100/100
Instream Storage Structure, Kudabega
Slump 80mm
Tm-2
❮
❯