1/100
UGPL, Right Lower Suktel Canal Division
OCS chamber door & angle fixing work is in progress OCS No:-0213055- C04B at village Bubel in presence of PMC team.
2/100
UGPL, Right Lower Suktel Canal Division
Bermad equipment installation work is in progress of OCS-0201345-C19A at village Madhiapali in presence of PMC team.
3/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE pipe connection at J-531, RM-4 in village Semelia.
4/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and IRR. Eng. Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site, RHS Pier No 8 Raft casting, Grabbing of panel number R 80, Excavation of foundation for pile cap of Pier number 9 and Right Pier number 7 3rd lift shuttering. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
5/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and IRR. Eng. Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site, RHS Pier No 8 Raft casting, Grabbing of panel number R 80, Excavation of foundation for pile cap of Pier number 9 and Right Pier number 7 3rd lift shuttering. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
6/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and IRR. Eng. Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site, RHS Pier No 8 Raft casting, Grabbing of panel number R 80, Excavation of foundation for pile cap of Pier number 9 and Right Pier number 7 3rd lift shuttering. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
7/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and IRR. Eng. Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site, RHS Pier No 8 Raft casting, Grabbing of panel number R 80, Excavation of foundation for pile cap of Pier number 9 and Right Pier number 7 3rd lift shuttering. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
8/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and IRR. Eng. Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site, RHS Pier No 8 Raft casting, Grabbing of panel number R 80, Excavation of foundation for pile cap of Pier number 9 and Right Pier number 7 3rd lift shuttering. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
9/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and IRR. Eng. Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site and Pile number. 97 concrete pouring. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
10/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and IRR. Eng. Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site and Pile number. 97 concrete pouring. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
11/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and IRR. Eng. Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site and Pile number. 97 concrete pouring. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
12/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and IRR. Eng. Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site and Pile number. 97 concrete pouring. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
13/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and IRR. Eng. Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site and Pile number. 97 concrete pouring. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
14/100
Instream Storage Structure, Gudvella
Paint work under progress on 08.04.2026
15/100
Instream Storage Structure, Gudvella
Paint work under progress on 08.04.2026
16/100
Instream Storage Structure, Gudvella
Trestle final alignment work under progress on 08.04.2026
17/100
Instream Storage Structure, Gudvella
Curing work is under progress at site on 08.04.2026
18/100
Instream Storage Structure, Gudvella
Brick work at 1st floor of building on 08.04.2026
19/100
Instream Storage Structure, Gudvella
Casting of precast railing over parapet wall on the deck slab has been commenced with dimensions 1.424 m × 0.13 m × 0.17 m on 08.04.2026
20/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no. 1 is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 86mm on 08.04.2026
21/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no. 1 is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 86mm on 08.04.2026
22/100
Instream Storage Structure, Nandagaon
• 2 (i).Fixing & fittings and alignment of All trestle and columns foundation bolts measurements has been checked at pier no.-1 for Blockout area of 6.8m length and found correct by HM Expert of PMC during his site visit on dt.01.04.2026 in presence of mechanical Site Engineers of PMC and EPC Agency.
(ii) Rigid and smooth shuttering for Blockout area with M35A20 grade at pier no.-1 from RL-245.40m to RL-246.30m are found completed.
(iii).The area is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with M35A20 grade on 08.04.2026
23/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.1& left abutment for 10th lift of undersluice bay-1 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 86mm on 08.04.2026
24/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of 2nd stage concrete at pier no.1& left abutment for 10th lift of undersluice bay-1 is in progress in presence of PM EPC agency, Site Engineers of PMC & EPC agency. The slump test value is 86mm on 08.04.2026
25/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no. 8 is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 88mm on 08.04.2026
26/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no. 8 is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 88mm on 08.04.2026
27/100
Instream Storage Structure, Nandagaon
• 1 Fixing & fittings and alignment of 2nd. stage embedded parts and sufficient numbers of dowel bars at roller tracks of both stoplog & service gate grooves at undersluice bay No.-1 of Pier No.1& left abutment for 10th lift have been checked and found correct by HM Expert of PMC during his site visit on dt.01.04.2026 in presence of all civil n mechanical Site Engineers of PMC and EPC Agency as per the approved Mechanical drawing & designs.
(i) Accordingly the rigid n smooth shuttering for placing the 2nd. Stage concrete is completed as follows:
(ii) Chipping of old vertical concrete surface is done.
(iii).The area is cleaned properly through water pressure and passed by SE, KID, Bhawanipatna for placing with RCC M35A20 grade on 08.04.2026
28/100
Instream Storage Structure, Nandagaon
Gate no 12 both barrage bay gate and stoplog gate 2nd stage embedded parts erection work under progress on 08.04.2026
29/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no.1 on 08.04.2026
30/100
Instream Storage Structure, Nandagaon
Shuttering for Blockout portion is in progress at pier no.9 on 08.04.2026
31/100
Instream Storage Structure, KansariGanda
Visit the ISS Kansariganda site by PMC team consisting of HME, Irr. Eng. Expert and Site Engineers Mechanical & Civil, the following observations made on HM Equipment fabrication work at the site: 1. Sill Beams fabrication work is in progress for 7 bays (6 Barrage+ 1 Under Sluice- Service & Stop log gate grooves) 2. Fabrication work is in progress for 4 nos Barrage Gates and 2 no.s Stop log Gate elements. 3. Some of the structural steel items procured from MSPL and Topworth steel (Amalgam Steel) makes, this makes are not as per Approved Vendors mentioned in the contract agreement, prior approval is required before use of these structural steel items for fabrication. 4. The draft Quality Assurance Plan QAP collected from the Agency, after Scrutiny, reverted back on the same. 5. LHS U/S divide wall pier 1st lift concrete pouring. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
32/100
Instream Storage Structure, KansariGanda
Visit the ISS Kansariganda site by PMC team consisting of HME, Irr. Eng. Expert and Site Engineers Mechanical & Civil, the following observations made on HM Equipment fabrication work at the site: 1. Sill Beams fabrication work is in progress for 7 bays (6 Barrage+ 1 Under Sluice- Service & Stop log gate grooves) 2. Fabrication work is in progress for 4 nos Barrage Gates and 2 no.s Stop log Gate elements. 3. Some of the structural steel items procured from MSPL and Topworth steel (Amalgam Steel) makes, this makes are not as per Approved Vendors mentioned in the contract agreement, prior approval is required before use of these structural steel items for fabrication. 4. The draft Quality Assurance Plan QAP collected from the Agency, after Scrutiny, reverted back on the same. 5. LHS U/S divide wall pier 1st lift concrete pouring. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
33/100
Instream Storage Structure, KansariGanda
Visit the ISS Kansariganda site by PMC team consisting of HME, Irr. Eng. Expert and Site Engineers Mechanical & Civil, the following observations made on HM Equipment fabrication work at the site: 1. Sill Beams fabrication work is in progress for 7 bays (6 Barrage+ 1 Under Sluice- Service & Stop log gate grooves) 2. Fabrication work is in progress for 4 nos Barrage Gates and 2 no.s Stop log Gate elements. 3. Some of the structural steel items procured from MSPL and Topworth steel (Amalgam Steel) makes, this makes are not as per Approved Vendors mentioned in the contract agreement, prior approval is required before use of these structural steel items for fabrication. 4. The draft Quality Assurance Plan QAP collected from the Agency, after Scrutiny, reverted back on the same. 5. LHS U/S divide wall pier 1st lift concrete pouring. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
34/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and IRR. Eng. Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site and Rhs pier no 7 1st lift, 2nd layer concrete and LHS 4no Girder beam casting. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
35/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and IRR. Eng. Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site and Rhs pier no 7 1st lift, 2nd layer concrete and LHS 4no Girder beam casting. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
36/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and IRR. Eng. Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site and Rhs pier no 7 1st lift, 2nd layer concrete and LHS 4no Girder beam casting. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
37/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and IRR. Eng. Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site and Rhs pier no 7 1st lift, 2nd layer concrete and LHS 4no Girder beam casting. Slump cone test conducted at site. Curing continuing at site. Cube cast at site.
38/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and QA/QC Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site and Pile no-133,135,159 & 131 casting, RHS U/S divide Wall Panel no-79. Reinforcement checked
39/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and QA/QC Exp. along with Site Engineers PMC to the ISS Site. Inspected the overall progress of site and Pile no-133,135,159 & 131 casting, RHS U/S divide Wall Panel no-79. Reinforcement checked
40/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and Site Engineer PMC to the ISS Site. Inspected the overall progress of site, Left side Barrage bay pier no-5 pier cap reinforcement binding and shuttering work, Right side Barrage bay pier no-7, 1st lift concrete pouring and Right side Barrage bay pier no-8 pcc.
41/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and Site Engineer PMC to the ISS Site. Inspected the overall progress of site, Left side Barrage bay pier no-5 pier cap reinforcement binding and shuttering work, Right side Barrage bay pier no-7, 1st lift concrete pouring and Right side Barrage bay pier no-8 pcc.
42/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and Site Engineer PMC to the ISS Site. Inspected the overall progress of site, Left side Barrage bay pier no-5 pier cap reinforcement binding and shuttering work, Right side Barrage bay pier no-7, 1st lift concrete pouring and Right side Barrage bay pier no-8 pcc.
43/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site.
44/100
Instream Storage Structure, KansariGanda
Slump cone test conducted at site.
45/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and Site Engineer PMC to the ISS Site. Inspected the overall progress of site and Girder no 3 casting, R/ S Divide wall Pile No 106 casting and Rhs under-sluice panel no- R61 concrete pouring.
46/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and Site Engineer PMC to the ISS Site. Inspected the overall progress of site and Girder no 3 casting, R/ S Divide wall Pile No 106 casting and Rhs under-sluice panel no- R61 concrete pouring.
47/100
Instream Storage Structure, KansariGanda
Visit of AEE, AE of Dept. and Site Engineer PMC to the ISS Site. Inspected the overall progress of site and Girder no 3 casting, R/ S Divide wall Pile No 106 casting and Rhs under-sluice panel no- R61 concrete pouring.
48/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-3, 5th lift done in presence of Client & PSS Team.
49/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-3, 5th lift is under progress in presence of Client & PSS Team.
50/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Pier No-2, 4th lift done in presence of Client & PSS Team.
51/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-2, 4th lift is under progress in presence of Client & PSS Team.
52/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-16, 13th lift done in presence of Client & PSS Team.
53/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-16, 13th lift is under progress in presence of Client & PSS Team.
54/100
Instream Storage Structure, Hamirpur
Slump testing M35A20 (Value 85 mm) of Gantry Girder No-14 done in presence of Client & PSS Team.
55/100
Instream Storage Structure, Hamirpur
Concreting M35A20 of Gantry Girder No-14 is under progress in presence of Client & PSS Team.
56/100
Instream Storage Structure, Hamirpur
Testing of Compressive M25A20 (Strength is 30.93/mm2 for 28 days) of Pier No-21, 6th lift and (Strength is 31.01/mm2 for 28 days) of D/S Flared out Cut-off wall, 3rd lift at Block No-5 and M30A20 (Strength is 37.78/mm2 for 07 days) of Gantry Girder No-10 has done in presence of Client & PSS team.
57/100
Instream Storage Structure, Hamirpur
LHS Pier No-10 barrage bay groove 2nd stage embedded parts roller track and side guide erection work is in progress.
58/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-5 is under progress.
59/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-3, 5th lift is under progress.
60/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-2, 4th lift is under progress.
61/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for D/S Abutment wall (A1), 7th lift at Block No-1 is under progress.
62/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-1, 4th lift is under progress.
63/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for Pier No-15, 12th lift is under progress.
64/100
Instream Storage Structure, Hamirpur
Binding of reinforcement for U/S Flank wall at Block no-1 is under progress.
65/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Gantry Girder is under progress.
66/100
Instream Storage Structure, Hamirpur
Shuttering & Binding of reinforcement for Pier no-21, 12th lift is under progress
67/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Excavation of U/S Divide wall for Cut-off and Shuttering of Divide wall, 9th lift and binding of reinforcement for Middle pier Cap is under progress.
68/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Shuttering of D/S Wing wall Counterfort is under progress.
69/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Slump testing M25A20 (Value 85 mm) of Abutment with Counterfort wall, 8th lift done in presence of Client & PSS Team.
70/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE SANTEIBHANJA
Concreting M25A20 of Abutment with Counterfort wall, 8th lift is under progress in presence of Client & PSS Team.
71/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Slump testing M25A20 (Value 85 mm) of RHS D/S Double pier, 3rd lift done in presence of Client & PSS Team.
72/100
INSTREAM STORAGE STRUCTURE ACROSS RIVER SAMAKOI NEAR VILLAGE TELKOI
Concreting M25A20 of RHS D/S Double pier, 3rd lift is under progress in presence of Client & PSS Team.
73/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Barrage bay No-2 Middle Cut-off is under progress in presence of Client & PSS Team.
74/100
Instream Storage Structure, Khalpal
Slump testing M25A20 (Value 85 mm) of Pier No-19 (Crest portion) done in presence of Client & PSS Team.
75/100
Instream Storage Structure, Khalpal
Concreting M25A20 of Pier No-19 (Crest portion) is under progress in presence of Client & PSS Team.
76/100
UGPL, Right Lower Suktel Canal Division
Joint verification work is in progress of OCS NO 0213120-C04A and outlets at Village Budhisindhol in presence of SDO, AE, JE of DoWR, PMC team and L&T personnel.
77/100
UGPL, Left Lower Suktel Canal Division
Di pipe line Air valve fitting work is in progress of Lm-10, from J-279 to J-280 at village Khairpali.
78/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE pipe TEE connection (160*125*125) at J-531, RM-4 near village Semelia.
79/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for connection of DI to HDPE pipeline at J-479, LM-8 near Taliudar in presence of DoWR AE and PMC team.
80/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for HDPE pipe TEE connection (180*140*140) at J-64, LM-18 near village Badimunda.
81/100
UGPL, Left Lower Suktel Canal Division
Excavation work is in progress for 450mm Dia DI pipe gap closing from J-254 to J-38 near village Birkel in presence of AE DoWR and PMC team.
82/100
UGPL, Left Lower Suktel Canal Division
1ha outlet point fixing work is in progress at LO-198B(Z-2730),LM-10 near village Jharmunda in presence of PMC team.
83/100
Instream Storage Structure, Gudvella
Cast of concrete at endseal portion from in between A1 to P1 under sluice bay of grade M25A20 RCC with RL 147.45m to 148.60m is under progress through chute in the presence of Dept JE, site engineer of PMC and agency. The slump test value is 76mm on 07.04.2026
84/100
Instream Storage Structure, Gudvella
Cast of concrete at endseal portion from in between A1 to P1 under sluice bay of grade M25A20 RCC with RL 147.45m to 148.60m is under progress through chute in the presence of Dept JE, site engineer of PMC and agency. The slump test value is 76mm on 07.04.2026
85/100
Instream Storage Structure, Gudvella
Column, trestle final allignment work under progress on 07.04.2026
86/100
Instream Storage Structure, Gudvella
Paint work under progress on 07.04.2026
87/100
Instream Storage Structure, Gudvella
Stoplog ss plate welding work under progress on 07.04.2026
88/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no.7&8 is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 85mm on 07.04.2026
89/100
Instream Storage Structure, Nandagaon
Concrete casting with M35A20 grade of Blockout portion at pier no.7&8 is in progress in presence of PM EPC agency,Site Engineers of PMC & EPC agency. The slump test value is 85mm on 07.04.2026
90/100
Instream Storage Structure, Nandagaon
• 1 (i).Fixing & fittings and alignment of All trestle and columns foundation bolts measurements has been checked at pier no.-7&8 for Blockout area of 6.8m length and found correct by HM Expert of PMC during his site visit on dt.01.04.2026 in presence of mechanical Site Engineers of PMC and EPC Agency.
(ii) Rigid and smooth shuttering for Blockout area with M35A20 grade at pier no.-7&8 from RL-245.40m to RL-246.30m are found completed.
(iii).The area is cleaned properly through air water jet and passed by SE, KID, Bhawanipatna for placing with M35A20 grade on 07.04.2026
91/100
Instream Storage Structure, Nandagaon
Gate no 13 both barrage bay gate and stoplog gate 2nd stage embedded parts erection work completed and it is ready for concrete on 07.04.2026
92/100
Instream Storage Structure, Nandagaon
Gate no 13 both barrage bay gate and stoplog gate 2nd stage embedded parts erection work completed and it is ready for concrete on 07.04.2026
93/100
Instream Storage Structure, Nandagaon
Shuttering for 2nd stage concrete is in progress at pier no. 1 on 07.04.2026
94/100
Instream Storage Structure, Nandagaon
Placing of CC blocks is in progress at U/s side on 07.04.2026
95/100
Instream Storage Structure, Nandagaon
• 1) De-Shuttering is in progress at U/S right divide wall.
2) De-watering is in progress through well point system on 07.04.2026
96/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 85 mm) of Fish pass, Raft at Block No-1 done in presence of Client & PSS Team.
97/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Fish pass, Raft at Block No-1 is under progress in presence of Client & PSS Team.
98/100
Instream Storage Structure, Hamirpur
Slump testing M25A20 (Value 90 mm) of Pier No-1, 3rd lift done in presence of Client & PSS Team.
99/100
Instream Storage Structure, Hamirpur
Concreting M25A20 of Pier No-1, 3rd lift is under progress in presence of Client & PSS Team.
100/100
Instream Storage Structure, Hamirpur
Column base plate drilling work is in progress.
❮
❯